This document is a Task Group Instruction (TGI) for electrical work on the USS Blue Ridge (LCC-19), specifically focused on upgrading the Emergency Diesel Generator No. One as part of an Extended Service Life Program. The work involves comprehensive electrical removals, modifications, and installations across multiple ship compartments, including the Emergency Generator Room, various fan rooms, offices, and other spaces. The project is scheduled to start on 1/12/2026 and complete by 8/5/2027.
Key technical requirements include electrical work on the power system, lighting system, ventilation controllers, and various communication and alarm systems. The instruction specifies detailed procedures for electrical installations, protective device inspections, potable water piping modifications, and compliance with specific technical standards. Special requirements include working in spaces with potential asbestos, lead, and PCB hazards, and maintaining fire zone boundary integrity. The work will be performed using government-furnished materials and supported by various service work from SRF-JRMC, including crane services, utility services, safety inspections, and quality assurance.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
FOUO: Public availability to be determined under 5 USC 552
TASK GROUP INSTRUCTION
AIM REV 20.11.4.0 (OCTOBER 2020)
TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:
NO.: SA 79243K ELEC EDG#1 AY A 0 2
SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE:
*(RE) F/O-S/A 79243K, ACCOMPLISH ELEC WORK FOR EDG#1, ESLP SS/EDG GENSET UPGRADE
PREPARING ACTIVITY:
PREPARED BY: CODE PHONE DATE
KAZUKI ONO 233.1 080-9350-1438 15-FEB-2025
APPROVED BY: CODE PHONE DATE
MASAHIRO HOSONO 233.1 080-9350-1455 15-FEB-2025
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
REASON FOR WORK/NEED FOR CHANGE:
Additional materials was required. Update of material list is required.
CHANGE INSTRUCTIONS:
CH1: Modify document number of reference 2.23. (2/26/2025) CH2: Add materials and update material list. (3/3/2025)
SPECIAL REQUIREMENTS:
CLASS P-2 PIPING, CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL II, CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL III, This work affects a fire zone boundary. Fabrication and/or staging of a non-flammable closure is required.
WORK CERTIFICATION SIGNATURES
COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
ACCEPTANCE OF COMPLETED WORK
PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:
REQUIRED:☐YES ☒NO
RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
TGI NO.: SA 79243K ELEC EDG#1 AY A 0
FOUO
SHIP: LCC-19 CHG/VER: 2/2
LIST OF EFFECTIVE PAGES
SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.
1-9 J1-5 M1-3
1. SCOPE/PURPOSE
1.1 Title: Electrical Work for Emergency Diesel Generator No. One, Extended Service Life Program Ship Service/Emergency Diesel Generator Generator-set Upgrade; accomplish
1.2 Location of Work:
1.2.1 Emergency Generator Room No. One (7-30-0-E)
1.2.2 01 Level Weather, Frames between 36 and 37, Port
1.2.3 Main Deck Weather, Frame 35, Port
1.2.4 Main Deck Weather, Frames between 36 and 38, Starboard (Stbd)
1.2.5 Fan Room (1-34-1-Q)
1.2.6 Fan Room (1-34-2-Q)
1.2.7 Fan Room (1-36-0-Q)
1.2.8 Fan Room (1-36-2-Q)
1.2.9 Fan Room (1-38-0-Q)
1.2.9.1 Vent Plenum for Heating Ventilation and Air Conditioning (HVAC) Supply Systems (SS) 1-39-1, Frames between 37 and 39, Stbd
1.2.10 Fan Room (1-38-2-Q)
1.2.11 N3 Office (2-30-1-Q)
1.2.12 N3 ACOS Office (2-33-2-Q)
1.2.13 N7 Office (2-36-0-Q)
1.2.14 Radio Transmitter Room No. One (3-19-0-Q)
1.2.15 S-5 Office (3-30-0-Q)
1.2.16 Passage (3-30-01-L)
1.2.17 Diesel Exhaust Piping Space and Deck Gear Locker (3-31-3-Q)
1.2.18 Wardroom Galley (3-34-0-Q)
1.2.19 Wardroom Scullery (3-34-2-Q)
1.2.20 State Room (3-37-1-L)
FOUO
SHIP: LCC-19 CHG/VER: 2/2
1.2.21 Boatswain Storeroom (4-D-0-A)
1.2.22 Crew and Troop Messroom and FWD Battle Dressing Station (4-30-0-L)
1.2.23 Crew Sculley (4-36-0-Q)
1.2.24 Load Center 21/22 (4-57-2-Q)
1.2.25 Trunk (5-30-0-T)
1.2.26 Crew Living Space (STAFF) (5-30-01-L)
1.2.27 CPO Staff Washroom, Water Closet, Shower and Decontamination Station (5-30-2-L)
1.2.28 Crew Living Space (Female) (5-40-0-L)
1.2.29 Crew Living Space (5-52-0-L)
1.2.30 Passage (5-60-4-L)
1.2.31 Crew Lounge (5-60-0-L)
1.2.32 Passage (5-64-4-L)
1.2.33 CPO Staff Washroom, Water Closet, Shower and Decontamination Station (5-64-2-L)
