This is an Invitation for Bids (IFB) document issued by the City of Plant City, Florida for the North Woodrow Wilson Street Sidewalk Improvements project funded through Community Development Block Grant (CDBG) monies. The City seeks qualified design-build respondents to complete sidewalk improvements on the east side of North Woodrow Wilson Street from West Lowry Avenue to the CSX railroad. The project scope includes flexible paving, grading, drainage, concrete sidewalks and driveways, stripping, signage, tree removal, sodding, and replacement of an existing potable watermain and appurtenances, with coordination for relocation of underground private utilities. A pre-proposal meeting is scheduled for Tuesday, March 31, 2026, at 10:00 AM at the City Commission Chambers located at 302 West Reynolds Street, Plant City, Florida 33563. The question deadline is 5:00 PM on Monday, April 13, 2026, and the submittal deadline is 2:00 PM on Thursday, April 23, 2026. All solicitation documents are available for public inspection and submission through the City E-Procurement Portal at https://procurement.opengov.com/portal/plantcitygov.

The project is funded through CDBG resources. Pricing, set-asides, incumbent information, and additional funding details are not specified in this legal notice document.

View the file

Other files

File Type Posted
26-024EN-IFB_Pre-Proposal_Meeting_Sign-in_Sheet.pdf PDF
TAMPA_BAY_TIMES_AD_PLACEMENT_REQUEST_FORM_02.16.26.pdf PDF
North_Woodrow_Wilson_Street_Sidewalk_Improvements_CDBG.pdf PDF
FL20260252_WageDetermination.pdf PDF
HUD_24_CFR,_Part_75_Section_3.pdf PDF
BABA_FORM.pdf PDF
2026-03-20_N._Woodrow_Wilson_Sidewalk_Improvement_Construction_Contract.pdf PDF
[H]_CSX_Railroad_TROE_Location.pdf PDF
HUD_Form_4010_updated_10.2023.pdf PDF
[I]_ROW_Use_Permit_Application.pdf PDF
GC_and_Subcontractor_E-Verify_Affidavit_(07-12-23)CAO.pdf PDF
Federal_Debarment_Certification_Form_Final_(9-12-23).pdf PDF
Davis_Bacon_and_Section_3_Acknowledgment_Form.docx.pdf PDF
[B]_Construction_Plans-DS.pdf PDF
[A]_Project_Exhibits.pdf PDF
[G]_Material_&_Equipment_Storage_Site.pdf PDF
[D]_Technical_Manual_for_Water,_Wastewater_and_Reclaimed_Water_Utilities.pdf PDF
[F]_ERP_Project_Exemption_Approval_N_Woodrow_Wilson_Street_Sidewalk.pdf PDF
[C]_Technical_Specifications-DS.pdf PDF
[E]_Standards_Specs_for_Traffic_Control_Signals_&_Devices,_Signing,_Pavement_Marking,_and_Lighting_Construction.pdf PDF
Addition_to_Special_Provisions.docx DOCX document
Worksheet_for_Construction_Agreement_NWoodrowWilsonStSW.docx DOCX document
Bid_Form.xlsx XLSX spreadsheet
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

City of Plant City Plant City, Florida

26-024EN-IFB

North Woodrow Wilson Street Sidewalk Improvements CDBG

The City of Plant City, Florida seeks submittals from qualified and experienced design-build respondents to complete all specified requirements in the solicitation documents, which are open for public inspection, question, and submittal online, via the City E-Procurement Portal, located at:

https://procurement.opengov.com/portal/plantcitygov.

There will be a pre-proposal meeting on Tuesday, March 31, 2026, at 10:00AM at the City Commission Chambers of the Nettie Berry Draughn Municipal Building (City Hall) located at 302 W. Reynolds St, Plant City, FL 33563.

The question deadline is not later than 5:00 PM on Monday, April 13, 2026.

The submittal deadline is not later than 2:00 PM on Thursday, April 23, 2026.