This invitation to bid document is issued by the University System of New Hampshire (USNH), representing the University of New Hampshire (UNH) Facilities Project Management, for the Memorial Union Building Elevator Controller Replacements project located at 83 Main Street, Durham, New Hampshire. The scope of work includes control upgrades for two elevators in the Memorial Union Building, along with supporting electrical, mechanical, and finish upgrades, with the east elevator to be completed prior to work on the west elevator. The project maintains building operations during construction. Construction is scheduled to begin on May 17, 2027, and be completed by August 20, 2027. The document does not specify a mandatory pre-bid meeting, though bidders are required to visit the site and examine all contract documents. Interpretations and addenda will be posted to the Q&A Board no less than four business days prior to the bid opening date. Interested parties should submit bids on Document 00310 - Bid Form using the Jaggaer eSource tool. The contract will be awarded to the lowest, most responsive and responsible qualified bidder, with written notice of acceptance to be made within thirty days after bid opening.
Bid security in the form of a bid bond, bank draft, or certified check equal to five percent of the base bid is required for this project, as the contract value exceeds $100,000. Bidders must also provide performance and payment bonds each in the amount of 100 percent of the contract sum. The USNH uses a modified form of ConsensusDocs 200 Standard Agreement and General Conditions Between Owner and Constructor (Lump Sum), and the UNH Planning, Design and Construction Guidelines will be part of the contract. Bidders must submit a statement of qualifications on Document 00420 and provide project data forms for at least three similar projects completed within the last three years. All contractors and subcontractors must comply with current USNH health, safety, and environmental protocols, as well as all applicable federal and State of New Hampshire requirements. The design professionals for the project are Joe Morrissey of Elevator Consulting Associates and Mark Gianniny of Portsmouth Architects, PLLC, with Karen Sayers serving as the USNH Owner's Agent and Richard Saklad as the UNH Owner's Representative.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rev. 01/14/2020 1
University System of New Hampshire Event # 2120271006
DOCUMENT 00020 INVITATION TO BID
Project: UNH Memorial Union Building Elevator Controller Replacements, 2023-0076 University of New Hampshire Durham, New Hampshire
Project Site: Memorial Union Building 83 Main Street
Durham, New Hampshire
Owner: University of New Hampshire of the University System of New Hampshire
Owner's Agent: Karen Sayers, Contract and Sourcing Specialist USNH Procurement Services
Farnum Hall 28 College Drive Concord, NH 03301
Telephone: 603-862-6187 Email: karen.sayers@usnh.edu
Owner’s Rep.: Richard Saklad, Project Manager UNH Facilities Project Management
Design Professional: Joe Morrissey Elevator Consulting Associates
3 Charmarand Row Londonderry, NH 030531
Mark Gianniny Portsmouth Architects,PLLC 4 Market St Ste 3 Portsmouth, New Hampshire 03801-3983
Construction Schedule: Construction Begins 5/17/2027 Construction Complete 8/20/2027
Health, Safety & Environmental Protocols All contractors, sub-contractors, design professionals, and other personnel performing work on USNH property shall comply with current USNH health, safety, and environmental protocols, as well as all applicable federal and State of New Hampshire requirements in effect at the time of performance. Campus specific procedures (e.g., site access requirements, screening, PPE, or jobsite practices) will be communicated by the respective campus (UNH, PSU, or KSC) and must be followed for the duration of the work.
Rev. 01/14/2020 2
Purpose
The University System of New Hampshire (hereafter referred to as USNH or Owner) representing the University of New Hampshire (UNH) Facilities Project Management, is requesting bids for UNH Memorial Union Building Elevator Controller Replacements.
Scope of Services
The general scope of work for this project includes Memorial Union Building control upgrades for 2 elevators.
Work also includes supporting electrical, mechanical, and finish upgrades.
The East elevator shall be completed prior to starting work on the West elevator.
The building will remain open and operational while this project is under construction.
General Information
All interested subcontractors, suppliers, distributors, etc. should submit their sub-bids to the bidding contractor(s) of their choice.
Special attention is called to:
• The University System of New Hampshire (USNH) uses a modified form of ConsensusDocs 200 Standard Agreement and General Conditions Between Owner and Constructor (Lump Sum). This document is available on the web in the Buyer Attachments section of this Event.
• The UNH Planning, Design and Construction Guidelines will be a part of this contract and is available at https://scholars.unh.edu/facilities/
• This solicitation package contains a mix of USNH documents and documents provided by the design professional. If any discrepancy is noted between a USNH document and one provided by the design professional, the USNH document shall prevail. In addition, if any discrepancy is noted between a design professional-supplied document and the UNH Planning, Design and Construction Guidelines the UNH standards shall prevail.
• All definitions in the bid, contract, general conditions, supplemental conditions, specifications, and other bidding and contract documents are incorporated herein by reference and are fully applicable hereto.
• For all construction contracts; wherever the word “Contractor” is used, it is also meant to apply to Design/Build firms and CM firms.
• If there is no outside (third party) design engineer on the project, then the word “Owner” should be substituted in any place where the term “design engineer” is stated.
