This document is a ConsensusDocs 200 Standard Agreement and General Conditions Between Owner and Constructor for lump sum construction contracts, utilized by the University System of New Hampshire (USNH) for the Memorial Union Building Elevator Controller Replacements project at the University of New Hampshire. The agreement establishes the contractual framework governing the relationship between the Owner (USNH/UNH Facilities Project Management), the Constructor, and the Design Professional. The contract is structured as a lump sum agreement with specific provisions for the scope of work, construction timeline, and performance requirements. The Constructor is responsible for providing all labor, materials, equipment, and services necessary to complete the work in accordance with the Contract Documents, which include drawings, specifications, addenda, and other referenced exhibits. The agreement requires the Constructor to submit a Schedule of the Work before the first payment application, formatted as a detailed critical path method schedule identifying critical activities and dates necessary for timely completion. Substantial Completion and Final Completion dates are to be specified in the executed agreement, with adjustments permitted through Change Orders as provided in the contract terms.

The contract establishes a lump sum Contract Price subject to equitable adjustments for changes in the work, delays caused by factors beyond the Constructor's control, and costs arising from concealed conditions or hazardous materials discovery. Payment terms provide for progress payments based on applications for payment, with the Design Professional responsible for reviewing and approving submittals within ten business days. The Constructor must maintain insurance and bonds as required by Article 10, obtain necessary permits and licenses (with Owner responsible for primary building permit fees and the Constructor responsible for trade permit fees), and comply with all applicable laws and regulations. The agreement includes a one-year correction period for defective work following Substantial Completion, with the Constructor warranting that all materials and equipment are new, of good quality, and free from defective workmanship unless otherwise specified. The document does not identify specific funding sources or amounts, as these details are to be inserted in the blank fields upon contract execution. Liquidated damages provisions are included as optional terms to be specified by the parties, allowing for daily damages if Substantial Completion or Final Completion dates are not achieved.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ConsensusDocs® 200 - Standard Agreement and General Conditions Between Owner and Constructor - © 2011, Revised April 2018. THIS DOCUMENT MAY HAVE BEEN MODIFIED. The ConsensusDocs technology platform creates a redline comparison to the standard language which the purchaser of this contract is authorized to share for review purposes. Consultation with legal and insurance counsel are strongly encouraged. You may only make copies of finalized documents for distribution to parties in direct connection with this contract. Any other uses are strictly prohibited.

University System of New Hampshire/ConsensusDocs® 200

STANDARD AGREEMENT AND GENERAL CONDITIONS BETWEEN OWNER AND

CONSTRUCTOR (Lump Sum)

TABLE OF ARTICLES

1. AGREEMENT

2. GENERAL PROVISIONS

3. CONSTRUCTOR’S RESPONSIBILITIES

4. OWNER'S RESPONSIBILITIES

5. SUBCONTRACTS

6. TIME

7. PRICE

8. CHANGES

9. PAYMENT

10. INDEMNITY, INSURANCE, AND BONDS

11. SUSPENSION, NOTICE TO CURE, AND TERMINATION

12. DISPUTE MITIGATION AND RESOLUTION

13. MISCELLANEOUS

14. CONTRACT DOCUMENTS

ARTICLE 1 AGREEMENT

Contract Number: [_____] Project ID: [_____]

This Agreement is between

OWNER

(Name, legal status and address) and

CONSTRUCTOR

(Name, legal status and address)

ConsensusDocs® 200 - Standard Agreement and General Conditions Between Owner and Constructor - © 2011, Revised April 2018. THIS DOCUMENT MAY HAVE BEEN MODIFIED. The ConsensusDocs technology platform creates a redline comparison to the standard language which the purchaser of this contract is authorized to share for review purposes. Consultation with legal and insurance counsel are strongly encouraged. You may only make copies of finalized documents for distribution to parties in direct connection with this contract. Any other uses are strictly prohibited.

for construction and services in connection with the following

PROJECT

(Name and address or location)

Design Professional is (Name, address and other information)

The Owner’s Designated Representative:

(Name, address and other information)

The Constructor’s Designated Representative: (Name, address and other information)

The Design Professional’s Designated Representative: (Name, address and other information

ARTICLE 2 GENERAL PROVISIONS

2.1 PARTIES’ RELATIONSHIP Each Party agrees to act on the basis of mutual trust, good faith, and fair dealing, and perform in an economical and timely manner. The Parties shall each endeavor to promote harmony and cooperation among all Project participants.

2.1.1 Constructor represents that it is an independent contractor and that it is familiar with the type of Work it is undertaking.

2.1.2 Neither Constructor nor any of its agents or employees shall act on behalf of or in the name of Owner.

2.1.3 In accordance with the specific requirements of the Contract Documents set forth below, the Owner agrees to furnish or approve, in a timely manner, information required by the Constructor and to make payments to the Constructor.

2.2 ETHICS Each Party shall perform with integrity. Each shall: (a) avoid conflicts of interest; and (b) promptly disclose to the other Party any conflicts that may arise. Each Party warrants it has not and shall

ConsensusDocs® 200 - Standard Agreement and General Conditions Between Owner and Constructor - © 2011, Revised April 2018. THIS DOCUMENT MAY HAVE BEEN MODIFIED. The ConsensusDocs technology platform creates a redline comparison to the standard language which the purchaser of this contract is authorized to share for review purposes. Consultation with legal and insurance counsel are strongly encouraged. You may only make copies of finalized documents for distribution to parties in direct connection with this contract. Any other uses are strictly prohibited.

not pay or receive any contingent fees or gratuities to or from the other Party, including its agents, officers, employees, Subcontractors, Sub-subcontractors, Suppliers, or Others to secure preferential treatment.

