This document is a Task Group Instruction (TGI) for electrical work on the USS Blue Ridge (LCC-19), specifically focused on upgrading the Emergency Diesel Generator No. One as part of an Extended Service Life Program. The work involves comprehensive electrical removals, modifications, and installations across multiple ship compartments, including the Emergency Generator Room, various fan rooms, offices, and other spaces. The project is scheduled to start on 1/12/2026 and complete by 8/5/2027.

Key technical requirements include electrical work on the power system, lighting system, ventilation controllers, and various communication and alarm systems. The instruction specifies detailed procedures for electrical installations, protective device inspections, potable water piping modifications, and compliance with specific technical standards. Special requirements include working in spaces with potential asbestos, lead, and PCB hazards, and maintaining fire zone boundary integrity. The work will be performed using government-furnished materials and supported by various service work from SRF-JRMC, including crane services, utility services, safety inspections, and quality assurance.

View the file

Other files

File Type Posted
TGI_3819P31003A06_c0v0_redact.pdf PDF
TGI_3819P31003A05_c0v0_redact.pdf PDF
TGI_3819P31003A03_c0v0_redact.pdf PDF
TGI_3819P31003A02_c0v0.pdf PDF
TGI_3819P31002A04_c3v3.pdf PDF
TGI_3819P31001A01_c3v4.pdf PDF
TGI_3819P31003A01_c0v0_redact.pdf PDF
TGI_3819P31002A05_c2v0.pdf PDF
TGI_3819P31002A03_c3v2_redact.pdf PDF
TGI_3819P31002A02_c1v1_redact.pdf PDF
TGI_3819P31001A06_c2v1.pdf PDF
TGI_3819P31001A04_c2v2.pdf PDF
TGI_3819P31001A03_c0v0_redact.pdf PDF
Attachment II Price Proposal Form N6264925RA041_CLIN 0002 and CLIN 0004.xlsx XLSX spreadsheet
N6264925RA041-0010.pdf PDF
TGI_3819P31002A05_c2v0.pdf PDF
N6264925RA041-00006.pdf PDF
N6264925RA041-0003.pdf PDF
N6264925RA041-0002.pdf PDF
TGI_3819P31003A03_c0v0_redact.pdf PDF
TGI_3819P31002A04_c0v2_redact.pdf PDF
TGI_3819P31003T09_c0v0_redact.pdf PDF
TGI_3819P31003T06_c0v0_redact.pdf PDF
TGI_3819P31002T12_c0v0_redact.pdf PDF
TGI_3819P31002T09_c0v0_redact.pdf PDF
TGI_3819P31002T08_c0v0_redact.pdf PDF
TGI_3819P31002T06_c0v0_redact.pdf PDF
TGI_3819P31002T05_c0v0_redact.pdf PDF
TGI_3819P31002T01_c0v0_redact.pdf PDF
TGI_3819P31001T06_c0v0_redacted.pdf PDF
Attachment II Price Proposal Form N6264925RA041.xlsx XLSX spreadsheet
2.01 N6264925RA041.pdf PDF
TGI_3819P31003A05_c0v0_redact.pdf PDF
TGI_3819P31003A01_c0v0_redact.pdf PDF
TGI_3819P31002A01_c0v0_redact.pdf PDF
TGI_3819P31001A03_c0v0_redact.pdf PDF
TGI_3819P31003T10_c0v0_redact.pdf PDF
TGI_3819P31003T05_c0v0_redact.pdf PDF
TGI_3819P31002T02_c0v0_redact.pdf PDF
TGI_3819P31001T09_c0v0_redacted.pdf PDF
TGI_3819P31001T05_c0v0_redacted.pdf PDF
Attachment V Contract Data Sheet.pdf PDF
TGI_3819P31002A06_c0v0_redact.pdf PDF
TGI_3819P31002A05_c1v0_redact.pdf PDF
TGI_3819P31002A03_c3v2_redact.pdf PDF
TGI_3819P31001A05_c0v0_redact.pdf PDF
TGI_3819P31001A02_c2v1_redact.pdf PDF
TGI_3819P31001A01_c0v3_redact.pdf PDF
TGI_3819P31003T04_c0v0_redact.pdf PDF
TGI_3819P31002T04_c0v0_redact.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

FOUO: Public availability to be determined under 5 USC 552

TASK GROUP INSTRUCTION

AIM REV 20.11.4.0 (OCTOBER 2020)

TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:

NO.: SA 79243K ELEC EDG#1 AY A 0 2

SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE:

*(RE) F/O-S/A 79243K, ACCOMPLISH ELEC WORK FOR EDG#1, ESLP SS/EDG GENSET UPGRADE

PREPARING ACTIVITY:

PREPARED BY: CODE PHONE DATE

KAZUKI ONO 233.1 080-9350-1438 15-FEB-2025

APPROVED BY: CODE PHONE DATE

MASAHIRO HOSONO 233.1 080-9350-1455 15-FEB-2025

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

REASON FOR WORK/NEED FOR CHANGE:

Additional materials was required. Update of material list is required.

CHANGE INSTRUCTIONS:

CH1: Modify document number of reference 2.23. (2/26/2025) CH2: Add materials and update material list. (3/3/2025)

SPECIAL REQUIREMENTS:

CLASS P-2 PIPING, CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL II, CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL III, This work affects a fire zone boundary. Fabrication and/or staging of a non-flammable closure is required.

WORK CERTIFICATION SIGNATURES

COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:

ACCEPTANCE OF COMPLETED WORK

PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:

REQUIRED:☐YES ☒NO

RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:

TGI NO.: SA 79243K ELEC EDG#1 AY A 0

FOUO

SHIP: LCC-19 CHG/VER: 2/2

LIST OF EFFECTIVE PAGES

SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.

