TE-4 Contractors Progress Status and Management Report Redacted.pdf
PDF 956 KB Posted
- Attached to
- Mission Command Training Program (MCTP) RFP Amendment 3 Administratively Final Copy of Solicitation Amendment W91QF425RA0080003 Federal contract opportunity
- Solicitation number
- W91QF425RA008
About this file
This document is a Contractor's Progress, Status, and Management Report for April 2023 from the Mission Command Training Program (MCTP) contract, specifically for Contract No. W911S0-18-C-0004. The report details the contractor's activities across multiple Operations Groups (A, B, C, and J) and support teams during April 2023, focusing on various Warfighter Exercises (WFX) including WFX 23-4, 23-5, and 24-2.
Key activities included supporting multiple military exercises across different locations such as Fort Hood, Fort Bliss, Fort Riley, Fort Bragg, and international sites in Germany. The report highlights technical support activities like database preparation, terrain development, simulation testing, and training efforts. In April 2023, the contractor delivered 14 CDRL (Contract Deliverable Requirements List) items, conducted 1,280 hours of sustainment training, and 615 hours of exercise-specific deployment training. The report also notes contract modifications that decreased funding by $1,728,166.67 in early April and added $5,082,232.00 later in the month, indicating ongoing financial adjustments to the contract.
View the file
Other files for this federal contract opportunity
Show all 50
Mission Command Training Program (MCTP) RFP Amendment 3 Administratively Final Copy of Solicitation Amendment W91QF425RA0080003 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract No: W911S0-18-C-0004 UNCLASSIFIED Management Report
CDRL A-01 APRIL 2023
UNCLASSIFIED
Table of Contents for APRIL 2023
SECTION PAGE
1. APRIL 2023 Planning Facts:…….………………………………..…………….………...3
2. APRIL 2023 Execution……....…………………………………...….……..………..…….3
Operations Group A……………………………………………………………………….4
Operations Group B……………………………………………………………………….7
Operations Group C……………………………………………………………………
Operations Group J………….…………………………………………………………...11
Headquarters Support Team (HST)……………………………………………………12
Technical Support Team (TST)………………………………………………………
3. Previously Identified Problem Areas.…………………………………………………..21
4. Changes to Contractor Organization…………………………………………………..21
5. Government equipment Issued / Turned in during APRIL 2023.………...……..…21
6. Travel………………………………………………………………………………………...22
7. Shipments Made during the month of APRIL.……………………….….………..…..23
8. Record of Significant Commitments Received……………………………………….23
9. Plans for MAY 2023………..………….…………………………...…….….……..…
10. List of Annexes…………………………………………………….………………….….24
11. Name and Phone Number of Preparer……………………….………………………..24
CONTRACTOR’S PROGRESS, STATUS, AND MANAGEMENT
REPORT for APRIL 2023
1. APRIL 2023 Planning Facts: A detailed CDRL delivery schedule for the month of APRIL is at Annex-A (Page A–1).
Figure 1. Items Programmed, Delivered, and General Support Items Worked during
APRIL 2023.
For the month of APRIL 2023, 14 CDRL items were delivered. Support included
Warfighter Exercises (WFXs) 23-4, 23-5, 24-2, and FS-23.
2. APRIL 2023 Execution
OPERATIONS GROUP – A
A listing of CDRL items programmed and delivered by Operations Group-A, for the month of APRIL 2023, is at Annex-A.
ROTATIONAL:
Warfighter Exercise 23-4 (WFX 23-4). III Corps, 1CD, 1ACB, 3UK.
Rotational Milestones:
Event Location Date
WFX 23-4 FHTX/FRKS 19-28 APR 23
Current Status: COMPLETE Issues: NONE
Austere Challenge 23 (AC 23), Grafenwohr, Germany, 56th AC, 7th ATC, 10th AAMDC, 19th BCD, 21st TSC, 416th TEC, 2nd MDTF, 66th MI BDE. Exercise
POC:
Rotational Milestones:
Event Location Date AC23 Exercise Wiesbaden 5-12 MAY 23
Current Status: CANCELLED Issues: NONE
Warfighter Exercise 23-5 (WFX 23-5); No Training Audience for OPS-A. OPS-B Exercise Lead Team and Site Lead at Fort Indiantown Gap, PA.
Exercise POC:
Rotational Milestones:
Event Location Date
WFX 23-5 FITG 3-12 JUN 23
Current Status: On-Track Issues: None
Defender Europe 23 (DE23) V Corps, Fort Knox, KY (FKKY).
Exercise POC:
Rotational Milestones:
Event Location Date
WFX 23-5 FKKY 5-14 JUN 23
Current Status: The last collective planning event is complete so additional coordination for this exercise continues via email and telephone calls. This exercise will be conducted over the Mission Partner Environment (MPE). All exercise HICOM
UNCLASSIFIED
and simulation management is conducted from Grafenwöhr Germany. A small contingent of Observer-Coach / Trainers and two NGSC Analysts will deploy to Kaiserslautern, Germany to provide observation and feedback to the 21st Theater Support Command (TSC). The OGA is coordinating to conduct a site survey at Fort Knox, Kentucky prior to the deployment of the ADVON.
Issues: None
Warfighter Exercise 24-1 CANCELLED
Warfighter Exercise 24-2 (WFX 24-1), NO TA, Exercise POC:
WFX 24-2 IPE DCS 2-4 MAY 23
WFX 24-2 FPE ROK 18-20 JUL 23
WFX 24-2 ROK 6-15 NOV 23
Current Status: On Track.
