Sheet1 Solicitation Attachment 1-Price List
| Base Year-FFP Orders | | | | |
| Task | Estimated Quantity | Unit | Price per unit | Total |
| 1 | Comprehensive Radiation Safety SURVEYS | 1730 | Each | | |
| 2 | Monthly Surveys | 5650 | Each | | |
| 3 | Weekly Surveys | 830 | Each | | |
| 4 | Part 35 Weekly Surveys | 180 | Each | | |
| 5 | Corridor Surveys | 1000 | Each | | |
| 6 | Alpha Lab Surveys | 30 | Each | | |
| 7 | Naturally Occurring Alpha Surveys | 40 | Each | | |
| 8 | Lab Clearance Surveys | 100 | Each | | |
| 9 | SECURITY Checks (Hours) Normal Workday | 55 | Hours | | |
| 10 | Security Checks (Hours) Outside M-F/9-5 | 190 | Hours | | |
| 11 | Patient THERAPY Rooms (Full Decon) | 70 | Hours | | |
| 12 | Patient Therapy Rooms (Reset) | 100 | Hours | | |
| 13 | Contamination Instrument CALIBRATIONS | 890 | Each | | |
| 14 | Exposure Instrument Calibrations | 120 | Each | | |
| 15 | Incentive Payment (at most 10% of invoice) | | | | TBD |
| 16 | Decommissioning- Ceiling Over a 5 year period* | To be priced on task order level | | | $10,000,000 |
| Base Year Estimated Total | | | | |
| Option Year One -FFP Orders | | | | |
| Task | Estimated Quantity | Unit | Price per unit | Total |
| 1 | Comprehensive Radiation Safety SURVEYS | 1730 | Each | | |
| 2 | Monthly Surveys | 5650 | Each | | |
| 3 | Weekly Surveys | 830 | Each | | |
| 4 | Part 35 Weekly Surveys | 180 | Each | | |
| 5 | Corridor Surveys | 1000 | Each | | |
| 6 | Alpha Lab Surveys | 30 | Each | | |
| 7 | Naturally Occurring Alpha Surveys | 40 | Each | | |
| 8 | Lab Clearance Surveys | 100 | Each | | |
| 9 | SECURITY Checks (Hours) Normal Workday | 55 | Hours | | |
| 10 | Security Checks (Hours) Outside M-F/9-5 | 190 | Hours | | |
| 11 | Patient THERAPY Rooms (Full Decon) | 70 | Hours | | |
| 12 | Patient Therapy Rooms (Reset) | 100 | Hours | | |
| 13 | Contamination Instrument CALIBRATIONS | 890 | Each | | |
| 14 | Exposure Instrument Calibrations | 120 | Each | | |
| 15 | Incentive Payment (at most 10% of invoice) | | | | TBD |
| 16 | Decommissioning- Ceiling Over a 5 year period* | To be priced on task order level | | | $10,000,000 |
| Option Year One Estimated Total | | | | |
| Option Year Two -FFP Orders | | | | |
| Task | Estimated Quantity | Unit | Price per unit | Total |
| 1 | Comprehensive Radiation Safety SURVEYS | 1730 | Each | | |
| 2 | Monthly Surveys | 5650 | Each | | |
| 3 | Weekly Surveys | 830 | Each | | |
| 4 | Part 35 Weekly Surveys | 180 | Each | | |
| 5 | Corridor Surveys | 1000 | Each | | |
| 6 | Alpha Lab Surveys | 30 | Each | | |
| 7 | Naturally Occurring Alpha Surveys | 40 | Each | | |
| 8 | Lab Clearance Surveys | 100 | Each | | |
| 9 | SECURITY Checks (Hours) Normal Workday | 55 | Hours | | |
| 10 | Security Checks (Hours) Outside M-F/9-5 | 190 | Hours | | |
| 11 | Patient THERAPY Rooms (Full Decon) | 70 | Hours | | |
| 12 | Patient Therapy Rooms (Reset) | 100 | Hours | | |
| 13 | Contamination Instrument CALIBRATIONS | 890 | Each | | |
| 14 | Exposure Instrument Calibrations | 120 | Each | | |
| 15 | Incentive Payment (at most 10% of invoice) | | | | TBD |
| 16 | Decommissioning- Ceiling Over a 5 year period* | To be priced on task order level | | | $10,000,000 |
| Option Year Two Estimated Total | | | | |
| Option Year Three-FFP Orders | | | | |
| Task | Estimated Quantity | Unit | Price per unit | Total |
| 1 | Comprehensive Radiation Safety SURVEYS | 1730 | Each | | |
| 2 | Monthly Surveys | 5650 | Each | | |
| 3 | Weekly Surveys | 830 | Each | | |
| 4 | Part 35 Weekly Surveys | 180 | Each | | |
| 5 | Corridor Surveys | 1000 | Each | | |
| 6 | Alpha Lab Surveys | 30 | Each | | |
| 7 | Naturally Occurring Alpha Surveys | 40 | Each | | |
| 8 | Lab Clearance Surveys | 100 | Each | | |
| 9 | SECURITY Checks (Hours) Normal Workday | 55 | Hours | | |
| 10 | Security Checks (Hours) Outside M-F/9-5 | 190 | Hours | | |
| 11 | Patient THERAPY Rooms (Full Decon) | 70 | Hours | | |
| 12 | Patient Therapy Rooms (Reset) | 100 | Hours | | |
| 13 | Contamination Instrument CALIBRATIONS | 890 | Each | | |
| 14 | Exposure Instrument Calibrations | 120 | Each | | |
| 15 | Incentive Payment (at most 10% of invoice) | | | | TBD |
| 16 | Decommissioning- Ceiling Over a 5 year period* | To be priced on task order level | | | $10,000,000 |
| Option Year Three Estimated Total | | | | |
| Option Year Four -FFP Orders | | | | |
| Task | Estimated Quantity | Unit | Price per unit | Total |
| 1 | Comprehensive Radiation Safety SURVEYS | 1730 | Each | | |
| 2 | Monthly Surveys | 5650 | Each | | |
| 3 | Weekly Surveys | 830 | Each | | |
| 4 | Part 35 Weekly Surveys | 180 | Each | | |
| 5 | Corridor Surveys | 1000 | Each | | |
| 6 | Alpha Lab Surveys | 30 | Each | | |
| 7 | Naturally Occurring Alpha Surveys | 40 | Each | | |
| 8 | Lab Clearance Surveys | 100 | Each | | |
| 9 | SECURITY Checks (Hours) Normal Workday | 55 | Hours | | |
| 10 | Security Checks (Hours) Outside M-F/9-5 | 190 | Hours | | |
| 11 | Patient THERAPY Rooms (Full Decon) | 70 | Hours | | |
| 12 | Patient Therapy Rooms (Reset) | 100 | Hours | | |
| 13 | Contamination Instrument CALIBRATIONS | 890 | Each | | |
| 14 | Exposure Instrument Calibrations | 120 | Each | | |
| 15 | Incentive Payment (at most 10% of invoice) | | | | TBD |
| 16 | Decommissioning- Ceiling Over a 5 year period* | To be priced on task order level | | | $10,000,000 |
| Option Year Four Estimated Total | | | | |
| Contract Estimated Total Base + Four Year Options | | | | |
| *Do not price decommissioning | | | | |