1-9 J1-5 M1-3

1. SCOPE/PURPOSE

1.1 Title: Electrical Work for Emergency Diesel Generator No. One, Extended Service Life Program Ship Service/Emergency Diesel Generator Generator-set Upgrade; accomplish

1.2 Location of Work:

1.2.1 Emergency Generator Room No. One (7-30-0-E)

1.2.2 01 Level Weather, Frames between 36 and 37, Port

1.2.3 Main Deck Weather, Frame 35, Port

1.2.4 Main Deck Weather, Frames between 36 and 38, Starboard (Stbd)

1.2.5 Fan Room (1-34-1-Q)

1.2.6 Fan Room (1-34-2-Q)

1.2.7 Fan Room (1-36-0-Q)

1.2.8 Fan Room (1-36-2-Q)

1.2.9 Fan Room (1-38-0-Q)

1.2.9.1 Vent Plenum for Heating Ventilation and Air Conditioning (HVAC) Supply Systems (SS) 1-39-1, Frames between 37 and 39, Stbd

1.2.10 Fan Room (1-38-2-Q)

1.2.11 N3 Office (2-30-1-Q)

1.2.12 N3 ACOS Office (2-33-2-Q)

1.2.13 N7 Office (2-36-0-Q)

1.2.14 Radio Transmitter Room No. One (3-19-0-Q)

1.2.15 S-5 Office (3-30-0-Q)

1.2.16 Passage (3-30-01-L)

1.2.17 Diesel Exhaust Piping Space and Deck Gear Locker (3-31-3-Q)

1.2.18 Wardroom Galley (3-34-0-Q)

1.2.19 Wardroom Scullery (3-34-2-Q)

1.2.20 State Room (3-37-1-L)

FOUO

SHIP: LCC-19 CHG/VER: 2/2

1.2.21 Boatswain Storeroom (4-D-0-A)

1.2.22 Crew and Troop Messroom and FWD Battle Dressing Station (4-30-0-L)

1.2.23 Crew Sculley (4-36-0-Q)

1.2.24 Load Center 21/22 (4-57-2-Q)

1.2.25 Trunk (5-30-0-T)

1.2.26 Crew Living Space (STAFF) (5-30-01-L)

1.2.27 CPO Staff Washroom, Water Closet, Shower and Decontamination Station (5-30-2-L)

1.2.28 Crew Living Space (Female) (5-40-0-L)

1.2.29 Crew Living Space (5-52-0-L)

1.2.30 Passage (5-60-4-L)

1.2.31 Crew Lounge (5-60-0-L)

1.2.32 Passage (5-64-4-L)

1.2.33 CPO Staff Washroom, Water Closet, Shower and Decontamination Station (5-64-2-L)

1.2.34 Emergency Switchgear Room No. One (6-30-2-E)

1.2.35 Main GSK / SD Storeroom (6-40-0-A)

1.2.36 Storeroom (6-52-4-A)

1.2.37 Passage (6-60-0-L)

1.2.38 Passage (6-61-2-L)

1.2.39 Photo Lab Office (6-64-2-Q)

1.2.40 Passage (6-64-4-L)

1.2.41 Changing Area (6-68-4-Q)

1.2.42 Production Chief Office (6-70-2-Q)

1.2.43 EIC (6-72-2-Q)

1.2.44 B Division Storeroom (6-76-2-A)

1.2.45 Engine Room Enclosed Operating Station (6-86-0-E)

1.2.46 Ship Fitter Storeroom (6-86-2-A)

1.2.47 SD Storeroom (7-30-1-A)

1.2.48 Crew Baggage Storeroom (7-30-2-A)

FOUO

SHIP: LCC-19 CHG/VER: 2/2

1.2.49 Distillate Fuel Service Tank (7-82-2-F)

1.2.50 Fire Room (8-76-0-E)

1.2.51 Engine Room (8-86-0-E)

1.2.52 Potable Water Tank (9-76-4-W)

1.2.53 Fresh Water Ballast (9-86-6-W)

1.3 Identification:

1.3.1 Quantity (One EA), Power System

Remarks: See 2.3 through 2.15, and 2.22 and 2.23 for details

1.3.1.1 Quantity (One EA), Controller for Seawater Pump Motor of Emergency Diesel Generator (EDG) No. One Remarks: See 2.8 for details

1.3.1.2 Quantity (One EA), Controller for Ventilation Fan S1-37-1 Remarks: See 2.12 for details

1.3.1.3 Quantity (One EA), Controller for Ventilation Fan E1-37-2 Remarks: See 2.12 for details

1.3.2 Quantity (One EA), Lighting System

Remarks: See 2.3, 2.16 through 2.18 and 2.22 for details

1.3.3 Quantity (One EA), Propulsion Plant Announcing System (2MC) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details

1.3.4 Quantity (One EA), Surveillance Camera System (6TV) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details

1.3.5 Quantity (One EA), Television Closed Circuit System (2TV) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details

1.3.6 Quantity (One EA), General Announcing System (1MC) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details

1.3.7 Quantity (One EA), Machinery Space Halon Alarm System (2FR) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details

1.3.8 Quantity (One EA), Alarm Safety and Warning System (3FR) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details

1.3.9 Quantity (One EA), Sound Powered Telephone System (J) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details

1.3.10 Quantity (One EA), Sound Powered Telephone System (JV) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details

1.3.11 Quantity (One EA), Sound Powered Telephone System (JAZ) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details

1.3.12 Quantity (One EA), Sound Powered Telephone System (X40J) for EDG No. One

FOUO

SHIP: LCC-19 CHG/VER: 2/2

Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details

1.3.13 Quantity (One EA), Tank Level Indicating System (5TK) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details

1.3.14 Quantity (One EA), Alarm Safety Waring System (5EK) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details

1.3.15 Quantity (One EA), Tank Level Indicating System (6TK) for EDG No. One Remarks: See 2.3, 2.19 through 2.21 and 2.22 for details

1.3.16 Quantity (One EA), Electronics System of Local Area Network (LAN) Drop Box Remarks: See Ref. No. 19 and Ref. No. 21 for details.

