FBO_Questions_and_Answers.pdf

PDF 22 KB Posted

Attached to
Scotia Depot Facility Upgrades Federal contract opportunity
Solicitation number
SP8000-17-R-0010
Issued by
Defense Logistics Agency Strategic Materials

About this file

Questions and Answers

View the file

Other files for this federal contract opportunity

Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers- Scotia Depot Facility Upgrades

SP8000-17-R-0010

Question: Could you provide me with the budget range for this project?

Answer: The Government does not provide the budget of projects to contractors. We ask interested contractors to submit a proposal consistent with the requirement.

Question: What is the general scope of work?

Answer: There are four (4) buildings at the depot facility that will require upgrade services. Please refer to Section 1.1 Scope of Work and Section 5 Specific Task(s) of the Performance Work Statement (PWS) for the specific tasks required at each building.

Question: What is the construction schedule - start & finish date?

Answer: Services must be completed within 120 days of the contract award date.

Question: Is it one contract, or multiple primes?

Answer: DLA Strategic Materials intends to award one contract.

Question: What is the estimated contract Price?

Answer: The Government does not provide the budget of projects to contractors. We ask interested contractors to submit a proposal consistent with the requirement.

Question: Do you think the bid date will be extended from the original June 19th date?

Answer: At this time, we do not have a request to extend the closing date.

Question: Is there a website where we can view the bid documents at no cost? And if not, where would I be able to purchase such documents?

Answer: We cannot provide a sample of a bid document, and we do not know where or if these documents can be purchased. There is no template for the bid documents. However, offerors should create their proposal in accordance with the requirements stated in the Combined/Synopsis Solicitation documents and attachments.