This document is a Price Proposal Form for the USS BLUE RIDGE (LCC-19) Dry Ship Repair and Alteration (DSRA) Modernization project. The solicitation (N6264925RA041) covers 17 Technical Work Items (TGIs) focused on Emergency Diesel Generator No. 2 upgrades and associated system tests, including electrical work, structural modifications, piping adjustments, and comprehensive system tightness and operational testing for various ship systems such as oily wastewater, air, heating, firemain, potable water, chill water, sewage, and auxiliary seawater systems.

The period of performance is from 12 Jan 2026 through 13 Dec 2027, with the work to be conducted at Commander, Fleet Activities Yokosuka (CFAY) Naval Base in Japan. Offerors must submit proposals by 9 Jun 2025 at 10:00 AM Japan Standard Time, with access to detailed work specifications requiring a request to specific Navy contact emails. The solicitation is restricted to sources authorized to operate and do business in Japan, and all proposal materials must be accessed through the secure DoD SAFE repository.

View the file

Other files

File Type Posted
TGI_3819P31002A02_c1v1_redact.pdf PDF
Attachment II Price Proposal Form N6264925RA041_CLIN 0001 and CLIN 0003.xlsx XLSX spreadsheet
TGI_3819P31003A05_c0v0_redact.pdf PDF
TGI_3819P31003A06_c0v0_redact.pdf PDF
TGI_3819P31002A01_c0v0_redact.pdf PDF
TGI_3819P31002A03_c3v2_redact.pdf PDF
TGI_3819P31001A06_c2v1.pdf PDF
N6264925RA041-0010.pdf PDF
TGI_3819P31002A04_c3v3.pdf PDF
TGI_3819P31001A01_c3v4.pdf PDF
TGI_3819P31002A05_c2v0.pdf PDF
TGI_3819P31003A01_c0v0_redact.pdf PDF
TGI_3819P31001A04_c2v2.pdf PDF
TGI_3819P31001A03_c0v0_redact.pdf PDF
TGI_3819P31003A04_c1v1.pdf PDF
TGI_3819P31003A02_c0v0.pdf PDF
TGI_3819P31003A03_c0v0_redact.pdf PDF
TGI_3819P31002A06_c0v0_redact.pdf PDF
EXHIBIT - Contract Data Requirements List (CDRL)_R1.pdf PDF
TGI_3819P31001A05_c0v0_redact.pdf PDF
TGI_3819P31001A02_c2v1_redact.pdf PDF
TGI_3819P31002A05_c2v0.pdf PDF
N6264925RA041-0009.pdf PDF
TGI_3819P31001A06_c2v1.pdf PDF
N6264925RA041-0008.pdf PDF
N6264925RA041-0007.pdf PDF
N6264925RA041-00006.pdf PDF
TGI_3819P31001A01_c2v4.pdf PDF
TGI_3819P31003A04_c1v1.pdf PDF
N6264925RA041-0005.pdf PDF
TGI_3819P31002A04_c2v3.pdf PDF
TGI_3819P31002A04_c1v2_redact.pdf PDF
TGI_3819P31001A01_c1v3_redact.pdf PDF
N6264925RA041-0004.pdf PDF
N6264925RA041-0003.pdf PDF
N6264925RA041-0002.pdf PDF
N6264925RA041-0001.pdf PDF
TGI_3819P31002A03_c3v2_redact.pdf PDF
TGI_3819P31002T01_c0v0_redact.pdf PDF
TGI_3819P31001T06_c0v0_redacted.pdf PDF
2.01 N6264925RA041.pdf PDF
TGI_3819P31003T09_c0v0_redact.pdf PDF
TGI_3819P31002T06_c0v0_redact.pdf PDF
TGI_3819P31001A04_c2v2.pdf PDF
TGI_3819P31002T10_c0v0_redact.pdf PDF
TGI_3819P31001T03_c0v0_redacted.pdf PDF
TGI_3819P31002T03_c0v0_redact.pdf PDF
Attachment III Government Furnished Property (GFP-GFM listings).xlsx XLSX spreadsheet
TGI_3819P31003T10_c0v0_redact.pdf PDF
TGI_3819P31003T07_c0v0_redact.pdf PDF
Show 40 more

Latest 50 of 94 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUMMARY

OFFEROR/COMPANY NAME:

TABSUMMARYSUMMARYCLINTotal Labor (MH)Labor CostMaterial CostODC CostProposed Price
SOLICITATION NO:N6264925RA041CLIN 0002(17 TGIs)0¥0¥0¥0¥0
SHIP NAME:USS BLUE RIDGE (LCC-19)CLIN 0004 (Growth CLIN)0¥0¥0¥0¥0
AVAILABILITY:FY26 CNO 5C1Total for All CLIN0¥0¥0¥0¥0
Total TGIs (Specify Total)17Total Evaluated Price¥0
Growth CLIN %32.00%
Note to Offerors: The values in this Summary table is linked to the corresponding data from Tabs for each TGI listed, manual input is not necessary.
No.TGI No.DESCRIPTIONProposed LaborMaterial/ODCsProposed Price (JPY)
In-House Labor (MH)Sub-Contractor Labor (MH)Total Labor (MH)Overall Total Labor Cost (JPY)Material Cost (JPY)ODC (JPY)
13819P31002A01Accomplish S/A 79243K, Electrical Work for Emergency Diesel Generator No. 2, Extended Service Life Program Ship Service/Emergency Diesel Generator Generator-set Upgrade000¥0¥0¥0¥0
23819P31002A02Accomplish S/A 79243K, Structural, Sheet Metal, Preservation, Insulation, and Deck Covering Work for Emergency Diesel Generator (EDG) No. 2 Generator Set Upgrade000¥0¥0¥0¥0
33819P31002A03Accomplish S/A 79243K, Modification of Various Piping000¥0¥0¥0¥0
43819P31002A04Accomplish S/A 79243K, Diesel Exhaust System Piping Work of Emergency Diesel Generator (EDG) No. 2000¥0¥0¥0¥0
53819P31002A05Prepare New Machinery Components for No.2 Emergency Diesel Generator (EDG2) for S/A 79243K000¥0¥0¥0¥0
63819P31002A06Replace Emergency Diesel Generator No. 2, Extended Service Life Program Ship Service/Emergency Diesel Generator Generator-set Upgrade000¥0¥0¥0¥0
73819P31002T01Tightness & Operational Test for All Repaired/Reinstalled Components for EDG #2, Support System - KTR000¥0¥0¥0¥0
83819P31002T02Tightness and Operational Test for All Repaired/Reinstalled Components for Oily Waste Water System - KTR000¥0¥0¥0¥0
93819P31002T03Tightness & Operational Test for Low Pressure Air System - KTR000¥0¥0¥0¥0
103819P31002T04Tightness and Operational Test for High Pressure Air System - KTR000¥0¥0¥0¥0
113819P31002T05Tightness & Operational Test for Heating System S/A 79243K - KTR000¥0¥0¥0¥0
123819P31002T06Tightness & Operational Test for Firemain System - KTR000¥0¥0¥0¥0
133819P31002T07Tightness & Operational Test for Potable Water System - KTR000¥0¥0¥0¥0
143819P31002T08Tightness & Operational Test for Chill Water System - KTR000¥0¥0¥0¥0
153819P31002T09Tightness & Operational Test for Distilled Water Service - KTR000¥0¥0¥0¥0
163819P31002T10Tightness & Operational Test for Sewage System - KTR000¥0¥0¥0¥0
173819P31002T12Tightness & Operational Test for AUX Seawater System - KTR000¥0¥0¥0¥0
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200

1_3819P31002A01

SHIP NAME/AVAILABILITY:USS BLUE RIDGE (LCC-19) - FY26 CNO 5C1TGI 1_3819P31002A01 SUMMARY
SOLICITATION #:N6264925RA041
SRF-JRMC TGI #:1_3819P31002A01In-House MHSub-KTR MHLabor Cost (JPY)Material (JPY)ODC (JPY)TOTAL (JPY)
DESCRIPTION:Accomplish S/A 79243K, Electrical Work for Emergency Diesel Generator No. 2, Extended Service Life Program Ship Service/Emergency Diesel Generator Generator-set Upgrade00¥0¥0¥0¥0
Note to Offerrors: Please input data on cells highlighted in ORANGE. The TOTAL will not show if KEY WORK ITEM column is empty. Please insert rows as needed.
IN-HOUSE LABOR HOUR BREAKDOWN
KEY WORK ITEMSFTRINSLWELDSMTLRGRSPNTRELECPFTRQAOTHERSTOTAL

TOTAL IN-HOUSE M/Hs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

KEY WORK ITEMIN-HOUSE LABOR BREAKDOWNSUB-CONTRACTOR LABOR BREAKDOWNTOTAL
TOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
HOURSTOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL

HOURS

TOTAL M/Hs0TOTAL M/Hs0
COST PER M/H (¥)<--- Please input in-house labor rateCOST PER M/H (¥)<--- Please input sub-contractor labor rate
LABOR COST (¥)¥0LABOR COST (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Plese insert rows as needed.
MATERIAL COST BREAKDOWN
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS
TOTAL (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Please insert rows as needed.
OTHER DIRECT COST (ODC) (IF ANY)
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS

TOTAL (¥) ¥0

2_3819P31002A02

SHIP NAME/AVAILABILITY:USS BLUE RIDGE (LCC-19) - FY26 CNO 5C1TGI 2_3819P31002A02 SUMMARY
SOLICITATION #:N6264925RA041
SRF-JRMC TGI #:2_3819P31002A02In-House MHSub-KTR MHLabor Cost (JPY)Material (JPY)ODC (JPY)TOTAL (JPY)
DESCRIPTION:Accomplish S/A 79243K, Structural, Sheet Metal, Preservation, Insulation, and Deck Covering Work for Emergency Diesel Generator (EDG) No. 2 Generator Set Upgrade00¥0¥0¥0¥0
Note to Offerrors: Please input data on cells highlighted in ORANGE. The TOTAL will not show if KEY WORK ITEM column is empty. Please insert rows as needed.
IN-HOUSE LABOR HOUR BREAKDOWN
KEY WORK ITEMSFTRINSLWELDSMTLRGRSPNTRELECPFTRQAOTHERSTOTAL

TOTAL IN-HOUSE M/Hs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

KEY WORK ITEMIN-HOUSE LABOR BREAKDOWNSUB-CONTRACTOR LABOR BREAKDOWNTOTAL
TOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
HOURSTOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
TOTAL M/Hs0TOTAL M/Hs0
COST PER M/H (¥)<--- Please input in-house labor rateCOST PER M/H (¥)<--- Please input sub-contractor labor rate
LABOR COST (¥)¥0LABOR COST (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Plese insert rows as needed.
MATERIAL COST BREAKDOWN
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS
TOTAL (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Please insert rows as needed.
OTHER DIRECT COST (ODC) (IF ANY)
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS

TOTAL (¥) ¥0

3_3819P31002A03

SHIP NAME/AVAILABILITY:USS BLUE RIDGE (LCC-19) - FY26 CNO 5C1TGI 3_3819P31002A03 SUMMARY
SOLICITATION #:N6264925RA041
SRF-JRMC TGI #:3_3819P31002A03In-House MHSub-KTR MHLabor Cost (JPY)Material (JPY)ODC (JPY)TOTAL (JPY)
DESCRIPTION:Accomplish S/A 79243K, Modification of Various Piping00¥0¥0¥0¥0
Note to Offerrors: Please input data on cells highlighted in ORANGE. The TOTAL will not show if KEY WORK ITEM column is empty. Please insert rows as needed.
IN-HOUSE LABOR HOUR BREAKDOWN
KEY WORK ITEMSFTRINSLWELDSMTLRGRSPNTRELECPFTRQAOTHERSTOTAL

TOTAL IN-HOUSE M/Hs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

KEY WORK ITEMIN-HOUSE LABOR BREAKDOWNSUB-CONTRACTOR LABOR BREAKDOWNTOTAL
TOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
HOURSTOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
TOTAL M/Hs0TOTAL M/Hs0
COST PER M/H (¥)<--- Please input in-house labor rateCOST PER M/H (¥)<--- Please input sub-contractor labor rate
LABOR COST (¥)¥0LABOR COST (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Plese insert rows as needed.
MATERIAL COST BREAKDOWN
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS
TOTAL (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Please insert rows as needed.
OTHER DIRECT COST (ODC) (IF ANY)
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS

TOTAL (¥) ¥0

4_3819P31002A04

SHIP NAME/AVAILABILITY:USS BLUE RIDGE (LCC-19) - FY26 CNO 5C1TGI 4_3819P31002A04 SUMMARY
SOLICITATION #:N6264925RA041
SRF-JRMC TGI #:4_3819P31002A04In-House MHSub-KTR MHLabor Cost (JPY)Material (JPY)ODC (JPY)TOTAL (JPY)
DESCRIPTION:Accomplish S/A 79243K, Diesel Exhaust System Piping Work of Emergency Diesel Generator (EDG) No. 200¥0¥0¥0¥0
Note to Offerrors: Please input data on cells highlighted in ORANGE. The TOTAL will not show if KEY WORK ITEM column is empty. Please insert rows as needed.
IN-HOUSE LABOR HOUR BREAKDOWN
KEY WORK ITEMSFTRINSLWELDSMTLRGRSPNTRELECPFTRQAOTHERSTOTAL