1.3.17 Quantity (One AY), Potable Water System Piping for Drinking Fountain located in 1.2.31 Size: 1/4 Inch IPS and 3/8 Inch IPS Material: Copper Alloy Overall Remarks: See Sheet One (Zone 4-D) of 2.37 and Sheet One (Zone 7-B) of 2.38 for detail

1.4 Security Classification:

1.4.1 Space - 1.2.11 through 1.2.15 and 1.2.41 through 1.2.43

1.5 Initial Condition:

1.5.1 Potential Asbestos Hazard.

1.5.2 Potential Lead Hazard

1.5.3 Potential PCB Hazard

1.5.4 Dry Dock Work.

1.6 Contractor work start date: 1/12/2026

1.7 Contractor work completion date: 8/5/2027

2. REFERENCES:

REF.

NO.

DOCUMENT

/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV CHG

NO.

COPY

REQ’D

(Y/N)

SOURCE

DOC

(Y/N)

PARA SEC PG CHP

1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N

3 DWG 345-

8574539 SCD-9243.00K Genset Upgrade Equipment Arrangement EDG Rm 1 & Emer Switchgear Rm

B Y AL

L

4 DWG 301-

8621260

SCD-9243K Power System 2000KW Emergency Diesel Generator 1 Upgrade Removal

B Y AL

L

5 DWG 301-

8621261

SCD-9243K Power System 2000KW Emergency Diesel Generator 1 Upgrade Installation

B Y AL

L

6 DWG 301-

8622088

SCD-9243 EDG No. 1 Pmp Fuse Panel Power Modification

A Y AL

L

7 DWG 301-

8974217

SCD-9243.00K Load Center Modifications Incidental to EDG 1 Upgrade

- Y AL

L

FOUO

SHIP: LCC-19 CHG/VER: 2/2

REF.

NO.

DOCUMENT

/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV CHG

NO.

COPY

REQ’D

(Y/N)

SOURCE

DOC

(Y/N)

PARA SEC PG CHP

8 DWG 302-

8621267

SCD-9243K Power System Modifications Incidental to Emergency Diesel Generator 1

A Y AL

L

9 DWG 302-

8622224

SCD-9243K Power System Removal Emergency Diesel Generator 1 Upgrade

A Y AL

L

10 DWG 302-

8622225

SCD-9243K Power System Install Emergency Diesel Generator 1 Upgrade

B Y AL

L

11 DWG 302-

8622226

SCD-9243K Power System Removal EDG 1 Upgrade HVAC

A Y AL

L

12 DWG 302-

8622227

SCD-9243K Power System Installation EDG 1 Upgrade HVAC

B Y AL

L

13 DWG 302-

8622329

SCD-9243 Cableway Modifications Incidental to Emergency Diesel Generator 1

A Y AL

L

14 LAR

NSWCPD-

0666-24

SCD 9243 8621261A Power System 2000KW EDG No 1 Upgrade Installation

- Y AL

L

15 LAR SRFY-

0036-25

Discrepancies regarding DWG 302-

8622329 REV A

- Y AL

L

16 DWG 303-

8622306

SCD 9243 Lighting System Modifications Incidental to Cableway EDG 1

A Y AL

L

17 DWG 303-

8622307

SCD 9243 Lighting System Removals Emergency Diesel Generator No. 1

A Y AL

L

18 DWG 303-

8622308

SCD 9243 Lighting System Installation Emergency Diesel Generator No. 1

A Y AL

L

19 DWG 401-

8621337

SCD 9243 MISC IC Mods Incdt to Ship Service EDG 1 Replacement

A Y AL

L

20 DWG 401-

8623071

SCD 9243 MISC Damper Alarm Mods Incid to SCD 9243

A Y AL

L

21 LAR SRFY-

0270-24

Discrepancies regarding DWG 401-

8621337 REV A

- Y AL

L

22 PDD 301-

ELM-250187

SUPPL INFO FOR SCD 9243

GENSET UPGRADE (EDG #1)

- Y AL

L

23 PDD 302-

ELM-250168

Patch for Removed Strl Pen of Cableway Incid to EDG #1 Upgrade

- Y AL

L

24 PDD 300-

ELM-230313

SRF-JRMC STD ELM

INSTALLATION OF STEEL &

CRES STUFFING TUBE

A Y AL

L

25 DWG 114-

2491155

TRANSV BHD FR 40, Pump RM BHD and Trunk BHD FR 44-45

K Y AL

L

26 DWG 103-

2491035

1st PLATF PLTG FR 8 - FR 52 F Y AL L

27 DWG 104-

2491047

5TH DK PLTG STEM - FR 51 1/2 H Y AL

L

28 DWG 103-

2491032

2ND PLTF PLATING FR 8-52 G Y AL

L

29 DWG 114-

2491156

AGC19 TRANSV BHD FR 52 & 64 G Y AL

L

30 DWG 604-

2491423

NON STRUCT BHD 1ST PLATF K Y 4,7

31 DWG 604-

2491689

MET JOINER BHD BEL 5TH DK G Y AL

L

32 DWG 114-

2491157

TRANSV BHD FR 76 & 86 N Y AL

L

33 DWG 103-

2491036

1ST PLATF PLTG FR 52-98 G Y AL

L

34 DWG 107-

2491059

MN DK PLTG STEM - FR 51-1/2 G Y AL

L

FOUO

SHIP: LCC-19 CHG/VER: 2/2

REF.

NO.

DOCUMENT

/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV CHG

NO.

COPY

REQ’D

(Y/N)

SOURCE

DOC

(Y/N)

PARA SEC PG CHP

35 MIL MIL-

STD-2003

Electric Plant Installation Standard Methods for Surface Ships and Submarines

B N

36 TM S9AA0-

AB-GOS-

010/GSO

General Specifications for Overhaul of Surface Ships (GSO)

11 N

37 DWG 509-

2492391

POTABLE WATER SYS FR 52-76

5TH DK & BELOW, ARR

E Y AL

L

38 DWG 509-

2492384

POTABLE WATER SYS - DIAG

PLANS - 4TH DK & BEL

E Y AL

L

3. APPENDICES:

3.1. Appendix “J” TGI Job Summary Information Sheet

3.2. Appendix "M" TGI Material List

3.3. Appendix “D” Deficiency Form

4. GENERAL REQUIREMENTS:

4.1. Not Applicable.

5. PROCEDURE:

5.1 Pump out, clean and dry the bilge area located in 1.2.50 and 1.2.51 free from oil, debris, and other foreign matter.

5.2 Accomplish electrical removals, modifications and installations of the system listed in 1.3.1 through 1.3.16 in accordance with 2.3 through 2.24, using 2.25 through 2.34 for guidance.

