About this file

This document outlines first article testing requirements for three power supply national stock numbers to be procured by the Department of the Air Force Materiel Command Lifecycle Management Center Robins Air Force Base. Key details include a requirement for 2 units of first article testing for NSN 6130-01-269-3624 with full qualification testing and government testing at the next higher assembly level. The solicitation number for this opportunity is SPRWA1-19-R-0007 and it describes plans to award multiple IDIQ contracts worth a total of $800 million over 10 years to support the design, development and manufacture of power supplies ranging from low voltage to 20kVDC for various military aircraft. Award is anticipated for up to 6 contracts including 2 set aside for small businesses.

First Article Requirements NSN 3624

View the file

Other files for this federal contract opportunity

Other files attached to Power Supply Solutions (PS2), newest first.
File Type Posted
SPRWA1-19-R-0007_0002.pdf PDF
SPRWA119R0007_Question_and_Answer__6.docx DOCX document
SPRWA119R00010001.pdf PDF
SPRWA119R0007_QA__5.docx DOCX document
SPRWA119R0007_QA__4.docx DOCX document
SPRWA119R0007_Q__A__3.docx DOCX document
SPRWA119R0007_Q&A_2.docx DOCX document
SPRWA119R0007_Questions_and_Answers.docx DOCX document
UpdatedReqDescriptionandCDRLA007Continuation3624v6.pdf PDF
SOW05212019wAppendixA.pdf PDF
Attachment2PastPerformanceQuestionnaireDLA.docx DOCX document
QA807NSN3927.pdf PDF
EDL5626.pdf PDF
QA807NSN5626.pdf PDF
IUIDChecklist5626.pdf PDF
PackagingRequirements3927v2.pdf PDF
Transportation5626.pdf PDF
EDL3624.pdf PDF
PackagingRequirements3624v3.pdf PDF
IUIDChecklist3927.pdf PDF
Attachment3ClientAuthorizationLetter.docx DOCX document
IUIDChecklist3624.pdf PDF
Transportation3624.pdf PDF
UpdatedReqDescription5626v4.pdf PDF
PackagingRequirements5626v3.pdf PDF
CDRLpackage04172019.pdf PDF
Attachment4PricingMatrixv44.xlsx XLSX spreadsheet
Transportation3927.pdf PDF
SPRWA119R0007final.pdf PDF
FirstArticleRequirement5626.pdf PDF
Attachment1FACTSSHEET.docx DOCX document
QA807NSN3624.pdf PDF
EDL3927.pdf PDF
UpdatedReqDescription3927v4.pdf PDF
FirstArticleRequirement3927.pdf PDF
Virtual_Industry_Day_Questions_and_Answers.docx DOCX document
Show all 36

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FIRST ARTICLE REQUIREMENTS 1. DATE

11 FEB 2019(AFMCI 64-110, AFMCI 23-102 and FAR Part 9, Sub Part 9.3)(Additional Instructions on Page 3)

2. PR / MIPR NUMBER 3. CAGE / REFERENCE NUMBER

00752 / 442529-6

4. NSN

6130012693624EW

5. FIRST ARTICLE QUANTITY

THE FIRST ARTICLE IS 2 UNIT(S) OF LOT / ITEM 0001

AND WILL BE: PART OF PRODUCTION QUANTITY X IN ADDITION TO PRODUCTION QUANTITY

6. ARTICLES

WILL X WILL NOT SERVE AS A MANUFACTURING STANDARD

7. LONG LEAD TIME ITEMS

REQUIRED X NOT REQUIRED

(See FAR 52.209-3 OR -4, alternate II)

8. SPECIAL REQUIREMENT/PRODUCTION FACILITIES (See FAR 52.209-3 OR -4 Alternate I)

REQUIRED X NOT REQUIRED

"The First Article offered must be manufactured at the facilities in which that item is to be produced under the contract, or if the First Article is a component not manufactured by the contractor, such component must be manufactured at the facilities in which the component is to be produced for the contract. A certification to this effect must accompany each First Article which is offered."

9. TEST / INSPECTION REQUIREMENTS

A. X

X

CONTRACTOR TESTING

GOVERNMENT TESTING

Performance or other characteristics which the First Articles must meet are

Technical/performance requirements are defined in the documents listed in the Engineering Data List, which include, but are not limited to, the following:

442529 - Power Supply Assembly 439906-3 - Power Supply Specification 235010 - General Specification for Functional Assemblies 438463 - Envelope Drawing, Dual TWT Power Supply

B. The detailed technical requirements for First Article approval tests are contained in

FA test requirements will be defined by the contractor in a CDRL. Full qualification testing is required to ensure compliance with the LRU environmental and EMI/EMC requirements. Legacy power supply test requirements for spares are defined in the following documents:

484266 - Acceptance Test Procedure 484407 - Burn-in Procedure Government testing will consist of installation in the Next Higher Assembly (NHA) with full ATP at the NHA level and aircraft ground testing as a minimum. Flight test may be required as well; this will be determined prior to award.