2.3 DESIGN PROFESSIONAL

2.3.1 Owner, through its Design Professional, shall provide all architectural and engineering design services necessary for the completion of the Work excluding, however, (a) design services delegated to Constructor in accordance with §3.15, and (b) services within the construction means, methods, techniques, sequences, and procedures employed by Constructor, its Subcontractors and Sub-subcontractors in connection with their construction operations.

2.3.2 Owner shall obtain from Design Professional either a license for Constructor and Subcontractors to use the design documents prepared by Design Professional or ownership of the copyrights for such design documents. Owner shall indemnify and hold harmless Constructor against any suits or claims of infringement of any copyrights or licenses arising out of the use of the design documents for the Project.

2.3.3 The Constructor, Subcontractors, Sub-subcontractors, and material or equipment suppliers are authorized to use and reproduce applicable portions of the Drawings, Specifications and other documents prepared by the Design Professional and the Design Professional’s subconsultants appropriate to and for use in the execution of their Work under the Contract Documents. All copies made under this authorization shall bear the statutory copyright notice, if any, shown on the Drawings, Specifications and other documents prepared by the Design Professional and the Design Professional’s subconsultant.

2.3.4 Submittal or distribution to meet official regulatory requirements or for other purposes in connection with this Project is not to be construed as publication in derogation of the Design Professional’s or Design Professional’s subconsultants’ copyrights or other reserved rights.

2.4 DEFINITIONS

2.4.1 “Agreement” means this University System of New Hampshire/ConsensusDocs 200 Standard Agreement and General Conditions Between Owner and Constructor (Lump Sum), as modified, and exhibits and attachments as listed in ARTICLE 14.

2.4.2 “Business Day” means all Days, except weekends and official federal or state holidays where the Project is located.

2.4.3 A “Change Order” is a written order signed by the Parties after execution of this Agreement, indicating a change in the scope of the Work, Contract Price, or Contract Time, including substitutions proposed by Constructor and accepted by Owner.

2.4.4 The “Contract Documents” consist of (a) this Agreement; (b) documents listed in §14.1 as existing contract documents; (c) drawings, specifications, addenda issued and acknowledged before execution of this Agreement; (d) information furnished by Owner pursuant to §3.13.4; and (e) Change Orders, Interim Directives, and amendments issued in accordance with this Agreement.

2.4.5 “Contract Price” is the amount indicated in §7.1 and represents full compensation for performance by the Constructor of the Work in conformance with the Contract Documents.

2.4.6 “Contract Time” is the period between the Date of Commencement and the total time authorized to achieve Final Completion in §6.1.1.

ConsensusDocs® 200 - Standard Agreement and General Conditions Between Owner and Constructor - © 2011, Revised April 2018. THIS DOCUMENT MAY HAVE BEEN MODIFIED. The ConsensusDocs technology platform creates a redline comparison to the standard language which the purchaser of this contract is authorized to share for review purposes. Consultation with legal and insurance counsel are strongly encouraged. You may only make copies of finalized documents for distribution to parties in direct connection with this

2.4.7 “Constructor” is the person or entity identified in ARTICLE 1. References to General Contractor or Contractor in the Contract Documents may be a reference to Constructor.

2.4.8 “Cost of the Work” means the costs and discounts specified in §8.3

2.4.9 “Date of Commencement” means the date of commencement as identified in the notice to proceed.

2.4.10 “Day” means a calendar day.

2.4.11 “Defective Work” is any portion of the Work that does not conform to the requirements of the Contract Documents.

2.4.12 “Design Professional” means the licensed architect or engineer, and its consultants, retained by Owner to perform design services for the Project.

2.4.13 “Final Completion” occurs on the date when Constructor's obligations under this Agreement are complete and accepted by Owner and final payment becomes due and payable. This date shall be confirmed by a Certificate of Final Completion signed by the Parties.

2.4.14 “Hazardous Material” is any substance or material identified now or in the future as hazardous under the Law, or any other substance or material that may be considered hazardous or otherwise subject to statutory or regulatory requirement governing handling, transportation, disposal, or cleanup.

2.4.15 “Interim Directive” is a written order containing Work instructions directed by Owner pursuant to §8.2 and that is signed by Owner after execution of this Agreement and before Substantial Completion. “

2.4.16 “Law” means federal, state, or local law, ordinance, code, rule, and regulations applicable to the Work with which Constructor must comply that are enacted as of the Agreement date.

2.4.17 “Others” means Owner’s other: (a) contractors/constructors, (b) suppliers, (c) subcontractors, sub-subcontractors, or suppliers of (a) and (b); and others employed directly or indirectly by (a), (b), or (c) or individuals for whose acts any of them may be liable.

2.4.18 “Overhead” means (a) payroll costs, burden, and other reasonable compensation of Constructor’s employees in Constructor's principal and branch offices; and (b) general and administrative expenses of Constructor's principal and branch offices.

2.4.19 “Owner” is the person or entity identified in ARTICLE 1 and includes Owner’s Representative.