TOTAL IN-HOUSE M/Hs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

KEY WORK ITEMIN-HOUSE LABOR BREAKDOWNSUB-CONTRACTOR LABOR BREAKDOWNTOTAL
TOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
HOURSTOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
TOTAL M/Hs0TOTAL M/Hs0
COST PER M/H (¥)<--- Please input in-house labor rateCOST PER M/H (¥)<--- Please input sub-contractor labor rate
LABOR COST (¥)¥0LABOR COST (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Plese insert rows as needed.
MATERIAL COST BREAKDOWN
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS
TOTAL (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Please insert rows as needed.
OTHER DIRECT COST (ODC) (IF ANY)
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS

TOTAL (¥) ¥0

5_3819P31002A05

SHIP NAME/AVAILABILITY:USS BLUE RIDGE (LCC-19) - FY26 CNO 5C1TGI 5_3819P31002A05 SUMMARY
SOLICITATION #:N6264925RA041
SRF-JRMC TGI #:5_3819P31002A05In-House MHSub-KTR MHLabor Cost (JPY)Material (JPY)ODC (JPY)TOTAL (JPY)
DESCRIPTION:Prepare New Machinery Components for No.2 Emergency Diesel Generator (EDG2) for S/A 79243K00¥0¥0¥0¥0
Note to Offerrors: Please input data on cells highlighted in ORANGE. The TOTAL will not show if KEY WORK ITEM column is empty. Please insert rows as needed.
IN-HOUSE LABOR HOUR BREAKDOWN
KEY WORK ITEMSFTRINSLWELDSMTLRGRSPNTRELECPFTRQAOTHERSTOTAL

TOTAL IN-HOUSE M/Hs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

KEY WORK ITEMIN-HOUSE LABOR BREAKDOWNSUB-CONTRACTOR LABOR BREAKDOWNTOTAL
TOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
HOURSTOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
TOTAL M/Hs0TOTAL M/Hs0
COST PER M/H (¥)<--- Please input in-house labor rateCOST PER M/H (¥)<--- Please input sub-contractor labor rate
LABOR COST (¥)¥0LABOR COST (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Plese insert rows as needed.
MATERIAL COST BREAKDOWN
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS
TOTAL (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Please insert rows as needed.
OTHER DIRECT COST (ODC) (IF ANY)
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS

TOTAL (¥) ¥0

6_3819P31002A06

SHIP NAME/AVAILABILITY:USS BLUE RIDGE (LCC-19) - FY26 CNO 5C1TGI 6_3819P31002A06 SUMMARY
SOLICITATION #:N6264925RA041
SRF-JRMC TGI #:6_3819P31002A06In-House MHSub-KTR MHLabor Cost (JPY)Material (JPY)ODC (JPY)TOTAL (JPY)
DESCRIPTION:Replace Emergency Diesel Generator No. 2, Extended Service Life Program Ship Service/Emergency Diesel Generator Generator-set Upgrade00¥0¥0¥0¥0
Note to Offerrors: Please input data on cells highlighted in ORANGE. The TOTAL will not show if KEY WORK ITEM column is empty. Please insert rows as needed.
IN-HOUSE LABOR HOUR BREAKDOWN
KEY WORK ITEMSFTRINSLWELDSMTLRGRSPNTRELECPFTRQAOTHERSTOTAL

TOTAL IN-HOUSE M/Hs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

KEY WORK ITEMIN-HOUSE LABOR BREAKDOWNSUB-CONTRACTOR LABOR BREAKDOWNTOTAL
TOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
HOURSTOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
TOTAL M/Hs0TOTAL M/Hs0
COST PER M/H (¥)<--- Please input in-house labor rateCOST PER M/H (¥)<--- Please input sub-contractor labor rate
LABOR COST (¥)¥0LABOR COST (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Plese insert rows as needed.
MATERIAL COST BREAKDOWN
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS
TOTAL (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Please insert rows as needed.
OTHER DIRECT COST (ODC) (IF ANY)
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS

TOTAL (¥) ¥0

7_3819P31002T01

SHIP NAME/AVAILABILITY:USS BLUE RIDGE (LCC-19) - FY26 CNO 5C1TGI 7_3819P31002T01 SUMMARY
SOLICITATION #:N6264925RA041
SRF-JRMC TGI #:7_3819P31002T01In-House MHSub-KTR MHLabor Cost (JPY)Material (JPY)ODC (JPY)TOTAL (JPY)
DESCRIPTION:Tightness & Operational Test for All Repaired/Reinstalled Components for EDG #2, Support System - KTR00¥0¥0¥0¥0
Note to Offerrors: Please input data on cells highlighted in ORANGE. The TOTAL will not show if KEY WORK ITEM column is empty. Please insert rows as needed.
IN-HOUSE LABOR HOUR BREAKDOWN
KEY WORK ITEMSFTRINSLWELDSMTLRGRSPNTRELECPFTRQAOTHERSTOTAL

TOTAL IN-HOUSE M/Hs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

KEY WORK ITEMIN-HOUSE LABOR BREAKDOWNSUB-CONTRACTOR LABOR BREAKDOWNTOTAL
TOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
HOURSTOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
TOTAL M/Hs0TOTAL M/Hs0
COST PER M/H (¥)<--- Please input in-house labor rateCOST PER M/H (¥)<--- Please input sub-contractor labor rate
LABOR COST (¥)¥0LABOR COST (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Plese insert rows as needed.
MATERIAL COST BREAKDOWN
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS
TOTAL (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Please insert rows as needed.
OTHER DIRECT COST (ODC) (IF ANY)
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS

TOTAL (¥) ¥0

8_3819P31002T02

SHIP NAME/AVAILABILITY:USS BLUE RIDGE (LCC-19) - FY26 CNO 5C1TGI 8_3819P31002T02 SUMMARY
SOLICITATION #:N6264925RA041
SRF-JRMC TGI #:8_3819P31002T02In-House MHSub-KTR MHLabor Cost (JPY)Material (JPY)ODC (JPY)TOTAL (JPY)
DESCRIPTION:Tightness and Operational Test for All Repaired/Reinstalled Components for Oily Waste Water System - KTR00¥0¥0¥0¥0
Note to Offerrors: Please input data on cells highlighted in ORANGE. The TOTAL will not show if KEY WORK ITEM column is empty. Please insert rows as needed.
IN-HOUSE LABOR HOUR BREAKDOWN
KEY WORK ITEMSFTRINSLWELDSMTLRGRSPNTRELECPFTRQAOTHERSTOTAL

TOTAL IN-HOUSE M/Hs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

KEY WORK ITEMIN-HOUSE LABOR BREAKDOWNSUB-CONTRACTOR LABOR BREAKDOWNTOTAL
TOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
HOURSTOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
TOTAL M/Hs0TOTAL M/Hs0
COST PER M/H (¥)<--- Please input in-house labor rateCOST PER M/H (¥)<--- Please input sub-contractor labor rate
LABOR COST (¥)¥0LABOR COST (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Plese insert rows as needed.
MATERIAL COST BREAKDOWN
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS
TOTAL (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Please insert rows as needed.
OTHER DIRECT COST (ODC) (IF ANY)
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS

TOTAL (¥) ¥0

9_3819P31002T03

SHIP NAME/AVAILABILITY:USS BLUE RIDGE (LCC-19) - FY26 CNO 5C1TGI 9_3819P31002T03 SUMMARY
SOLICITATION #:N6264925RA041
SRF-JRMC TGI #:9_3819P31002T03In-House MHSub-KTR MHLabor Cost (JPY)Material (JPY)ODC (JPY)TOTAL (JPY)
DESCRIPTION:Tightness & Operational Test for Low Pressure Air System - KTR00¥0¥0¥0¥0
Note to Offerrors: Please input data on cells highlighted in ORANGE. The TOTAL will not show if KEY WORK ITEM column is empty. Please insert rows as needed.
IN-HOUSE LABOR HOUR BREAKDOWN
KEY WORK ITEMSFTRINSLWELDSMTLRGRSPNTRELECPFTRQAOTHERSTOTAL

TOTAL IN-HOUSE M/Hs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

KEY WORK ITEMIN-HOUSE LABOR BREAKDOWNSUB-CONTRACTOR LABOR BREAKDOWNTOTAL
TOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
HOURSTOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
TOTAL M/Hs0TOTAL M/Hs0
COST PER M/H (¥)<--- Please input in-house labor rateCOST PER M/H (¥)<--- Please input sub-contractor labor rate
LABOR COST (¥)¥0LABOR COST (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Plese insert rows as needed.
MATERIAL COST BREAKDOWN
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS
TOTAL (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Please insert rows as needed.
OTHER DIRECT COST (ODC) (IF ANY)
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS

TOTAL (¥) ¥0

10_3819P31002T04

SHIP NAME/AVAILABILITY:USS BLUE RIDGE (LCC-19) - FY26 CNO 5C1TGI 10_3819P31002T04 SUMMARY
SOLICITATION #:N6264925RA041
SRF-JRMC TGI #:10_3819P31002T04In-House MHSub-KTR MHLabor Cost (JPY)Material (JPY)ODC (JPY)TOTAL (JPY)
DESCRIPTION:Tightness and Operational Test for High Pressure Air System - KTR00¥0¥0¥0¥0
Note to Offerrors: Please input data on cells highlighted in ORANGE. The TOTAL will not show if KEY WORK ITEM column is empty. Please insert rows as needed.
IN-HOUSE LABOR HOUR BREAKDOWN
KEY WORK ITEMSFTRINSLWELDSMTLRGRSPNTRELECPFTRQAOTHERSTOTAL

TOTAL IN-HOUSE M/Hs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

KEY WORK ITEMIN-HOUSE LABOR BREAKDOWNSUB-CONTRACTOR LABOR BREAKDOWNTOTAL
TOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
HOURSTOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
TOTAL M/Hs0TOTAL M/Hs0
COST PER M/H (¥)<--- Please input in-house labor rateCOST PER M/H (¥)<--- Please input sub-contractor labor rate
LABOR COST (¥)¥0LABOR COST (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Plese insert rows as needed.
MATERIAL COST BREAKDOWN
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS
TOTAL (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Please insert rows as needed.
OTHER DIRECT COST (ODC) (IF ANY)
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS

TOTAL (¥) ¥0

11_3819P31002T05

SHIP NAME/AVAILABILITY:USS BLUE RIDGE (LCC-19) - FY26 CNO 5C1TGI 11_3819P31002T05 SUMMARY
SOLICITATION #:N6264925RA041
SRF-JRMC TGI #:11_3819P31002T05In-House MHSub-KTR MHLabor Cost (JPY)Material (JPY)ODC (JPY)TOTAL (JPY)
DESCRIPTION:Tightness & Operational Test for Heating System S/A 79243K - KTR00¥0¥0¥0¥0
Note to Offerrors: Please input data on cells highlighted in ORANGE. The TOTAL will not show if KEY WORK ITEM column is empty. Please insert rows as needed.
IN-HOUSE LABOR HOUR BREAKDOWN
KEY WORK ITEMSFTRINSLWELDSMTLRGRSPNTRELECPFTRQAOTHERSTOTAL

TOTAL IN-HOUSE M/Hs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

KEY WORK ITEMIN-HOUSE LABOR BREAKDOWNSUB-CONTRACTOR LABOR BREAKDOWNTOTAL
TOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
HOURSTOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
TOTAL M/Hs0TOTAL M/Hs0
COST PER M/H (¥)<--- Please input in-house labor rateCOST PER M/H (¥)<--- Please input sub-contractor labor rate
LABOR COST (¥)¥0LABOR COST (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Plese insert rows as needed.
MATERIAL COST BREAKDOWN
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS
TOTAL (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Please insert rows as needed.
OTHER DIRECT COST (ODC) (IF ANY)
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS

TOTAL (¥) ¥0

12_3819P31002T06

SHIP NAME/AVAILABILITY:USS BLUE RIDGE (LCC-19) - FY26 CNO 5C1TGI 12_3819P31002T06 SUMMARY
SOLICITATION #:N6264925RA041
SRF-JRMC TGI #:12_3819P31002T06In-House MHSub-KTR MHLabor Cost (JPY)Material (JPY)ODC (JPY)TOTAL (JPY)
DESCRIPTION:Tightness & Operational Test for Firemain System - KTR00¥0¥0¥0¥0
Note to Offerrors: Please input data on cells highlighted in ORANGE. The TOTAL will not show if KEY WORK ITEM column is empty. Please insert rows as needed.
IN-HOUSE LABOR HOUR BREAKDOWN
KEY WORK ITEMSFTRINSLWELDSMTLRGRSPNTRELECPFTRQAOTHERSTOTAL