EXAMINATION OF SITE, CONTRACT DOCUMENTS AND GENERAL BID REQUIREMENT
All bidders are expected to visit the site of the proposed work and fully acquaint themselves with the conditions as they exist and shall thoroughly examine the contract documents. Failure of any bidders to visit the site and acquaint themselves with the contract documents shall in no way relieve them from any obligations with respect to their bid.
If a mandatory pre-bid meeting/site inspection is scheduled, (see event timeline), bids will not be accepted from firms that did not attend a mandatory meeting. Business cards will be collected as evidence of attendance.
The Bidder shall be conclusively deemed to have known and seen all facts and circumstances reasonably observable by an experienced contractor visiting the site for the purpose of preparing and submitting a bid.
By submitting a bid, the Bidder agrees that the contract documents are adequate and that the required result can be produced. Should the Bidder find, during examination of the contract documents or after visiting the site, any discrepancies, omissions, ambiguities or conflicts in or among the contract documents, or be in doubt as to their meaning, the Bidder shall so notify the Owners Agent and request interpretation.
The successful Bidder shall furnish any and all extras and make any changes needed to produce the required result to https://scholars.unh.edu/facilities/
Rev. 01/14/2020 3 the satisfaction of the Owners Representative. The successful Bidder will be reimbursed for extra work as provided under "Changes in the Work" in the General Conditions of the Contract.
INTERPRETATIONS AND ADDENDA
No interpretation of the meaning of the drawings, specifications, or other contract documents will be made to any bidder orally. Any and all such interpretations and any supplemental instructions will be on the Q&A Board or as a supplemental attachment. Anything stated orally yet not confirmed in the Event shall be considered as not having been said.
Interpretations or supplemental attachments will be posted in the Event not less than four (4) business days, prior to the bid opening date. Failure of any bidder to review the Q&A Board and supplemental attachments shall not relieve him/her from any obligation under his/her bid as submitted. All supplemental attachments issued shall become part of the contract documents.
INSURANCE
Simultaneously with delivery of the executed contract, the successful bidder shall deliver to the Owner’s Agent the certificate of insurance required by USNH Insurance Requirements of Construction Contract (Rev 02/15/2022).
This document is available in the Buyer Attachments section of this event online. All limits will be required unless changes are made in Document 00100 Instructions to Bidders. No work will begin on campus until USNH is in receipt of the Certificate of Insurance.
BID SECURITY AND BONDING
Bid security and performance and payment bonds are required for all projects of $100,000 or greater.
USNH bond documents, 00410, 00610 and 00620 are available in the Buyer Attachments section.
Other bid bond formats are not acceptable.
Original bid security documents and bonds shall be delivered to:
UNH Project Manager Richard Saklad at: Richard.Saklad@unh.edu USNH will only accept electronic bonds
END OF SECTION 00020
Rev. 01/14/2020 4
DOCUMENT 00100 INSTRUCTIONS TO BIDDERS
PREPARATION OF BIDS
The word "OWNER" as used in this document means the University of New Hampshire of the University System of New Hampshire.
The word “Bidder” as used in this document means the qualified (contractor submitting a bid on the required bid form.
General Requirements
All documents will be submitted as a single attachment in PDF format under Supplier Attachments. Attachments must not exceed 50 MB/each. The submission PDF document should be in the prescribed order in the Format requirements below. The information presented under each heading should strictly conform to the information and/or issues requested.
PRICING
Base bid shall be submitted on Document 00310 – Bid Form and entered in the Item Section under the Base Bid Group.
ALTERNATES
Attention is called to other applicable sections of the specifications and drawings (including addenda, if any) for the description of the alternates, and to the fact that the prices of selected alternates are taken into consideration in determining the low bid.
Alternate bids shall be submitted on 0310 Attachment 3 and entered in the Item section under the Alternates Group.
Alternate pricing shall also be entered in the Item section of the Jaggaer eSource tool. If any discrepancies exist between Attachment 3 and the Jaggaer Item section pricing submitted in the Jaggaer Item section shall prevail.
Bidders must bid on all alternates; the term “No Bid” must not be used. If the price for an alternate does not change the amount of the base bid, the term “No Change” shall be inserted and $0 entered in Jaggaer.
All prices for alternates must be net and shall include all charges for overhead, profit, labor, materials, taxes, insurance, and all other charges of any nature.
Each alternate bid shall state the amounts of any changes in sub-bids, and the names of any sub-bidders proposed to be substituted for any sub-bidder listed under the base contract work per Paragraph 8 of these Instructions to Bidders.
Selection and acceptance of alternate bids shall be made by the Owner to use available funds in the best interest of the project. Alternates are listed on the Bid Form in order of the Owner’s priority and will be accepted in that order as allowed by the available funding, with additive alternates, if any, being considered in the event that the lowest base bid is less than the available funding and deductive alternates, if any, being considered in the event that the lowest base bid exceeds the available funding. The amount of funds available for the award of the contract shall be made public at the commencement of the bid opening. An alternate will be skipped over only in the event that (1) its acceptance would effectively negate an accepted higher priority alternate, or (2) in the case of all bidders, the sum of the base bid plus higher priority alternate bids plus said skipped alternate bid exceeds the available funds, yet lower priority alternates exist which can be accepted within the available funds. The Owner retains the right to accept any or all of the listed alternates and the lowest bid shall be considered to be the lowest sum of the base bid and accepted alternates.