Issues: None
Avenger Triad 24 (AvT-24) (USAREUR-AF). OPSGRP A supports US V Corps at Grafenwoehr, DEU. Exercise POC:
AvT-24 IPC Grafenwoehr, DEU 26-30 JUN 23 AvT-24 MPC Grafenwoehr, DEU 15-19 APR 24 AvT-24 SS Grafenwoehr, DEU TBD AvT-24 FPC Grafenwoehr, DEU 8-12 JUL 24 AvT-24 Grafenwoehr, DEU 10-19 SEP 24 Current Status: Exercise AvT-24 is a multi-corps, multinational, multi-domain, (M3) command post exercise (CPX). The exercise was formerly known as Defender Europe (DE) M3 CPX, and that designation is still seen on some briefing products. AvT-24 is designed to deter adversaries through exercising Large Scale Ground Combat Operations (LSGCO) and associated Mission Essential Tasks (METs), increasing scale, capability, and interoperability of Allied and partner forces, and strengthening the Alliance in United States Army Europe and Africa’s Area of Operation. Exercise classification will likely be Secret Releasable to USA, NATO, SWE, FIN. The exercise will be conducted in the Mission Partner Environment (MPE). OGA’s Training Audiences (TAs) will be US V Corps, and possibly 56 Artillery Command. The OPT schedule will be every four weeks initially.
Issues: Planners need to confirm whether 56 Artillery Command, identified as a TA, will also be supported by OGA.
UNCLASSIFIED
Internal Look 24 (IL 24), United States Army Central Command (USARCENT) HQs, Shaw Air Force Base, SC. OGA Exercise POC:
MSEL CONFERENCE SUFFOLK, VA 22-25 MAY 23
MSEL2 CONFERENCE SUFFOLK, VA 10-14 JUL 23
CRISIS ACT PLANNING SUFFOLK, VA 24-29 AUG 23
FPC MACDILL AFB, FL 31-04 AUG 23
IL-24 Execution SHAW AFB, SC 06-09 NOV 23 Current Status: Between 3-7APR23, the IL24 MPC was conducted live and in person at MACDILL, AFB, Tampa Florida between USCENTCOM, USARCENT and OGA. The USARCENT was represented by Mr. Timothy Marzano. USCENTCOM was represented by Mr. Robert Linschoten and LTCOL Trevor Wilk. The MCTP is on azimuth to support
USARCENT.
Issues: None
TRAINING CONDUCTED APRIL 2023
Phase I, Initial Training: 0 person hours.
Phase II, Sustainment Training: 1280 person hours.
Phase III, Exercise Specific Deployment Training: 615 person hours.
UNCLASSIFIED
OPERATIONS GROUP – B
A listing of CDRL items programmed and delivered by Operations Group-B, for the month of APRIL 2023, is at Annex-A.
ROTATIONAL:
Warfighter Exercise 23-4 (WFX 23-4). OG-B will support 1CD and the 3rd UK Division as their primary training audiences at FHTX. OG-B Senior Control will support WC/RCs at FRKS. WFX 23-4 POC is OG-A is FHTX Site Lead.
Rotational Milestones:
Event Location Date
WXF 23-4 CPX3 FHTX 10-13 APR 23
WFX 23-4 FHTX 19-28 APR 23
Current Status: COMPLETE Issues: NONE
Warfighter Exercise 23-5 (WFX 23-5); 42ID primary Training Audience for OPS-B.
OPS-B Exercise Lead Team and Site Lead at Fort Indiantown Gap, PA.
Exercise POC:
Rotational Milestones:
Event Location Date
WFX 23-5 FITG 3-12 JUN 23
Current Status: Military will support 42ID’s CPX 2 and will derive further understanding of the setup and challenges at FIGPA prior to WFX 23-5.
Issues:
• Final ECG size and the impact on the SCP is TBD but adequate space exists for all COAs.
• Work/Response Cells are distributed to four separate buildings. This will add friction to command and control of the WC/RCs. This may change in early May pending the number of MCTP Staff (i.e. ECG) forward.
Warfighter Exercise 24-1 (WFX 24-1), CANCELLED
Warfighter Exercise 24-2 (WFX 24-1), 2ID (ROK) (8A HICOM).
Exercise POC:
Rotational Milestones:
Event Location Date WFX 24-2 IPE MS Teams 2-4 MAY 23
WFX 24-2 FPE ROK 18-20 JUL 23
2ID Academics ROK 14-18 AUG 23
WFX 24-2 ROK 6-15 NOV 23
UNCLASSIFIED
Current Status: The current COA is to house all contractors in off post hotels.
Transportation plan for movement on post and to the MTC is TBD Issues:
• There is consideration of positioning the ECG at FLKS rather than forward. This COA will have impacts on the SCP, lodging, and the transportation plan.
• Currently, 19 ESC is not a training audience. OG-C will provide coverage under OG- B if needed. No analyst support is required as of this date.
• The cancelation of WFX 24-1 creates the possibility of OG-B supporting WFX 24-2 (2ID) CPX 3 from 25 SEP-3 OCT 23. MCTP must define desired contractor deliverables to determine the analyst and equipment required to execute CPX 3. If contractors support CPX 3 we will deploy and return to FLKS and then redeploy to support the WFX.
