Additional RFI Question and Answer
After conferring with our Electrical Engineer, we have concluded that the following applies:
1) What will the amperage of the panel be? When the heat load is determined, the amperage of the panel can be determined.
2) Will the panel be a 120/08V panel? Depends on the HVAC unit that is sized/ determined/ used.
3) How many breaker spaces does the panel need to be? 3
4) What panel will the new panel be fed from? Depends on the load.
5) Will load calculations on the existing panel be needed YES and will the new panel need to be engineered? YES
The voltage panels are in communication room #12. Room 12 is down the hall from rooms 9 and
10. Circuit directories show spare breaker space.