TE_5_5_Performance_Requirements_Summary_conformed_thru_SP330013R5002_Amendment_0002_for_FBO_Post.doc

DOC document 46 KB Posted

Attached to
Hazardous Materials Management (3PL) Services in support of the Marine Corps and Navy organizations located in Okinawa, Japan
Solicitation number
SP3300-13-R-5002
Issued by

About this file

Revised Technical Exhibit 5.5-Performance Requirements Summary SP3300-13-R-5002 Amendment 0002

View the file

Other files

File Type Posted
SF33_SP330013R5002_Amendment_0003.pdf PDF
Amendment_0003_SP330013R5002_6-11-13.pdf PDF
JEMMS_RFP_SP330013R5002_Attachment_1_to_Amendment_0003_for_FBO_Post.docx DOCX document
Attachment_2_Questions_and_Answers_SP330013R5002_Amendment_0003_for_FBO_Post.docx DOCX document
JEMMS_RFP_SP330013R5002_Attachment_1_to_Amendment_0003_with_accepted_changes.pdf PDF
EMSP_11_2_Spill_Response_and_Notification_Procedures_(EN)__ver_5_for_FBO_Post_via_Amendment_0002.pdf PDF
TE_5_6_GF_Gas_Cylinders_conformed_thru_SP330013R5002_Amendment_0002_for_FBO_Post.pdf PDF
JEMMS_SOW_SP330013R5002_Attachment_2_to_Amendment_0002_for_FBO_Post.docx DOCX document
Marine_Corps_Order_MCSN's_and_NSN's_for_FBO_Post_via_Amendment_0002.pdf PDF
Attachment_3_Questions_and_Answers_SP330013R5002_Amendment_0002_for_FBO_Post.docx DOCX document
JEMMS_RFP_SP330013R5002_Attachment_1_to_Amendment_0002_for_FBO_Post.docx DOCX document
Amendment_0002_SP330013R5002_6-5-13.pdf PDF
JEMMS_RFP_SP330013R5002_Attachment_1_to_Amendment_0002_with_accepted_changes.pdf PDF
EMSP_11_1_2_UER_Spill_Report_Form_ver_2_for_FBO_post_via_Amendment_0002.docx DOCX document
SP330013R5002_PPC_slides_for_FBO_Post_.ppt PPT presentation
SP330013R5002_QASP_for_FBO_Post.docx DOCX document
JEMMS_SOW_SP330013R5002_Attachment_2_to_Amendment_0001_Final.docx DOCX document
Amendment_0001_SP330013R5002_5-15-13.pdf PDF
JEMMS_RFP_SP330013R5002_Attachment_1_to_Amendment_0001.docx DOCX document
Revised_PPC_Check-In_Location_From_Terrace_Garden_Mihama_to_Gate_5_Camp_Foster.pdf PDF
Revised_PPC_Check-In_Location_From_SeaSide_Hotel_to_Camp_Foster_Gate_5.pdf PDF
Revised_PPC_Check-In_Location_From_Sunny's_Project_Condominiums_to_Camp_Foster_Gate_5.pdf PDF
Revised_PPC_Check-In_Location_From_Hamagawa_Lodge_to_Camp_Foster_Gate_5.pdf PDF
Windshield_Tour_Schedule_for_Site_Visit_SP330013R5002.xlsx XLSX spreadsheet
Revised_PPC_Check-In_Location_From_Beach_Tower_to_Camp_Foster_Gate_5.pdf PDF
Exhibit_A_Attachment_J.2_CDRLs_SP330013R5002_for_FBO_FINAL.pdf PDF
Attachment_J.4-_Past_Performance_Questionnaire_SP330013R5002_for_FBO_FINAL.docx DOCX document
Attachment_J.3_TE_5.6_Gas_Cylinders_SP330013R5002_for_FBO_FINAL.pdf PDF
Attachment_J.3_TE_2.1_Definitions_SP330013R5002_for_FBO_FINAL.pdf PDF
Attachment_J.3_TE_5.5_Performance_Requirements_Summary_SP330013R5002_for_FBO_FINAL.pdf PDF
Attachment_J.3_TE_5.4_Inventory_DMD_History_BY_CY_SP330013R5002_for_FBO_FINAL.xlsx XLSX spreadsheet
Attachment_J.3_TE_5.2_Mileage_Chart_SP330013R5002_for_FBO_FINAL.pdf PDF
Attachment_J.3_TE_3.2_GFE_SP330013R5002_for_FBO_FINAL.pdf PDF
Attachment_J.3_TE_3.1a_GFF-_Camp_Hansen_SP330013R5002_for_FBO_FINAL.pdf PDF
Attachment_J.3_TE_5.3b_HW_Pick_Up_Points_and_Schedule_SP330013R5002_for_FBO_FINAL.pdf PDF
JEMMS_RFP_SP330013R5002_for_FBO_Final.docx DOCX document
Attachment_J.3_TE_5.3a_HM_Drop_Points_SP330013R5002_for_FBO_FINAL.pdf PDF
Attachment_J.3_TE_5.1_Map_of_Okinawa_SP330013R5002_for_FBO_FINAL.pdf PDF
Attachment_J.3_TE_4.1_CFM_SP330013R5002_for_FBO_FINAL.pdf PDF
Attachment_J.3_TE_3.1b_GFF-_Camp_Kinser_SP330013R5002_for_FBO_FINAL.pdf PDF
Attachment_J.3_TE_5.7_LFORM_Breakdown_SP330013R5002_for_FBO_FINAL.xlsx XLSX spreadsheet
SF33_SP330013R5002_for_FBO_FINAL.pdf PDF
Attachment_J.1_SOW_for_FBO_Final.docx DOCX document
Draft_Attachment_J.3_TE_3.2_GFE_SP330013R5002_for_FBO_5-3-13.pdf PDF
Draft_Attachment_J.3_TE_5.4_Inventory_DMD_History_BY_CY_SP330013R5002_for_FBO_5-3-13.xlsx XLSX spreadsheet
Draft_Exhibit_A_Attachment_J.2_CDRLs_SP330013R5002_for_FBO_5-3-13.pdf PDF
Draft_Attachment_J.3_TE_5.5_Performance_Requirements_Summary_SP330013R5002_for_FBO_5-3-13.pdf PDF
DRAFT_RFP_SP330013R5002_for_FBO_5-3-13.docx DOCX document
Draft_Attachment_J.3_TE_3.1b_GFF-_Camp_Kinser_SP330013R5002_for_FBO_5-3-13.pdf PDF
Draft_Attachment_J.3_TE_5.1_Map_of_Okinawa_SP330013R5002_for_FBO_5-3-13.pdf PDF
Show 40 more