Unlisted alternate bids (contractor’s alternates) shall not be considered in determining the lowest bid. Bidders desiring to have such alternate bids considered in determining the lowest bid should propose them in writing during the bidding period. If accepted by the Owner, they shall be included by addendum in the project documents as listed alternates.
Rev. 01/14/2020 5
SUBSTITUTIONS
Refer to USNH CD200.
SUB-BID LIST
Each bidder shall list on Attachment 1 of the bid the name and bid amount of each sub-bidder whose bid is carried in the base bid under the trades indicated thereon, as well as any other sub-bids which are individually greater than ten percent of the base bid. The stated amount of each listed sub-bid shall include all work identified as "Work Included" in the corresponding division or divisions of the specifications and shall exclude any work identified as "Work Not Included" or "Related Work in Other Divisions".
Sub-Bid Lists will remain confidential. The Owner reserves the right to review the lists and, together with its consultants, evaluate the three apparent lowest bids, but neither the sub-bidders' names nor the amounts of their bids will be divulged to any other party. Upon request of the Owner, the three apparent lowest bidders shall provide the Owner with the addresses and telephone/fax numbers of their listed sub-bidders. The Owner reserves the right to communicate directly with any or all of the listed sub-bidders to confirm the accuracy of any information contained in the sub-bid lists. Any inaccuracy will be grounds for rejection of the applicable bidder’s bid. After the award is made, all sub-bid lists, except for that of the awarded firm, will remain confidential.
Substitutions for listed sub-bidders, or changes in the amounts of their subcontracts from the listed amounts, may be requested by the Bidder only in the event of refusal by the sub-bidder to enter into an agreement on the basis of his bid, documented evidence of arithmetic error, or similar cause beyond the Bidder’s control. If the Bidder requests a decrease in the amount of a listed subcontractor’s bid or substitution of another subcontractor for a listed sub-bidder at a lower price, and the request is approved by the Owner, the contract sum shall be reduced by the difference between the listed and the requested subcontract amounts. If the Bidder requests an increase in the amount of a listed subcontractor’s bid or substitution of another subcontractor for a listed sub-bidder at a higher price, and the request is approved by the Owner, the contract sum shall be unchanged. Any such substitution or change must be approved by the Owner in writing.
The Owner may request substitutions of listed sub-bidders, subject to written agreement of the Bidder. If the substitute subcontractor’s bid exceeds that of the listed sub-bidder, the contract sum shall be increased by the difference between the two bids. If the subcontractor’s bid is less than or equal to the listed sub-bid, the contract sum shall remain unchanged.
BIDDER QUALIFICATIONS
Each bid must be accompanied by a statement of the Bidder's experience, organization, and financial resources.
This statement shall be on Document 00420 - STATEMENT OF QUALIFICATIONS (attached separately). All questions must be answered, and the data given must be clear and comprehensive. Additional sheets may be attached where necessary. Attachments may be included if necessary.
Bidder must complete Appendix A - Project Data Form for at least three projects of a similar nature which Bidder has completed satisfactorily within the last three years. The completed forms shall be submitted as a PDF attachment.
The Owner reserves the right to reject any bid when the information supplied does not satisfy the Owner that the Bidder is sufficiently responsible to entrust with the work of this contract.
AWARD OF CONTRACT
Selection Criteria listed in order of importance:
1. Lowest bid
2. Most qualified bidder
3. Ability to complete the project within the owner's requested schedule
4. Experience with similar projects
The contract will be awarded to the lowest, most responsive and responsible qualified bidder complying with the submittal instructions and the contract documents.
Rev. 01/14/2020 6
Written notice of the acceptance of the bid will be made to the Bidder within thirty (30) days after the opening of bids, or any time thereafter before such bid expires. The Bidder agrees to execute and deliver a contract for the work and the performance bond and payment bond to the Owner within thirty (30) days after the date of such notice.
In the event that the successful bidder fails to execute or deliver the contract upon his part, or to furnish satisfactory surety upon the Performance Bond and Payment Bond, the Owner, after declaring the security deposit of such bidder forfeited, reserves the right to accept the bid of the next lowest, most responsive and responsible bidder within ten
(10) days from such default, provided this second bid is accepted within the time limits for such bid acceptance as provided in these documents, in which case such acceptance shall have the same effect on such bidder as if such bidder were the original successful bidder.
In case of a second or further default, this procedure shall be in effect and followed, subject to the discretion of the Owner, until a contract is successfully awarded within the time limits as outlined above.
The Owner shall have the right to reject any and all bids and, in the event the lowest, most responsive bid is in excess of the budget or appropriation, shall have the right to negotiate with the low bidder or with the three lowest bidders for a contract upon terms deemed most advantageous to the Owner. If only one bid is received, the Owner may negotiate a contract upon terms deemed most advantageous to the Owner.
Any authorization contained herein which is at variance with the requirements of applicable federal or state laws and regulations shall be controlled by the terms of such laws and regulations.
INSURANCE (See Document 00020)
• USNH Insurance Requirements for Construction Contract (Rev 02/15/2022), Sections 1.2.b. Other Liability, Contractor’s Pollution Legal Liability will be required for this project.
• USNH Insurance Requirements for Construction Contract (Rev 02/15/2022), Sections 1.2.b. Other Liability, Owner’s Protective Liability may be required for this project. See Paragraph 1.4.2.