5.2.1 Electrical installations must be in accordance with 2.35.

5.2.2 Accomplish the requirements of 009-12 of 2.1, including Table 2, Column(s) A, Lines One through 7.

5.2.3 Accomplish the requirements of 009-25 of 2.1 for a local air hose test of each new weld of the watertight/airtight structural boundary. Allowable leakage: None.

5.2.4 Inspect each protective device of the equipment listed in 1.3.1.1 through 1.3.1.3.

5.2.4.1 Verify that size and setting of each overload heater are correctly used under motor full load running current in accordance with Section 302g of 2.36, 2.8 and 2.12.

(V) "SIZE/SETTING"

5.2.4.2 Verify that each fuse is correctly sized in accordance with Section 302g of 2.36, 2.8 and 2.12.

(V) "SIZE"

5.3 Remove existing and reinstall each potable water piping listed in 1.3.17 for accomplishment of electrical work, using 2.37 and 2.38 for guidance.

5.3.1 Accomplish the requirements of 009-87 of 2.1 for each potable water piping listed in 1.3.17.

FOUO

SHIP: LCC-19 CHG/VER: 2/2

5.3.1.1 Accomplish the requirements of 009-09 of 2.1 for chlorination and bacteriological tests. Analysis and testing conducted by a qualified Japanese laboratory (accredited by ISO 17025 or equal) are authorized by the

SUPERVISOR.

5.3.1.2 Record results of chlorination and bacteriological test on a Laboratory Analysis Record(s) and DD Form 686, and submit one legible copy, in hard copy or approved transferrable media, of completed record(s) and form(s) to the

SUPERVISOR.

5.3.2 Accomplish the requirements of 009-12 of 2.1, including Table One, Column(s) A, Lines One through 10.

5.4 Confirm that all personnel have exited the space prior to closure of the space listed in 1.2.9.1. Designate one person to account for all personnel who may have entered the space.

5.5 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.

5.6 Notes:

5.6.1 Planner: Code 233 K. Ono, 080-9350-1438

Planner: Code 233 I. Tochigi, 080-9350-1457 Planner: Code 231B, T. Oosera, 243-9935 Planner: Code 231B, M. Haga, 243-2513 Planner: Code 231B, Y. Arakawa, 243-4496 Planner: Code 231B, A. Suzuki, 243-0968 Planner: Code 234, O. Mitsui 070-7787-2048 Planner: Code 234, K. Furukawa 243-2242

5.6.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598

5.6.3 Replacement of electrical grade sheet deck covering system of each space listed in 1.2.34 will be covered by TGI No. 3819P14122A01 (KTR TGI).

5.6.4 Opening, initial cleaning, closing, and installation/removal of FMEs of each space listed in 1.2.49 and 1.2.52 will be covered by the following TGI No(s).

Distillate Fuel Service Tank (7-82-2-F): 3819P12303A01 (KTR TGI) Potable Water Tank (9-76-4-W): 3819P12325A01 (KTR TGI)

5.6.5 Opening, initial cleaning, and closing of each space listed in 1.2.53 will be covered by TGI No.

3819P12319A01 (KTR TGI).

5.6.6 Provision of oily/chemical water barge will be coordinated by Project Team.

5.6.7 Work per this instruction involves cutting an access (or removal of a door) through a fire zone bulkhead, through the hull of the ship above the turn of the bilge, through ventilation components (ducting, plenums, etc.), or through any air-tight, fume-tight or watertight bulkheads normally used to control air flow in the event of a shipboard fire. A nonflammable closure is required in accordance with COMNAVSEASYSCOM MSG R 261400Z JUL 12. The closure, if not continuously in use, shall be staged near the access, readily visible and accessible, so that any emergency responder can install the closure to affect proper air flow onboard the ship.

5.6.8 JCN EE01-L106 is related to this TGI.

5.7 Government Furnished Material (GFM):

5.7.1 All GFM listed in each S/A drawing will be provided as kitted material.

5.8 SRF-JRMC will provide the following service work: (TGI No. 3819P31001S02)

FOUO

SHIP: LCC-19 CHG/VER: 2/2

5.8.1 [C740] Crane and crane rigging service.

5.8.2 [X99E] Utility service, electrical.

5.8.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.

5.8.4 [C106.1] Safety inspection for SRF-JRMC employees.

5.8.5 [C106.2] Gas free inspection for SRF-JRMC employees.

5.8.6 [C133] QA inspection for (G) symbol(s).

5.8.7 [C292] Visual TEMPEST Configuration Control Inspection (VTCCI).