Austere Challenge 24 (AC-24) / Warfighter Exercise 24-3 (WFX 24-3). Designated training audience is 1st Infantry Division (1ID). WFX 24-3 POC is
WFX AC-24 IPC Germany 24-27 JUL 23 WFX AC-24 Site Survey FRKS TBD WFX AC-24 FPC Germany 29 JAN-02 FEB 24
WFX 24-3 FRKS 04-15 MAR 24
Current Status: On Track.
Issues: NONE
TRAINING CONDUCTED APRIL 2023:
Phase I, Initial Training: 10 person hours Phase II, Sustainment Training: 266 person hours Phase III, Exercise Specific Training: 525 person hours
UNCLASSIFIED
OPERATIONS GROUP – C
A listing of CDRL items programmed and delivered by Operations Group-C, for the month of APRIL 2021, is at Annex-A.
ROTATIONAL:
Warfighter Exercise 23-4 (WFX 23-4): III Corps, 1 CD and 3 UK Div at FHTX, 1 AD at FBTX. OG-A is the Site Lead. OG-C Exercise POC:
WFX 23-4 FHTX/FBTX/FRKS 19-28 APR 23
Current Status: COMPLETE Issues: NONE.
VIBRANT RESPONSE 23: TF 76 & TF 46 at CAIN. OG-C Exercise
POC:
Rotational Milestones:
Event Location Date
VR-23 CAIN 4-14 MAY 23
Current Status: The culminating event for the Defense CBRN Response Force (DCRF), whose headquarters is Joint Task Force – Civil Support (JTF-CS), and Command and Control CBRN Response Elements A and B (2CRE-A/B) who are with Task Forces 76 and 46, respectively.
Issues: None.
Warfighter Exercise 23-5 (WFX 23-5); NO Training Audience for OPS-C. OPS-B Exercise Lead Team and Site Lead at Fort Indiantown Gap, PA.
Exercise POC:
Rotational Milestones:
Event Location Date
WFX 23-5 FITG 3-12 JUN 23
Current Status: On Track.
Issues: No issues.
Warfighter Exercise 24-1 (WFX 24-1), CANCELLED
Warfighter Exercise 24-2 (WFX 24-1), NO Training Audience
Rotational Milestones:
Event Location Date WFX 24-2 IPE MS Teams 2-4 MAY 23
WFX 24-2 FPE ROK 18-20 JUL 23
UNCLASSIFIED
WFX 24-2 ROK 6-15 NOV 23
Issues: None
Phase I, Initial Training: 0 person hours Phase II, Sustainment Training: 1228 person hours Phase III, Exercise Specific Training: 1180 person hours
UNCLASSIFIED
Operations Group - J A listing of CDRL items programmed and delivered by OPS-J, for the month of APRIL 2023, is at Annex-A.
ROTATIONAL:
Warfighter Exercise 23-4 (WFX 23-4). 18 ABC, 5th SFG. Exercise
POC:
Rotational Milestones:
Event Location Date
WFX 23-4 FBNC 19-28 APR 23
Current Status: COMPLETE Issues: NONE
Warfighter Exercise 23-5 (WFX 23-5); CJSOTF support to HICOM. OPS-B Exercise Lead Team and Site Lead at Fort Indiantown Gap, PA. Exercise
POC:
Rotational Milestones:
Event Location Date
WFX 23-5 FITG 3-12 JUN 23
Current Status: On Track.
Issues: No issues.
Warfighter Exercise 24-1 (WFX 24-1), CANCELLED
Warfighter Exercise 24-2 (WFX 24-1), NO Training Audience
Rotational Milestones:
Event Location Date WFX 24-2 IPE MS Teams 2-4 MAY 23
WFX 24-2 FPE ROK 18-20 JUL 23
WFX 24-2 ROK 6-15 NOV 23
Issues: None
Phase I, Initial Training: 0 person hours Phase II, Sustainment Training: 37 person hours Phase III, Exercise Specific Training: 0 person hours
Headquarters Support Team (HST) A listing of CDRL items programmed and delivered by PLEX, for the month of APRIL 2023, is at Annex-A.
ROTATIONAL:
Warfighter Exercise 23-4 (WFX 23-4). Lead Team at FLKS / FBNC.
HST Exercise POC:
Rotational Milestones:
Event Location Date
WFX 23-4 FBTXFHTX/FRKS/FBNC 19-28 APR 23
Current Status: COMPLETE Issues: NONE
Warfighter Exercise 23-5 (WFX 23-5); Lead Team at FLKS. HST Exercise POC:
Rotational Milestones:
Event Location Date
WFX 23-5 FTIG 3-12 JUN 23
Current Status: On Track.
Issues: None
Warfighter Exercise 24-1 (WFX 24-1), CANCELLED
Warfighter Exercise 24-2 (WFX 24-1), 2ID (ROK) (8A HICOM) Exercise POC:
Rotational Milestones:
Event Location Date WFX 24-2 IPE MS Teams 2-4 MAY 23
WFX 24-2 FPE ROK 18-20 JUL 23
WFX 24-2 ROK 6-15 NOV 23
Current Status: On Track.
Issues: None.
TRAINING CONDUCTED APRIL 2023:
Phase I, Initial Training: 520 person hours Phase II, Sustainment Training: 89 person hours Phase III, Exercise Specific Training: 272 person hours
UNCLASSIFIED
Technical Support Team (TST) A listing of CDRL items programmed and delivered by TST, for the month of APRIL 2023, is at Annex-A.