Latest 50 of 79 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SP3300-13-R-5002

Conformed through Amendment 0002

TECHNICAL EXHIBIT 5.5

PERFORMANCE REQUIREMENTS SUMMARY (PRS)

Performance Requirement
Performance Measure
Method of Surveillance
Frequency
Minimum Satisfactory Rating
C-1 through C-5 Customer Support
1) Customer Satisfaction as determined by Customer’s response to Customer Satisfaction Survey
100% Surveillance supplemented by Customer Complaints
Semi-Annual
95%
C-1.6 Environmental, Safety, and Occupational Health (ESOH)
1) Establish written ESOH plan; HAZCOM plan; and Spill Response Plan
100% Surveillance
Annual
100%
2) No Notification of Violation or Findings of Contractor HM operations as a result of DoD or Non-DoD inspections
100% Surveillance
Each Inspection
100%
C.5.3 Material Management; C-5.7 Inventory Management
1) The receipt cost per line item shall equal the cost of issue per line item for all HM issued
Random Sampling
Monthly
100%
2) For any HM, the contents of the MSDS contained in HMMS shall match the manufacturer specific MSDS
Random Sampling
Quarterly
100%
3) Maintain or have immediate access to a 30-day inventory of all HM identified on the AUL that have experienced three (3) or more issue transactions during the prior six (6) months
Random Sampling
Monthly
95%
4) Contractor is financially liable for all Government-Owned inventory discrepancies (losses) in excess of 2 ½% of stock inventory value based on the stock inventory of the last calendar year. Gains will not be applied to losses.
Random Sampling
Monthly, Annually, or as required
98%
5) HM inventory accuracy level of Government-Owned material
Random Sampling
Monthly
95%
C-5.6 Storage
1) Shelf-life Management of material (IAW DoD Shelf-Life Management Program and DoDI 4140.27M
Random Sampling
Monthly
100%
C-5.8 Issue
1) HM requisitions filled by RDD
100%
Monthly
95%
C-5.8.2 Container Tracking and Close-Out in HMMS
1) Contractor has made documented efforts of distributing and collecting container tracking information and closing out container in HMMS
100%
Monthly
100%
C-5.2 HMMS
1) Contractor entered data is accurate and current for all records at each site.
Random Sampling
Monthly
95%
2) Contractor has updated and maintained AUL activity. Contractor has made all updates based on customers’ AUL authorization forms. Contractor has entered all approved, pertinent AUL information into HMMS within 2 days of receipt of the command approved AUL.
Random Sampling
Monthly
100%