1.2.34 Emergency Switchgear Room No. One (6-30-2-E)
1.2.35 Main GSK / SD Storeroom (6-40-0-A)
1.2.36 Storeroom (6-52-4-A)
1.2.37 Passage (6-60-0-L)
1.2.38 Passage (6-61-2-L)
1.2.39 Photo Lab Office (6-64-2-Q)
1.2.40 Passage (6-64-4-L)
1.2.41 Changing Area (6-68-4-Q)
1.2.42 Production Chief Office (6-70-2-Q)
1.2.43 EIC (6-72-2-Q)
1.2.44 B Division Storeroom (6-76-2-A)
1.2.45 Engine Room Enclosed Operating Station (6-86-0-E)
1.2.46 Ship Fitter Storeroom (6-86-2-A)
1.2.47 SD Storeroom (7-30-1-A)
1.2.48 Crew Baggage Storeroom (7-30-2-A)
FOUO
SHIP: LCC-19 CHG/VER: 2/2
1.2.49 Distillate Fuel Service Tank (7-82-2-F)
1.2.50 Fire Room (8-76-0-E)
1.2.51 Engine Room (8-86-0-E)
1.2.52 Potable Water Tank (9-76-4-W)
1.2.53 Fresh Water Ballast (9-86-6-W)
1.3 Identification:
1.3.1 Quantity (One EA), Power System
Remarks: See 2.3 through 2.15, and 2.22 and 2.23 for details
1.3.1.1 Quantity (One EA), Controller for Seawater Pump Motor of Emergency Diesel Generator (EDG) No. One Remarks: See 2.8 for details
1.3.1.2 Quantity (One EA), Controller for Ventilation Fan S1-37-1 Remarks: See 2.12 for details
1.3.1.3 Quantity (One EA), Controller for Ventilation Fan E1-37-2 Remarks: See 2.12 for details
1.3.2 Quantity (One EA), Lighting System
Remarks: See 2.3, 2.16 through 2.18 and 2.22 for details
1.3.3 Quantity (One EA), Propulsion Plant Announcing System (2MC) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details
1.3.4 Quantity (One EA), Surveillance Camera System (6TV) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details
1.3.5 Quantity (One EA), Television Closed Circuit System (2TV) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details
1.3.6 Quantity (One EA), General Announcing System (1MC) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details
1.3.7 Quantity (One EA), Machinery Space Halon Alarm System (2FR) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details
1.3.8 Quantity (One EA), Alarm Safety and Warning System (3FR) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details
1.3.9 Quantity (One EA), Sound Powered Telephone System (J) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details
1.3.10 Quantity (One EA), Sound Powered Telephone System (JV) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details
1.3.11 Quantity (One EA), Sound Powered Telephone System (JAZ) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details
1.3.12 Quantity (One EA), Sound Powered Telephone System (X40J) for EDG No. One
FOUO
SHIP: LCC-19 CHG/VER: 2/2
Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details
1.3.13 Quantity (One EA), Tank Level Indicating System (5TK) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details
1.3.14 Quantity (One EA), Alarm Safety Waring System (5EK) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details
1.3.15 Quantity (One EA), Tank Level Indicating System (6TK) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details
1.3.16 Quantity (One EA), Electronics System of Local Area Network (LAN) Drop Box Remarks: See Ref. No. 19 and Ref. No. 21 for details.
1.3.17 Quantity (One AY), Potable Water System Piping for Drinking Fountain located in 1.2.31 Size: 1/4 Inch IPS and 3/8 Inch IPS Material: Copper Alloy Overall Remarks: See Sheet One (Zone 4-D) of 2.37 and Sheet One (Zone 7-B) of 2.38 for detail
1.4 Security Classification:
1.4.1 Space - 1.2.11 through 1.2.15 and 1.2.41 through 1.2.43
1.5 Initial Condition:
1.5.1 Potential Asbestos Hazard.
1.5.2 Potential Lead Hazard
1.5.3 Potential PCB Hazard
1.5.4 Dry Dock Work.
1.6 Contractor work start date: 1/12/2026
1.7 Contractor work completion date: 8/5/2027
2. REFERENCES:
REF.
NO.
DOCUMENT
/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV CHG
NO.
COPY
REQ’D
(Y/N)
SOURCE
DOC
(Y/N)
PARA SEC PG CHP
1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N
3 DWG 345-
8574539 SCD-9243.00K Genset Upgrade Equipment Arrangement EDG Rm 1 & Emer Switchgear Rm
B Y AL
L
4 DWG 301-
8621260
SCD-9243K Power System 2000KW Emergency Diesel Generator 1 Upgrade Removal
B Y AL
L
5 DWG 301-
8621261
SCD-9243K Power System 2000KW Emergency Diesel Generator 1 Upgrade Installation
B Y AL
L
6 DWG 301-
8622088
SCD-9243 EDG No. 1 Pmp Fuse Panel Power Modification
A Y AL
L
7 DWG 301-
8974217
SCD-9243.00K Load Center Modifications Incidental to EDG 1 Upgrade
- Y AL
L
FOUO
SHIP: LCC-19 CHG/VER: 2/2
REF.
NO.
DOCUMENT
/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV CHG
NO.