FOUO

J-1

SHIP: LCC-19 CHG/VER: 2/2

APPENDIX "J"

TGI JOB SUMMARY INFORMATION SHEET

SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH

VERSION:

CASREP

CAT:

SA 79243K ELEC EDG#1 AY A 0 2

CU PHASE TITLE:

*(RE) F/O-S/A 79243K, ACCOMPLISH ELEC WORK FOR EDG#1, ESLP SS/EDG GENSET UPGRADE

PRIMARY COMPONENT:

COMPONENT UNIT LIST (FOR ASSEMBLIES):

FOUO

J-2

SHIP: LCC-19 CHG/VER: 2/2

(6-35-2)-2P-A C- (6-35-2)-4P-A C- K-1EG11 C- K-1EG27 C- K-1EG14 C-

K-1EG16 C- K-1EG17 C- K-1EG18 C- K-1EG19 C- K-1EG24

C- K-1EG13 C- K-1EG15 C- K-1EG26 C- K-EC509 C- K-EC510

C- K-EC511 C- K-EC512 C- K-1EG25 C- K-1EG26 C- VNT SS 1-39-1

DT CMPT 6-40-0-A MS#1EDG BTRY#1 BA #1EDG BTRY#4 BA #1EDG BTRY#2

BA #1EDG BTRY#3 BA #1EDG BATCHG7-30-0-E BC CKT 1BC1 IC (6-39-2)-28P-A C-

(6-35-2)-1P-(6-37-2) C- (6-35-2)-4P-(6-37-2) C- (6-39-2)-28P-A C- (6-39-2)-28P-B C- (6-39-2)-28P-C C- (6-39-2)-28P-D C- (6-39-2)-28P-G C- 11-4P(3-39-2)(3-39-4 C-11-4P-(3-39-2) C- 1E-1P-PMP

C- 1E-1P-PMP(CNTRL-1) C- 1E-1P-PMP(CNTRL-2) C- 1E-1P-PMP(SENS) C- 1E-28P-PMP

C- 1E-4EP-(6-39-4) C- 1E-4EP-6-39-2 C- 6-35-2-1P-C C- 6-35-2-4P-C C- 6-39-2-4EP-A

C- PMP-1E(COM) C- PMP-28P-NTWK 2A C- PMP-28P-NTWK 2AALTDC C- PMP-28P-NTWK 2B

C- PMP-28P-NTWK 2BALTDC C- RECT 1A-28P-1E DIST C- RECT 1A-28P-PMP C- RECT 1B-28P-

1E DIST C- RECT 1B-28P-PMP C- PP 6-39-2 PA 32123-3-301KTR TT TF 6-36-2

XF 6-37-2-1P-A C- (6-37-2)-1P-D C- 6-37-2-1P-D C- (3-29-5)-4P-A(CC1F) C- (6-39-

4)-4EP-A C-(6-39-4)-4EP-B C- 6-39-4-4EP-A C- 6-39-4-4EP-B C- (6-35-2)-4P-B C- 1WDG-

4EP-1E C- K-1EG101 C- K-1EG102 C- K-1EG103 C- K-1EG105 C-

K-1EG106 C- K-1EG107 C- K-1EG108 C- K-1EG110 C- K-1EG111

C- K-1EG112 C- K-1EG114 C- K-1EG123 C- K-1EG124 C- LSSHOF-150

C- POT WTR 9-76-4-W TK 1E-4EP-(6-37-4)(EMER C- 1EA-4EP-(6-39-2) C- 44-4P-(6-37-4)(NORM) C- PP 6-37-4 PA (5-39-1)-1L-B2/F13 LF(2-38-1)-1L-C2E RC (5-39-1)-1L-B2/F13 RC (2-38- 1)-1L-H1 LF(2-38-1)-1L-J11&J12 LF (2-38-1)-1L-J7 LF (2-38-1)-1L-J9 LF (3-53-1)-1L-C2E LF

(4-36-1)-1L-C1A&C1C LF (4-36-1)-1L-C1D LF (4-36-1)-1L-C1F LF (4-36-1)-1L-C3A LF (4-36- 1)-1L-F11 LF (4-36-1)-1L-F1B LF (4-36-1)-1L-F2F LF (6-81-1)-1L-B1 LF (6-37-2)-1P-A C-

(6-37-2)-1P-G(M) C- (6-37-2)-1P-G(MTR) C- (6-37-2)-1P-G(SW) C- (6-37-2)-1P-H(M) C- (6-37- 2)-1P-H(MTR) C- (6-37-2)-1P-H(SW) C- (6-37-4)-4P-A(INTLK) C- CKT 5AV IC CKT FR IC/SM-

20 SB CKT FR IC/SM-50 SB (6-37-4)-1P-C(CONT1) C- (6-37-4)-1P-C(CONT2) C- (6-37-

4)-1P-C(OT1) C- (6-37-4)-1P-C(OT2) C- (6-37-4)-1P-C(TS) C- (6-37-4)-4P-B C- (6-37-4)-4P-D C-

RHR 1-36-1 HT RHR 1-36-3 HT CONTACTOR 1-36-1 RE CONTACTOR 1-36-3 RE

(4-36-1)-1L-C3G C- (4-36-1)-1L-C5A C- (4-36-1)-1L-C5B C- (4-36-1)-1L-C5C C- (4-36-1)-1L-

C5F C- (4-36-1)-1L-C5G C- (4-36-1)-1L-C5H C- (6-37-4)-1P-C(CONT) C- (6-37-4)-1P-C(CTR) C- (6-37-4)-4-A C- (6-37-4)-4P-A C- (6-37-4)-4P-A(HALON) C- (6-37-4)-4P-A(PB) C- (6-37- 4)-4P-C C- (6-37-4)-4P-C(CT) C- (6-37-4)-4P-C(HALON) C- (6-37-4)-4P-C(PB) C- (6-37-4)-4P-C(RLY) C-

(6-39-4)-4EP-A(HALON C- (6-39-4)-4EP-A(MLS) C- (6-39-4)-4EP-A(PB) C-(6-39-4)-4EP-B(HALON

C- (6-39-4)-4EP-B(MLS) C- (6-39-4)-4EP-B(PB) C-VNT E1-37-2 CT VNT S1-37-1 CT VNT

E1-37-2 FA VNT S1-37-1 FA 2-RLY PNL 6-30-2-E PA (6-39-2)-1EP-C(CONT2 C- (6-39-

2)-4EP-C(CONT1 C- 6-39-2-1EP-C(CONT2) C- (3-39-4)-24P-B(CONT) C- (3-39-4)-4P-B(CONV) C-

(3-39-4)-4P-B(DISPEN C- (3-39-4)-4P-B(RACKSW C- (3-39-4)-4P-B(RINSE) C- (3-39-4)-4P-

B(WASH) C- (4-34-2)-4P-B(P) C- CMPT 6-52-4-A MSPOTW 5-60-0-L PPR-DD C- FOST

7-82-2-F TK CMPT 8-86-0-E MSCMPT 6-64-4-L MSCMPT 6-70-2-Q MS CMPT 6-72-2-Q

MS (6-39-2)-1EP-C C- (6-39-2)-4EP-C C- (3-39-4)-4P-A C- (3-39-4)-4P-B C- (3-39-4)-4P-C C- (3-39-4)-4P-D C- (4-34-2)-4P-B C- (4-34-2)-4P-B1 C- (4-34-2)-4P-B2 C- (4-34-2)-4P-B3 C- CTE 6-30-2-E XF TF BANK 6-34-2 XF(6-37-2)-1P-F C- 6-35-2-24P-A4 C- 6-35-2-4P-G