TOTAL IN-HOUSE M/Hs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

KEY WORK ITEMIN-HOUSE LABOR BREAKDOWNSUB-CONTRACTOR LABOR BREAKDOWNTOTAL
TOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
HOURSTOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
TOTAL M/Hs0TOTAL M/Hs0
COST PER M/H (¥)<--- Please input in-house labor rateCOST PER M/H (¥)<--- Please input sub-contractor labor rate
LABOR COST (¥)¥0LABOR COST (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Plese insert rows as needed.
MATERIAL COST BREAKDOWN
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS
TOTAL (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Please insert rows as needed.
OTHER DIRECT COST (ODC) (IF ANY)
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS

TOTAL (¥) ¥0

13_3819P31002T07

SHIP NAME/AVAILABILITY:USS BLUE RIDGE (LCC-19) - FY26 CNO 5C1TGI 13_3819P31002T07 SUMMARY
SOLICITATION #:N6264925RA041
SRF-JRMC TGI #:13_3819P31002T07In-House MHSub-KTR MHLabor Cost (JPY)Material (JPY)ODC (JPY)TOTAL (JPY)
DESCRIPTION:Tightness & Operational Test for Potable Water System - KTR00¥0¥0¥0¥0
Note to Offerrors: Please input data on cells highlighted in ORANGE. The TOTAL will not show if KEY WORK ITEM column is empty. Please insert rows as needed.
IN-HOUSE LABOR HOUR BREAKDOWN
KEY WORK ITEMSFTRINSLWELDSMTLRGRSPNTRELECPFTRQAOTHERSTOTAL

TOTAL IN-HOUSE M/Hs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

KEY WORK ITEMIN-HOUSE LABOR BREAKDOWNSUB-CONTRACTOR LABOR BREAKDOWNTOTAL
TOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
HOURSTOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
TOTAL M/Hs0TOTAL M/Hs0
COST PER M/H (¥)<--- Please input in-house labor rateCOST PER M/H (¥)<--- Please input sub-contractor labor rate
LABOR COST (¥)¥0LABOR COST (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Plese insert rows as needed.
MATERIAL COST BREAKDOWN
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS
TOTAL (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Please insert rows as needed.
OTHER DIRECT COST (ODC) (IF ANY)
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS

TOTAL (¥) ¥0

14_3819P31002T08

SHIP NAME/AVAILABILITY:USS BLUE RIDGE (LCC-19) - FY26 CNO 5C1TGI 14_3819P31002T08 SUMMARY
SOLICITATION #:N6264925RA041
SRF-JRMC TGI #:14_3819P31002T08In-House MHSub-KTR MHLabor Cost (JPY)Material (JPY)ODC (JPY)TOTAL (JPY)
DESCRIPTION:Tightness & Operational Test for Chill Water System - KTR00¥0¥0¥0¥0
Note to Offerrors: Please input data on cells highlighted in ORANGE. The TOTAL will not show if KEY WORK ITEM column is empty. Please insert rows as needed.
IN-HOUSE LABOR HOUR BREAKDOWN
KEY WORK ITEMSFTRINSLWELDSMTLRGRSPNTRELECPFTRQAOTHERSTOTAL

TOTAL IN-HOUSE M/Hs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

KEY WORK ITEMIN-HOUSE LABOR BREAKDOWNSUB-CONTRACTOR LABOR BREAKDOWNTOTAL
TOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
HOURSTOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
TOTAL M/Hs0TOTAL M/Hs0
COST PER M/H (¥)<--- Please input in-house labor rateCOST PER M/H (¥)<--- Please input sub-contractor labor rate
LABOR COST (¥)¥0LABOR COST (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Plese insert rows as needed.
MATERIAL COST BREAKDOWN
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS
TOTAL (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Please insert rows as needed.
OTHER DIRECT COST (ODC) (IF ANY)
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS

TOTAL (¥) ¥0

15_3819P31002T09

SHIP NAME/AVAILABILITY:USS BLUE RIDGE (LCC-19) - FY26 CNO 5C1TGI 15_3819P31002T09 SUMMARY
SOLICITATION #:N6264925RA041
SRF-JRMC TGI #:15_3819P31002T09In-House MHSub-KTR MHLabor Cost (JPY)Material (JPY)ODC (JPY)TOTAL (JPY)
DESCRIPTION:Tightness & Operational Test for Distilled Water Service - KTR00¥0¥0¥0¥0
Note to Offerrors: Please input data on cells highlighted in ORANGE. The TOTAL will not show if KEY WORK ITEM column is empty. Please insert rows as needed.
IN-HOUSE LABOR HOUR BREAKDOWN
KEY WORK ITEMSFTRINSLWELDSMTLRGRSPNTRELECPFTRQAOTHERSTOTAL