2.4.20 The “Parties” are collectively Owner and Constructor.

2.4.21 The “Project,” as identified in ARTICLE 1, is the building, facility, or other improvements for which Constructor is to perform Work under this Agreement. It may also include construction by Owner or Others.

2.4.22 “Related Party” means a parent, subsidiary, affiliate or other entity having common ownership or management with the Constructor; any entity in which any stockholder in, or management employee of, the Constructor owns any interest in excess of ten percent in the aggregate; or any

ConsensusDocs® 200 - Standard Agreement and General Conditions Between Owner and Constructor - © 2011, Revised April 2018. THIS DOCUMENT MAY HAVE BEEN MODIFIED. The ConsensusDocs technology platform creates a redline comparison to the standard language which the purchaser of this contract is authorized to share for review purposes. Consultation with legal and insurance counsel are strongly encouraged. You may only make copies of finalized documents for distribution to parties in direct connection with this contract. Any other uses are strictly prohibited.

person or entity which has the right to control the business or affairs of the Constructor. The term “related party” includes any member of the immediate family of any person identified above.

2.4.23 The “Schedule of the Work” is the document prepared by Constructor that specifies the dates on which Constructor plans to begin and complete various parts of the Work, including dates on which information and approvals are required from Owner.

2.4.24 A “Subcontractor” is a person or entity retained by Constructor as an independent contractor to provide the labor, materials, equipment, or services necessary to complete a specific portion of the Work. The term Subcontractor does not include Design Professional or Others.

2.4.25 “Substantial Completion” of the Work, or of a designated portion, occurs on the date when the Work is sufficiently complete in accordance with the Contract Documents so that Owner may occupy or utilize the Project, or a designated portion, for the use for which it is intended, without unapproved disruption. This date shall be confirmed by a Certificate of Substantial Completion signed by the Parties.

2.4.26 A “Sub-subcontractor” is a person or entity who has an agreement with a Subcontractor, another Sub-subcontractor, or Supplier to perform a portion of the Subcontractor’s Work or to supply material or equipment.

2.4.27 A “Supplier” is a person or entity retained by Constructor to provide material or equipment for the Work.

2.4.28 “Terrorism” means a violent act, or an act that is dangerous to human life, property, or infrastructure, that is committed by an individual or individuals and that appears to be part of an effort to coerce a civilian population or to influence the policy or affect the conduct of any government by coercion. Terrorism includes, but is not limited to, any act certified by the United States government as an act of terrorism pursuant to the Terrorism Risk Insurance Act, as amended.

2.4.29 “Work” means the construction and services necessary or incidental to fulfill Constructor's obligations for the Project in accordance with and reasonably inferable from the Contract Documents.

The Work may refer to the whole Project or only a part of the Project if work is also being performed by Owner or Others.

2.4.30 “Worksite” means the area of the Project location identified in ARTICLE 1 where the Work is to be performed.

ARTICLE 3 CONSTRUCTOR'S RESPONSIBILITIES

Constructor shall use its diligent efforts to perform the Work in an expeditious manner consistent with the Contract Documents. Such Work includes furnishing construction administration and management services.

3.1 GENERAL RESPONSIBILITIES

3.1.1 Constructor shall provide all labor, materials, equipment, and services necessary to complete the Work, all of which shall be provided in full accord with the Contract Documents and shall include any Work reasonably inferable from the Contract Documents.

3.1.1.1 The Constructor shall be responsible for determining that all materials furnished for the Work meet all requirements of the Contract Documents. If the Design Professional reasonably

ConsensusDocs® 200 - Standard Agreement and General Conditions Between Owner and Constructor - © 2011, Revised April 2018. THIS DOCUMENT MAY HAVE BEEN MODIFIED. The ConsensusDocs technology platform creates a redline comparison to the standard language which the purchaser of this contract is authorized to share for review purposes. Consultation with legal and insurance counsel are strongly encouraged. You may only make copies of finalized documents for distribution to parties in direct connection with this contract. Any other uses are strictly prohibited.

believes that a material proposed by the Constructor, but not specified by brand name and grade or model designation, may not comply with all such requirements, the Design Professional may require the Constructor to produce, at the Constructor’s expense, reasonable evidence of such compliance. This provision shall not require the Constructor to pay for periodic testing of different batches of the same material, unless such testing is specifically required by the Contract Documents, to be performed at the Constructor’s expense.

3.1.1.2 If a manufacturer’s name, trade name or proprietary designation is used in the Contract Documents in connection with materials or products to be furnished under this Agreement, the Constructor shall furnish the product of the named manufacturer, except as follows:

3.1.1.2.1 Where the words “or equal” are used after such manufacturer’s name, trade name or proprietary designation, Constructor’s proposed substitutions will be accepted only if they are, in the opinion of the Design Professional, proved equal to the specified material or product through the submittal of comparative manufacturer’s information or as otherwise provided in §3.1.1.1. The Constructor shall inform the Design Professional in writing of the proposed substitution and request approval thereof prior to or at the time the material or product is submitted for approval. Written approval by the Design Professional shall be required for the acceptance of any such substitution.

3.1.1.2.2 Where the words “or equal” are not used after such manufacturer’s name, trade name or proprietary designation, Constructor proposed substitutions may be accepted or rejected whether or not they are or can be, in the opinion of the Design Professional, proved equal to the specified material or product through the submittal of comparative manufacturer’s information or as otherwise provided in §3.1.1.1. The Constructor shall inform the Design Professional in writing of the proposed substitution and request approval thereof prior to or at the time the material or product is submitted for approval. Written approval by the Design Professional shall be required for the acceptance of any such substitution.