OWNER CONTRACT SIGNATORY
Contracts Equal to or Greater than $500,000 Contracts Less than $500,000 Karen Benincasa Vice Chancellor for Finance & Treasurer University System of New Hampshire 5 Chenell Drive, Suite 301 Concord, NH 03301-8503
Robert Watling Executive Vice President of Finance & Administration University of New Hampshire Thompson Hall 105 Main Street Durham, NH 03824-2512
BID SECURITY AND BONDING (See Document 00020)
Each bid must be accompanied by a bid bond, bank draft or certified check in an amount not less than five percent (5%) of the base bid.
If a bid bond, it must be duly executed by the Bidder as the principal, and have as surety a company authorized to transact business in the state of New Hampshire and appearing in the U.S. Treasury Department’s most current Circular 570, as amended. The completed bid bond shall be submitted as a PDF attachment in the Jaggaer tool with the bid.
If a bank draft or certified check, it shall be drawn upon a state, or national, bank or trust company to the order of the University System of New Hampshire and must be dated on or before the date named for the opening of bids.
A copy of the bank draft or certified check must be submitted as a PDF attachment in the Jaggaer tool with the bid. The original bank draft or certified check must be submitted within 24 hours of the bid due date & time in an envelope with the Event number and the name and address of the successful bidder on the envelope.
Within ten (10) days after the formal opening of bids, bid securities in the form of bank drafts and certified checks will be returned to all except the three (3) lowest bidders. Except for the successful bidder, bid securities in the form of bank drafts and certified checks of the three lowest bidders will be returned within three (3) days after the execution of the contract. The successful bidder’s bid security will be returned upon delivery of satisfactory one hundred percent (100%) performance and payment bonds.
Rev. 01/14/2020 7
Performance and Payment Bonds (See Document 00020)
Simultaneously with delivery of the fully executed contract, the successful bidder shall deliver to the Owner’s Agent executed performance and payment bonds, each in the amount of one hundred percent (100%) of the contract sum, as security for the faithful performance of his contract and for the payment of all persons performing labor or furnishing materials in connection therewith. The bonds shall be drawn and have as surety a surety company acceptable to the Owner. Performance and payment bonds shall carry the Event number and the name and address of the successful bidder on the envelope.
Should the successful bidder fail or refuse to execute and deliver the contract and the performance and payment bonds required within ten (10) days after the date of mailing, faxing, or delivery of the Owner's notice of the bid acceptance, the Bidder shall forfeit to the Owner, as liquidated damages for such failure or refusal, the deposit which the Bidder makes pursuant to the Bid Security section above, or the difference between his bid and the amount of the contract which the Owner actually enters into for the Work, whichever is less.
If the contractor is a partnership, the bonds shall be signed and sealed by each of the individuals who are partners; if a corporation, the bonds shall be signed and sealed in the correct corporate name by a duly authorized officer, agent, or attorney-in-fact. The executed bonds shall be accompanied by (a) appropriate acknowledgments of the respective parties; (b) appropriate duly certified copy of power of attorney or other certificates of authority when bonds are executed by an agent, officer, or other representative of contractor or surety; (c) a duly certified extract from by-laws or resolutions of surety under which power of attorney or other certificate of authority of its agent, officer or representative was issued; and (d) certified copy of latest published financial statement of assets and liabilities of surety.
COMMENCEMENT AND COMPLETION OF WORK
Attention is called to the importance of meeting the project timeline for commencement and completion of the work per the schedule in Document 00020, INVITATION TO BID or as modified by addendum.
END OF SECTION 00100
SECTION 01 1000 - GENERAL REQUIREMENTS
This document is used for all construction contracts; wherever the word “Contractor” is used, it is also meant to apply to Design/Build firms and CM firms.
The term "Day", where used throughout the Contract unless otherwise stated, shall mean "Calendar Day."
If there is no outside (third party) design professional on the project, then the word “Owner” should be substituted in any place where the term “design professional” is stated.
PART 1 - GENERAL
1.1 DESCRIPTION
These General Requirements are intended to complement the University System of New Hampshire ConsensusDocs Standard Agreement and General Conditions (the Agreement) .
The Agreement, Supplemental Conditions, if required, and Division 1 Specifications of this Contract shall apply to each and every contract and contractor or other person or persons supplying labor, material, equipment and/or services entering into this Project and/or on the premises directly or indirectly.
Work Included in this Contract: Providing all labor, materials, equipment, and services, etc., as required to complete all Work identified in or otherwise required by the Contract Documents.
Work Excluded from this Contract: Work noted as "Not in Contract" (N.I.C.) or “By Owner”. However, the Contractor shall provide services and coordination related to items not in the Contract as required by the Contract Documents.
Rev. 01/14/2020 8
1.2 RULES/REGULATIONS
General: The Contractor shall fully comply with all governing Local, State and Federal Laws, Codes, Rules, Regulations and Ordinances, including but not limited to The Americans with Disabilities Act, Equal Employment Opportunity and Affirmative Action provisions, and Occupational Safety and Health Administration provisions.
