About this file

This is a Request for Proposals (RFP) issued by the Department of Veterans Affairs VISN 7 Network Contracting Office for Project No. 679-22-106 to replace HVAC systems in Buildings 2 and 46 at the Tuscaloosa Veterans Health Care System in Alabama. The solicitation is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) under NAICS code 238160 with a size standard of $19 million.

The work involves removal, replacement and installation of new HVAC systems, including plumbing, electrical, general construction, fire piping, carpentry and related tasks. The magnitude of construction is between $1-5 million. Key dates include a site visit on January 23, 2025 at 9:30 AM CST, RFI submission deadline of January 29, 2025, and proposal due date of February 18, 2025 at 1:00 PM CST. The period of performance is 365 days after notice to proceed. Contractors must provide a bid guarantee of 20% of the bid price (not exceeding $3 million) and performance/payment bonds. The evaluation factors are past performance (significantly more important than price) and price. Past performance references must be from projects completed within the past 5 years. Electronic proposals must be submitted via email to the designated contracting officers.

View the file

Other files for this federal contract opportunity

Other files attached to 679-22-106 Replace HVAC Various Buildings, newest first.
File Type Posted
Amendment 0006 36C24725R0031.pdf PDF
Attachment 0005 G -Addendum 1 Drawings.pdf PDF
Amendment 0005 36C24725R0031.pdf PDF
Attachment 0005 C - Appendix P - Building 46.pdf PDF
Attachment 0005 D - Appendix S - Building 46.pdf PDF
Attachment 0005 E- Addendum 1 Change Narrative.pdf PDF
Attachment 0005 A- Pre-Bid RFIs_Responses.pdf PDF
Attachment 0005 B - Appendix B - Building 2.pdf PDF
Attachment 0005 F- Appendix B - Building 2.pdf PDF
Attachment 0005 H-Wage DBA AL20250098.txt TXT text file
Amendment 36C24725R0031 0004.pdf PDF
Amendment 36C24725R0031 0003.pdf PDF
Amendment 36C24725R0031 0002.pdf PDF
679-22-106 -Replace HVAC Various Buildings Site Visit.pdf PDF
Amendment 36C24725R0031 0001.pdf PDF
Attachment 6 - INVOICING.docx DOCX document
Attachment 5 -DBA Number AL20240136.pdf PDF
679-22-106 Specifications.pdf PDF
Attachment 3 - Past Performance Questionnaire -PPQ.docx DOCX document
Attachment 2 - VAAR 852.219-75 VA Notice of Limitations on Subcontracting Jan 2023 Deviation.pdf PDF
Attachment 1 - Experience Modification Rate Form.pdf PDF
Attachment 4 - Itemized Cost Breakdown.xlsx XLSX spreadsheet
679-22-106_Drawings.pdf PDF
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

7. ISSUED BY CODE 8. ADDRESS OFFER TO

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES NO

a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________

(hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b. An offer guarantee is, is not required.

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

1 79

36C24725R0031

X

01-16-2025

679-25-1-5656-0001

679-22-106

36C247

Department of Veterans Affairs

VISN 7 Network Contracting Office

TUSCALOOSA VAMC

3701 Loop Road

Tuscaloosa AL 35404

Email only. Send to contract specialist:

William.Barton2@va.gov

CC: Joyce.Powers1@va.gov

William Barton William.Barton2@va.gov

Project No. 679-22-106 - Replace HVAC, Various Buildings

Project Location: Tuscaloosa Veterans Health Care System Tuscaloosa AL 35404

This acquisition is 100% Set-aside for Services Disabled Veteran Owned Small Businesses (SDVOSB) only.

The SDVOSB Business must be 51% or more owned and controlled by one or more service-connected veterans.

Contractor required to complete VAAR 852.219-75. Limitations Subcontracting. Attachment 2

MAGNITUDE OF CONSTRUCTION: Between $1,000,000.00 and $5,000,000.00

NAICS Code: 238160; Small Business Standard: $19 Million

To be eligible for award, the offeror shall be registered at the following websites: System for Award Management at sam.gov with completed electronic annual representations certifications, VetCert at veterans.certify.sba.gov and comply with VETS 4212, Federal Contractor Veterans Employment Report. Offerors MUST ensure registration in these websites are accurate, complete, and have not expired prior to proposal due date or thereafter.

Offerors who have not done business with the VA must complete VA 10091 to register in the financial database, Refer to

VA's Customer Engagement Portal (CEP) at cep.fsc.va.gov. See Attachment 6 - Invoicing.

Site Visit: An organized site visit is scheduled for January 23rd at 9:30 am CST

Location: Building 5: Second Floor Conference Room Tuscaloosa VAMC 3701 Loop Road, Tuscaloosa, AL 36109

(Information provided at the site visit shall not alter the terms and conditions of the solicitation, and the terms and the terms and specifications remain unchanged unless the solicitation is amended in writing. Contractors are required to submit all questions in writing to the Contracting Officer following the site visit.)

Requests for Information (RFIs): Due Date: NLT January 29th, 2025 at 10:00 AM CST Sent to contact listed in block 8 above.

