SOW Attachment 7.3 - Project Management Information System.docx
DOCX document 21 KB Posted
- Attached to
- R10 South Multiple Award Task Order Contract MATOC Replacement Federal contract opportunity
- Solicitation number
- 47PL0123R0014
About this file
This document outlines requirements for a Project Management Information System (PMIS) to be used on a construction project awarded under solicitation number 47PL0123R0014 by the General Services Administration Public Buildings Service Region 10. The selected contractor must effectively manage and use the GSA's web-based PMIS, which is currently Kahua Project Management Software, to upload, store, and share all project documentation and submittals. This includes using the PMIS for submitting and receiving approval of deliverables, and continuously monitoring the system through project closeout. The contractor must also require any subcontractors and vendors to use the PMIS. Training will be provided by GSA on using the PMIS, but contractors are responsible for any equipment needed for access via the web-based system. An HSPD-12 security clearance is initially required for full access to the PMIS, with limited interim access available. GSA will retain ownership of all PMIS data and provide administration and support for the system throughout the project duration.
View the file
Other files for this federal contract opportunity
Show all 37
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R10 Statement of Work (SOW) - Project Management Information System (PMIS)
1.1 PURPOSE
A. Project Management Information System (PMIS)
The Contractor is required to use GSA’s web-based electronic Project Management Information System (PMIS). PMIS is a web-based project management tool which provides GSA with an automated workflow, collaboration, document management and project management solution to assist GSA in the management of design and construction projects.
GSA uses PMIS throughout the design and construction phases as a repository for all project information and as a tool to manage and monitor progress and modifications. Unless as otherwise provided, the Contractor will rely exclusively on PMIS to post, review, access, comment on, collaborate, or otherwise submit all project information.
The current PMIS system in use by GSA is Kahua Project Management Software.
1.2 PROJECT COLLABORATION AND DOCUMENTATION
A. General
1. The Contractor is required to effectively manage the GSA Project Management Information System including maintaining adequate staffing levels and ensuring that personnel attend the mandatory GSA-provided training sessions.
2. The Contractor is required to use the GSA Project Management Information System to upload, store, capture, preserve, record, maintain, update, and route all project-related documentation to comply with GSA's Document Security Requirements. Classified material is not permitted to be stored in this system. Properly marked Controlled Unclassified (CUI) material is permitted to be stored in this system.
3. The Contractor is required to use the workflow processes contained within the GSA Project Management Information System to submit and receive approval for all project deliverables.
4. The Contractor is required to continuously monitor and review the GSA Project Management Information System to ensure the Contractor data is current through completion of the Close-out Phase of Construction.
5. The Contractor is required to store documents from their subcontractors and vendors in the GSA Project Management Information System.
B. Contents of the GSA Project Management Information System
1. Refer to the Statement of Work for all required submittals
2. The Contractor is required to use the GSA Project Management Information System as the electronic filing cabinet for all project-related documentation, correspondence and submittals.
1.3 SCHEDULING REQUIREMENTS
1.3.1 The Project Schedule shall be produced using widely used, commercially available computer software that is capable of generating and monitoring a CPM schedule. Contractor provided schedules should be uploaded or imported to the GSA Project Management Information System on a recurring basis.
1.4 EQUIPMENT AND TRAINING
A. Equipment
1. GSA will not furnish any equipment related to accessing the GSA Project Management Information System. The GSA Project Management Information System is web-accessible, and can therefore be accessed via any computer with an Internet connection.
B. GSA Project Management Information System Training
1. GSA will provide no cost training to familiarize team members with the GSA Project Management Information System. The GSA Project Manager will ensure that appropriate personnel should attend training and what roles will be set up within the system based on their project responsibilities.
C. GSA Project Management Information System Support
1. GSA will provide GSA Project Management Information System administration and end user support, for the duration of the project.
1.5 PERSONNEL REQUIREMENTS
An HSPD-12 (Homeland Security Presidential Directive 12) security clearance is required for full access to the PMIS.
Project team members without an HSPD-12 clearance will be given limited access to the PMIS system at contract award to allow initial document submissions while clearances are in process.
1.6 DATA OWNERSHIP
A. GSA will retain ownership of all data entered into the system and will administer all information contained therein. Distribution of any system data will be made upon request.
1.7 DOCUMENT SECURITY
A. GSA Project Management Information System security access levels ensure that sensitive documents can only be accessed by the appropriate personnel. It is the contractor’s responsibility to ensure their employees, subcontractors and vendors have the appropriate level of security to ensure document security.
Updated April 2022 GSA R10 Project Management Information System - 1