Review of Employees: Owner reserves the right to request, from time to time, information relating to Contractor’s employees, agents, or other employed by or associated with the Contractor, including employees and agents of sub-contractors and sub-sub-contractors, who have access to the Owner campus, as required by USNH to comply with the provisions of the Jeanne Clery Act, as amended, 20 U.S.C. Section 1092(f) and to ensure that no such personnel represent a safety or security risk to Owner, its employees, agents, students or guests. Owner reserves the right to deny entry to the Owner campus, at its sole discretion, to any consultant, sub-consultant, sub-sub-consultant, contractor, sub-contractor and sub-sub-contractor personnel who Owner believes represents a safety or security risk to Owner, its employees, agents, students or guests.
NH RSAs 21-I:81-a, and 21-I:81-b: The Contractor shall comply with State of New Hampshire RSAs 21-I:81-a (http://www.gencourt.state.nh.us/rsa/html/I/21-I/21-I-81-a.htm) and 21-I:81-b (http://www.gencourt.state.nh.us/rsa/html/I/21-I/21-I-81-b.htm). A blank reporting form (“Subcontractor/Employee Master List” in MS Word format which may be expanded as necessary) may be accessed on the web in the Buyer Attachments section of the Event.
NH RSA277:5-a: The Contractor shall comply with State of New Hampshire RSA 277:5-a, Occupational Safety and Health Administration Certification. All on-site employees shall have completed an OSHA 10-hour construction safety program prior to beginning work. (See:
http://www.gencourt.state.nh.us/rsa/html/XXIII/277/277-5-a.htm.)
State Building Codes and Permits: The University System of New Hampshire, falls under the jurisdiction of the statewide building code (see: http://www.nh.gov/safety/divisions/firesafety/legal/codebuilding.html).
Permitting is required in accordance with Section 105 of the International Building Code currently enforced in the state of New Hampshire. The Contractor shall comply therewith and shall cooperate with the Owner and with NH authorities having jurisdiction (and/or their agents) regarding necessary reviews, testing and inspections. Normally, such construction phase reviews, testing and inspections include review of contractor submittals for sprinkler and fire alarm systems; observation of sprinkler flow, emergency lighting, and fire alarm testing; fireproofing verification; elevator, plumbing, electrical, and health inspections; as well as certificate of occupancy permitting and inspection(s).
Local Building Codes and Permits: In general, the Owner does not fall under local jurisdiction. However, the Owner is subject to local and State water/sewer connection permitting requirements, road cut/closure permitting requirements, and noise ordinances. Therefore, the Contractor shall comply with local and State water and sewer connection details and installation requirements; apply and pay for all road cut/closure permits; provide and pay for all required bond premiums and police/traffic details; comply with all associated excavation, backfill, patching, and safety requirements, etc.; and comply with local noise ordinances.
Environmental Regulations: The Contractor shall comply with all applicable environmental laws and regulations. Particular attention shall be paid to proper erosion, sedimentation, and dust control.
Parking: Parking shall be subject to Owner parking regulations, enforcement and procedures. The Contractor shall coordinate with Owner Parking Services relative to contractor parking permits/fees and the availability of contractor parking. It shall be understood by the Contractor that parking for all contractor and subcontractor vehicles may not be available immediately adjacent to the Project Site and that the Contractor may be directed to park some, most, or even all such vehicles remotely. Transferable contractor parking permits are available from Owner Parking Services.
1.3 SPECIAL CONDITIONS
All work associated with this project must comply with the provisions of Executive Order 11246, as amended, Section 402 of the Vietnam Era Veterans Readjustment Act of 1974, and Section 503 of the Rehabilitation Act of 1973, as well as all regulations and orders of the Secretary of Labor pursuant to these provisions. Further, http://www.gencourt.state.nh.us/rsa/html/I/21-I/21-I-81-a.htm http://www.gencourt.state.nh.us/rsa/html/I/21-I/21-I-81-b.htm http://www.gencourt.state.nh.us/rsa/html/XXIII/277/277-5-a.htm http://www.nh.gov/safety/divisions/firesafety/legal/codebuilding.html
Rev. 01/14/2020 9 all work associated with this project must comply with the equal employment and affirmative action clauses contained in 41 CFR 60-1.4, 41 CFR 60-250.4, and 41 CFR 60-741.4.
Supplemental Conditions… Not Used.
Site constraints include… Not Used.
Under a separate contract… Not Used.
This project is subject to conditions imposed by project permits. See Specification Section 01 4100 Regulatory Requirements… Not Used.
This project is funded through a grant from… Not Used.
1.4 GENERAL RESPONSIBILITIES OF THE CONTRACTOR
Use of Local and Campus Roads: Existing roads, lanes, and required emergency access shall always remain accessible. At times when the work interferes with the normal flow of traffic (including vehicles, bicycles, and pedestrians), both on and off the site, the Contractor shall coordinate with and comply with the requirements of the local and Owner police, highway, and public works departments including but not limited to the provision of adequate personnel, flagmen, and equipment to properly regulate traffic. Roadways and driveways shall be kept free of debris resulting from construction-related traffic. Where the work results in the accumulation of dirt, dust, debris, etc. on local roads or in adjacent drainage channels or structures, the Contractor shall remedy said condition immediately and shall continue to do so in a manner, duration, and frequency appropriate to the condition and acceptable to the Owner and the authority having jurisdiction.