3.1.1.3 If the Constructor proposes to use a material which, while suitable for the intended use, deviates in any way from the detailed requirements of the Contract Documents, the Constructor shall inform the Design Professional in writing as to the nature of such deviations at the time the material is submitted for approval, and shall request written approval of the deviation from the requirements of the Contract Documents. Written approval by the Design Professional shall be required for the acceptance of any such deviation.

3.1.1.4 The Contract Documents are intended to produce a building of consistent character and quality of design. All components of the building including visible items of mechanical and electrical equipment have been selected to produce a coordinated design in relation to the overall appearance of the building. The Design Professional will judge the design and appearance of proposed substitutes based on their appropriateness in relation to the overall design of the project, as well as for their intrinsic merits. The Design Professional will not approve as equal to materials specified, proposed substitutions which, in the Design Professional’s opinion, would be out of character, obtrusive, or otherwise inconsistent with the character or quality of design of the Project. In order to permit coordinated design of color and finishes the Contractor shall, if required by the Design Professional, furnish the substituted material in any color, finish, texture or pattern which would have been available from the manufacturer originally specified, at no additional cost to the Owner.

3.1.1.5 Any additional cost, loss, or damage arising from the substitution of any materials or products for those originally specified shall be borne by the Constructor, notwithstanding approval or acceptance of such substitution by the Owner or the Design Professional, unless

ConsensusDocs® 200 - Standard Agreement and General Conditions Between Owner and Constructor - © 2011, Revised April 2018. THIS DOCUMENT MAY HAVE BEEN MODIFIED. The ConsensusDocs technology platform creates a redline comparison to the standard language which the purchaser of this contract is authorized to share for review purposes. Consultation with legal and insurance counsel are strongly encouraged. You may only make copies of finalized documents for distribution to parties in direct connection with this contract. Any other uses are strictly prohibited.

such substitution was made at the written request or direction of the Owner or the Design Professional.

3.1.2 Unless the Contract Documents instruct otherwise, Constructor shall solely be responsible for and have control over the construction means, methods, techniques, sequences, procedures, site security and safety precautions, and for coordinating all portions of the Work under the Agreement.

3.1.3 Constructor shall perform Work only within locations allowed by the Contract Documents, Law, and applicable permits unless otherwise directed by the Owner.

3.2 CONSTRUCTION PERSONNEL AND SUPERVISION

3.2.1 Constructor shall provide competent supervision for the performance of the Work. Before commencing the Work, or making a change in the supervisory personnel, the Constructor shall notify Owner in writing of the name and qualifications of its proposed superintendent(s) and project manager so Owner may review their qualifications. If, for reasonable cause, Owner refuses to approve an individual, or withdraws its approval after giving it, Constructor shall name a different superintendent or project manager for Owner's review. Any disapproved superintendent shall not perform in that capacity thereafter at the Worksite. The superintendent shall represent the Constructor, and communications given to the superintendent shall be as binding as if given to the Constructor. The Parties shall use best efforts to confirm communications in writing.

3.2.2 Constructor shall be responsible to Owner for acts or omissions of the Constructor’s employees, Subcontractors and their agents and employees, and other persons or entities performing portions of the Work for or on behalf of the Constructor or any of its Subcontractors and Suppliers.

3.2.3 Constructor shall permit only fit and skilled persons to perform the Work. Constructor shall enforce safety procedures, strict discipline, and good order among persons performing the Work. If Owner determines that a particular person does not follow safety procedures, or is unfit or unskilled for the assigned Work, Constructor shall immediately reassign the person upon receipt of Owner's written notice to do so.

3.2.4 CONSTRUCTOR'S REPRESENTATIVE Constructor's Representative shall possess full authority to receive instructions from Owner and to act on those instructions.

3.2.5 The Constructor shall coordinate and supervise the work performed by Subcontractors to ensure that the Work is carried out without conflict between trades and so that no trade, at any time, causes delay to the general progress of the Work. The Constructor and all Subcontractors at all times shall afford each trade, any separate contractor, or the Owner, every reasonable opportunity for the installation of their work and the storage of materials, subject to the specific limitations or restrictions of a particular site.

3.3 COOPERATION WITH WORK OF OWNER AND OTHERS

3.3.1 Owner may perform work at the Worksite directly or by Others. Any agreements with Others to perform construction or operations related to the Project shall include provisions pertaining to insurance, indemnification, waiver of subrogation, consequential damages, coordination, interference, cleanup, and safety that are substantively the same as the corresponding provisions of this Agreement.

3.3.2 If Owner elects to perform work at the Worksite directly or by Others, the Parties shall coordinate the activities of all forces at the Worksite and agree upon fair and reasonable schedules and operational procedures for Worksite activities. Owner shall require each separate contractor to

ConsensusDocs® 200 - Standard Agreement and General Conditions Between Owner and Constructor - © 2011, Revised April 2018. THIS DOCUMENT MAY HAVE BEEN MODIFIED. The ConsensusDocs technology platform creates a redline comparison to the standard language which the purchaser of this contract is authorized to share for review purposes. Consultation with legal and insurance counsel are strongly encouraged. You may only make copies of finalized documents for distribution to parties in direct connection with this contract. Any other uses are strictly prohibited.

cooperate with Constructor and to assist with the coordination of activities and the review of construction schedules and operations. In accordance with §6.3, Contract Price and Contract Time may be equitably adjusted for changes resulting from the coordination of construction activities, and the Schedule of the Work shall be revised accordingly.