C- K-1EG-1 C- PMP-1SSEDG MPU-1 C- #1EDG CAT PANEL PA K-1EG23 C-

(6-37-2)-1P-F CB K-1EG12 C- K-1EG135 C- (6-39-2)-28P-E C- (6-39-2)-28P-F

C- PMP-1E BATT CHRGR C- (4-36-1)-1L-C1B C- K-EG-130 C- 1EG-4EP-1E C-

1PLMC-1SSEDG C- 1SSEDG-DLOP C- 1SSEDG-DPS C- 1SSEDG-GLOP

C- 4-36-1-1L-C1B HTR C- 6-35-2-4P-B2 C- 6-35-2-4P-D2 C- 6-37-2-1P-G4 C- 6-37-2-

1P-G5 C- EDG124PEMERSHUTDOW1A C- K-EG-1 C- K-EG-109 C- K-EG-110

C- K-EG-111 C- K-EG-112 C- K-EG-117 C- K-EG-119 C- MPU-

1SSEDG(MPU) C- PMP-1PLMC C- PMP-1SSEDG(COM 1) C- PMP-1SSEDG(COM) C- PMP-

ASSEDG COM 2 C- #1EDG PRE-LUBE MO CT 1E-1P-PMP RECT 1A C- 1E-4P-CPT C- 1E-4P-

PMP UPS1 C- 1S-4P-1E C- PMP FUSE 6-30-2-E PA 6-35-2-4P-B1 C- 6-35-2-4P-D1

C- 6-37-2-1P-G2 C- 6-37-2-1P-G3 C- #1EDG JKTWH CR ENL#1 MQ #1EDG JKTWH CR ENL#2 MQ

(4-36-1)-1L-C1B C- 6-35-2-4P-A C- #1 EDG SW CLG PUMP CT CKT JV IC CKT J

IC 1MC 2-342 LD 1MC 2-900A LD 1MC 2-901 LD 1MC 2-902 LD CKT 2FR

IC CKT 3FR IC CKT 5EK IC CKT TD51 IC IC/SM-4 ALM 7-30-0-E SB I/O

FOUO

J-3

SHIP: LCC-19 CHG/VER: 2/2

ENCLOSURE #1 EE CKT 5TK IC IC CKT2TV IF7-30-0-E BX CAMERA 7-30-0-E EE K-

1EG129 C- K-1EG130 C- K-1EG131 C- K-1EG132 C- K-1EG133 C-

K-1EG134 C- 1E-4EP-1EA C- K-1EG20 C- K-1EG21 C- K-EC500

C- K-EC501 C- K-EC502 C- K-EC504 C- K-EC505 C- K-EC506

C- K-EC507 C- K-EC508 C- K-1EG109 C- K-1EG113 C- K-1EG115

C- K-1EG116 C- K-1EG117 C- K-1EG118 C- K-1EG119 C- K-1EG120

C- K-1EG121 C- K-1EG122 C- K-1EG125 C- K-1EG126 C- K-1EG127

C- K-1EG128 C- DG SENSING ENCLOSURE EE LGE ENG COT PNL PA DUAL VR

RG 6-35-2-24P-A1 C- 5-91-2-1SF-A C- (5-91-2)-4P-A C- (5-91-2)-4P-B C- UPS1EP-5-91- 2-1P-B-1 C- UPS4EP-(5-91-2)-4P-B C- UPS4EP-5-91-2-4P-B-5 C- #1 EDG GE CMPT 6-30-2-E

MS CMPT 6-64-2-Q MS CMPT 8-76-0-E MSCMPT 6-68-4-Q MS CMPT 7-30-0-E MS

CMPT 2-36-0-Q MS BLST 9-86-6-W TK #1 EDG ENGINE EN

ATTACHMENT LIST:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

TAKAHASHI ,YASUHIKO

JO: KO: TOTAL MAN HRS: PLANNING ACCEPTANCE:

3819P31001 A04

TOTAL DURATION:

CU PHASE DESCRIPTION:

The purpose of this TGI is to accomplish electrical work for emergency diesel generator no. one, extended service life program ship service/emergency diesel generator generator-set upgrade.

Location of Work:

Emergency Generator Room No. One (7-30-0-E) 01 Level Weather, Frames between 36 and 37, Port Main Deck Weather, Frame 35, Port Main Deck Weather, Frames between 36 and 38, Starboard (Stbd) Fan Room (1-34-1-Q) Fan Room (1-34-2-Q) Fan Room (1-36-0-Q) Fan Room (1-36-2-Q) Fan Room (1-38-0-Q) Vent Plenum for Heating Ventilation and Air Conditioning (HVAC) Supply Systems (SS) 1-39-1, Frames between 37 and 39, Stbd Fan Room (1-38-2-Q) N3 Office (2-30-1-Q) N3 ACOS Office (2-33-2-Q) N7 Office (2-36-0-Q) Radio Transmitter Room No. One (3-19-0-Q) S-5 Office (3-30-0-Q) Passage (3-30-01-L) Diesel Exhaust Piping Space and Deck Gear Locker (3-31-3-Q) Wardroom Galley (3-34-0-Q) Wardroom Scullery (3-34-2-Q) State Room (3-37-1-L) Boatswain Storeroom (4-D-0-A) Crew and Troop Messroom and FWD Battle Dressing Station (4-30-0-L) Crew Sculley (4-36-0-Q) Load Center 21/22 (4-57-2-Q) Trunk (5-30-0-T) Crew Living Space (STAFF) (5-30-01-L) CPO Staff Washroom, Water Closet, Shower and Decontamination Station (5-30-2-L) Crew Living Space (Female) (5-40-0-L)

