USS TRIPOLI (LHA 7) FY23 SRA PPI_5.pdf

PDF 89 KB Posted

Attached to
AMENDMENT 0008 - USS TRIPOLI (LHA 7) FY23 SELECTED RESTRICTED AVAILABILITY (SRA)
Solicitation number
N00024-22-R-4403
Issued by

About this file

This document contains a pre-proposal information exchange and questions and answers related to solicitation N00024-22-R-4403 for the USS TRIPOLI (LHA 7) FY23 Selected Restricted Availability. The Naval Sea Systems Command is seeking a contractor to execute maintenance, modernization, and repair of the USS TRIPOLI for approximately 12 months beginning in March 2023. The availability requires substantial facilities and human resources capable of completing ship maintenance, repair, and modernization. The solicitation was issued via SAM.gov and the Navy anticipates awarding a single contract by December 2022. Interested parties must request access to technical attachments, and limited distribution references and drawings must be requested separately. Questions were answered clarifying paint abatement requirements, scope of work details, and generator needs depending on work location.

View the file

Other files

File Type Posted
USS TRIPOLI (LHA 7) FY23 SRA A0008_Conformed.pdf PDF
USS TRIPOLI (LHA 7) FY23 SRA A0008.pdf PDF
USS TRIPOLI (LHA 7) FY23 SRA PPI_7.pdf PDF
USS TRIPOLI (LHA 7) FY23 SRA A0007.pdf PDF
USS TRIPOLI (LHA 7) FY23 SRA A0007 Conformed.pdf PDF
USS TRIPOLI (LHA 7) FY23 SRA A0006_Conformed.pdf PDF
USS TRIPOLI (LHA 7) FY23 SRA A0006.pdf PDF
USS TRIPOLI (LHA 7) FY23 SRA PPI_6.pdf PDF
USS TRIPOLI (LHA 7) FY23 SRA Conformed_A0005.pdf PDF
USS TRIPOLI (LHA 7) FY23 SRA PPI_3-4.pdf PDF
USS TRIPOLI (LHA 7) FY23 SRA_A0005.pdf PDF
USS TRIPOLI Attachment S-7 Proposal Assessment Rev_1.xlsx XLSX spreadsheet
USS TRIPOLI Attachment J-10 20 Percent Open and Inspect Milestone Reports Due Rev_1.xlsx XLSX spreadsheet
USS TRIPOLI (LHA 7) FY23 SRA_A0004.pdf PDF
USS TRIPOLI (LHA 7) FY23 SRA Conformed_A0004.pdf PDF
USS TRIPOLI (LHA 7) FY23 SRA Conformed_A0003.pdf PDF
USS TRIPOLI (LHA 7) FY23 SRA_A0003.pdf PDF
USS TRIPOLI (LHA 7) FY23 SRA PPI_2.pdf PDF
USS TRIPOLI (LHA 7) FY23 SRA Conformed_A0002.pdf PDF
USS TRIPOLI (LHA 7) FY23 SRA_A0002.pdf PDF
USS TRIPOLI (LHA 7) FY23 SRA PPI_1.pdf PDF
USS TRIPOLI (LHA 7) FY23 SRA_A0001.pdf PDF
USS TRIPOLI (LHA 7) FY23 SRA Conformed_A0001.pdf PDF
USS TRIPOLI Attachment J-8 Government Furnished Material List Rev_1.xlsx XLSX spreadsheet
USS TRIPOLI Attachment J-10 20 Percent Open and Inspect Milestone Reports Due.xlsx XLSX spreadsheet
USS TRIPOLI Attachment J-5 Quality Assurance Surveillance Plan.docx DOCX document
USS TRIPOLI Attachment S-9 Past Performance Questionnaire.docx DOCX document
(USS TRIPOLI) CDRL Exhibit A.pdf PDF
USS TRIPOLI Attachment S-3 Pre-Proposal Information Form.xlsx XLSX spreadsheet
USS TRIPOLI Attachment J-7 IPTD Events and SMR.docx DOCX document
USS TRIPOLI Attachment S-2 Past Performance CPARS References.docx DOCX document
USS TRIPOLI FY23 SRA Solicitation.pdf PDF
USS TRIPOLI Attachment J-8 Government Furnished Material List.xlsx XLSX spreadsheet
(USS TRIPOLI) CDRL Exhibit C.pdf PDF
(USS TRIPOLI) CDRL Exhibit B.pdf PDF
USS TRIPOLI Attachment S-7 Proposal Assessment.xlsx XLSX spreadsheet
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-Proposal Information (PPI)