3.3.3 With regard to the work of Owner and Others, Constructor shall: (a) proceed with the Work in a manner that does not hinder, delay, or interfere with the work of Owner or Others or cause the work of Owner or Others to become defective; (b) afford Owner and Others reasonable access for introduction and storage of their materials and equipment and performance of their activities; and (c) coordinate Constructor's Work with theirs.

3.3.4 Before proceeding with any portion of the Work affected by the construction or operations of Owner or Others, Constructor shall give Owner prompt written notification of any defects Constructor discovers in their work which will prevent the proper execution of the Work. Constructor's obligations in this subsection do not create a responsibility for the work of Owner or Others but are for the purpose of facilitating the Work. If Constructor does not notify Owner of defects interfering with the performance of the Work, Constructor acknowledges that the work of Owner or Others is not defective and is acceptable for the proper execution of the Work. Following receipt of written notice from Constructor of defects, Owner shall promptly issue an Interim Directive informing Constructor what action, if any, Constructor shall take regarding the defects.

3.4 CONTRACT DOCUMENT REVIEW

3.4.1 Before commencing the Work, Constructor shall examine and compare the drawings and specifications with information furnished in the Contract Documents, relevant field measurements made by Constructor, and any visible conditions at the Worksite affecting the Work.

3.4.1.1 Requests by the Constructor for additional information relative to the Contract Documents (RFIs) shall be submitted simultaneously to the Owner and Design Professional in writing, on a form prepared or approved by the Design Professional, and shall include a detailed statement indicating the specific drawings or specifications in need of clarification and the nature of the clarification requested, such as supplementary drawings or specifications, or review and approval of product data, samples or sketches submitted by the Constructor. If mutually agreed upon by the Design Professional, Constructor and Owner, “in writing” may include fax transmissions, electronic mail, or other documentable communication methods.

3.4.1.2 RFIs shall be submitted in a timely manner so as to cause no delay in the progress of the Work, and to allow adequate time for review and response prior to the date on which the Constructor’s current schedule of submittals requires a subsequent submittal which is dependent on the information requested. Unless another period of time is reasonably requested by the Design Professional and agreed to at the time of submittal, the Design Professional shall respond to each RFI within ten Business Days after receiving it.

3.4.2 Should Constructor discover any defects which shall include but not be limited to errors, omissions, or inconsistencies in the Contract Documents, Constructor shall promptly report them to Owner and Design Professional. It is recognized, however, that Constructor is not acting in the capacity of a licensed design professional, and that Constructor's examination is to facilitate construction and does not create an affirmative responsibility to detect errors, omissions, or inconsistencies or to ascertain compliance with applicable laws, statutes, ordinances, building codes, and rules and regulations. Following receipt of written notice from Constructor of defects, Owner shall promptly inform Constructor what action, if any, Constructor shall take regarding the defects.

ConsensusDocs® 200 - Standard Agreement and General Conditions Between Owner and Constructor - © 2011, Revised April 2018. THIS DOCUMENT MAY HAVE BEEN MODIFIED. The ConsensusDocs technology platform creates a redline comparison to the standard language which the purchaser of this contract is authorized to share for review purposes. Consultation with legal and insurance counsel are strongly encouraged. You may only make copies of finalized documents for distribution to parties in direct connection with this contract. Any other uses are strictly prohibited.

3.4.3 Constructor shall have no liability for errors, omissions, or inconsistencies discovered under this section, unless Constructor knowingly fails to report a recognized problem to Owner or request supplementary instructions when a problem is identified. If Constructor proceeds with the Work without first obtaining such supplementary instructions, the Constructor shall correct work incorrectly done at the Constructor’s expense.

3.4.4 Constructor may be entitled to adjustments of the Contract Price or Contract Time because of clarifications or instructions arising out of Constructor's reports described in this §3.4.

3.4.5 Nothing in §3.4 shall relieve Constructor of responsibility for its own errors, inconsistencies, or omissions.

3.5 WORKMANSHIP

3.5.1 The Work shall be executed in accordance with the Contract Documents in a workmanlike manner. All materials used in the Work shall be furnished in sufficient quantities to facilitate the proper and expeditious execution of the Work and shall be new except as otherwise provided in the Contract Documents.

3.5.2 Work for which no explicit quality of standards of materials and/or workmanship is defined in the Contract Documents shall be of good quality for the intended use and consistent with the quality of surrounding work and of the construction of the Project generally.

3.5.3 All manufactured articles, materials and equipment shall be applied, installed, connected, erected, used, cleaned, and conditioned in accordance with the manufacturers’ written instructions, unless specifically indicated otherwise in the Contract Documents.

3.5.4 Where the Work is to fit with existing conditions or work to be performed by Others, the Constructor shall join the Work fully and completely with such conditions or work, unless otherwise specified.