ROTATIONAL:
• Data Visualization Team (DVT)
- After Action Review System (AARS) System Administrators (Archer) o Provided support to III Armored Corps CPX 3 and WFX 23-4 working with
Multinational Partners.
o Continued support preparation for WFXs 23-5 and 24-2.
o Continued planning support for VR-23 in Camp Atterbury, IN and DEF 23
CPX in Ft. Knox, KY.
- Virtual Three-Dimensional (V3D) Map and Command Information Center
(CIC)
o Provided support to III Armored Corps CPX 3 and WFX 23-4 working with
Multinational Partners.
o Conducted 100% inventory and Pre-Deployment Checks on equipment, in preparation for WFX 23-4.
o Participated in Teams meetings for upcoming WFXs 23-5 and 24-2.
o Continued to Modify VTC equipment integration for AARs.
o Continued preparation for support to WFXs 23-5 and 24-2.
- Innovations Team o Continued Innovations Control Board (ICB) “Roadshows” to determine requirements, refine programming initiatives, and coordinate with customers from each line operations group.
o Continued development and work on NGSC Initiatives, Research and
Development project. Specifically, completed the Agile Backlog Tracker for March, completed the Virtual MDO/Kiosk Architecture, reviewed, and submitted the V3D Kiosk System Design Documents, prepared for the IRAD MDO/Kiosk demo at WFX 23-4 at Ft. Hood, and conducted several MDO Tests with JED Cell at FLKS.
o Continued RID and Crosshair innovations work.
o Received back generally positive SCA-V RMF audit report; continued work on identified issues moving forward.
o Extensive work on Innovations operations and processes documentation to fulfill RMF documentation requirements.
o Supported WFX 23-4 as necessary. Specifically, worked on RID issues related to misconfiguration by operators, bad data input from HST/WCOPFOR, and duplicate data entry into WARSIM Oracle database;
also conducted extensive work on helping to diagnose issues with WARSIM Oracle o ICW V3 MDO engineer, conducted Test Event 1 and 2 during WFX 23-4 of
Multi Domain Operational capacity. Test was successful overall with several areas of refinement identified.
• Digital Support Team (DST):
- C4I Engineers acquired updated image for WFX 23-5 and downloaded new drivers and applications to start verification for WFX support at Ft. Indiantown Gap, PA.
- C4I Engineers provided common services server, COP and ECC support for WFX 23-4 in preparation for work cell training and CPX 3 (RRE 3).
- C4I supported WFX 23-5 with ECC clients and common services for the MCTP Ops Groups and staff.
- Fires and MCA supported ICI testing ICW CPX 3 (RRE 3) with AFATADS database build for UK units and NATO allies.
• Fort Leavenworth Support Team (FLST):
− continued to work with MCTP OPS groups and teams to complete future planning for WFXs and training events. Participated in WARSIM v9.0 meetings and RFIs. Became the main LNO for regarding Cross Domain Solution (CDS) fielding and training at MCTP. Execution of WFX 23-4 (CPX and WFX). Updated and distributed 23-4, 23-5 draft Tech Timelines and Critical Paths. Participated in TST manager meetings. Updated exercise and rig usage calendars based off most recent Exercise Life Cycles, ORE IPRs, and CDS fielding discussions. Supported WFX 23-4 as FLST TST lead. Coordinated with RSC facility manager for cleaning support during WFXs. Prepared an updated RIG Usage calendar for TST Team Lead and CIO.
UNCLASSIFIED
− deployed to the WFX 23-4 exercise as military leadership for the duration of the exercise.
− attended WFX 24-2 planning work group meetings as database lead. Monitoring MCTP PLEX sources for WFX 24-2 calendars and data resources. Provided database products to meet WFX 24-2 IPE requirements.
Completed training and forms for WFX24-2 FPE and WFX travel. Updating Foundational BLUEAIR and BLUEFLEET to support WFX 23-5. Analyzing FY24 Protection MTOE’s and building FY24 Foundational Protection, BLUEAIR and BLUEFLEET databases. Publishing updates to Forward Unit Database Annex of the SGen Scenario Database SOP. Completed all required mandatory NGSC and MCTP online training through LX and Army training websites. Provided forward database support for Multinational Partner (UK) for WFX23-4. Documented modifications to the Multinational Partner portions of the WFX database for use in upcoming Multinational Partner WFX event. Continued training WFX23-5 rear support and for WFX forward support.
− attended WFX23-4 planning meetings and MASTIF as scheduled through MS Teams. Working on the WFX23-4 exercise with updating and changes as needed. Updating FY 24 Foundational database for Military Intel, PSYOPS, Civil Affairs and Special Forces with input from SME’s from OPGRP’s A, B, C, SEG and Intel Systems Coordinator.
− . Assisted on management of Database issues in the WFX 23-4 exercise. Acted as Working Group Lead in the absence of MS who is deployed to the WFX 23-4 exercise as military leadership in the
WFX.
- continued PDM and SGEN training. Worked on yearly classes and updates. Conducted multiple edit sessions on the PDS for a new foundation based off the PDS0, re-did the slides input, went back to March 1st, and entered all edits for WFX 23-5 that were on the PDSO slides. Created a new PDS deck for WFX 23-5 for to convert. Conducted testing on multiple Platforms for WFX 23-4 during lead up to the exercise WFX 23-4 along with edit changes. Conducted Census and Consumption reports for LOGFED and for the NEMOC. Built the slide deck for the Edits and PDS0 changes for SIM Specialist and MCTP Chief of Simulations, . Worked on the Census Report for checkpoints and Sensing Zone for the checkpoints and PAUSEX. Worked on MASTIF Slide updates daily for WFX 23-4 and helped with the issues as we were told about them. Worked night shift for Exercise WFX 23- 4.