COPY
REQ’D
(Y/N)
SOURCE
DOC
(Y/N)
PARA SEC PG CHP
8 DWG 302-
8621267
SCD-9243K Power System Modifications Incidental to Emergency Diesel Generator 1
A Y AL
L
9 DWG 302-
8622224
SCD-9243K Power System Removal Emergency Diesel Generator 1 Upgrade
A Y AL
L
10 DWG 302-
8622225
SCD-9243K Power System Install Emergency Diesel Generator 1 Upgrade
B Y AL
L
11 DWG 302-
8622226
SCD-9243K Power System Removal EDG 1 Upgrade HVAC
A Y AL
L
12 DWG 302-
8622227
SCD-9243K Power System Installation EDG 1 Upgrade HVAC
B Y AL
L
13 DWG 302-
8622329
SCD-9243 Cableway Modifications Incidental to Emergency Diesel Generator 1
A Y AL
L
14 LAR
NSWCPD-
0666-24
SCD 9243 8621261A Power System 2000KW EDG No 1 Upgrade Installation
- Y AL
L
15 LAR SRFY-
0036-25
Discrepancies regarding DWG 302-
8622329 REV A
- Y AL
L
16 DWG 303-
8622306
SCD 9243 Lighting System Modifications Incidental to Cableway EDG 1
A Y AL
L
17 DWG 303-
8622307
SCD 9243 Lighting System Removals Emergency Diesel Generator No. 1
A Y AL
L
18 DWG 303-
8622308
SCD 9243 Lighting System Installation Emergency Diesel Generator No. 1
A Y AL
L
19 DWG 401-
8621337
SCD 9243 MISC IC Mods Incdt to Ship Service EDG 1 Replacement
A Y AL
L
20 DWG 401-
8623071
SCD 9243 MISC Damper Alarm Mods Incid to SCD 9243
A Y AL
L
21 LAR SRFY-
0270-24
Discrepancies regarding DWG 401-
8621337 REV A
- Y AL
L
22 PDD 301-
ELM-250187
SUPPL INFO FOR SCD 9243
GENSET UPGRADE (EDG #1)
- Y AL
L
23 PDD 302-
ELM-250168
Patch for Removed Strl Pen of Cableway Incid to EDG #1 Upgrade
- Y AL
L
24 PDD 300-
ELM-230313
SRF-JRMC STD ELM
INSTALLATION OF STEEL &
CRES STUFFING TUBE
A Y AL
L
25 DWG 114-
2491155
TRANSV BHD FR 40, Pump RM BHD and Trunk BHD FR 44-45
K Y AL
L
26 DWG 103-
2491035
1st PLATF PLTG FR 8 - FR 52 F Y AL L
27 DWG 104-
2491047
5TH DK PLTG STEM - FR 51 1/2 H Y AL
L
28 DWG 103-
2491032
2ND PLTF PLATING FR 8-52 G Y AL
L
29 DWG 114-
2491156
AGC19 TRANSV BHD FR 52 & 64 G Y AL
L
30 DWG 604-
2491423
NON STRUCT BHD 1ST PLATF K Y 4,7
31 DWG 604-
2491689
MET JOINER BHD BEL 5TH DK G Y AL
L
32 DWG 114-
2491157
TRANSV BHD FR 76 & 86 N Y AL
L
33 DWG 103-
2491036
1ST PLATF PLTG FR 52-98 G Y AL
L
34 DWG 107-
2491059
MN DK PLTG STEM - FR 51-1/2 G Y AL
L
FOUO
SHIP: LCC-19 CHG/VER: 2/2
REF.
NO.
DOCUMENT
/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV CHG
NO.
COPY
REQ’D
(Y/N)
SOURCE
DOC
(Y/N)
PARA SEC PG CHP
35 MIL MIL-
STD-2003
Electric Plant Installation Standard Methods for Surface Ships and Submarines
B N
36 TM S9AA0-
AB-GOS-
010/GSO
General Specifications for Overhaul of Surface Ships (GSO)
11 N
37 DWG 509-
2492391
POTABLE WATER SYS FR 52-76
5TH DK & BELOW, ARR
E Y AL
L
38 DWG 509-
2492384
POTABLE WATER SYS - DIAG
PLANS - 4TH DK & BEL
E Y AL
L
3. APPENDICES:
3.1. Appendix “J” TGI Job Summary Information Sheet
3.2. Appendix "M" TGI Material List
3.3. Appendix “D” Deficiency Form
4. GENERAL REQUIREMENTS:
4.1. Not Applicable.
5. PROCEDURE:
5.1 Pump out, clean and dry the bilge area located in 1.2.50 and 1.2.51 free from oil, debris, and other foreign matter.
5.2 Accomplish electrical removals, modifications and installations of the system listed in 1.3.1 through 1.3.16 in accordance with 2.3 through 2.24, using 2.25 through 2.34 for guidance.
5.2.1 Electrical installations must be in accordance with 2.35.
5.2.2 Accomplish the requirements of 009-12 of 2.1, including Table 2, Column(s) A, Lines One through 7.
5.2.3 Accomplish the requirements of 009-25 of 2.1 for a local air hose test of each new weld of the watertight/airtight structural boundary. Allowable leakage: None.
5.2.4 Inspect each protective device of the equipment listed in 1.3.1.1 through 1.3.1.3.
5.2.4.1 Verify that size and setting of each overload heater are correctly used under motor full load running current in accordance with Section 302g of 2.36, 2.8 and 2.12.
(V) "SIZE/SETTING"
5.2.4.2 Verify that each fuse is correctly sized in accordance with Section 302g of 2.36, 2.8 and 2.12.
(V) "SIZE"
5.3 Remove existing and reinstall each potable water piping listed in 1.3.17 for accomplishment of electrical work, using 2.37 and 2.38 for guidance.
5.3.1 Accomplish the requirements of 009-87 of 2.1 for each potable water piping listed in 1.3.17.
FOUO
SHIP: LCC-19 CHG/VER: 2/2
5.3.1.1 Accomplish the requirements of 009-09 of 2.1 for chlorination and bacteriological tests. Analysis and testing conducted by a qualified Japanese laboratory (accredited by ISO 17025 or equal) are authorized by the
SUPERVISOR.