Hauling permits and route approvals shall be obtained from governing authorities as applicable.
Campus/Site Access: The Owner will coordinate with the Contractor to determine access to the campus and project site for construction-related vehicles, workers and the delivery or removal of construction materials and/or equipment.
Use of the Site: The Contractor shall have use of the site as indicated elsewhere in the Contract Documents.
Stockpiling of all materials shall be coordinated with the Owner and governing authorities.
Use of the Existing Building: The Contractor shall maintain the existing building in a weather tight condition throughout the construction period and shall immediately repair to its pre-construction condition or better any damage caused by construction operations. Furthermore, the Contractor shall limit storage of on-site materials to locations acceptable to the Owner and governing authorities.
Building areas outside the limits of work may be occupied for the duration of the project. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's operations. Owner reserves the right to perform maintenance in completed areas prior to Final Completion. Such partial occupancy and maintenance activities shall not constitute acceptance of the total Work.
Document existing damage with photographs or video prior to start of on-site construction. Show existing conditions of adjoining construction and site improvements, including finish surfaces that might be misconstrued as Contractor-caused damage. Transmit copies to Design Professional and Owner prior to commencing work.
Undocumented existing damage will be construed as Contractor-caused.
Prevent false fire alarms due to generation of construction-related dust.
Erect temporary partitions to keep dust and debris contained in work areas. Temporary partitions shall be provided with self-closing doors or other means of maintaining emergency egress routes.
Work Hours: The normal working hours for this contract shall be from 7 a.m. to 5 p.m., Monday through Friday, unless otherwise authorized by Owner. Such authorization will not be unreasonably withheld.
Rev. 01/14/2020 10
Noise: Noise that is unnecessary or not construction-related (e.g. radios, boom boxes, headphones, excessive hollering, etc.) shall be prohibited.
Superintendent/Supervision: The Contractor shall provide competent supervision for the performance of the Work. The superintendent shall represent the Contractor, and communications given to the superintendent shall be as binding as if given to the Contractor. The Parties shall use best efforts to confirm communications in writing. Except as may be approved by the Owner for periods of minor or minimal activity, this superintendent shall always be on the job site while work is in progress, including overtime operations by the Contractor's forces or by subcontractors. The Owner shall have the right to review the qualifications of the proposed superintendent and ask for a replacement if, in the Owner’s opinion, the person proposed does not meet the qualifications that the project will demand. The same superintendent who was in charge during the general progress of the work shall oversee the completion of all punch list items.
Coordination: Except as specifically indicated otherwise, the Contractor shall be fully responsible for coordinating all construction activities, verifying dimensions and existing field conditions, establishing on-site lines of authority and communication, monitoring schedules and progress, monitoring quality and ensuring quality workmanship, maintaining records and reports and assuring the proper administration of the work.
Disruptions and inconveniences to the activities of existing facilities to remain in operation during construction shall be minimized and shall be subject to the prior approval of the Owner.
Job Meetings: The Contractor shall attend regular job meetings once every week during the construction period, at such time and place as is mutually acceptable to the Owner, Design Professional, and Contractor.
All major subcontractors shall be represented at each meeting as needed. Other trades or subcontractors may be called to job meetings, as the progress of the work requires. The Contractor shall record and distribute the minutes of each meeting.
Utilities and Roadways: Except as indicated otherwise, existing facilities, systems, and roadways shall remain in operation throughout the execution of the work of this Contract. The Contractor shall schedule and coordinate the work with the Owner and local police, highway, and public works departments as required to maintain the safe and functional use of such facilities, systems, and roadways. The Contractor shall send proper notices, make all necessary arrangements, and perform all other services required for the removal or the protection and maintenance of all existing utilities and services, assuming all responsibility and paying all costs related thereto. Existing utilities and services shall not be disrupted without the prior approval, and then only to the minimum extent required. The Owner reserves the right to require the Contractor to implement temporary measures/services rather than allowing a disruption of service, especially regarding water and sewer, where applicable.
The Contractor, through the Owner’s Representative, shall comply with the "Underground Utility Damage Prevention System" by notification to DIG SAFE SYSTEM of intent to excavate or otherwise disturb the ground surface. The Contractor shall notify the Owner’s Representative at least five days in advance of starting any such work. The Contractor shall continually maintain associated markings. Failing that, the Contractor shall provide the services of a utility locating company for re-marking efforts. Note: Dig Safe coordination at the University of New Hampshire is managed internally.
Means and Methods: Except as specifically indicated otherwise, the Contractor shall be fully responsible for all means, methods, procedures, sequences and techniques of construction employed toward the completion of the Work.
Site Safety: The Contractor shall comply with all applicable OSHA standards.
The Contractor shall comply with all “hot work” and “confined space” safety standards and permit procedures required by the Owner’s Office of Environmental Health and Safety.
The Contractor shall take all measures required to ensure the safety of construction workers, as well as the safety of the campus community and the public. The Contractor shall make safety a top priority and ensure that all necessary barricades and fencing are provided and that they comply with applicable regulations and standards of good practice.
The construction site is near existing occupied buildings and roadways. Therefore, site safety is of the utmost importance. The Contractor shall pay all costs necessary for temporary partitioning, barricading, fencing, Rev. 01/14/2020 11 walks, ramps, enclosures, security and safety devices required for the maintenance of a clean and safe construction site.