− added the Danish, Hungary, Spain, and Greece units to the NATO Database. Restarted the rebuild on the BRITISH Unit database base on New IRON DIVISION BLUEBOOK V2.1. Start the build for the WFX 24-3 Exercise that
UNCLASSIFIED
include the British Division. Continuing to analyze FY24 Aviation MTOEs and NATO units.
− completed WF X23-5 OPFOR force structure build. Completed list and capabilities of all hostile equipment in WARSIM and providing a list of needs and changes to equipment. Currently revising all ADA systems and builds providing all changes to PLANS.
− attended weekly WFX 23-5 Working Groups as the Lead Database Analyst. Edited the WFX 23-5 WARSIM databases as needed based on Annex A and Sustainment changes received from the WFX 23-5 Database Scrub. Worked with both Intel and Fires to successfully import their address book into WFX 23-5 Database. Generated the WFX 23-5 Final Database in preparation for execution of WFX 23-5. Attended WFX 24-2 Internal and External Tech Syncs with
(Lead Database Analyst) to work on completing a left seat/right seat for a second exercise. Supported the database team, as needed, for WFX 23-
4. Continued analyzing fiscal year 2024 sustainment unit MTOEs to update the sustainment foundational database for FY2024.
− : Terrain: Supporting WFX 23-4 for Terrain. Continuing to work with HST for future terrains using Google Earth and various open-source sites and Classified MIDB/BE Data. Converting Open-Source GIS data to produce future terrain. Produced and delivered revised Baltic Terrain and Fixed Site Files for WFX 23-5. Analyzed terrain data provided by KBSC determining that it would not meet the expectations of MCTP for a WFX. Started Producing a Korea terrain for WFX 24-2 using data has edited. Working with TPO-C and to develop future terrains for USARPAC Exercises. Continuing working on UKRAINE/BALTIC/EASTERN EUROPE/ASIA region of the Terrain for future WFXs. Attended weekly JLCCTC Community Teleconference and bi-weekly JLCCTC Data Working Group over MS Teams.
− : Parametrics: Supporting WFX 23-4 for Parametrics. Working with SST, SIM SPECs, Sr Control and EXCON to build and test experimental platforms in WARSIM for WFX23-4. Assisted production of a new Revised Foundational PDS and PDS for WFX23-5. Continuing Krahenbuhl training in the Parametric Database Manager and SGEN software.
Assisting Mr. Randy Krahenbuhl with modification and republishing edits that had been approved by MODS and SIMS. Troubleshooting simulation issues with PDS during WFX23-4.
- The Tech Section – supported the OPFOR New
Hire Training (NHT).
- The Tech Section supported WFX 23-4.
- The Tech Section supported WFX 23-5 OPFOR Data Load.
- The Fort Leavenworth Support Team’s Intelligence Simulations Section (FLST-
ISS) - (
) setup ME BSWS’s and prepared the Middle Enclave for New Hire Training, conducted ICI Testing, IEWTPT testing, and supported WFX 23-4.
- The FLST-ISS COMMs members ( ) monitored, maintained, and provided troubleshooting of the communications lines to deliver intelligence product via the Joint Worldwide Intelligence Communications System (JWICS) to Enhanced Communications Gateway Server (ECGS). Established connections to the 513th MIBN at Fort Gordon, GA, 1st Cavalry Division, 1st Armored Division, and III Armored Corps at Fort Hood, TX.
• Forward Support Team (FST):
− WARSIM Engineers have completed all Tech Control Forward Suites (TCF) with the Anti-Virus Updates as required throughout the WFX to ensure we are following compliance guidance.
o Completed the ESMD for WFX 23-5 to reduce the amount of time employees are on site, while saving the company money during the process.
o Initiated planning and review of the Simulation Control Plans for WFX 23-5.
Submitted the estimate for cables, printer cartridges, and other supply requirements as necessary.
o Coordinated with the Technical Support Team at Fort Leavenworth, to ship and use a Virtual TCF for WFX 23-5.
o Completed multiple planning meetings with KCSB for WFX 24-2 in Korea for support.
o Team worked on training required to help support the WFX in Korea.
o Continued to support WFX 23-4 at 4 Forward sites, Fort Hood, Fort Bliss, Fort
Riley, and Fort Bragg respectively.
− WARSIM Engineers and System Administrators continued preparation for WFXs 23-5 and 24-2.
• Simulation Support, Operations and Plans (SSOP):
− Tech POC/Planners ( ) continued to participate in all EPT/IPRs and Main Planning Event (MPE) conferences for support planning of WFXs 23-5 and 24-2.
UNCLASSIFIED
− Cyber/IA team conducted security scans during WFX 23-4 Risk Reduction Events (RRE) 1, 2, 3, CPX 3 and WFX 23-4 execution to ensure RMF and IA compliance procedures were properly followed while working with Multinational Partners.
− Simulation Support Analysts (SST) continued preparation support for WFXs 23-5 and 24-2.
− SST assisted SIM Specialists and FLST with functional testing of IEWTPT.
− Simulation Support Team (SST) continued functional inoperability support, testing of PIL and work around capabilities with our Multinational Partners in direct support of WFX 23-4.
TRAINING:
• Phase I, Initial Training:
- DST C4I Engineer completed her IAT-II certification.
- FST Engineer and System Admin continued their IAT-II certification training.
- FST System Admin continued his Security+ certification training.