5.3.1.2 Record results of chlorination and bacteriological test on a Laboratory Analysis Record(s) and DD Form 686, and submit one legible copy, in hard copy or approved transferrable media, of completed record(s) and form(s) to the
SUPERVISOR.
5.3.2 Accomplish the requirements of 009-12 of 2.1, including Table One, Column(s) A, Lines One through 10.
5.4 Confirm that all personnel have exited the space prior to closure of the space listed in 1.2.9.1. Designate one person to account for all personnel who may have entered the space.
5.5 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
5.6 Notes:
5.6.1 Planner: Code 233 K. Ono, 080-9350-1438
Planner: Code 233 I. Tochigi, 080-9350-1457 Planner: Code 231B, T. Oosera, 243-9935 Planner: Code 231B, M. Haga, 243-2513 Planner: Code 231B, Y. Arakawa, 243-4496 Planner: Code 231B, A. Suzuki, 243-0968 Planner: Code 234, O. Mitsui 070-7787-2048 Planner: Code 234, K. Furukawa 243-2242
5.6.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
5.6.3 Replacement of electrical grade sheet deck covering system of each space listed in 1.2.34 will be covered by TGI No. 3819P14122A01 (KTR TGI).
5.6.4 Opening, initial cleaning, closing, and installation/removal of FMEs of each space listed in 1.2.49 and 1.2.52 will be covered by the following TGI No(s).
Distillate Fuel Service Tank (7-82-2-F): 3819P12303A01 (KTR TGI) Potable Water Tank (9-76-4-W): 3819P12325A01 (KTR TGI)
5.6.5 Opening, initial cleaning, and closing of each space listed in 1.2.53 will be covered by TGI No.
3819P12319A01 (KTR TGI).
5.6.6 Provision of oily/chemical water barge will be coordinated by Project Team.
5.6.7 Work per this instruction involves cutting an access (or removal of a door) through a fire zone bulkhead, through the hull of the ship above the turn of the bilge, through ventilation components (ducting, plenums, etc.), or through any air-tight, fume-tight or watertight bulkheads normally used to control air flow in the event of a shipboard fire. A nonflammable closure is required in accordance with COMNAVSEASYSCOM MSG R 261400Z JUL 12. The closure, if not continuously in use, shall be staged near the access, readily visible and accessible, so that any emergency responder can install the closure to affect proper air flow onboard the ship.
5.6.8 JCN EE01-L106 is related to this TGI.
5.7 Government Furnished Material (GFM):
5.7.1 All GFM listed in each S/A drawing will be provided as kitted material.
5.8 SRF-JRMC will provide the following service work: (TGI No. 3819P31001S02)
FOUO
SHIP: LCC-19 CHG/VER: 2/2
5.8.1 [C740] Crane and crane rigging service.
5.8.2 [X99E] Utility service, electrical.
5.8.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.
5.8.4 [C106.1] Safety inspection for SRF-JRMC employees.
5.8.5 [C106.2] Gas free inspection for SRF-JRMC employees.
5.8.6 [C133] QA inspection for (G) symbol(s).
5.8.7 [C292] Visual TEMPEST Configuration Control Inspection (VTCCI).
FOUO
J-1
SHIP: LCC-19 CHG/VER: 2/2
APPENDIX "J"
TGI JOB SUMMARY INFORMATION SHEET
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
SA 79243K ELEC EDG#1 AY A 0 2
CU PHASE TITLE:
*(RE) F/O-S/A 79243K, ACCOMPLISH ELEC WORK FOR EDG#1, ESLP SS/EDG GENSET UPGRADE
PRIMARY COMPONENT:
COMPONENT UNIT LIST (FOR ASSEMBLIES):
FOUO
J-2
SHIP: LCC-19 CHG/VER: 2/2
(6-35-2)-2P-A C- (6-35-2)-4P-A C- K-1EG11 C- K-1EG27 C- K-1EG14 C-
K-1EG16 C- K-1EG17 C- K-1EG18 C- K-1EG19 C- K-1EG24
C- K-1EG13 C- K-1EG15 C- K-1EG26 C- K-EC509 C- K-EC510
C- K-EC511 C- K-EC512 C- K-1EG25 C- K-1EG26 C- VNT SS 1-39-1
DT CMPT 6-40-0-A MS#1EDG BTRY#1 BA #1EDG BTRY#4 BA #1EDG BTRY#2
