This document is a WebAIM Short Form Task Group Instruction (TGI) for a Low Pressure Air System tightness and operational test for the USS Blue Ridge (LCC-19), dated 03-MAR-2025. The task instruction is specific to System 55121 and Project 19P, with a Task Group Instruction number of 55121-3-300KTR. The document details work requirements for contractor, quality assurance (QA), and ship's force personnel to visually inspect mechanical, welded, and brazed joints of the Low Pressure Air System at Normal Operating Pressure (NOP) and Normal Operating Temperature (NOT), ensuring no external leakage for a minimum of 30 minutes. The instruction references two key documents: an Expanded Ship Work Breakdown Structure and an Engineering Operational Sequencing System (EOSS) for guidance and system scope definition.

View the file

Other files

File Type Posted
TGI_3819P31003A01_c0v0_redact.pdf PDF
TGI_3819P31002A05_c2v0.pdf PDF
TGI_3819P31002A03_c3v2_redact.pdf PDF
TGI_3819P31002A02_c1v1_redact.pdf PDF
TGI_3819P31001A06_c2v1.pdf PDF
TGI_3819P31001A04_c2v2.pdf PDF
TGI_3819P31001A03_c0v0_redact.pdf PDF
Attachment II Price Proposal Form N6264925RA041_CLIN 0002 and CLIN 0004.xlsx XLSX spreadsheet
N6264925RA041-0010.pdf PDF
TGI_3819P31003A06_c0v0_redact.pdf PDF
TGI_3819P31003A05_c0v0_redact.pdf PDF
TGI_3819P31003A03_c0v0_redact.pdf PDF
TGI_3819P31003A02_c0v0.pdf PDF
TGI_3819P31002A04_c3v3.pdf PDF
TGI_3819P31001A01_c3v4.pdf PDF
TGI_3819P31002A05_c2v0.pdf PDF
N6264925RA041-00006.pdf PDF
N6264925RA041-0003.pdf PDF
N6264925RA041-0002.pdf PDF
TGI_3819P31003A05_c0v0_redact.pdf PDF
TGI_3819P31003A01_c0v0_redact.pdf PDF
TGI_3819P31002A01_c0v0_redact.pdf PDF
TGI_3819P31001A03_c0v0_redact.pdf PDF
TGI_3819P31003T10_c0v0_redact.pdf PDF
TGI_3819P31003T05_c0v0_redact.pdf PDF
TGI_3819P31002T02_c0v0_redact.pdf PDF
TGI_3819P31001T09_c0v0_redacted.pdf PDF
Attachment V Contract Data Sheet.pdf PDF
TGI_3819P31003A03_c0v0_redact.pdf PDF
TGI_3819P31002A04_c0v2_redact.pdf PDF
TGI_3819P31001A04_c2v2.pdf PDF
TGI_3819P31003T09_c0v0_redact.pdf PDF
TGI_3819P31003T06_c0v0_redact.pdf PDF
TGI_3819P31002T12_c0v0_redact.pdf PDF
TGI_3819P31002T09_c0v0_redact.pdf PDF
TGI_3819P31002T08_c0v0_redact.pdf PDF
TGI_3819P31002T06_c0v0_redact.pdf PDF
TGI_3819P31002T05_c0v0_redact.pdf PDF
TGI_3819P31002T01_c0v0_redact.pdf PDF
TGI_3819P31001T06_c0v0_redacted.pdf PDF
Attachment II Price Proposal Form N6264925RA041.xlsx XLSX spreadsheet
2.01 N6264925RA041.pdf PDF
TGI_3819P31002A06_c0v0_redact.pdf PDF
TGI_3819P31002A05_c1v0_redact.pdf PDF
TGI_3819P31002A03_c3v2_redact.pdf PDF
TGI_3819P31001A05_c0v0_redact.pdf PDF
TGI_3819P31001A02_c2v1_redact.pdf PDF
TGI_3819P31001A01_c0v3_redact.pdf PDF
TGI_3819P31003T04_c0v0_redact.pdf PDF
TGI_3819P31002T04_c0v0_redact.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

03-MAR-2025 0950

20.14.15.2.9020 (September 2024) ICN: 3819P31001 KeyOp: T05

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 55121-3-300KTR TT T 4 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 55121

CU PHASE TITLE: LOW PRESSURE AIR (T & OP), S/A 79243K - KTR

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 3

EE01L106

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

OHTA, JASON Y. 246.2 3152435901 20-FEB-2025

APPROVED BY: CODE: PHONE: DATE:

OHTA, JASON Y. 246.2 3152435901 26-FEB-2025

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

EE01-L106

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE U

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

310G0001

Tightness & Operational Test for Low Pressure Air System - KTR.

TGI Short Form

03-MAR-2025 0950

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P31001 KeyOp: T05

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 55121-3-300KTR TT T 4 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 55121

CU PHASE TITLE: LOW PRESSURE AIR (T & OP), S/A 79243K - KTR

FOUO Pg 2 of 3

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 TM S9040-AA-IDX-

EXPANDED SHIP WORK

BREAKDOWN STRUCTURE

FOR ALL SHIPS AND

SHIP/COMBAT SYSTEMS

LAT N

2 TM EOSS ENGINEERING

OPERATIONAL SEQUENCING

SYSTEM (EOSS)

LAT N

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

(V) Contractor work:

Visually inspect all mechanical, welded &/or brazed joints of the LOW PRESSURE AIR SYS at NOP and NOT for no external leakage for 30 minutes plus sufficient length of time. No permanent deformation of brazed/welded joints allowed.

Actual Duration:____

Sign:_____________

Print:_____________

Date:____________ continued

22/KE PC N

Note: The scope of the LOW PRESSURE AIR SYS is as described in reference 1, ESWBS.

22/KE PC N

(G) QA work:

Visually inspect all mechanical, welded &/or brazed joints of the LOW PRESSURE AIR SYS at NOP and NOT for no external leakage for 30 minutes plus sufficient length of time.

Sign:_______________

Print:_______________

Date:_______________

33/G1 QA N

(S) S/F work:

Line up system in accordance with reference 2, EOSS. Visually inspect all mechanical, welded &/or brazed joints of the LOW PRESSURE AIR SYS at NOP and NOT for no external leakage for 30 minutes plus sufficient length of time.

Sign:_______________

Print:_______________

Date:_______________

/ EXSA N

MATERIAL REFERENCES

03-MAR-2025 0950

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P31001 KeyOp: T05

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 55121-3-300KTR TT T 4 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 55121

CU PHASE TITLE: LOW PRESSURE AIR (T & OP), S/A 79243K - KTR

FOUO Pg 3 of 3

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 3819P31001 KEY OP: T05