3.5.5 The Constructor shall be responsible for inspection of portions of Work already performed to determine that such portions are in proper condition to receive subsequent Work

3.5.6 The Constructor shall study and compare all Drawings and verify all figures shown thereon before laying out or constructing the Work. The Constructor shall be responsible for errors in its work and the work of its Subcontractors that might reasonably have been avoided thereby. The Constructor shall establish and be responsible for the accuracy of all lines, grades, measurements, levels, column lines, wall and partition lines required by the various Subcontractors in laying out their Work and shall protect and preserve all permanent bench and other markers. Checking of the figures or layout by the Design Professional shall not relieve the Constructor of these responsibilities

3.6 MATERIALS FURNISHED BY OWNER OR OTHERS

3.6.1 If the Work includes installation of materials or equipment furnished by Owner or Others, it shall be the responsibility of Constructor to examine the items so provided and thereupon handle, store, and install the items, unless otherwise provided in the Contract Documents, with such skill and care as to provide a satisfactory and proper installation. Loss or damage due to acts or omissions of Constructor shall be the responsibility of Constructor and may be deducted from any amounts due or to become due Constructor. Any defects discovered in such materials or equipment shall be reported at once to Owner. Following receipt of written notice from Constructor of defects, Owner shall promptly inform Constructor what action, if any, Constructor shall take regarding the defects.

3.7 TESTS AND INSPECTIONS

ConsensusDocs® 200 - Standard Agreement and General Conditions Between Owner and Constructor - © 2011, Revised April 2018. THIS DOCUMENT MAY HAVE BEEN MODIFIED. The ConsensusDocs technology platform creates a redline comparison to the standard language which the purchaser of this contract is authorized to share for review purposes. Consultation with legal and insurance counsel are strongly encouraged. You may only make copies of finalized documents for distribution to parties in direct connection with this

3.7.1 Constructor shall schedule all tests, inspections and approvals of the Work required by the Contract Documents or by laws, ordinances, rules, regulations, or orders of public authorities having jurisdiction at an appropriate time so as to not delay the progress of the Work. Constructor shall give proper notice to all required parties of such tests, approvals, and inspections. If feasible, Owner and Others may timely observe the tests at the normal place of testing. Except as provided in §3.7.3, Owner shall bear all expenses associated with tests, inspections, and approvals required by the Contract Documents, which shall be conducted by an independent testing laboratory or entity retained by Owner. Unless otherwise required by the Contract Documents, required certificates of testing, approval, or inspection shall be secured by Constructor and promptly delivered to Owner.

3.7.2 If Owner or appropriate authorities determine that tests, inspections, or approvals in addition to those required by the Contract Documents will be necessary, Constructor shall arrange for the procedures and give timely notice to Owner and Others who may observe the procedures. Costs of the additional tests, inspections, or approvals are at Owner's expense except as provided in the subsection below.

3.7.3 If the procedures described in the two subsections immediately above indicate that portions of the Work fail to comply with the Contract Documents, Constructor shall be responsible for costs of correction and retesting.

3.8 WARRANTY

3.8.1 Constructor warrants that all materials and equipment furnished shall be new unless otherwise specified, of good quality, in conformance with the Contract Documents, and free from defective workmanship and materials. At Owner's request, Constructor shall furnish satisfactory evidence of the quality and type of materials and equipment furnished. Constructor further warrants that the Work shall be free from material defects not intrinsic in the design or materials required in the Contract Documents. Constructor's warranty does not include remedies for defects or damages caused by normal wear and tear during normal usage, use for a purpose for which the Project was not intended, improper or insufficient maintenance, modifications performed by Owner or others, or abuse.

Constructor's warranty shall commence on the Date of Substantial Completion of the Work, or of a designated portion. Work not conforming to these requirements, including substitutions not properly approved and authorized, may be considered defective.

3.8.2 With respect to any portion of Work first performed after Substantial Completion, Constructor's warranty obligation shall be extended by the period of time between Substantial Completion and the actual performance of the later Work.

3.8.3 Constructor shall obtain from its Subcontractors and Suppliers any special or extended warranties required by the Contract Documents. Constructor's liability for such warranties shall be limited to the one-year correction period as provided in the section below. After that period, Constructor shall provide reasonable assistance to Owner in enforcing the obligations of Subcontractors or Suppliers for such extended warranties.

3.9 CORRECTION OF WORK WITHIN ONE YEAR

3.9.1 If before Substantial Completion and within one year after the date of Substantial Completion of the Work, any Defective Work is found, Owner shall promptly notify Constructor in writing. Unless Owner provides written acceptance of the condition, Constructor shall promptly correct the Defective Work at its own cost and time and bear the expense of additional services required for correction of any Defective Work for which it is responsible. If within the one-year correction period Owner discovers and does not promptly notify Constructor or give Constructor an opportunity to test or correct Defective Work as reasonably requested by Constructor, Owner waives Constructor's

ConsensusDocs® 200 - Standard Agreement and General Conditions Between Owner and Constructor - © 2011, Revised April 2018. THIS DOCUMENT MAY HAVE BEEN MODIFIED. The ConsensusDocs technology platform creates a redline comparison to the standard language which the purchaser of this contract is authorized to share for review purposes. Consultation with legal and insurance counsel are strongly encouraged. You may only make copies of finalized documents for distribution to parties in direct connection with this contract. Any other uses are strictly prohibited.

obligation to correct that Defective Work as well as Owner's right to claim a breach of the warranty with respect to that Defective Work.

3.9.2 With respect to any portion of Work first performed after Substantial Completion, the one-year correction period shall commence when that portion of the Work is substantially complete. Correction periods shall not be extended by corrective work performed by Constructor.