BA #1EDG BTRY#3 BA #1EDG BATCHG7-30-0-E BC CKT 1BC1 IC (6-39-2)-28P-A C-
(6-35-2)-1P-(6-37-2) C- (6-35-2)-4P-(6-37-2) C- (6-39-2)-28P-A C- (6-39-2)-28P-B C- (6-39-2)-28P-C C- (6-39-2)-28P-D C- (6-39-2)-28P-G C- 11-4P(3-39-2)(3-39-4 C-11-4P-(3-39-2) C- 1E-1P-PMP
C- 1E-1P-PMP(CNTRL-1) C- 1E-1P-PMP(CNTRL-2) C- 1E-1P-PMP(SENS) C- 1E-28P-PMP
C- 1E-4EP-(6-39-4) C- 1E-4EP-6-39-2 C- 6-35-2-1P-C C- 6-35-2-4P-C C- 6-39-2-4EP-A
C- PMP-1E(COM) C- PMP-28P-NTWK 2A C- PMP-28P-NTWK 2AALTDC C- PMP-28P-NTWK 2B
C- PMP-28P-NTWK 2BALTDC C- RECT 1A-28P-1E DIST C- RECT 1A-28P-PMP C- RECT 1B-28P-
1E DIST C- RECT 1B-28P-PMP C- PP 6-39-2 PA 32123-3-301KTR TT TF 6-36-2
XF 6-37-2-1P-A C- (6-37-2)-1P-D C- 6-37-2-1P-D C- (3-29-5)-4P-A(CC1F) C- (6-39-
4)-4EP-A C-(6-39-4)-4EP-B C- 6-39-4-4EP-A C- 6-39-4-4EP-B C- (6-35-2)-4P-B C- 1WDG-
4EP-1E C- K-1EG101 C- K-1EG102 C- K-1EG103 C- K-1EG105 C-
K-1EG106 C- K-1EG107 C- K-1EG108 C- K-1EG110 C- K-1EG111
C- K-1EG112 C- K-1EG114 C- K-1EG123 C- K-1EG124 C- LSSHOF-150
C- POT WTR 9-76-4-W TK 1E-4EP-(6-37-4)(EMER C- 1EA-4EP-(6-39-2) C- 44-4P-(6-37-4)(NORM) C- PP 6-37-4 PA (5-39-1)-1L-B2/F13 LF(2-38-1)-1L-C2E RC (5-39-1)-1L-B2/F13 RC (2-38- 1)-1L-H1 LF(2-38-1)-1L-J11&J12 LF (2-38-1)-1L-J7 LF (2-38-1)-1L-J9 LF (3-53-1)-1L-C2E LF
(4-36-1)-1L-C1A&C1C LF (4-36-1)-1L-C1D LF (4-36-1)-1L-C1F LF (4-36-1)-1L-C3A LF (4-36- 1)-1L-F11 LF (4-36-1)-1L-F1B LF (4-36-1)-1L-F2F LF (6-81-1)-1L-B1 LF (6-37-2)-1P-A C-
(6-37-2)-1P-G(M) C- (6-37-2)-1P-G(MTR) C- (6-37-2)-1P-G(SW) C- (6-37-2)-1P-H(M) C- (6-37- 2)-1P-H(MTR) C- (6-37-2)-1P-H(SW) C- (6-37-4)-4P-A(INTLK) C- CKT 5AV IC CKT FR IC/SM-
20 SB CKT FR IC/SM-50 SB (6-37-4)-1P-C(CONT1) C- (6-37-4)-1P-C(CONT2) C- (6-37-
4)-1P-C(OT1) C- (6-37-4)-1P-C(OT2) C- (6-37-4)-1P-C(TS) C- (6-37-4)-4P-B C- (6-37-4)-4P-D C-
RHR 1-36-1 HT RHR 1-36-3 HT CONTACTOR 1-36-1 RE CONTACTOR 1-36-3 RE
(4-36-1)-1L-C3G C- (4-36-1)-1L-C5A C- (4-36-1)-1L-C5B C- (4-36-1)-1L-C5C C- (4-36-1)-1L-
C5F C- (4-36-1)-1L-C5G C- (4-36-1)-1L-C5H C- (6-37-4)-1P-C(CONT) C- (6-37-4)-1P-C(CTR) C- (6-37-4)-4-A C- (6-37-4)-4P-A C- (6-37-4)-4P-A(HALON) C- (6-37-4)-4P-A(PB) C- (6-37- 4)-4P-C C- (6-37-4)-4P-C(CT) C- (6-37-4)-4P-C(HALON) C- (6-37-4)-4P-C(PB) C- (6-37-4)-4P-C(RLY) C-
(6-39-4)-4EP-A(HALON C- (6-39-4)-4EP-A(MLS) C- (6-39-4)-4EP-A(PB) C-(6-39-4)-4EP-B(HALON
C- (6-39-4)-4EP-B(MLS) C- (6-39-4)-4EP-B(PB) C-VNT E1-37-2 CT VNT S1-37-1 CT VNT
E1-37-2 FA VNT S1-37-1 FA 2-RLY PNL 6-30-2-E PA (6-39-2)-1EP-C(CONT2 C- (6-39-
2)-4EP-C(CONT1 C- 6-39-2-1EP-C(CONT2) C- (3-39-4)-24P-B(CONT) C- (3-39-4)-4P-B(CONV) C-
(3-39-4)-4P-B(DISPEN C- (3-39-4)-4P-B(RACKSW C- (3-39-4)-4P-B(RINSE) C- (3-39-4)-4P-
B(WASH) C- (4-34-2)-4P-B(P) C- CMPT 6-52-4-A MSPOTW 5-60-0-L PPR-DD C- FOST
7-82-2-F TK CMPT 8-86-0-E MSCMPT 6-64-4-L MSCMPT 6-70-2-Q MS CMPT 6-72-2-Q
MS (6-39-2)-1EP-C C- (6-39-2)-4EP-C C- (3-39-4)-4P-A C- (3-39-4)-4P-B C- (3-39-4)-4P-C C- (3-39-4)-4P-D C- (4-34-2)-4P-B C- (4-34-2)-4P-B1 C- (4-34-2)-4P-B2 C- (4-34-2)-4P-B3 C- CTE 6-30-2-E XF TF BANK 6-34-2 XF(6-37-2)-1P-F C- 6-35-2-24P-A4 C- 6-35-2-4P-G
C- K-1EG-1 C- PMP-1SSEDG MPU-1 C- #1EDG CAT PANEL PA K-1EG23 C-
(6-37-2)-1P-F CB K-1EG12 C- K-1EG135 C- (6-39-2)-28P-E C- (6-39-2)-28P-F
C- PMP-1E BATT CHRGR C- (4-36-1)-1L-C1B C- K-EG-130 C- 1EG-4EP-1E C-
1PLMC-1SSEDG C- 1SSEDG-DLOP C- 1SSEDG-DPS C- 1SSEDG-GLOP
C- 4-36-1-1L-C1B HTR C- 6-35-2-4P-B2 C- 6-35-2-4P-D2 C- 6-37-2-1P-G4 C- 6-37-2-
1P-G5 C- EDG124PEMERSHUTDOW1A C- K-EG-1 C- K-EG-109 C- K-EG-110
C- K-EG-111 C- K-EG-112 C- K-EG-117 C- K-EG-119 C- MPU-
1SSEDG(MPU) C- PMP-1PLMC C- PMP-1SSEDG(COM 1) C- PMP-1SSEDG(COM) C- PMP-
ASSEDG COM 2 C- #1EDG PRE-LUBE MO CT 1E-1P-PMP RECT 1A C- 1E-4P-CPT C- 1E-4P-
