About this file

This document contains a past performance questionnaire template for evaluation of contractors on a federal contract. It requests information on contract details, project description, client ratings of contractor performance on quality, schedule, customer satisfaction, management, cost, safety, and sustainability. Ratings are on a scale of exceptional, very good, satisfactory, marginal, and unsatisfactory. The questionnaire is to be completed by the client and sent directly to contracting officials at the General Services Administration for Contractor 47PL0123R00XX, which is the replacement for the Region 10 South Multiple Award Task Order Contract. Relevant details include the variety of contract types and industries addressed, performance metrics evaluated, and the federal agency and solicitation number involved.

View the file

Other files for this federal contract opportunity

Other files attached to R10 South Multiple Award Task Order Contract MATOC Replacement, newest first.
File Type Posted
Amendment 0003.pdf PDF
Amendment 0002.pdf PDF
A. Attachment D Seed Project SOW dated 10-20-2023.pdf PDF
D. Pre-Propsal Site Visit Roster 09-28-2023.pdf PDF
B. SOW Attachment 7.10 Drawings - Site Plan 10.20.2023.pdf PDF
C. Pre-Proposal Questions and Answers 1 through 17.pdf PDF
Attachment C - TORFP Seed Project - Rev 1.pdf PDF
Amendment 0001.pdf PDF
Attachment E Seed Project Price and Services Schedule.xlsx XLSX spreadsheet
Attachment C - TORFP Seed Project.pdf PDF
SOW Attachment 7.10 - Drawings - Site Plan.pdf PDF
SOW Attachment 7.2 - Submittal Transmittal Form.xlsx XLSX spreadsheet
SOW Attachment 7.3 - Project Management Information System.docx DOCX document
GSA527-21.pdf PDF
RFP SOUTH MATOC 47PL0123R0014.pdf PDF
South MATOC Agreement.pdf PDF
SOW Attachment 7.11 - Trench Drain.pdf PDF
SOW Attachment 7.5 - C D Waste Mgmt Plan Reporting Template.xlsx XLSX spreadsheet
SOW Attachment 7.9 - Low embodied carbon concrete-Sept 22.pdf PDF
SOW Attachment 7.8 - Environmentally Preferable Asphalt-Sept 22.pdf PDF
SOW Attachment 7.6 - Sample ROCAL.xlsx XLSX spreadsheet
SF1442 47PL0123R0055 Seed Project.pdf PDF
Attachment F SEED Project Wage Deterimination - WA202330001 09-01-2023.pdf PDF
Exhibit 1 3490.3 Policy.pdf PDF
Exhibit 4 Sample Key Personnel Resume Form.docx DOCX document
Exhibit 3 Project Experience Form.docx DOCX document
SOW Attachment 7.1 - Vendor Security Training 6 2021.pptx PPTX presentation
SF1442 47PL0123R0014 SMATOC.pdf PDF
South MATOC SOW 11222022.pdf PDF
Attachment D Seed Project SOW dated 07-25-2023.pdf PDF
Attachment A South MATOC Terms and Conditions.pdf PDF
Attachment B Example of TO Reps and Certs March 2023.pdf PDF
Exhibit 6 GSA Security Manual.pdf PDF
Exhibit 2 GSA Affiliated Customer Accounts.pdf PDF
SOW Attachment 7.4 - P120 - Cost and Schedule Management Policy and Requirements.pdf PDF
SOW Attachment 7.7 - CIW FORM 850.docx DOCX document
Exhibit 7 IDIQ Price Schedule.xlsx XLSX spreadsheet
Show all 37

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PBS PAST PERFORMANCE QUESTIONNAIRE

CONTRACT INFORMATION (Contractor to complete Blocks 1-4)

1. CONTRACTOR INFORMATION

Firm Name:

Address:

Phone Number:
UEI Number:

Contact Name:

Email Address:
Contact Phone Number:

2. GENERAL WORK INFORMATION

Work performed as: ☐ Prime Contractor ☐ Sub Contractor ☐ Joint Venture ☐ Other (Please explain):

Percent (%) of project work performed:

If a subcontractor, who was the prime (Name/Phone #):

3. CONTRACT INFORMATION

Contract Number:

Delivery/Task Order Number (if applicable):

Contract Type: ☐ Firm Fixed Price ☐ Cost Reimbursement ☐ Other (Please explain)

Contract Title:

Contract Location:

Award Date (mm/dd/yy):

Original Contract Completion Date (mm/dd/yy):

Actual Completion Date (mm/dd/yy):

Explain Schedule Change:

Original Contract Price (Award Amount):

Final Contract Price (to include all modifications, if applicable):

Explain Differences:

4. PROJECT DESCRIPTION

Complexity of Work: ☐High ☐ Med ☐ Routine

How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)

NOTE: Completed PPQs shall be sent directly to the Government’s point of contacts, Maribeth Bonner, Contracting Officer, via email at maribeth.bonner@gsa.gov and Savanah Cilk, Contracts Specialist, via email at savannah.cilk@gsa.gov , prior to the Proposal closing date. The subject line must include: 47PL0123R00XX Western Multiple Award Task Order Contract (WMATOC), Project Owner Name and the Contractor being rated.