3.9.3 If Constructor fails to correct Defective Work within a reasonable time after receipt of written notice from Owner before final payment, Owner may correct it in accordance with Owner's right to carry out the Work. In such case, an appropriate Change Order shall be issued deducting the cost of correcting the Defective Work from payments then or thereafter due Constructor. If payments then or thereafter due Constructor are not sufficient to cover such amounts, Constructor shall pay the difference to Owner.

3.9.4 Constructor’s obligations and liability, if any, with respect to any Defective Work discovered after the one-year correction period shall be determined in accordance with New Hampshire law. If, after the one-year correction period but before the applicable limitation period has expired, Owner discovers any Work which Owner considers Defective Work, Owner shall, unless the Defective Work requires emergency correction, promptly notify Constructor and allow Constructor an opportunity to correct the Work if Constructor elects to do so. If Constructor elects to correct the Work, it shall provide written notice of such intent within 14 Days of its receipt of notice from Owner and shall complete the correction of Work within a mutually agreed timeframe. If Constructor does not elect to correct the Work, Owner may have the Work corrected by itself or others, and, if Owner intends to seek recovery of those costs from Constructor, Owner shall promptly provide Constructor with an accounting of actual correction costs.

3.9.5 If Constructor's correction or removal of Defective Work causes damage to or destroys other completed or partially completed Work or existing buildings, Constructor shall be responsible for the cost of correcting the destroyed or damaged property.

3.9.6 The one-year period for correction of Defective Work does not constitute a limitation period with respect to the enforcement of Constructor's other obligations under the Contract Documents.

3.9.7 At Owner's option and with Constructor's agreement, Owner may elect to accept Defective Work rather than require its removal and correction. In such case, the Contract Price shall be equitably adjusted for any diminution in the value of the Project caused by such Defective Work. Such adjustment shall be effected whether or not final payment has been made.

3.10 CORRECTION OF COVERED WORK

3.10.1 Upon issuance of an Interim Directive, Work that has been covered without a requirement that it be inspected before being covered shall be uncovered for Owner's or Design Professional’s inspection. Owner shall pay for the costs of uncovering and replacement if the Work proves to be in conformance with the Contract Documents, or if the defective condition was caused by Owner or Others. If the uncovered Work proves to be defective, Constructor shall pay the costs of uncovering and replacement.

3.10.2 If any Work is covered contrary to requirements in the Contract Documents, Owner may issue an Interim Directive to uncover the Work for Owner's observation and recover the Work all at Constructor's expense and with no Contract Time adjustment.

3.11 SAFETY

ConsensusDocs® 200 - Standard Agreement and General Conditions Between Owner and Constructor - © 2011, Revised April 2018. THIS DOCUMENT MAY HAVE BEEN MODIFIED. The ConsensusDocs technology platform creates a redline comparison to the standard language which the purchaser of this contract is authorized to share for review purposes. Consultation with legal and insurance counsel are strongly encouraged. You may only make copies of finalized documents for distribution to parties in direct connection with this contract. Any other uses are strictly prohibited.

3.11.1 SAFETY PROGRAMS Constructor holds overall responsibility for safety programs. However, such obligation does not relieve Subcontractors of their safety responsibilities or the requirement to comply with the Law. Constructor shall prevent against injury, loss, or damage to persons or property by taking reasonable steps to protect: (a) its employees and other persons at the Worksite; (b) materials and equipment stored onsite or offsite for use in the Work whether under the care, custody or control of the Constructor or the Constructor’s Subcontractors or Sub-subcontractors; and (c) property located at the Worksite and adjacent to work areas, whether or not the property is part of the Worksite.

3.11.2 CONSTRUCTOR'S SAFETY REPRESENTATIVE Constructor shall designate an individual at the Worksite in its employ as its safety representative. Unless otherwise identified by Constructor in writing to Owner, Constructor’s project superintendent shall serve as its safety representative.

Constructor shall report promptly in writing to Owner all recordable accidents and injuries occurring at the Worksite. When Constructor is required to file an accident report with a public authority, Constructor shall furnish a copy of the report to Owner.

3.11.3 The Constructor shall give notices and comply with applicable laws, ordinances, rules, regulations, and lawful orders of public authorities bearing on safety of persons or property or their protection from damage, injury, or loss.

3.11.4 Damage or loss not insured under property insurance which may arise from the Work, to the extent caused by the actions or inactions or intentionally wrongful acts or omissions of Constructor, or anyone for whose acts Constructor may be liable, shall be promptly remedied by Constructor.

3.11.5 The Constructor shall erect and maintain, as required by existing conditions and performance of the Contract, reasonable safeguards for safety and protection, including posting danger signs and other warnings against hazards, promulgating safety regulations and notifying owners and users of adjacent sites and utilities.

3.11.6 When use or storage of explosives or other hazardous materials or equipment or unusual methods are necessary for execution of the Work, the Constructor shall exercise utmost care and carry on such activities under supervision of properly qualified personnel.

3.11.7 The Constructor shall at all times be responsible for maintaining fire safety on the site, including prompt removal of all combustible rubbish, provision of fire extinguishing apparatus, and other measures and/or services specified herein or required by the State Fire Marshal or other authority having jurisdiction. If such authority determines that the Constructor has failed to provide or maintain adequate fire safety, the Constructor shall provide at its own expense any compensatory services, equipment, or devices required by the authority having jurisdiction including, but not limited to, maintaining a continuous fire watch.