PMP UPS1 C- 1S-4P-1E C- PMP FUSE 6-30-2-E PA 6-35-2-4P-B1 C- 6-35-2-4P-D1
C- 6-37-2-1P-G2 C- 6-37-2-1P-G3 C- #1EDG JKTWH CR ENL#1 MQ #1EDG JKTWH CR ENL#2 MQ
(4-36-1)-1L-C1B C- 6-35-2-4P-A C- #1 EDG SW CLG PUMP CT CKT JV IC CKT J
IC 1MC 2-342 LD 1MC 2-900A LD 1MC 2-901 LD 1MC 2-902 LD CKT 2FR
IC CKT 3FR IC CKT 5EK IC CKT TD51 IC IC/SM-4 ALM 7-30-0-E SB I/O
FOUO
J-3
SHIP: LCC-19 CHG/VER: 2/2
ENCLOSURE #1 EE CKT 5TK IC IC CKT2TV IF7-30-0-E BX CAMERA 7-30-0-E EE K-
1EG129 C- K-1EG130 C- K-1EG131 C- K-1EG132 C- K-1EG133 C-
K-1EG134 C- 1E-4EP-1EA C- K-1EG20 C- K-1EG21 C- K-EC500
C- K-EC501 C- K-EC502 C- K-EC504 C- K-EC505 C- K-EC506
C- K-EC507 C- K-EC508 C- K-1EG109 C- K-1EG113 C- K-1EG115
C- K-1EG116 C- K-1EG117 C- K-1EG118 C- K-1EG119 C- K-1EG120
C- K-1EG121 C- K-1EG122 C- K-1EG125 C- K-1EG126 C- K-1EG127
C- K-1EG128 C- DG SENSING ENCLOSURE EE LGE ENG COT PNL PA DUAL VR
RG 6-35-2-24P-A1 C- 5-91-2-1SF-A C- (5-91-2)-4P-A C- (5-91-2)-4P-B C- UPS1EP-5-91- 2-1P-B-1 C- UPS4EP-(5-91-2)-4P-B C- UPS4EP-5-91-2-4P-B-5 C- #1 EDG GE CMPT 6-30-2-E
MS CMPT 6-64-2-Q MS CMPT 8-76-0-E MSCMPT 6-68-4-Q MS CMPT 7-30-0-E MS
CMPT 2-36-0-Q MS BLST 9-86-6-W TK #1 EDG ENGINE EN
ATTACHMENT LIST:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
TAKAHASHI ,YASUHIKO
JO: KO: TOTAL MAN HRS: PLANNING ACCEPTANCE:
3819P31001 A04
TOTAL DURATION:
CU PHASE DESCRIPTION:
The purpose of this TGI is to accomplish electrical work for emergency diesel generator no. one, extended service life program ship service/emergency diesel generator generator-set upgrade.
Location of Work:
Emergency Generator Room No. One (7-30-0-E) 01 Level Weather, Frames between 36 and 37, Port Main Deck Weather, Frame 35, Port Main Deck Weather, Frames between 36 and 38, Starboard (Stbd) Fan Room (1-34-1-Q) Fan Room (1-34-2-Q) Fan Room (1-36-0-Q) Fan Room (1-36-2-Q) Fan Room (1-38-0-Q) Vent Plenum for Heating Ventilation and Air Conditioning (HVAC) Supply Systems (SS) 1-39-1, Frames between 37 and 39, Stbd Fan Room (1-38-2-Q) N3 Office (2-30-1-Q) N3 ACOS Office (2-33-2-Q) N7 Office (2-36-0-Q) Radio Transmitter Room No. One (3-19-0-Q) S-5 Office (3-30-0-Q) Passage (3-30-01-L) Diesel Exhaust Piping Space and Deck Gear Locker (3-31-3-Q) Wardroom Galley (3-34-0-Q) Wardroom Scullery (3-34-2-Q) State Room (3-37-1-L) Boatswain Storeroom (4-D-0-A) Crew and Troop Messroom and FWD Battle Dressing Station (4-30-0-L) Crew Sculley (4-36-0-Q) Load Center 21/22 (4-57-2-Q) Trunk (5-30-0-T) Crew Living Space (STAFF) (5-30-01-L) CPO Staff Washroom, Water Closet, Shower and Decontamination Station (5-30-2-L) Crew Living Space (Female) (5-40-0-L)
1.2.29 Crew Living Space (5-52-0-L)
Emergency Switchgear Room No. One (6-30-2-E) Passage (5-60-4-L)
FOUO
J-4
SHIP: LCC-19 CHG/VER: 2/2
CU PHASE DESCRIPTION:
Crew Lounge (5-60-0-L) Passage (5-64-4-L) CPO Staff Washroom, Water Closet, Shower and Decontamination Station (5-64-2-L) Main GSK / SD Storeroom (6-40-0-A) Storeroom (6-52-4-A) Passage (6-60-0-L) Passage (6-61-2-L) Photo Lab Office (6-64-2-Q) Passage (6-64-4-L) Changing Area (6-68-4-Q) Production Chief Office (6-70-2-Q)
EIC (6-72-2-Q)
B Division Storeroom (6-76-2-A) Engine Room Enclosed Operating Station (6-86-0-E) Ship Fitter Storeroom (6-86-2-A) SD Storeroom (7-30-1-A) Crew Baggage Storeroom (7-30-2-A) Distillate Fuel Service Tank (7-82-2-F) Fire Room (8-76-0-E) Engine Room (8-86-0-E) Potable Water Tank (9-76-4-W) Fresh Water Ballast (9-86-6-W)
TASK NAME
SHOP TSD/WC TS CREW# MHRS
HIGH RAD
HOURS
RC
GRID#
5.1 LBR . 22 KE PC
5.2 ELEC , ELEX , SFTR , WELD , STML , INSL , RGRS ,
PNTR , CARP , QA , PFTR , BLRM .