NOTE: Completed PPQ shall not be reviewed by the Offeror or subcontractor prior to submission. The PPQ must be submitted by the client/evaluator directly to the POC noted above. The PPQ shall include project owner and the contractor being rated.

Use the following adjective ratings and definitions in your evaluation of the Contractor’s performance.

RATING
DEFINITION
NOTE
(E) Exceptional
Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.
An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.
(VG) Very Good
Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.
(S) Satisfactory
Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract. There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.
(M) Marginal
Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.
A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.
(U) Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.
An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.
(N) Not Applicable
No information or did not apply to your contract
Rating will be neither positive nor negative.

TO BE COMPLETED BY CLIENT

CLIENT INFORMATION

Client Information:

Name:

Title:

Phone Number:

Email Address:

Describe the client’s role in the project:

Date Questionnaire was completed (mm/dd/yy):

Client’s Signature:

Instructions: Please select the adjective rating and the Yes/No reply that best reflects your evaluation of the contractor’s performance.

1. QUALITY:
E VG S M U N
(a) Quality of technical data/report preparation efforts.
☐ ☐ ☐ ☐ ☐ ☐
(b) Ability to meet quality standards specified for technical performance.
☐ ☐ ☐ ☐ ☐ ☐
(c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance.
☐ ☐ ☐ ☐ ☐ ☐
(d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance).
☐ ☐ ☐ ☐ ☐ ☐
2. SCHEDULE/TIMELINESS OF PERFORMANCE:
E VG S M U N
(a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below.)
☐ ☐ ☐ ☐ ☐ ☐
(b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract.
☐ ☐ ☐ ☐ ☐ ☐
3. CUSTOMER SATISFACTION:
E VG S M U N
(a) To what extent were the end users satisfied with the project?
☐ ☐ ☐ ☐ ☐ ☐
(b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes; responsiveness to administrative reports, businesslike and communication).
☐ ☐ ☐ ☐ ☐ ☐
(c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer?
☐ ☐ ☐ ☐ ☐ ☐
(d) Overall customer satisfaction.
☐ ☐ ☐ ☐ ☐ ☐
4. MANAGEMENT/ PERSONNEL/LABOR
E VG S M U N
(a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force?
☐ ☐ ☐ ☐ ☐ ☐
(b) Ability to hire, apply, and retain a qualified workforce to this effort.
☐ ☐ ☐ ☐ ☐ ☐
(c) Government Property Control.
☐ ☐ ☐ ☐ ☐ ☐
(d) Knowledge/expertise demonstrated by contractor personnel.
☐ ☐ ☐ ☐ ☐ ☐
(e) Utilization of Small Business concerns.
☐ ☐ ☐ ☐ ☐ ☐
(f) Ability to simultaneously manage multiple projects with multiple disciplines.
☐ ☐ ☐ ☐ ☐ ☐
(g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes.
☐ ☐ ☐ ☐ ☐ ☐
(h) Effectiveness of overall management (including ability to effectively lead, manage and control the program).
☐ ☐ ☐ ☐ ☐ ☐
5. COST/FINANCIAL MANAGEMENT
E VG S M U N
(a) Ability to meet the terms and conditions within the contractually agreed price(s)?
☐ ☐ ☐ ☐ ☐ ☐
(b) Contractor proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client.
☐ ☐ ☐ ☐ ☐ ☐
(c) If this is/was a Government cost type contract, or a CMc/CMc at Risk Contract, please rate the Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns).
☐ ☐ ☐ ☐ ☐ ☐
(d) Is the Contractor’s accounting system adequate for management and tracking of costs? (If no, please explain in comment section below.)
☐ Yes ☐ No
(e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? (Indicate if show cause or cure notices were issued, or any default action in comment section below.)
☐ Yes ☐ No
(f) Have there been any indications that the contractor has had any financial problems? (If yes, please explain in the comment section below.)
☐ Yes ☐ No
6. SAFETY/SECURITY
E VG S M U N
(a) To what extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues? (Includes: following the users rules, regulations, and requirements regarding housekeeping, safety, correction of noted deficiencies, etc.).
☐ ☐ ☐ ☐ ☐ ☐
(b) Contractor complied with all security requirements for the project and personnel security requirements.
☐ ☐ ☐ ☐ ☐ ☐

7. SUSTAINABILITY

Were sustainability methods, processes, or materials incorporated into the project? (If yes, please explain in the comments section below.)
☐ Yes ☐ No
8. GENERAL
E VG S M U N
(a) Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).
☐ ☐ ☐ ☐ ☐ ☐
(b) Compliance with contractual terms/provisions (If there were specific issues, please explain in the comments sections below.)
☐ ☐ ☐ ☐ ☐ ☐
(c) Would you hire or work with this firm again? (If no, please explain in the comments section below.)
☐ Yes ☐ No
(d) In summary, provide an overall rating for the work performed by this contractor.
☐ ☐ ☐ ☐ ☐ ☐

COMMENTS SECTION

Please provide additional information below, and attach additional pages if necessary.

Please provide responses to the above questions (if applicable) and/or additional remarks. Also please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk (please attach additional pages if necessary):