SOW Replace Campus Fire Hydrants 0001.docx
DOCX document 16 KB Posted
- Attached to
- Y1PZ--402-25-001 Replace Campus Fire Hydrants Federal contract opportunity
- Solicitation number
- 36C24125Q0164
About this file
This Statement of Work outlines requirements for replacing 13 fire hydrants at VA Maine Healthcare, with an option to omit hydrants 14 and 18. The contractor must provide all materials, labor, and supervision to install Waterous Pacer 5" dry-barrel hydrants with specific port configurations, replace up to 100 linear feet of existing piping as needed, and replace thrust blocks unless deemed reusable. The period of performance is 142 calendar days for full scope (13 hydrants) or 128 days for reduced scope (11 hydrants).
Key requirements include flow and pressure testing per NFPA 24, utility location, OSHA-compliant excavation, painting hydrants based on GPM flow, 7-foot fencing around excavations, and coordination of water shutoffs two weeks in advance. The solicitation (36C24125Q0164) includes a site visit on February 6, 2025, at 11:00 PM EST at Togus VA Medical Center. Questions are due by February 14, 2025, at 3:30 PM EST, and quotes must be submitted to diane.davis2@va.gov by February 24, 2025, at 3:30 PM EST. The contractor must verify field conditions and handle any encountered ledge or unsuitable soils, with remediation costs handled as contract modifications.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24125Q0164 0002.pdf | ||
| 36C24125Q0164 0001.pdf | ||
| 402-25-001 Hydrant Locations.pdf | ||
| 402-25-001 Replace Hydrants pre-bid site walkthrough.pdf | ||
| Attachment 1 Single Source Justification MPT to SAT.pdf | ||
| SOW Replace Campus Fire Hydrants 1.21.25 revised.docx | DOCX document | |
| 36C24125Q0164.docx | DOCX document | |
| PCRA Construction Only.pdf | ||
| Attachment 1 Campus water distribution network.jpg | JPG image | |
| 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING.docx | DOCX document | |
| Wage_Determination_Heavy - ME20250022.pdf | ||
| Attachment 3 Hydrant pictures.pptx | PPTX presentation | |
| Attachment 2 Campus Hydant Flow Testing.pdf | ||
| Attachment 4 Specifications.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work 402-25-001 Replace Campus Fire Hydrants.
(Rev. 2/13/2025)
The following is the scope of work for the subject contract at the VA Maine Healthcare. All installations shall be in accordance with NFPA 24 and the specifications that are listed in attachment 4. This solicitation shall include all materials, labor, and supervision necessary to replace a total of 13 campus fire hydrants. The Contractor shall replace 3 of the existing hydrant shutoff valves in the event the valves do not close. If all shutoff valves work fine, contractor shall replace the last 3 valves left on the construction schedule.
New hydrants shall be Waterous Pacer 5 ¼” and have 4.5” NST/NH steamer port and two 2.5” NST/NH side ports. Existing 4.5” Stortz adapters on current hydrants will be re-used on new hydrants.
New hydrants shall be dry-barrel type.
Contractor shall also replace no more than 100 linear feet of same sized piping as determined necessary by the contractor and COR to be unsuitable for re-use. If additional piping replacement is necessary to execute contract work, it will be treated as a modification to this contract. Contractor shall gain COR’s concurrence and permission prior to replacing any piping.
The 13 hydrants shown in attachment 3 shall be replaced. Existing thrust blocks shall also be replaced unless they are suitable for re-use as determined by the COR.
-Contractor will be required to flow and pressure test each hydrant IAW NFPA 24 and furnish a report to the COR.
Listed below are scope clarifications:
-Locating all existing underground utilities shall be the responsibility of the contractor.
-Excavation rules and regulations shall follow OSHA 29 CFR 1926 – Construction -If unsuitable or contaminated soils are encountered during excavation, the time and cost burden for testing shall be absorbed by the contractor and additional fill/remediation will be procured as a modification to this contract.
-There is no dumping of any materials allowed on this campus -Contractor will be responsible for painting the hydrants based on their GPM flow IAW NFPA 24.
-There is a possibility of ledge being encountered during excavation and must be removed to complete contract work.
-Removal and re-installation of asphalt, curbing, lawn, sidewalks or any other hardscape feature will be inclusive of this construction contract.
-The campus water distribution network attachment shall be field verified by the contractor. VA Maine cannot guarantee it is 100% accurate and current.
-Water service and hydrant interruptions resulting from this contract must be coordinated with the contracts COR 2 weeks prior to the date of the shutoff. Watermain and or hydrant shutdowns will be accomplished by Facilities Management, however the contractor shall to the best of his/her knowledge notify the VA what specifically will get shutdown using existing condition drawings, interviewing campus facility staff, and performing waterline tracing inside and outside of buildings.
-Contractor will be required to set up 7’ tall fencing around each open excavation.
-Contractor will not be responsible for providing temporary hydrants and connections.
-Contractor will be held responsible for all requirements listed in this job’s specifications Bid Deduct: In addition to supplying a bid for all 13 hydrants, contractor shall provide a price for omitting hydrant 14 and 18 shown in attachment 3.
Period of Performance for this contract shall be 142 Calendar days (full scope).
Period of Performance for the full scope minus hydrant 14 and 18 shall be 128 Calendar days.
Attachments:
1-Campus water distribution network 2-Campus Hydrant flow testing 3- Hydrant pictures 4- Specifications