Fire Protection: The Contractor shall provide and maintain in good operating condition suitable and adequate fire protection equipment and services, and shall comply with all reasonable recommendations regarding fire protection made by the representatives of the fire insurance company carrying insurance on the Work or by governing fire or building authorities. Flammable products shall be properly stored in containers acceptable to fire officials. The area within the site limits shall be kept orderly and clean, and all combustible rubbish shall be promptly removed from the site. A “Hot Work” permit shall be obtained through the Owner’s Representative for all work involving any type of flame or spark producing torch, saw, etc. At all times of “Hot Work”, the Contractor shall provide a dedicated “fire watch” person, who shall have no other responsibilities and whom the Contractor shall provide with appropriate fire protection and extinguishing equipment and training.
Protection of Adjoining Property: The Contractor shall restrict construction operations and provide all shoring, fencing, and other work necessary to support, protect and keep unharmed all walls, footings, floors, roofs, walks, roadways and all other parts of any existing buildings, facilities, site improvements, land forms, trees and plant materials, etc. outside the limits of the Work or otherwise shown to remain. The Contractor shall hold the Owner and Design Professional harmless from any such damage due to any operations under this Contract. Any existing work or property damaged or disrupted as a result of this Contract shall be replaced or repaired to match original existing conditions at no additional cost to the Owner.
Building and Site Security: The Contractor will be issued one copy of the key(s) needed to access the applicable work area(s), which must be returned upon completion of the Work. It shall be the Contractor’s responsibility to, ensure upon leaving the project site at any time, that all doors into areas within the Contractor’s control are locked and properly latched and that all other doors that may be used by the Contractor are properly latched. Site shall be secured with a double padlock system.
Vandalism: The Contractor shall take all reasonable precautions necessary to prevent loss or damage caused by vandalism, theft, burglary, pilferage, or unexplained disappearance of property of the Owner, whether or not forming part of the Work, located within those areas of the Project to which the Contractor has access.
Hazardous Substances: The Design Professional’s Scope of Services and responsibilities exclude the investigation, discovery, detection, identification, presence, leakage, release, use, handling, disposal, encapsulation, abatement, treatment, or removal of, or exposure of a person or persons to hazardous materials, pollutants, contaminants, or disease transmitting organisms, pre-existing or otherwise deposited in any form at the project, indoors or outdoors, at any time before, during or after construction, including but not limited to volatile organic compounds, petroleum products, bacteria, molds, fungus, asbestos or asbestos products, lead, radon, electro-magnetic frequency radiation or other radiation. Should any such substances be encountered, the Owner and Design Professional shall be promptly notified, in writing.
Miscellaneous:
Smoking/Chewing: The use of tobacco products, including smoking, vaping, and chewing of tobacco or similar products, is prohibited on Owner property except where expressly permitted by Owner policy. The Contractor shall strictly enforce this prohibition and shall remove repeat offenders from the project site.
Alcohol: The possession or consumption of alcoholic beverages on Owner property and in Owner buildings is prohibited. The Contractor shall strictly enforce this prohibition and shall immediately remove offenders from the project site.
Sexual Harassment/Lewdness: Lewdness and other forms of sexual harassment including, but not limited to, catcalls, vulgar sounds or actions, and the display of prurient images will not be tolerated, especially when directed toward or observable by a member or members of the campus community or the public. The Contractor shall strictly enforce this policy and shall immediately remove offenders from the project.
1.5 MEASUREMENT AND PAYMENT
Schedule of Values: Prior to submittal of the first Application for Payment, the Contractor shall submit a schedule of values in accordance with the Agreement .
Payment Requisition: Prior to the submission of the first pay application the contractor shall, for approval by the Owner and Design Professional, a draft “Application and Certificate for Payment”, including “Request for
Rev. 01/14/2020 12
Payment Detail” in accordance with the approved schedule of values. The “Application and Certificate for Payment” shall at a minimum follow the AIA Form G702 or ConsensusDocs Form 292. The Contractor shall submit, the approved “Application and Certificate for Payment” in accordance with the Agreement for Progress Payments or Final Payment. The final “Application and Certificate for Payment” shall be fully completed, properly executed, and provided to Project Design Professional and Owner’s Representative in either electronic or written format.
Release of Lien: The Contractor shall furnish current Lien Waivers for itself and from all subcontractors and material suppliers with each Application for Payment, in accordance with the Agreement in the form of contract.
1.6 SUBMITTALS
Submittal Schedule: Within thirty (30) days of award and prior to submitting any submittal for review, the Contractor shall provide the Design Professional and Owner with a complete and acceptable submittal schedule, for all materials requiring review. The Submittal Schedule shall be organized chronologically to correspond to the sequence of construction and shall be coordinated with the Contractor’s construction schedule and schedule of values. For each submittal, schedule shall list the projected scheduled date for initial submittal, applicable specification section/paragraph, description of the work covered, name of respective subcontractor, supplier and/or manufacturer, projected scheduled date to allow for resubmittal if necessary, scheduled date for the final release/approval, type of submittal (IE: Shop Drawings, Samples, Manufacturer’s Recommendations, Product Data, Certificate of Compliance, Closeout, Warranty Operating Instructions, Record Drawings, Other) and actual submittal and review dates. Update and submit the submittal schedule at least monthly and more frequently if submittal activity warrants.
