About this file

This Statement of Work (SOW) outlines requirements for replacing 13 fire hydrants at the VA Maine Healthcare campus. The contractor must provide all materials, labor, and supervision to replace the hydrants according to NFPA 24 standards, including replacing 3 existing hydrant shutoff valves if needed, or the last 3 valves on the construction schedule if all valves function properly. New hydrants must have a 4.5" NST/NH steamer port and two 2.5" NST/NH side ports, reusing existing Stortz adapters.

The scope includes replacing up to 100 linear feet of existing piping as necessary, with additional piping replacement handled as contract modifications. Key requirements include flow and pressure testing per NFPA 24, locating underground utilities, following OSHA excavation regulations, painting hydrants based on GPM flow, and coordinating water service interruptions 2 weeks in advance. The period of performance is 142 calendar days for all 13 hydrants, or 128 calendar days if hydrants 14 and 18 are omitted per the bid deduct option. Contractors must submit quotes by February 24, 2025, at 3:30PM EST to diane.davis2@va.gov, with a site visit scheduled for February 6, 2025, at 11:00PM EST at the Togus VA Medical Center in Augusta, ME.

View the file

Other files for this federal contract opportunity

Other files attached to Y1PZ--402-25-001 Replace Campus Fire Hydrants, newest first.
File Type Posted
36C24125Q0164 0002.pdf PDF
36C24125Q0164 0001.pdf PDF
402-25-001 Hydrant Locations.pdf PDF
402-25-001 Replace Hydrants pre-bid site walkthrough.pdf PDF
Attachment 1 Single Source Justification MPT to SAT.pdf PDF
SOW Replace Campus Fire Hydrants 0001.docx DOCX document
36C24125Q0164.docx DOCX document
852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING.docx DOCX document
Wage_Determination_Heavy - ME20250022.pdf PDF
Attachment 3 Hydrant pictures.pptx PPTX presentation
Attachment 2 Campus Hydant Flow Testing.pdf PDF
Attachment 4 Specifications.pdf PDF
PCRA Construction Only.pdf PDF
Attachment 1 Campus water distribution network.jpg JPG image
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work 402-25-001 Replace Campus Fire Hydrants.

The following is the scope of work for the subject contract at the VA Maine Healthcare. All installations shall be in accordance with NFPA 24 and the specifications that are listed in attachment 4. This solicitation shall include all materials, labor, and supervision necessary to replace a total of 13 campus fire hydrants. The Contractor shall replace 3 of the existing hydrant shutoff valves in the event the valves do not close. If all shutoff valves work fine, contractor shall replace the last 3 valves left on the construction schedule.

New hydrants shall have 4.5” NST/NH steamer port and two 2.5” NST/NH side ports. Existing 4.5” Stortz adapters on current hydrants will be re-used on new hydrants.

Contractor shall also replace no more than 100 linear feet of same sized piping as determined necessary by the contractor and COR to be unsuitable for re-use. If additional piping replacement is necessary to execute contract work, it will be treated as a modification to this contract. Contractor shall gain COR’s concurrence and permission prior to replacing any piping.

The 13 hydrants shown in attachment 3 shall be replaced. Existing thrust blocks shall also be replaced unless they are suitable for re-use as determined by the COR.

-Contractor will be required to flow and pressure test each hydrant IAW NFPA 24 and furnish a report to the COR.

Listed below are scope clarifications:

-Locating all existing underground utilities shall be the responsibility of the contractor.

-Excavation rules and regulations shall follow OSHA 29 CFR 1926 – Construction -If unsuitable or contaminated soils are encountered during excavation, the time and cost burden for testing shall be absorbed by the contractor and additional fill/remediation will be procured as a modification to this contract.

-There is no dumping of any materials allowed on this campus -Contractor will be responsible for painting the hydrants based on their GPM flow IAW NFPA 24.

-If ledge is encountered and must be removed to complete contract work, a modification to this contract will get issued for ledge removal.

-Removal and re-installation of asphalt, curbing, lawn, sidewalks or any other hardscape feature will be inclusive of this construction contract.

-The campus water distribution network attachment shall be field verified by the contractor. VA Maine cannot guarantee it is 100% accurate and current.

-Water service and hydrant interruptions resulting from this contract must be coordinated with the contracts COR 2 weeks prior to the date of the shutoff. Watermain and or hydrant shutdowns will be accomplished by Facilities Management, however the contractor shall to the best of his/her knowledge notify the VA what specifically will get shutdown using existing condition drawings, interviewing campus facility staff, and performing waterline tracing inside and outside of buildings.

-Contractor will be required to set up 7’ tall fencing around each open excavation.

-Contractor will not be responsible for providing temporary hydrants and connections.

-Contractor will be held responsible for all requirements listed in this job’s specifications Bid Deduct: In addition to supplying a bid for all 13 hydrants, contractor shall provide a price for omitting hydrant 14 and 18 shown in attachment 3.

Period of Performance for this contract shall be 142 Callender days (full scope) Period of Performance for the full scope minus hydrant 14 and 18 shall be 128 Callender days Attachments:

1-Campus water distribution network 2-Campus Hydrant flow testing 3- Hydrant pictures 4- Specifications