- DVT System Admins continued their Security+ and IAT-II certification training.
- The FLST-ISS System Software Analysts (
) continued initial training to receive certification on the WARSIM Intelligence Model; Training conducted by FLST-ISS members
FLST-ISS
member continued to receive hands-on training in running the TCSP and MC Adapters in support of MCTP WFX exercises from FLST-ISS COMMs SSA .
- FLST Engineer continued initial systems training in configuring and running the Warfighters’ simulation (WARSIM) suites.
- FLST Engineer continued initial systems training in configuring and running the Warfighters’ simulation (WARSIM) suites.
• Phase II, Sustainment Training:
- DST C4I Engineer completed his Security+ and IAT-II recertification requirements.
- The FLST-ISS System Software Analysts (
) continue to receive hands-on training in configuring and running the Warfighters’ simulation (WARSIM-WIM) suites.
- The FLST-ISS COMMs System Software Analysts ( ) continue to receive hands-on training in configuring and running the TCSP and MC Adapters for Intel purposes, in support of MCTP WFX exercises.
- The FLST-ISS System Software Analysts received hands-on training in new RID installation and configuration procedures.
- FLST Engineers completed 32 cumulative hours of sustainment training for February 2023.
- FST Engineers completed 72 cumulative hours of sustainment training for
- DST Engineers completed 50 cumulative hours of sustainment training for
- DVT team completed 8 cumulative hours of sustainment training for February
2023.
- Cyber/IA team completed 13 cumulative hours of sustainment training for
- Simulation Support Operations and Plans (SSOP) team completed 8 cumulative hours of sustainment training for February 2023.
• Phase III, Exercise Specific Pre-Deployment Training:
− None.
GENERAL SUPPORT:
• DVT:
- Conducted multiple V3D Kiosk and MDO capability demonstrations during WFX 23-4 to key leadership for future WFX operational planning.
− CIC and Archer Administrators along with V3D Engr, , continued preparation support for WFXs 23-5 & 24-2.
• DST:
- C4I Engineers built out and maintained all common services in support of WFX 23-
4 Risk Reduction Events (RRE) 1, RRE2, RRE3 and CPX 3.
- Mission Command Adapter (MCA) Systems Software Analyst team continued updating and testing software in support of WFX 23-4 COP and Fires integration operability with Multinational Partners.
• FLST:
- The FLST-ISS System Software Analyst ( ) participated in various meetings with MCTP Army and Contractor Intel personnel and Simulation Specialists regarding WIM capabilities and exercises support, for WFX 23-4, ICI Testing, and IEWTPT testing.
operated and maintained the UE and ME, connected to the NATO MPE production suite, in support of ICI Testing, IEWTPT testing, and WFX 23-4.
tested and maintained MPE assets in support of WFX
23-4.
changed passwords in both enclaves.
- The FLST-ISS COMMs System Software Analysts ( participated in TCSP security scans and audit log acquisition, for the acting GSC ISSO and IA Analyst Cody Voelker to maintain MCTP TCSP ATO status.
updated anti-virus definitions IAW with established IA procedures.
deployed, configured, and troubleshooted RID in support of WFX 23-4.
• FST:
− WARSIM Engineers and System Administrators continued preparation for support to WFXs 23-5 and 24-2.
UNCLASSIFIED
• SSOP
− Planners (POCs) and Simulation Support Specialists (SST) continued participation in EWGs/MPEs/FPEs for WFXs 23-5 and 24-2 support.
− SST continued to support RWA improvements for FY 23.
LAB USE:
- Technicians used the lab to perform required image scans, baseline updates and security patching of WARSIM, Archer and C4I server suites for WFX 23-4 support and WFX 23-5 preparation.
3. Previously Identified Problem Areas: None
4. Changes to Contractor Organization: Nine (9) new full-time employee were processed in April. One (1) full-time employee transferred in April. Zero (0) full-time employees terminated in April.