Owner Review: With the delivery of any and all submittals to the Project Design Professional, the Contractor shall deliver a copy to the Owner and designated Owner’s specialty consultants for concurrent review. All Owner and the Owner’s specialty consultant’s comments will be forwarded to the Design Professional for consideration and incorporation, as appropriate, into a consolidated submittal response.
Identification: Each and every submittal shall be identified with a cover sheet inclusive of the following:
Unique submittal identifier referencing respective specification section and paragraph and including revision number. For example, Submittal # 078400-1.04-Rev.0 would identify the initial submittal for firestopping at all penetrations, as specified in Spec. Section 078400, Paragraph 1.04.
• Date
• Project name
• Name and address of Design Professional, Contractor, applicable subcontractor, supplier, and manufacturer.
• Drawing number and detail references, as appropriate
• Contractor's certification stating that information submitted complies with requirements of the Contract
Documents
• Identification of deviations from requirements of the Contract Documents, including minor variations and limitations and, for resubmittals, identification of revisions other than those requested by Design Professional on previous submittals
• Other necessary or otherwise appropriate identification
Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
• Name, address, and telephone number of entities performing subcontract or supplying products
• Number and title of related Specification Section(s) covered by subcontract
• Drawing number and detail references, as appropriate, covered by subcontract
Comprehensive Construction Schedule: The work of all trades shall be scheduled so that close coordination will be effected throughout all phases of construction. In accordance with the Agreement, the Contractor shall prepare a comprehensive "Critical Path" construction schedule for his own use and the Owner's information.
The schedule shall be submitted to the Engineer or Architect and Owner within ten (10) days after award of Contract. The Design Professional’s and/or Owner’s receipt and review of this schedule shall in no way be construed to be approval or endorsement thereof. The schedule shall show concisely the manner in which the
Rev. 01/14/2020 13 work will be prosecuted and shall specifically identify the start and completion dates of any work or activity that may disrupt or otherwise affect ongoing activities within or about the project site.
Materials Delivery Schedule: Accompanying the comprehensive construction schedule, the Contractor shall submit a materials delivery schedule with which the comprehensive construction schedule has been coordinated. The materials delivery schedule shall identify all materials required for the work that are not readily available from local suppliers and/or that have long lead times and shall indicate when such materials will be delivered and whether said delivery is contingent upon a specific submittal review timetable.
Testing and Inspections Schedule: Prepare a schedule of inspections, tests, and similar services required by the Contract Documents and the State Fire Marshalls Office (SMFO). Submit the schedule with the Contractor's construction schedule. The schedule shall be in tabular form and shall include, without limitation, the following: spec section number and name; description of the test; applicable standards; test methods; quantity and/or frequency of tests/samples; time requirements; entity responsible for performing tests; requirements for taking samples; and any unique characteristics of each service.
Electronic Shop Drawings, Cuts and Literature Submittals:
Electronic submittal submissions are the preferred distribution method by the Owner. The Contractor shall distribute required submittals, concurrently, to the Design Professional, the Owner and the Owner’s specialty consultants as required.
Electronic Submittals
• A complete submittal package shall be assembled into a single indexed file with links enabling navigation to each item in the package.
• Name file with the submittal number or other unique identifier, including revision identifier. For example: 078400-1.04-Rev.0 Firestopping.
• The Contractor shall provide a signed and stamped transmittal for each submittal package with the information included in the Identification section above.
• Provide means for insertion to permanently record Contractor’s review and approval markings and actions by the Architect.
Submittal Requirements:
• The Contractor shall check and correct submittals for compliance with the Contract Documents before submitting them to the Design Professional and Owner for review. Submittals shall be marked to show which products and options are applicable and annotated with the Contractor’s corrections, field dimensions, etc. Deviations from the Contract Documents shall be clearly identified.
• The submittal stamp shall state that the Contractor has reviewed the submittals and that the work shown is in accordance with the Contract requirements and has been checked for dimension, quantity, and relationship with work of all trades involved. Submittals will be returned to the Contractor without review if it is apparent that the Contractor has failed to properly review and/or stamp them prior to submittal.
• Completeness of Submittals: All shop drawings, brochures, cuts and manufacturer's literature relative to each material/item/product proposed for incorporation into the Work shall be compiled into a single submittal package. This applies also to resubmittals. That is, resubmittals shall include all documentation included in the initial submission, except as required to bring the submittal into compliance with contract requirements and/or to be responsive to the Design Professional prior review comments. Piecemeal or incomplete submittals and partial resubmittals will not be reviewed.
• The Contractor shall coordinate preparation and processing of submittals with performance of construction activities. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination. The Design Professional reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
Design Professional Review: In general, the Design Professional will complete his/her review of submittals/resubmittals and return them to the Contractor within ten (10) working days following receipt thereof.
Rev. 01/14/2020 14
Review of submittals by the Design Professional shall not relieve the Contractor of responsibility for compliance with the Contract Documents (unless specifically proposed as a substitution in accordance with the Agreement) and relative to verification of measurements and existing conditions, trade coordination, etc.
Among other limitations, the Design Professional’s review shall not include the calculation, coordination or verification of dimensions or…