Y1PZ--402-25-001 Replace Campus Fire Hydrants Federal contract opportunity
Solicitation number
36C24125Q0164
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 1

About this file

This is Amendment 0001 to solicitation 36C24125Q0164 for replacing campus fire hydrants at VA Maine Healthcare, updating the Statement of Work to include specific hydrant requirements and providing a map of hydrant locations.

The work involves replacing 13 campus fire hydrants with Waterous Pacer 5 1⁄4" dry-barrel hydrants featuring 4.5" NST/NH steamer ports and two 2.5" NST/NH side ports, reusing existing 4.5" Stortz adapters. The contractor must replace 3 existing hydrant shutoff valves if they don't close properly, or the last 3 valves if all function correctly. The scope includes replacing up to 100 linear feet of piping as needed, flow and pressure testing per NFPA 24, painting hydrants based on GPM flow, and installing 7' fencing around excavations. Two pricing options are required: one for all 13 hydrants (142 calendar day performance period) and another excluding hydrants 14 and 18 (128 calendar day period). The contractor must coordinate with the COR 2 weeks prior for any service interruptions, with Facilities Management handling actual shutdowns.

View the file

Other files for this federal contract opportunity

Other files attached to Y1PZ--402-25-001 Replace Campus Fire Hydrants, newest first.
File Type Posted
36C24125Q0164 0002.pdf PDF
402-25-001 Hydrant Locations.pdf PDF
SOW Replace Campus Fire Hydrants 0001.docx DOCX document
402-25-001 Replace Hydrants pre-bid site walkthrough.pdf PDF
Attachment 1 Single Source Justification MPT to SAT.pdf PDF
SOW Replace Campus Fire Hydrants 1.21.25 revised.docx DOCX document
36C24125Q0164.docx DOCX document
PCRA Construction Only.pdf PDF
Attachment 1 Campus water distribution network.jpg JPG image
852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING.docx DOCX document
Wage_Determination_Heavy - ME20250022.pdf PDF
Attachment 3 Hydrant pictures.pptx PPTX presentation
Attachment 2 Campus Hydant Flow Testing.pdf PDF
Attachment 4 Specifications.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

0001 02-13-2025

402-25-001

36C241

Department of Veterans Affairs Network Contracting Office 1 VAMC Togus 1 VA Center Augusta ME 04330

To all Offerors/Bidders

36C24125Q0164

X

X X

X 1

See attached

Purpose of Amendment 0001 is to update statement of work to include specific hydrant to be used on VAMC Togus Campus. See attached revised SOW.

Amendment also includes a map of the hydrant locations.

Scope of Work

402-25-001 Replace Campus Fire Hydrants.

The following is the scope of work for the subject contract at the VA Maine Healthcare. All installations shall be in accordance with NFPA 24 and the specifications that are listed in attachment 4. This solicitation shall include all materials, labor, and supervision necessary to replace a total of 13 campus fire hydrants. The Contractor shall replace 3 of the existing hydrant shutoff valves in the event the valves do not close. If all shutoff valves work fine, contractor shall replace the last 3 valves left on the construction schedule.

New hydrants shall be Waterous Pacer 5 ¼” and have 4.5” NST/NH steamer port and two 2.5” NST/NH side ports. Existing 4.5” Stortz adapters on current hydrants will be re-used on new hydrants.

New hydrants shall be dry-barrel type.

Contractor shall also replace no more than 100 linear feet of same sized piping as determined necessary by the contractor and COR to be unsuitable for re-use. If additional piping replacement is necessary to execute contract work, it will be treated as a modification to this contract. Contractor shall gain COR’s concurrence and permission prior to replacing any piping.

The 13 hydrants shown in attachment 3 shall be replaced. Existing thrust blocks shall also be replaced unless they are suitable for re-use as determined by the COR.

-Contractor will be required to flow and pressure test each hydrant IAW NFPA 24 and furnish a report to the COR.

Listed below are scope clarifications:

-Locating all existing underground utilities shall be the responsibility of the contractor.

-Excavation rules and regulations shall follow OSHA 29 CFR 1926 – Construction

-If unsuitable or contaminated soils are encountered during excavation, the time and cost burden for testing shall be absorbed by the contractor and additional fill/remediation will be procured as a modification to this contract.

-There is no dumping of any materials allowed on this campus

-Contractor will be responsible for painting the hydrants based on their GPM flow IAW NFPA 24.

-There is a possibility of ledge being encountered during excavation and must be removed to complete contract work.

-Removal and re-installation of asphalt, curbing, lawn, sidewalks or any other hardscape feature will be inclusive of this construction contract.

-The campus water distribution network attachment shall be field verified by the contractor. VA Maine cannot guarantee it is 100% accurate and current.

-Water service and hydrant interruptions resulting from this contract must be coordinated with the contracts COR 2 weeks prior to the date of the shutoff. Watermain and or hydrant shutdowns will be accomplished by Facilities Management, however the contractor shall to the best of his/her knowledge notify the VA what specifically will get shutdown using existing condition drawings, interviewing campus facility staff, and performing waterline tracing inside and outside of buildings.

-Contractor will be required to set up 7’ tall fencing around each open excavation.

-Contractor will not be responsible for providing temporary hydrants and connections.

-Contractor will be held responsible for all requirements listed in this job’s specifications

Bid Deduct: In addition to supplying a bid for all 13 hydrants, contractor shall provide a price for omitting hydrant 14 and 18 shown in attachment 3.

Period of Performance for this contract shall be 142 Calendar days (full scope).

Period of Performance for the full scope minus hydrant 14 and 18 shall be 128 Calendar days.

Attachments:

1-Campus water distribution network

2-Campus Hydrant flow testing

3- Hydrant pictures

4- Specifications

See attached document: Hydrant locations 0001.

File details come from the government source that posted it. Updated .