22 KE PC
5.3 PFTR , WELD , INSL , QA . 22 KE PC
5.4 ELEC . 22 KE PC
5.5 PNTR , QA . 22 KE PC
Electrical Work CFM: for air compressor rental cost, fuel oil cost, asbestos sample and analysis cost, banding material, fasteners, insulation tape, plastic bags, rope, and other consumable.
22 MQ CS
Electronics Work CFM: or cable banding and other consumables.
22 MQ CS
Structure Work CFM: for all deck covering material, paints, thinner, grit, disposal cost, fire watch and tank watch cost, marine chemist cost, air compressor rental cost and fuel oil cost for air hose test, lead sampling/analysis cost, asbestos sample and analyze, cost for compartment and duct insulation, ---continue to below---
22 MQ CS
---continued from above---deck tile, and underlayment, adhesive for pin, pin, fasteners, rivets, tyvex suit, plastic bags, fasteners, and MISC such as electrode, gases, temporary closure, and covering material, and other consumable.
22 MQ CS
Piping Work CFM: for fire watch cost, bulk sample cost and analysis cost for asbestos, disinfection cost and MISC such as gases, electrode, saw blades, painting material, plastic bag/sheet, tyvek suit and etc.
22 MQ CS
Boiler Work CFM: for covering material, fastener and MISC. 22 MQ CS
FOUO
J-5
SHIP: LCC-19 CHG/VER: 2/2
TASK NAME
SHOP TSD/WC TS CREW# MHRS
HIGH RAD
HOURS
RC
GRID#
Lagging Work CFM: for covering material, asbestos sampler/analysis cost, paint, and MISC.
22 MQ CS
Process Funding Document. 10 CT OM
Version-1 modification of Ref. No. 23 was required.
[C233 M. Hosono, 2/26/2025] -/-/N
V-01
Version-2 update material information of KOI 404 and 405.
[C233 M. Toda, 3/3/2025] -/Y/N
V-02
FOUO
M-1
SHIP: LCC-19 CHG/VER: 2/2
APPENDIX “M”
TGI MATERIAL LIST
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
SA 79243K ELEC EDG#1 AY A 0 2
CU PHASE TITLE:
*(RE) F/O-S/A 79243K, ACCOMPLISH ELEC WORK FOR EDG#1, ESLP SS/EDG GENSET UPGRADE
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV
1 ELM-250187
2 605-8578020 A
JOB ORDER: KEY OP:
3819P31001 A04
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
001 1 1 M ANGLE,STRUCTURAL, ORDER
FOR KTR
ORIG: C226 K.YAMAMI, 080-
9350-1447
9B 9520 002774942 NA 4 N 50515114 15/FT
002 2 1 M PAD, TAPPED ROUND, PAD,
TAPPED ROUND, 1/4"-20UNC-
2B X 1"LG, STEEL, CARBON,
AISI-1020, CENTERED,
CONCENTRIC INTERNAL
THREAD THRU HOLE 5/8" OD,
FINISH: PLAIN.