3.11.8 The Constructor shall at all times protect excavations, trenches, buildings, and materials from rainwater, ground water, ice, snow, back-up or leakage of sewers, drains, or other piping, and from water of any other origin and shall remove promptly any accumulation of water. The Contractor shall provide and operate all pumps, piping, and other equipment necessary to this end.

3.11.9 If Owner deems any part of the Work or Worksite unsafe, Owner, without assuming responsibility for Constructor's safety program, may require by Interim Directive, Constructor to stop performance of the Work, take corrective measures satisfactory to Owner, or both. If Constructor does not adopt corrective measures, Owner may perform them and deduct their cost from the Contract Price. Constructor agrees to make no claim for damages, for an increase in the Contract Price or Contract Time based on Constructor's compliance with Owner's reasonable request.

ConsensusDocs® 200 - Standard Agreement and General Conditions Between Owner and Constructor - © 2011, Revised April 2018. THIS DOCUMENT MAY HAVE BEEN MODIFIED. The ConsensusDocs technology platform creates a redline comparison to the standard language which the purchaser of this contract is authorized to share for review purposes. Consultation with legal and insurance counsel are strongly encouraged. You may only make copies of finalized documents for distribution to parties in direct connection with this

3.12 EMERGENCIES

3.12.1 Prior to commencement of Work, Constructor shall work with the Owner to establish an emergency communication plan, and in an emergency affecting the safety of persons or property, Constructor shall act in a reasonable manner to prevent threatened damage, injury, or loss. Any change in the Contract Price or Contract Time resulting from the actions of Constructor in an emergency situation shall be determined as provided in ARTICLE 8.

3.13 HAZARDOUS MATERIALS

3.13.1 Constructor shall not be obligated to commence or continue Work until any Hazardous Material discovered at the Worksite has been removed, rendered, or determined to be harmless by Owner as certified by an independent testing laboratory and approved by the appropriate governmental agency.

3.13.2 If after commencing the Work, Hazardous Material is discovered at the Worksite, Constructor shall be entitled to immediately stop Work in the affected area. Constructor shall promptly report the condition to Owner, Design Professional, and, if required, the governmental agency with jurisdiction.

3.13.3 Constructor shall not resume nor be required to continue any Work affected by any Hazardous Material without written mutual agreement between the Parties after the Hazardous Material has been removed or rendered harmless and only after approval, if necessary, of the governmental agency with jurisdiction.

3.13.4 Owner shall be responsible for retaining an independent testing laboratory to determine the nature of the material encountered and whether the material requires corrective measures or remedial action. Such measures shall be the sole responsibility of Owner and shall be performed in a manner minimizing any adverse effect upon the Work.

3.13.5 If Constructor incurs additional costs or is delayed due to the presence or remediation of Hazardous Material, Constructor shall be entitled to an equitable adjustment in the Contract Price or the Contract Time.

3.13.6 To the extent not caused by the actions or inactions or intentionally wrongful acts or omissions of Constructor, its Subcontractors and Sub-subcontractors, and the agents, officers, directors, and employees of each of them, Owner shall defend, indemnify, and hold harmless Constructor, its Subcontractors and Sub-subcontractors, and the agents, officers, directors, and employees of each of them, from and against all claims, damages, losses, costs, and expenses, including but not limited to reasonable attorneys' fees, costs, and expenses incurred in connection with any dispute resolution procedure, arising out of or relating to the performance of the Work in any area affected by Hazardous Material.

3.13.7 MATERIALS BROUGHT TO THE WORKSITE

3.13.7.1 Safety Data Sheets (SDS) as required by Law and pertaining to materials or substances used or consumed in the performance of the Work, whether obtained by Constructor, Subcontractors, Owner, or Others, shall be maintained at the Worksite by Constructor and made available to Owner, Subcontractors, and Others.

3.13.7.2 Constructor shall be responsible for the proper delivery, handling, application, storage, removal, and disposal of all materials and substances brought to the Worksite by Constructor and used or consumed in the performance of the Work. Upon the issuance of the Certificate of Substantial Completion, Owner shall be responsible for materials and substances brought to the

ConsensusDocs® 200 - Standard Agreement and General Conditions Between Owner and Constructor - © 2011, Revised April 2018. THIS DOCUMENT MAY HAVE BEEN MODIFIED. The ConsensusDocs technology platform creates a redline comparison to the standard language which the purchaser of this contract is authorized to share for review purposes. Consultation with legal and insurance counsel are strongly encouraged. You may only make copies of finalized documents for distribution to parties in direct connection with this contract. Any other uses are strictly prohibited.

Worksite by Constructor if such materials or substances are required by the Contract Documents.

3.13.7.3 To the extent caused by the actions or inactions or intentionally wrongful acts or omissions of Constructor, its agents, officers, directors, and employees, Constructor shall indemnify and hold harmless Owner, its agents, officers, directors, and employees, from and against any and all claims, damages, losses, costs, and expenses, including but not limited to attorneys' fees, costs, and expenses incurred in connection with any dispute resolution procedure, arising out of or relating to the delivery, handling, application, storage, removal, and disposal of all materials and substances brought to the Worksite by Constructor.

3.13.8 Section 3.13 in its entirety shall survive the completion of the Work or Agreement termination.

3.14 SUBMITTALS

3.14.1 Constructor shall submit to Owner and Design Professional a submittal log with a proposed submittal schedule, all shop drawings, samples, product data,…