(Cite Spec and Para number)

C. X TEST PLAN REQUIRED

Number of days for government approval / disapproval 60 days.

D. Contractor's notification to ACO and

408 SCMS/GUEA

(Requesting Activity) of test time and location due 30 days prior to start of testing.

E. X TEST REPORT REQUIRED

(1) Forwarded to

408 SCMS/GUEA

235 Byron St. STE 19A

Robins AFB, GA 31098

(2) Government written notice of approval / disapproval due 60 days after receipt of contractor's report.

calendar days from date contract.

F. FIRST ARTICLE DELIVERY

(1) Due within 600

(2) Notify 30 calendar days prior to shipment.

(3) Delivered to government at

FD2060 - DLA Central Rcvg, DDWG ER

Special Handling, First Art. Unit

455 Byron Street WR-ALC

Robins AFB, GA 31098-1887

(Set Forth Consignee and Address)

(4) Government written notice of approval / disapproval within 180 days after receipt of first article package.

Page 1 of 3AFMC IMT 260, 20020830, V-3 Version 8Generated by PRPS using Jasper Reports on 11 Feb 2019

11 FEB 2019(AFMCI 64-110, AFMCI 23-102 and FAR Part 9, Sub Part 9.3)(Additional Instructions on Page 3)

G. Estimated cost of government testing / inspection evaluation.

$100,000.0000

Page 2 of 3AFMC IMT 260, 20020830, V-3 Version 8Generated by PRPS using Jasper Reports on 11 Feb 2019

11 FEB 2019(AFMCI 64-110, AFMCI 23-102 and FAR Part 9, Sub Part 9.3)(Additional Instructions on Page 3)

10. DISPOSITION OF FIRST ARTICLES

X Approved First Articles will be forwarded to

SW3119

X 2 (insert quantity) First Articles will be expended in testing. Residual components of disapproved First Articles

X will be returned to the contractor will be retained by pending disposition instructions from the contractor.

First Articles will be installed on aircraft/equipment to determine proper fit/function. Approved article will remain on the aircraft/equipment and will not be forwarded to USAF Supply, but will be considered part of the contract quantity.

X Disapproved First Articles

X will be returned to the contractor will be retained by pending disposition instructions from the contractor.

On purchase requests designated as direct shipments the following disposition will apply. (NOTE: Always applicable on Foreign Military Sales (FMS)).

a. Approved First Articles will be returned to the contractor for shipment with production item.

b. Disposition of disapproved First Articles will remain the same as marked above.

Other Disposition:

11. CONDITION(S) FOR WAIVER OF FIRST ARTICLE APPROVAL

a. Offerors who have previously furnished production quantities of the same or similar article to the prime contractor for delivery to the Government, DoD, Air Force.

b. Offerors currently in production of the same or similar article for a Government, DoD, Air Force contract and who have received First Article approval under the existing contract.

c. Offerors who have previously furnished production quantities of the same or similar articles to the Government, DoD, Air Force, provided articles thus furnished, have exhibited satisfactory performance in service in the opinion of the Air Force.

d. Provided not more than months have elapsed since completion of the contract.

e. X First Article testing will not be waived.

f. See Remarks in block 12 below.

NOTE TO BUYER: UNDER CONDITIONS A AND C ABOVE, THE COGNIZANT ENGINEERING ACTIVITY WILL DECIDE WHETHER OR NOT THE ITEM HAS EXHIBITED SATISFACTORY PERFORMANCE IN SERVICE AND PREPARE AND RETAIN SUPPORTING DOCUMENTATION TO FULLY JUSTIFY THIS DECISION. THE BUYER MUST SOLICIT DUAL PRICES (That is, both with and without requirement for first article approval) AND MUST FURNISH THE COGNIZANT ENGINEERING ACTIVITY WITH THE FOLLOWING INFORMATION ON THE PREVIOUSLY SUPPLIED ARTICLE:

A. PROCURING OFFICE B. CONTRACT NUMBER C. DATE OF CONTRACT D. SPECIFICATION NUMBER AND REVISION

12. REMARKS

13. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR APPROVING TEST

(Name, Organization, Phone)

Eidson, James D

408 SCMS / GU E A

478-472-4652

222-4652

14. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR CONDUCTING

TEST (Name, Organization, Phone)

Page 3 of 3AFMC IMT 260, 20020830, V-3 Version 8Generated by PRPS using Jasper Reports on 11 Feb 2019

File details come from the government source that posted it. Updated .