1.2.29 Crew Living Space (5-52-0-L)

Emergency Switchgear Room No. One (6-30-2-E) Passage (5-60-4-L)

FOUO

J-4

SHIP: LCC-19 CHG/VER: 2/2

CU PHASE DESCRIPTION:

Crew Lounge (5-60-0-L) Passage (5-64-4-L) CPO Staff Washroom, Water Closet, Shower and Decontamination Station (5-64-2-L) Main GSK / SD Storeroom (6-40-0-A) Storeroom (6-52-4-A) Passage (6-60-0-L) Passage (6-61-2-L) Photo Lab Office (6-64-2-Q) Passage (6-64-4-L) Changing Area (6-68-4-Q) Production Chief Office (6-70-2-Q)

EIC (6-72-2-Q)

B Division Storeroom (6-76-2-A) Engine Room Enclosed Operating Station (6-86-0-E) Ship Fitter Storeroom (6-86-2-A) SD Storeroom (7-30-1-A) Crew Baggage Storeroom (7-30-2-A) Distillate Fuel Service Tank (7-82-2-F) Fire Room (8-76-0-E) Engine Room (8-86-0-E) Potable Water Tank (9-76-4-W) Fresh Water Ballast (9-86-6-W)

TASK NAME

SHOP TSD/WC TS CREW# MHRS

HIGH RAD

HOURS

RC

GRID#

5.1 LBR . 22 KE PC

5.2 ELEC , ELEX , SFTR , WELD , STML , INSL , RGRS ,

PNTR , CARP , QA , PFTR , BLRM .

22 KE PC

5.3 PFTR , WELD , INSL , QA . 22 KE PC

5.4 ELEC . 22 KE PC

5.5 PNTR , QA . 22 KE PC

Electrical Work CFM: for air compressor rental cost, fuel oil cost, asbestos sample and analysis cost, banding material, fasteners, insulation tape, plastic bags, rope, and other consumable.

22 MQ CS

Electronics Work CFM: or cable banding and other consumables.

22 MQ CS

Structure Work CFM: for all deck covering material, paints, thinner, grit, disposal cost, fire watch and tank watch cost, marine chemist cost, air compressor rental cost and fuel oil cost for air hose test, lead sampling/analysis cost, asbestos sample and analyze, cost for compartment and duct insulation, ---continue to below---

22 MQ CS

---continued from above---deck tile, and underlayment, adhesive for pin, pin, fasteners, rivets, tyvex suit, plastic bags, fasteners, and MISC such as electrode, gases, temporary closure, and covering material, and other consumable.

22 MQ CS

Piping Work CFM: for fire watch cost, bulk sample cost and analysis cost for asbestos, disinfection cost and MISC such as gases, electrode, saw blades, painting material, plastic bag/sheet, tyvek suit and etc.

22 MQ CS

Boiler Work CFM: for covering material, fastener and MISC. 22 MQ CS

FOUO

J-5

SHIP: LCC-19 CHG/VER: 2/2

TASK NAME

SHOP TSD/WC TS CREW# MHRS

HIGH RAD

HOURS

RC

GRID#

Lagging Work CFM: for covering material, asbestos sampler/analysis cost, paint, and MISC.

22 MQ CS

Process Funding Document. 10 CT OM

Version-1 modification of Ref. No. 23 was required.

[C233 M. Hosono, 2/26/2025] -/-/N

V-01

Version-2 update material information of KOI 404 and 405.

[C233 M. Toda, 3/3/2025] -/Y/N

V-02

FOUO

M-1

SHIP: LCC-19 CHG/VER: 2/2

APPENDIX “M”

TGI MATERIAL LIST

SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH

VERSION:

CASREP

CAT:

SA 79243K ELEC EDG#1 AY A 0 2

CU PHASE TITLE:

*(RE) F/O-S/A 79243K, ACCOMPLISH ELEC WORK FOR EDG#1, ESLP SS/EDG GENSET UPGRADE

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV

1 ELM-250187

2 605-8578020 A

JOB ORDER: KEY OP:

3819P31001 A04

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

001 1 1 M ANGLE,STRUCTURAL, ORDER

FOR KTR

ORIG: C226 K.YAMAMI, 080-

9350-1447

9B 9520 002774942 NA 4 N 50515114 15/FT

002 2 1 M PAD, TAPPED ROUND, PAD,

TAPPED ROUND, 1/4"-20UNC-

2B X 1"LG, STEEL, CARBON,

AISI-1020, CENTERED,

CONCENTRIC INTERNAL

THREAD THRU HOLE 5/8" OD,

FINISH: PLAIN.

BIW CATALOG NO.53204-155

ORDER FOR KTR

ORIG: C226 K.YAMAMI, 080-

9350-1447

9B 5340 LL9003506 NA 4 N 50517454

100/EA

NOTES:

FOUO

M-2

SHIP: LCC-19 CHG/VER: 2/2

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

003 3 1 M PAD, TAPPED ROUND, PAD,

TAPPED ROUND,

CENTERED, CONCENTRIC

INTERNAL THREAD THRU

HOLE 3/4" OD,

SIZE: 3/8-16UNC-2B X 1" LG,

MATL: STEEL, CARBON, AISI-

1020, FINISH: PLAIN,

BIW CATALOG NO. 53204-040,

ORDER FOR KTR

ORIG: C226 K.YAMAMI, 080-

9350-1447

9B 5340 LL9306697 NA 4 N 50517457

100/EA

004 4 1 M PAD, TAPPED ROUND, ORDER

FOR KTR

ORIG: C226 K.YAMAMI, 080-

9350-1447

9B 5315 LL9307892 NA 4 N 50517450

100/EA

005 5 1 M PIPE,METALLIC, ORDER FOR

KTR

ORIG: C226 K.YAMAMI, 080-

9350-1447

9B 4710 002785348 NA 4 N 50515118 2/FT

006 6 1 M PLATE,METAL, SIZE: 2 FT X 1

FT,

ORDER FOR KTR

ORIG: C226 K.YAMAMI, 080-

9350-1447

9B 9515 001533184 NA 4 N 50515108 2/SF

100 M PLATE,ME, 5FT X 5FT X 1PM

REQUIRED

ORDERED FOR KTR

ORIG: C231B, T. OOSERA 243-

9B 9515 001533223 NA 4 N 50515107 25/SF

111 M INSULATI, MATERIAL ORDER

FOR KTR

ORIG: C231B M.HAGA 243-2513

9Q 5640 008096312 NA 4 N 50515133 16/EA

112 M INSULATI, MATERIAL ORDER

FOR KTR

ORIG: C231B M.HAGA 243-2513

9Q 5640 008096315 NA 4 N 50515134 18/EA

113 M TAPE,TEX, MATERIAL ORDER

FOR KTR

ORIG: C231B M.HAGA 243-2513

9B 8315 002671632 NA 4 N 50515135 3/RO

114 M TAPE,TEX, MATERIAL ORDER

FOR KTR

ORIG: C231B M.HAGA 243-2513

9B 8315 002671633 NA 4 N 50515136 3/RO

115 M CAP,SNAP, MATERIAL ORDER

FOR KTR

ORIG: C231B M.HAGA 243-2513

9B 5325 007377648 NA 4 N 50515147

300/EA

116 M ADHESIVE, MATERIAL ORDER

FOR KTR

ORIG: C231B M.HAGA 243-2513

9B 8040 002738708 NA 4 Y 50515109 1/GL

117 M SOUND CO, MATERIAL ORDER

FOR KTR

ORIG: C231B M.HAGA 243-2513

9Q 5640 007565866 NA 4 N 50515137 10/SH

FOUO

M-3

SHIP: LCC-19 CHG/VER: 2/2

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

118 27 2 M FLOOR COVERING, LONSEAL

FLOORING, UV SERIES,

FLOOR COVERING

INSULATION FOR HIGH

VOLTAGE APPLICATION,

SPEC: MIL-DTL-15562 TYPE 1,

SIZE: 6 FT W X 0.128"

OVERALL THK X 30 FT LG,

COLOR: BLUE MARBLE,

SURFACE CONDITION:

SMOOTH SURFACE,

ORDER FOR KTR

ORIG: C226 H.SHIMIZU, 080-

9350-1431

9B 7220 LL9311206 NA 4 N 50517486 1/RO

400 M INSULATI, ORDERED FOR KTR

ORIG:C234 O.MITSUI 070-7787-

9B 5640 LL9607841 NA 4 N 50517451 2/EA

401 M INSULATI, ORDERED FOR KTR

ORIG:C234 O.MITSUI 070-7787-

9B 5640 LL9607840 NA 4 N 50517453 2/EA

402 M COUPLING,TUBE, 1/4" IPS, CU-

NI 90-10, SW, PG=2EA

ORDERED FOR KTR

ORIG:C234 O.MITSUI 070-7787-

9B 4730 014635868 NA 4 N 50515121 1/PG

403 M COUPLING, 3/8" IPS, CU-NI 90-

10, SW

ORDERED FOR KTR

ORIG:C234 O.MITSUI 070-7787-

9C 4730 LL4462577 NA 4 N 50517455 2/EA

404 M COUPLING,TUBE, 2" IPS, CU-NI

90-10, BW

ORDERED FOR KTR

ORIG:C234 O.MITSUI 070-7787-

9B 4730 005423290 NA 4 N 2/EA

405 M SLEEVE,, 1-1/4" IPS, CU-NI 90-

10, BW

ORDERED FOR KTR

ORIG:C234 O.MITSUI 070-7787-

9C 4730 LL4903762 NA 4 N 2/EA

450 M INSULATI, ORDERED FOR KTR

C234 K.FURUKAWA, 243-2242

9B 5640 LL9607844 NA 4 N 50537450 2/EA

451 M INSULATI, ORDERED FOR KTR

C234 K.FURUKAWA, 243-2242

9B 5640 LL4783095 NA 4 N 50517456 2/EA

452 M ADHESIVE, ADHESIVE FOR

CLOTH,

C234 K.FURUKAWA, 243-2242

ORDERED FOR KTR

9B 8040 002738708 NA 4 Y 50515110 1/GL

453 M ADHESIVE, ADHESIVE FOR

PLASTIC TUBE

ORDERED FOR KTR

C234 K.FURUKAWA, 243-2242

9B 8040 008419773 NA 4 Y 50515115 2/PT

FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____

☐ NUCLEAR APPENDIX "D"

DEFICIENCY FORM

☐ NON-NUCLEAR

1. SHIP/HULL NO.: 2a. DL or DR No.

(Circle One)

2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:

LCC-19 SA 79243K ELEC EDG#1 AY A 0

4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:

3819P31001 A04

7. DESCRIPTION:

8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:

9. CORRECTIVE ACTION:

10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:

FOR NON-NUCLEAR USE ONLY

11. RFD/RFW REQ’D ☐ LAR REQ'D ☐

ILS MOD REQ’D ☐

SRD/PLAN REV REQ'D ☐

DWG NO.: _____________________ S/A NO.: ___________________

12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:

SATISFACTORY:

13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

YES ☐ NO ☐

14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

COMPLETE:

15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

_________:YES ☐ NO ☐

16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

COMPLETE (DR ONLY)

DL’s ISSUED

(DR ONLY)

FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____

☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR

1. SHIP/HULL NO.: 2a. DL or DR No.

(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:

LCC-19 SA 79243K ELEC EDG#1 AY A 0