5. Government equipment issued during APRIL 2023, ZERO (0) turn-in:
ITEMS ISSUED FOR THE MONTH OF APRIL 2023
Location SerialNumber NGSHR NGNomen Model Manufacturer Received
DV 793L 4 Monitor P2722H DELL April 18 2023
DV 307L 4 Monitor P2722H DELL April 18 2023
DV 810L 4 Monitor P2722H DELL April 18 2023
DV 823L 4 Monitor P2722H DELL April 18 2023
DV 301L 4 Monitor P2722H DELL April 18 2023
DV 315L 4 Monitor P2722H DELL April 18 2023
DV 316L 4 Monitor P2722H DELL April 18 2023
DV 310L 4 Monitor P2722H DELL April 18 2023
DV 811L 4 Monitor P2722H DELL April 18 2023
DV 317L 4 Monitor P2722H DELL April 18 2023
DV 821L 4 Monitor P2722H DELL April 18 2023
DV 364L 4 Monitor P2722H DELL April 18 2023
DV 308L 4 Monitor P2722H DELL April 18 2023
DV 311L 4 Monitor P2722H DELL April 18 2023
DV 312L 4 Monitor P2722H DELL April 18 2023
DV 390L 4 Monitor P2722H DELL April 18 2023
DV 302L 4 Monitor P2722H DELL April 18 2023
235 309L 0 Monitor P2722H DELL April 18 2023
ATM 181L 1 Monitor P2722H DELL April 18 2023
ATM 144L 1 Monitor P2722H DELL April 18 2023
ATM 189L 1 Monitor P2722H DELL April 18 2023
ATM 319L 1 Monitor P2722H DELL April 18 2023
ATM 149L 1 Monitor P2722H DELL April 18 2023
6. Travel. A summary of travel authorizations (TAs) issued for GFY 23 is at Annex C.
The following TAs were issued during the month of APRIL 2023:
PURPOSE LOCATION NO. PERSONNEL
VR-23 SS CAIN 2
IL 23 SS MacDill, FL 1
WFX 23-4 FBTX 117
WFX 23-4 FBNC 83
WFX 23-4 FHTX 245
ITEMS ISSUED FOR THE MONTH OF APRIL 2023 cont
Location SerialNumber NGSHR NGNomen Model Manufacturer Received
ATM 182L 1 Monitor P2722H DELL April 18 2023
ATM 323L 1 Monitor P2722H DELL April 18 2023
ATM 315L 1 Monitor P2722H DELL April 18 2023
HST 514L 12 Monitor P2722H DELL April 18 2023
HST 263L 12 Monitor P2722H DELL April 18 2023
HST 300L 12 Monitor P2722H DELL April 18 2023
HST 252L 12 Monitor P2722H DELL April 18 2023
HST 159L 12 Monitor P2722H DELL April 18 2023
HST 253L 12 Monitor P2722H DELL April 18 2023
HST 480L 12 Monitor P2722H DELL April 18 2023
HST 347L 12 Monitor P2722H DELL April 18 2023
BTM 186L 3 Monitor P2722H DELL April 18 2023
BTM 316L 3 Monitor P2722H DELL April 18 2023
BTM 317L 3 Monitor P2722H DELL April 18 2023
BTM 324L 3 Monitor P2722H DELL April 18 2023
BTM 114L 3 Monitor P2722H DELL April 18 2023
BTM 118L 3 Monitor P2722H DELL April 18 2023
BTM 329L 3 Monitor P2722H DELL April 18 2023
BTM 258L 3 Monitor P2722H DELL April 18 2023
PMO 187L 13 Monitor P2722H DELL April 18 2023
PMO 321L 13 Monitor P2722H DELL April 18 2023
PMO 256L 13 Monitor P2722H DELL April 18 2023
PMO 138L 13 Monitor P2722H DELL April 18 2023
PMO 259L 13 Monitor P2722H DELL April 18 2023
PMO 153L 13 Monitor P2722H DELL April 18 2023
CTM 155L 2 Monitor P2722H DELL April 18 2023
CTM 125L 2 Monitor P2722H DELL April 18 2023
CTM 134L 2 Monitor P2722H DELL April 18 2023
CTM 088L 2 Monitor P2722H DELL April 18 2023
CTM 742L 2 Monitor P2722H DELL April 18 2023
CTM 743L 2 Monitor P2722H DELL April 18 2023
JTM 818L 10 Monitor P2722H DELL April 18 2023
JTM 820L 10 Monitor P2722H DELL April 18 2023
JTM 814L 10 Monitor P2722H DELL April 18 2023
JTM 797L 10 Monitor P2722H DELL April 18 2023
JTM 306L 10 Monitor P2722H DELL April 18 2023
JTM 745L 10 Monitor P2722H DELL April 18 2023
JTM 795L 10 Monitor P2722H DELL April 18 2023
JTM 796L 10 Monitor P2722H DELL April 18 2023
UNCLASSIFIED
WFX 23-4 FRKS 71
WFX 23-4 FLKS 153
TOTAL 672
7. Shipments Made during the month of APRIL 2023:
OPSGP DATE EXERCISE SHIPMENT ORIGIN DELIVERY SITE
OPS-C 28APR23 WFX 23-4 FBTX CAIN
8. Record of Significant Commitments Received:
Modification P00044 to W911S0-18-C-0004, 4 April 2023: Decreased $1,728,166.67 of the FY 2023 year funding.
Modification P00045 to W911S0-18-C-0004, 27 April 2023: Added $5,082,232.00 to the FY 2023 year funding.
