UCB001319-19.00-Sample Substantial Completion.docx
DOCX document 37 KB Posted
- Solicitation number
- Notice No. 25-70
- Issued by
- Boulder County, Colorado
About this file
This document is a Notice of Substantial Completion issued by the State of Colorado Office of the State Architect for a University of Colorado Boulder project. The notice confirms that a specific construction project has been reviewed and determined to be substantially complete as of the date noted, meeting key criteria including occupancy suitability, code compliance, usability, and cleanliness. The project involves upgrades to the Chilled Hot Water (CHW) distribution system for future expansion, specifically providing a new 4" service to the PDPS Building, with work performed while adjacent CHW systems remain energized and buildings remain fully operational and occupied.
The notice includes provisions for a punch list of remaining work items, with the contractor required to provide a schedule for completing these items prior to final acceptance. Warranties and the contractor's one-year remedial work obligation are set to commence on the date of substantial completion. The document requires signatures from the architect/engineer, principal representative, State Buildings Program, and contractor to be fully executed, with responsibilities for security, maintenance, heat, utilities, and insurance to be specified in the contract documents.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT A
STATE OF COLORADO
OFFICE OF THE STATE ARCHITECT
STATE BUILDINGS PROGRAM
NOTICE OF SUBSTANTIAL COMPLETION
Date of Substantial Completion:
Institution or Agency: University of Colorado Boulder Project No./Name:
| TO: | , Project Manager |
| University of Colorado Boulder | |
| Department of Facilities Management | |
| Campus Box 453 UCB | |
| Boulder, CO 80309-0453 | |
| (Principal Representative) |
And
(Contractor)
This is to advise you that the Work has been reviewed, inspected and determined, to the best knowledge, information and belief of the Architect/Engineer, to be substantially complete as of the date noted above in accordance with the criteria outlined in Article 41 of The General Conditions of the Contract in SC-6.23 and SC-8.1 or Article 41 in SC-6.51 and the Specifications, including without limitation a) suitable for occupancy, b) inspected for code compliance with Building Inspection Records signed by code officials for the State, c) determined to be fully and comfortably usable, and d) fully cleaned and appropriate for presentation to the public.
A punch list of work to be completed, work not in compliance with the Drawings or Specifications, and unsatisfactory work is attached hereto, along with the Contractor’s schedule for the completion of each and every item identified on the punch list specifying the Subcontractor or trade responsible for the work, and the dates the completion or correction will be commenced and finished within any period indicated in the Agreement for punch list completion prior to Final Acceptance.
Except as stated below, all manufacturers’ warranties, other special warranties and the Contractor’s one-year obligation to perform remedial work, shall commence on the Date of Substantial Completion noted above.
This Notice of Substantial Completion shall be effective and establish the Date of Substantial Completion only when fully executed by the Contractor and the Principal Representative. The Principal Representative accepts the Work as substantially complete as of the Date of Substantial Completion herein noted. The Contractor agrees to complete or correct the Work identified on the attached punch list and to do so in accordance with attached punch list completion schedule
| By ________________________________________ | By ________________________________________ | |||
| Architect/Engineer | Date | Principal Representative | Date |
| By ________________________________________ | By ________________________________________ | |||
| State Buildings Program | Date | Contractor | Date |
The responsibilities of the Principal Representative and the Contractor for security, maintenance, heat, utilities, and insurance shall be as specified in the Contract Documents or as otherwise hereafter noted:
Exceptions, if any, to the commencement of warranties shall be:
The attached final punch list consists of pages, and the attached Contractor’s schedule showing the dates of commencement and completion of each punch list item consists of pages.
When completely executed, this form shall be sent to the Contractor and the Principal Representative with a copy to State Buildings Program/delegate.
Rev. 7/2012 3