NAVSEA POC: Derek Shirley derek.s.shirley.civ@us.navy.mil Brian Romano brian.c.romano.civ@us.navy.mil

Question Date Contractor Question Government Response

95 8/2/2022 If the availability is executed at the Naval Station, the Contractor believes that the (3) generators are not necessary to support a move (Para 3.5) and backup power (Para 3.6). Does the Government concur?

Government concurs, paragraph 3.5 will not be required if the ship is not moved to/from the Naval Base to/from the Contrtactors facilitiy.

Government does not concur, the KTR will provide a standby emergency generator IAW the requirements of paragraph 3.6.

96 8/2/2022

Contractor notes that there are tanks and voids that are not identified in Para. 1.2 of 123-10-001. However, the tanks voids are identified on Attachment A and do have repairs under other work items.

123-20-001

a. Void (5-51-1-V) 123-16-001

a. Ballast Tank (7-102-0-W)

b. Ballast Tank (7-125-0-W)

c. Ballast Tank (7-125-1-W)

d. Ballast Tank (7-125-2-W) 123-17-001

a. Contaminated Oily Waste Collecting Tank (7-96-2-F)

b. JP-5 Stowage/Contaminated/Settling (SETLG) Tank (6-37-2-J)

c. JP-5 Stowage/Contaminated/Settling Tank (6-37-1-J)

d. JP-5 Stowage/Contaminated/Settling Tank (7-104-1-J)

e. JP-5 Stowage/Contaminated/Settling Tank (7-104-2-J)

Does the Government concur that these tanks/void should be included in Para 1.2 of 123-10-001?

Government concurs, the tanks/void should be included in para 1.2 of 123-10- 001.

123-20-001

a. Void (5-51-1-V) Include in 1.2 123-16-001

a. Ballast Tank (7-102-0-W) Include in 1.2

b. Ballast Tank (7-125-0-W) Include in 1.2

c. Ballast Tank (7-125-1-W) Include in 1.2

d. Ballast Tank (7-125-2-W) Include in 1.2 123-17-001

a. Contaminated Oily Waste Collecting Tank (7-96-2-F) See Para 1.2.72 of 123- 10-001

b. JP-5 Stowage/Contaminated/Settling (SETLG) Tank (6-37-2-J) Include in 1.2

c. JP-5 Stowage/Contaminated/Settling Tank (6-37-1-J) Include in 1.2

d. JP-5 Stowage/Contaminated/Settling Tank (7-104-1-J) Include in 1.2

e. JP-5 Stowage/Contaminated/Settling Tank (7-104-2-J) Include in 1.2

97 8/2/2022 For Work Item 634-21-002, KTR notes Errata 1 changed the square footage of Para. 1.3.1. Does the Government intend to accomplish 1,500 SQFT or 500SQFT? Please Advise. Government intends to accomplish 1,500 sq. ft.

98 8/2/2022

Contractor notes a disparity between RFP Section C, para 5.4 and NSI 009-32, para 3.1.2.1 through 3.1.2.2.

Can bidders assume that any Abatement identified above 150 square feet per 009-32, paragraph 3.1.2.1 for Amphibious Assault Ships (LHD, LHA), will be subject to Change Order and Growth per paragraph 3.1.2.2?

If so, will an Amendment be issued revising the RFP as written to align with 009-32?

The Goverment concurs there is a conflict between the RFP paint abatement language, and the NSI 009-32 paint abatement language. The RFP paint abatement language stated in Section C paragraph 5.4 has been removed. NSI 009-32 is the requirement for paint abatement.

Attachment J-10 Para. 1.2

Attachment J-1 N/A

RFP Para. 5.4

Attachment J-1 Para. 3.5 and 3.6

USS TRIPOLI (LHA 7) FY23 SRA N00024-22-R-4403

Question Area Para. #