9. Plans for MAY 2023:
OPSGRP–A:
ROTATIONAL ACTIVITIES FOR MAY 2023:
WFX 24-2 IPE Teams 2-4 MAY 23
OPSGRP-B:
Event Location Date
WFX 23-5 FITG 19 MAY- 12 JUN 23
OPSGRP-C:
Event Location Date
VE-23 CAIN 4-13 MAY 23
UNCLASSIFIED
OPSGRP-J:
ROTATIONAL ACTIVITIES FOR MAY 2023:
Event Location Date
HST:
Event Location Date
TECHNICAL SUPPORT TEAM Projected Activities MAY 2023:
- TST will provide support to:
▪ WFX 23-5 Database Scrub
▪ WFX 23-5
▪ Functional Baseline and Security Updates (Summer)
▪ Summer New Hire Training
▪ WARSIM 9.0 ORE
▪ CDS Fielding and Training
▪ WFX 24-2 Database Scrub
▪ WFX 24-2
10. List of Annexes
ANNEX TITLE
ANNEX A CDRL Delivery Schedule APRIL 2023
ANNEX B Summary of Items Delivered GFY 2023
ANNEX C Summary of TAs Authorized GFY 2023
11. Name and Phone Number of Preparer
APRIL 2023 SYSTEMS CORPORATION SUPPORT SCHEDULE GFY 2023 ANNEX A
CDRL ROTATION OG DATE DUE DATE DEL COMMENTS
A-1 MARCH PSMR PM 11-Apr-23 4-Apr-23 PROGRAMMED DELIVERED NOT PROGRAMMED TOTAL DEL GS ITEMS
A-2 MAR COST REPORT PM 11-Apr-23 11-Apr-23 PM 2 2 2
A-5 23-4 THP A 28-Apr-23 28-Apr-23 A 2 2 2
A-4 23-5 EWG 4 APR 23 A 7-Apr-23 NO TA
A-4 23-5 EWG 11 APR 23 A 14-Apr-23 NO TA CPX 3 23-4 B 4 4 4
A-4 23-5 EWG 18 APR 23 A 21-Apr-23 NO TA WFX 23-4
A-4 23-5 EWG 25 APR 23 A 28-Apr-23 NO TA WFX 23-4 C 1 1 1
A-4 24-2 EWG 29 MAR 23 A 3-Apr-23 NO TA
A-4 24-2 EWG 4 APR 23 A 7-Apr-23 NO TA J 0 0 0
A-4 24-2 EWG 12 APR 23 A 17-Apr-23 NO TA CPX 3 23-4
A-4 24-2 EWG 19 APR 23 A 24-Apr-23 NO TA WFX 23-4 HST 5 5 5
A-4 24-2 EWG 26 APR 23 A 1-May-23 NO TA WFX 23-4
A-14 FS-23 CTR AAR A 23-Apr-23 17-Apr-23 TST 0 0 15 15
A-5 23-4 THP B 28-Apr-23 28-Apr-23
A-4 23-5 EWG 4 APR 23 B 7-Apr-23 CANCELLED TOTALS 14 14 0 29 15
A-4 23-5 EWG 11 APR 23 B 14-Apr-23 12-Apr-23 CPX 3 23-4
A-4 23-5 EWG 18 APR 23 B 21-Apr-23 CANCELLED WFX 23-4
A-4 23-5 EWG 25 APR 23 B 28-Apr-23 CANCELLED WFX 23-4
A-4 24-2 EWG 29 MAR 23 B 3-Apr-23 30-Mar-23
A-4 24-2 EWG 4 APR 23 B 7-Apr-23 5-Apr-23
A-4 24-2 EWG 12 APR 23 B 17-Apr-23 CANCELLED CPX 3 23-4
A-4 24-2 EWG 19 APR 23 B 24-Apr-23 CANCELLED WFX 23-4
A-4 24-2 EWG 26 APR 23 B 1-May-23 CANCELLED WFX 23-4
A-5 23-4 THP C 28-Apr-23 28-Apr-23
A-4 23-5 EWG 4 APR 23 C 7-Apr-23 NO TA
A-4 23-5 EWG 11 APR 23 C 14-Apr-23 NO TA CPX 3 23-4
A-4 23-5 EWG 18 APR 23 C 21-Apr-23 NO TA WFX 23-4
A-4 23-5 EWG 25 APR 23 C 28-Apr-23 NO TA WFX 23-4
A-4 24-2 EWG 29 MAR 23 C 3-Apr-23 NO TA
A-4 24-2 EWG 4 APR 23 C 7-Apr-23 NO TA
A-4 24-2 EWG 12 APR 23 C 17-Apr-23 NO TA CPX 3 23-4
A-4 24-2 EWG 19 APR 23 C 24-Apr-23 NO TA WFX 23-4
A-4 24-2 EWG 26 APR 23 C 1-May-23 NO TA WFX 23-4
A-4 23-5 EWG 4 APR 23 J 7-Apr-23 NO TA
A-4 23-5 EWG 11 APR 23 J 14-Apr-23 NO TA CPX 3 23-4
A-4 23-5 EWG 18 APR 23 J 21-Apr-23 NO TA WFX 23-4
A-4 23-5 EWG 25 APR 23 J 28-Apr-23 NO TA WFX 23-4
A-4 24-2 EWG 29 MAR 23 J 3-Apr-23 NO TA
A-4 24-2 EWG 4 APR 23 J 7-Apr-23 NO TA
A-4 24-2 EWG 12 APR 23 J 17-Apr-23 NO TA CPX 3 23-4
A-4 24-2 EWG 19 APR 23 J 24-Apr-23 NO TA WFX 23-4
A-4 24-2 EWG 26 APR 23 J 1-May-23 NO TA WFX 23-4
A-4 23-5 EWG 4 APR 23 HST 7-Apr-23 CANCELLED
A-4 23-5 EWG 11 APR 23 HST 14-Apr-23 12-Apr-23 CPX 3 23-4
A-4 23-5 EWG 18 APR 23 HST 21-Apr-23 CANCELLED WFX 23-4
A-12 23-5 HICOM OPORD HST 19-Apr-23 3-Apr-23
A-4 23-5 EWG 25 APR 23 HST 28-Apr-23 CANCELLED WFX 23-4
A-4 24-2 EWG 29 MAR 23 HST 3-Apr-23 30-Mar-23
A-1
APRIL 2023 SYSTEMS CORPORATION SUPPORT SCHEDULE GFY 2023 ANNEX A
A-4 24-2 EWG 4 APR 23 HST 7-Apr-23 6-Apr-23
A-4 24-2 EWG 12 APR 23 HST 17-Apr-23 CANCELLED CPX 3 23-4
A-4 24-2 EWG 19 APR 23 HST 24-Apr-23 CANCELLED WFX 23-4
A-4 24-2 EWG 26 APR 23 HST 1-May-23 CANCELLED WFX 23-4
A-13 23-5 OPFOR SCP HST 2-May-23 3-Apr-23
A-2