TOTAL IN-HOUSE M/Hs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

KEY WORK ITEMIN-HOUSE LABOR BREAKDOWNSUB-CONTRACTOR LABOR BREAKDOWNTOTAL
TOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
HOURSTOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
TOTAL M/Hs0TOTAL M/Hs0
COST PER M/H (¥)<--- Please input in-house labor rateCOST PER M/H (¥)<--- Please input sub-contractor labor rate
LABOR COST (¥)¥0LABOR COST (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Plese insert rows as needed.
MATERIAL COST BREAKDOWN
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS
TOTAL (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Please insert rows as needed.
OTHER DIRECT COST (ODC) (IF ANY)
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS

TOTAL (¥) ¥0

16_3819P31002T10

SHIP NAME/AVAILABILITY:USS BLUE RIDGE (LCC-19) - FY26 CNO 5C1TGI 16_3819P31002T10 SUMMARY
SOLICITATION #:N6264925RA041
SRF-JRMC TGI #:16_3819P31002T10In-House MHSub-KTR MHLabor Cost (JPY)Material (JPY)ODC (JPY)TOTAL (JPY)
DESCRIPTION:Tightness & Operational Test for Sewage System - KTR00¥0¥0¥0¥0
Note to Offerrors: Please input data on cells highlighted in ORANGE. The TOTAL will not show if KEY WORK ITEM column is empty. Please insert rows as needed.
IN-HOUSE LABOR HOUR BREAKDOWN
KEY WORK ITEMSFTRINSLWELDSMTLRGRSPNTRELECPFTRQAOTHERSTOTAL

TOTAL IN-HOUSE M/Hs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

KEY WORK ITEMIN-HOUSE LABOR BREAKDOWNSUB-CONTRACTOR LABOR BREAKDOWNTOTAL
TOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
HOURSTOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
TOTAL M/Hs0TOTAL M/Hs0
COST PER M/H (¥)<--- Please input in-house labor rateCOST PER M/H (¥)<--- Please input sub-contractor labor rate
LABOR COST (¥)¥0LABOR COST (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Plese insert rows as needed.
MATERIAL COST BREAKDOWN
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS
TOTAL (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Please insert rows as needed.
OTHER DIRECT COST (ODC) (IF ANY)
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS

TOTAL (¥) ¥0

17_3819P31002T12

SHIP NAME/AVAILABILITY:USS BLUE RIDGE (LCC-19) - FY26 CNO 5C1TGI 17_3819P31002T12 SUMMARY
SOLICITATION #:N6264925RA041
SRF-JRMC TGI #:17_3819P31002T12In-House MHSub-KTR MHLabor Cost (JPY)Material (JPY)ODC (JPY)TOTAL (JPY)
DESCRIPTION:Tightness & Operational Test for AUX Seawater System - KTR00¥0¥0¥0¥0
Note to Offerrors: Please input data on cells highlighted in ORANGE. The TOTAL will not show if KEY WORK ITEM column is empty. Please insert rows as needed.
IN-HOUSE LABOR HOUR BREAKDOWN
KEY WORK ITEMSFTRINSLWELDSMTLRGRSPNTRELECPFTRQAOTHERSTOTAL

TOTAL IN-HOUSE M/Hs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

KEY WORK ITEMIN-HOUSE LABOR BREAKDOWNSUB-CONTRACTOR LABOR BREAKDOWNTOTAL
TOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
HOURSTOTAL MAN HOURS (MH)# PERSONNELHOURS PER DAY# DAYSADDITIONAL
TOTAL M/Hs0TOTAL M/Hs0
COST PER M/H (¥)<--- Please input in-house labor rateCOST PER M/H (¥)<--- Please input sub-contractor labor rate
LABOR COST (¥)¥0LABOR COST (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Plese insert rows as needed.
MATERIAL COST BREAKDOWN
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS
TOTAL (¥)¥0
Note: The EXTENDED PRICE will not show if the DESCRIPTION column is empty. Please insert rows as needed.
OTHER DIRECT COST (ODC) (IF ANY)
DESCRIPTIONQUANTITYUNIT OF ISSUEUNIT PRICE (¥)EXTENDED PRICE (¥)REMARKS

TOTAL (¥) ¥0