310 Attachment 3 - Alternate Bids.pdf

PDF 96 KB Posted

Attached to
UNH Memorial Union Building Elevator Controller Replacements
Solicitation number
2120271006
Issued by
New Hampshire

About this file

This document is Attachment 3 of the bid submission form for the University of New Hampshire Memorial Union Building Elevator Controller Replacements project, a capital improvement initiative managed by USNH representing UNH Facilities Project Management in Durham, New Hampshire (USNH Event #2120271006). The attachment provides the framework for bidders to submit pricing for two alternates related to elevator car enclosure work: Alternate One for the East Elevator Car Enclosure and Alternate Two for the West Elevator Car Enclosure. For each alternate, bidders must designate whether the work represents an add or deduct to the base bid and provide the total dollar amount. Additionally, bidders must identify how each alternate impacts specific sub-bids by indicating whether sub-bid amounts increase or decrease, along with corresponding dollar adjustments. Bidders may also propose substitute sub-bidders if prices differ from those of listed sub-bidders.

The form does not specify pricing terms, contract duration, funding sources, or award dates within its contents. All sub-bid modifications and sub-bidder substitutions are designated as confidential information for use only by the Owner and its consultants, while the actual alternate bid amounts are designated as public information. Bidders must complete the form by providing their name and submission date. The document serves as a standard template for capturing alternate bid pricing and sub-bid impacts in a structured format to facilitate Owner evaluation and low-bid determination.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 3 - ALTERNATE BIDS

To Bid of: _____________________________________________, Bidder

For: USNH Event # 2120271006 UNH Memorial Union Building Elevator Controller Replacements

UNIVERSITY OF NEW HAMPSHIRE

DURHAM, NEW HAMPSHIRE

ALTERNATES

To the above base bid sum, the following amounts shall be added or deducted for each alternate, as listed below.

Bidder shall indicate whether each alternate is an “Add” or “Deduct”, as applicable. It shall be noted that, for the purposes of determining low bidder, the Owner has indicated, with bold print, whether each alternate is anticipated to be additive or deductive. Affected sub-bids shall be identified by the sub-bid reference number(s) listed in Attachment One.

Alternate One – EAST ELEVATOR CAR ENCLOSURE

1) (Add) (Deduct) $ ______________________

2) (Increases) (Decreases) Sub-bid # _________ by $ _______________________

(Increases) (Decreases) Sub-bid # _________ by $ _______________________

3) Name of substitute Sub-bidder(s) if price is not from listed Sub-bidder(s):

Sub-bid # _____ Substitute Sub-bidder _______________________________

Alternate Two – WEST ELEVATOR CAR ENCLOSURE

1) (Add) (Deduct) $ ______________________

2) (Increases) (Decreases) Sub-bid # _________ by $ _______________________

(Increases) (Decreases) Sub-bid # _________ by $ _______________________

3) Name of substitute Sub-bidder(s) if price is not from listed Sub-bidder(s):

The foregoing sub-bid modifications and sub-bidder substitutions shall be confidential information only for the use of the Owner together with its Consultants while the actual alternate amounts shall be public information.

Bidder: ______________________________________________ Date: ______________

END OF ATTACHMENT 3

To Bid of:
Add Deduct:
Increases Decreases Subbid:
by:
Increases Decreases Subbid_2:
by_2:
Increases Decreases Subbid_3:
by_3:
Increases Decreases Subbid_4:
by_4:
Increases Decreases Subbid_5:
by_5:
Subbid:
Substitute Subbidder:
Subbid_2:
Substitute Subbidder_2:
Add Deduct_2:
Increases Decreases Subbid_6:
by_6:
Increases Decreases Subbid_7:
by_7:
Increases Decreases Subbid_8:
by_8:
Increases Decreases Subbid_9:
by_9:
Increases Decreases Subbid_10:
by_10:
Subbid_3:
Substitute Subbidder_3:
Subbid_4:
Substitute Subbidder_4:
Bidder:
Date:

File details come from the government source that posted it. Updated .