BIW CATALOG NO.53204-155
ORDER FOR KTR
ORIG: C226 K.YAMAMI, 080-
9350-1447
9B 5340 LL9003506 NA 4 N 50517454
100/EA
NOTES:
FOUO
M-2
SHIP: LCC-19 CHG/VER: 2/2
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
003 3 1 M PAD, TAPPED ROUND, PAD,
TAPPED ROUND,
CENTERED, CONCENTRIC
INTERNAL THREAD THRU
HOLE 3/4" OD,
SIZE: 3/8-16UNC-2B X 1" LG,
MATL: STEEL, CARBON, AISI-
1020, FINISH: PLAIN,
BIW CATALOG NO. 53204-040,
ORDER FOR KTR
ORIG: C226 K.YAMAMI, 080-
9350-1447
9B 5340 LL9306697 NA 4 N 50517457
100/EA
004 4 1 M PAD, TAPPED ROUND, ORDER
FOR KTR
ORIG: C226 K.YAMAMI, 080-
9350-1447
9B 5315 LL9307892 NA 4 N 50517450
100/EA
005 5 1 M PIPE,METALLIC, ORDER FOR
KTR
ORIG: C226 K.YAMAMI, 080-
9350-1447
9B 4710 002785348 NA 4 N 50515118 2/FT
006 6 1 M PLATE,METAL, SIZE: 2 FT X 1
FT,
ORDER FOR KTR
ORIG: C226 K.YAMAMI, 080-
9350-1447
9B 9515 001533184 NA 4 N 50515108 2/SF
100 M PLATE,ME, 5FT X 5FT X 1PM
REQUIRED
ORDERED FOR KTR
ORIG: C231B, T. OOSERA 243-
9B 9515 001533223 NA 4 N 50515107 25/SF
111 M INSULATI, MATERIAL ORDER
FOR KTR
ORIG: C231B M.HAGA 243-2513
9Q 5640 008096312 NA 4 N 50515133 16/EA
112 M INSULATI, MATERIAL ORDER
FOR KTR
ORIG: C231B M.HAGA 243-2513
9Q 5640 008096315 NA 4 N 50515134 18/EA
113 M TAPE,TEX, MATERIAL ORDER
FOR KTR
ORIG: C231B M.HAGA 243-2513
9B 8315 002671632 NA 4 N 50515135 3/RO
114 M TAPE,TEX, MATERIAL ORDER
FOR KTR
ORIG: C231B M.HAGA 243-2513
9B 8315 002671633 NA 4 N 50515136 3/RO
115 M CAP,SNAP, MATERIAL ORDER
FOR KTR
ORIG: C231B M.HAGA 243-2513
9B 5325 007377648 NA 4 N 50515147
300/EA
116 M ADHESIVE, MATERIAL ORDER
FOR KTR
ORIG: C231B M.HAGA 243-2513
9B 8040 002738708 NA 4 Y 50515109 1/GL
117 M SOUND CO, MATERIAL ORDER
FOR KTR
ORIG: C231B M.HAGA 243-2513
9Q 5640 007565866 NA 4 N 50515137 10/SH
FOUO
M-3
SHIP: LCC-19 CHG/VER: 2/2
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
118 27 2 M FLOOR COVERING, LONSEAL
FLOORING, UV SERIES,
FLOOR COVERING
INSULATION FOR HIGH
VOLTAGE APPLICATION,
SPEC: MIL-DTL-15562 TYPE 1,
SIZE: 6 FT W X 0.128"
OVERALL THK X 30 FT LG,
COLOR: BLUE MARBLE,
SURFACE CONDITION:
SMOOTH SURFACE,
ORDER FOR KTR
ORIG: C226 H.SHIMIZU, 080-
9350-1431
9B 7220 LL9311206 NA 4 N 50517486 1/RO
400 M INSULATI, ORDERED FOR KTR
ORIG:C234 O.MITSUI 070-7787-
9B 5640 LL9607841 NA 4 N 50517451 2/EA
401 M INSULATI, ORDERED FOR KTR
ORIG:C234 O.MITSUI 070-7787-
9B 5640 LL9607840 NA 4 N 50517453 2/EA
402 M COUPLING,TUBE, 1/4" IPS, CU-
NI 90-10, SW, PG=2EA
ORDERED FOR KTR
ORIG:C234 O.MITSUI 070-7787-
9B 4730 014635868 NA 4 N 50515121 1/PG
403 M COUPLING, 3/8" IPS, CU-NI 90-
10, SW
ORDERED FOR KTR
ORIG:C234 O.MITSUI 070-7787-
9C 4730 LL4462577 NA 4 N 50517455 2/EA
404 M COUPLING,TUBE, 2" IPS, CU-NI
90-10, BW
ORDERED FOR KTR
ORIG:C234 O.MITSUI 070-7787-
9B 4730 005423290 NA 4 N 2/EA
405 M SLEEVE,, 1-1/4" IPS, CU-NI 90-
10, BW
ORDERED FOR KTR
ORIG:C234 O.MITSUI 070-7787-
9C 4730 LL4903762 NA 4 N 2/EA
450 M INSULATI, ORDERED FOR KTR
C234 K.FURUKAWA, 243-2242
9B 5640 LL9607844 NA 4 N 50537450 2/EA
451 M INSULATI, ORDERED FOR KTR
C234 K.FURUKAWA, 243-2242
9B 5640 LL4783095 NA 4 N 50517456 2/EA
452 M ADHESIVE, ADHESIVE FOR
CLOTH,
C234 K.FURUKAWA, 243-2242
ORDERED FOR KTR
9B 8040 002738708 NA 4 Y 50515110 1/GL
453 M ADHESIVE, ADHESIVE FOR
PLASTIC TUBE
ORDERED FOR KTR
C234 K.FURUKAWA, 243-2242
9B 8040 008419773 NA 4 Y 50515115 2/PT
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR APPENDIX "D"
DEFICIENCY FORM
☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One)
2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
LCC-19 SA 79243K ELEC EDG#1 AY A 0
4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:
3819P31001 A04
7. DESCRIPTION:
8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
9. CORRECTIVE ACTION:
10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
FOR NON-NUCLEAR USE ONLY
11. RFD/RFW REQ’D ☐ LAR REQ'D ☐
ILS MOD REQ’D ☐
SRD/PLAN REV REQ'D ☐
DWG NO.: _____________________ S/A NO.: ___________________
12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:
SATISFACTORY:
13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
YES ☐ NO ☐
14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE:
15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
_________:YES ☐ NO ☐
16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE (DR ONLY)
DL’s ISSUED
(DR ONLY)
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
LCC-19 SA 79243K ELEC EDG#1 AY A 0