This is a pricing template for submitting As-Built Production Unit Cost proposals in response to the Self-Propelled Howitzer-Modernization (SPH-M) Mobile Tactical Cannon (MTC) Request for Prototype Proposal. Offerors are required to submit cost responses in Base Year 2026 U.S. Dollars for three production quantity ranges: 1-24 MTC systems, 25-36 MTC systems, and 37-48 MTC systems. The cost breakdown must include Direct Labor Cost, Direct Material Cost, Direct Subcontract Cost, Overhead Cost, G&A Cost, and Profit/Fee for each quantity range, with totals calculated for each tier. This cost volume serves as an evaluation criterion as defined in the RPP section 4.2.4 and will be used for competitive technical evaluation by Project Manager Howitzer Systems (PM HS) within the Department of the Army.

The template is marked as UNCLASSIFIED with Distribution Statement A for public release. As part of the final Proposal-Based Learning (P-BL) development, offerors should delete the cover page sheet upon submission and provide only the Title Page and P-BL sheets. Responses to this draft Request for Prototype Proposal were requested by February 16, 2026, with the final RPP anticipated for release in the Second Quarter of Fiscal Year 2026. The Government intends to award one contract to a single vendor for a 155mm self-propelled howitzer solution to replace towed M777 howitzers, initially for Stryker Brigade Combat Teams.

View the file

Other files for this federal contract opportunity

Other files attached to Self-Propelled Howitzer-Modernization (SPH-M) Mobile Tactical Cannon (MTC) Draft #2 and Industry Day Slides/Q&A, newest first.
File Type Posted
Appendix E(1) - Milestone Pricing Sheet - Table F-1.xlsx XLSX spreadsheet
Cost Volume Language.pdf PDF
Appendix E - Milestone Pricing Summary.xlsx XLSX spreadsheet
Appendix E(2) - Milestone Pricing Sheet - Table F-2 Continuation.xlsx XLSX spreadsheet
Appendix A - Project Articles 12Feb26.docx DOCX document
Attachment 001 - Contract Data Requirements List (CDRLs) 12Feb26.xlsx XLSX spreadsheet
Appendix C - Representations and Certifications_Jan 2026.docx DOCX document
Appendix B - Project Other Terms and Conditions 12Feb26.docx DOCX document
(DRAFT2) Prototype Project Agreement (PDF Version) 12Feb26.pdf PDF
(DRAFT2) Prototype Project Agreement 12Feb26.docx DOCX document
(DRAFT2) MTC Request for Prototype Proposal (PDF Version).pdf PDF
(DRAFT2) Prototype Project Agreement (PDF Version).pdf PDF
Attachment 012 MTC Test Schedule Breakdown.xlsx XLSX spreadsheet
Attachment 014 POL Guide v1.2 2024.pdf PDF
Attachment 016 - MTC Sample SLA.docx DOCX document
PdM_SPHM_Industry Day 2026.pptx PPTX presentation
(DRAFT2) MTC Request for Prototype Proposal.docx DOCX document
(DRAFT2) Prototype Project Agreement.docx DOCX document
Appendix A - Project Articles.docx DOCX document
Appendix B - Project Other Terms and Conditions.docx DOCX document
Attachment 006 - I-BOM Sample.xlsx XLSX spreadsheet
Attachment 007 - MATCE Input Datasheet Wheeled Vehicles.xlsx XLSX spreadsheet
Attachment 010 - TDP OPTION WORKSHEET CAD.pdf PDF
Attachment 011 - TDP OPTION WORKSHEET TDP.pdf PDF
Attachment 001 - Contract Data Requirements List (CDRLs).xlsx XLSX spreadsheet
Attachment 003 - Supply Chain Market Checklist.pptx PPTX presentation
Attachment 004 - Assertion of Restrictions.xlsx XLSX spreadsheet
Attachment 005 - As-Built Configuration Template.xlsx XLSX spreadsheet
Attachment 009 - Proof Gun system Overview.pdf PDF
Attachment 013 ATTLA_Universal_Data_Sheet.xlsx XLSX spreadsheet
Industry_Day_Questions_and_Responses.pdf PDF
Show all 31

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cover Page

UNCLASSIFIED

Item Description:As-Built Production Unit Cost Volume
Cover Page

Distribution Statement A – Approved for Public Release; distribution unlimited

(*Distribution Statement A only applies when form is not filled in. Once filled check the Security Class Guide for proper distribution statement/markings)

As part of the P-BL development, delete this sheet and submit only the "Title Page" and "P-BL" sheets.

1. Introduction

Tab 1. Instructions Nothing to input, informational only.

Tab 2. Production Unit Cost Insert the required information in the blue highlighted cells. The offeror will submit responses in Base Year (BY) 2026 U.S. Dollars (USD) for the given production quantity ranges for the As-built Production Configuration. This cost volume will be used for Evaluation as defined in RPP section 4.2.4

2. Production Unit Cost

Total Cost-Price Summary

Form Instructions: Insert the required information in the blue highlighted cells. The offeror will submit responses in Base Year (BY) 2026 U.S. Dollars (USD) for the given production quantity ranges for the As-built Production Configuration. This cost volume will be used for Evaluation as defined in RPP section 4.2.4

Category Description1-24
MTC systems25-36
MTC systems37-48

MTC systems

Direct Labor Cost
Direct Material Cost
Direct Subcontract Cost
Overhead Cost
G&A Cost
Profit/Fee
Total Price$ -$ -$ -