This document contains a pre-proposal information package and questions and answers for solicitation N00024-22-R-4403 issued by the Naval Sea Systems Command. The solicitation is for the USS TRIPOLI (LHA 7) FY23 Selected Restricted Availability, which includes maintenance, modernization, and repair work. Offerors must request access to restricted attachments containing pricing workbooks, milestones, and compartment closeout information. The availability is approximately 12 months beginning in March 2023 and ending in March 2024. A single award is anticipated in December 2022 for a contractor capable of completing the complex work at a West Coast facility. The procurement will not be set aside for small business.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Proposal Information (PPI)
NAVSEA POC: Derek Shirley derek.s.shirley.civ@us.navy.mil Brian Romano brian.c.romano.civ@us.navy.mil
Question Date Contractor Question Government Response
1 6/21/2022 What is the maximum amount or maximum period for Liquidated Damages as prescribed in FAR 11.5? The Government does not have an answer at this time.
2 6/21/2022 Note E states, "…[z]ero-dollar changes and administrative contract changes (for example, drawing revision change where no additional work is required) shall not be executed using the Small Dollar Value Growth procedures…". Will the Government clearly identify changes in drawings when they have determined that "no additional work is required"?
Yes - the Government will clearly identify such changes in drawings that do not require additional work..
3 6/21/2022 Contractor notes that the J-3 "Exec Milestones" tab shows 03/08/2024 as the Availability Completion (AC) date; however, the "PERL" tab says the avail completes on 03/09/2024. Can the Government please confirm the correct AC date?
Attachment J-3 Execution Milesone has been updated by contract to state "Contract Completion" instead of "Availability Completion". The EOA date has been removed from both tabs.
4 6/21/2022 Paragraph 5.4 states, “PAINT ABATEMENT: Abatement work will be conducted in accordance with FY23 NSI 009-32. Paint abatement will be included as part of offerors proposed pricing and is not subject to additional growth.”. Has there been any paint applied that does not meet NAVSEA Standard Item FY23 Change 1, 009-32, tables 1 thru 8 requirements?
The Government does not have an answer at this time.
5 6/21/2022
Contractors understanding that all required references listed in paragraph 2 of a zero-tier specification (work item) are "first tier" references.
However, when a zero-tier specification directs to use a first-tier reference as "guidance", bidders should not estimate the reference and only use it to aid in the development of an estimate of references that are to be accomplished. Does the Government concur with this interpretation? If not, please advise.
Government does not concur. All zero-tier and first-tier references, as defined in C-211-H016, are mandatory for use (including pricing) .
RFP Section B, Note E, 1.
Attachment J-3 Availability Completion
RFP RFP page 83 of 184, Section C, Para 5.4
USS TRIPOLI (LHA 7) FY23 SRA N00024-22-R-4403
Question Area Para. #
RFP RFP page 132 of 184, Section H, 52.211-11
RFP RFP page 91 of 184, C-211-H016