Late RFIs may not be accepted, and offerors are responsible for ensuring questions are received on time. Responses will be provided in question-and-answer format via a posted amendment at www.SAM.gov.

Offer guarantee will be accepted via email only if received before the date/time specified in block 13a below to the

Email specified in block 8 above. Hand-delivered and/or mailed offer guarantees will not be accepted.

30 365 x x 52.211-10

X

1 electronic 1:00 PM CST

02-18-2025

X

14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY

PHONE: FAX:

28. NEGOTIATED AGREEMENT 29. AWARD Your

Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code)

(Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

(Type or print)

(4 copies unless otherwise specified)

(Type or print) (Type or print)

(Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror)

(To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

Complete Price Offer Schedule

36C247

Department of Veterans Affairs

VISN 7 Network Contracting Office

3701 Loop Rd

Tuscaloosa AL 35404

Austin Payment Center

Department of Veteran Affairs

PO Box 149971

Austin TX 78714-8971

(877) 353-9791 (512) 460-5545

Joyce Powers

VA-VHA-RPOE-2023-0023

Table of Contents

PART I - THE SCHEDULE

SECTION A - SOLICITATION/CONTRACT FORM

A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or

Repair)

A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION,

ALTERATION, OR REPAIR)– BACK

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 PRICE OFFER SCHEDULE

2.2 STATEMENT OF WORK

2.3 PROPOSAL PREPARATION AND EVALUATION INFORMATION

2.4 GENERAL SOLICITATION INFORMATION

2.5 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023)

2.6 52.216-1 TYPE OF CONTRACT (APR 1984)

2.7 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE

OF THE WORK (MAY 2014)

2.8 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE

EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

2.9 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION

MATERIALS (MAY 2014)

2.10 52.228-1 BID GUARANTEE (SEP 1996)

2.11 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE)

(FEB 2021)

2.12 52.233-2 SERVICE OF PROTEST (SEP 2006)

2.13 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB

1995)

2.14 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE

(FEB 1998)

2.15 52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)

2.16 VAAR 852.252-70 SOLICITATION PROVISIONS OR CLAUSES

INCORPORATED BY REFERENCE (JAN 2008)

2.17 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND

VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)

2.18 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)

2.19 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE

RESOLUTION (OCT 2018)

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY 2024) .. 28

3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS

AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)

3.3 52.204-29 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—

REPRESENTATION AND DISCLOSURES (DEC 2023)

3.4 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)

3.5 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—

CERTIFICATION (NOV 2021)

GENERAL CONDITIONS

4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND

CERTIFICATIONS (DEC 2014)

4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE,

AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB COVERED

ENTITIES (DEC 2023)

4.3 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING

RESPONSIBILITY MATTERS (OCT 2018)

4.4 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

(APR 1984) ALTERNATE I (APR 1984)

4.5 52.219-14 LIMITATIONS ON SUBCONTRACTING (OCT 2022)

4.6 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION

(FEB 2024)

4.7 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020)

4.8 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN

2020)

4.9 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL

LABOR RELATIONS ACT (DEC 2010)

4.10 52.223-2 REPORTING OF BIOBASED PRODUCTS UNDER SERVICE AND

CONSTRUCTION CONTRACTS (MAY 2024)

4.11 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)

4.12 52.228-15 PERFORMANCE AND PAYMENT BONDS—CONSTRUCTION (JUN

2020)

4.13 SUPPLEMENTAL INSURANCE REQUIREMENTS

4.14 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB

1997) ALTERNATE II (APR 1984)

4.15 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

4.16 52.223-3 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY

DATA (FEB 2021)

4.17 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)

4.18 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)

4.19 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018)

4.20 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED

SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023)

(DEVIATION)

4.21 VAAR 852.223-71 SAFETY AND HEALTH (SEP 2019)

4.22 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)

4.23 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION

CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)

4.24 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV

2018)

4.25 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION

(APR 2019)

4.26 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (APR

2019)

4.27 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)

4.28 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)

ALTERNATE I (APR 2019)

4.29 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT

ADMINISTRATION (OCT 2020)

4.30 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT

(SEP 2019)

4.31 List of Attachments

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO

BIDDERS/OFFERORS

2.1 PRICE OFFER SCHEDULE

Description U/I QTY UNIT PRICE TOTAL PRICE

A. ITEM 1, BASE BID: Provide all labor, materials, tools, equipment, and services necessary for construction for Replace HVAC, Various Buildings.

Completion Time: 365 days from Notice to Proceed (NTP)

B. ITEM 2-BID ALTERNATE 1 (Deduct alternate 1): All work as specified for Bid Item I (Base Bid) minus the following: Delete the Building 46 ceiling and roof insulation addition in the Nave.

Completion Time: 365 days from NTP

JB

JB

A single award will be made online item for which funds are determined available.

REFER TO VAAR Provision 852.236-92, Notice to Bidders-Additive or Deductive Bid Line Items

Bidders shall price each item. Bidders who do not bid each item may be determined non-responsive.

The Period of Performance includes submittal phase and the completion of all punch list items.

ATTACH YOUR ITEMIZED COST BREAKDOWN

Offerors are to include a construction price/cost breakdown using Attachment 4.

2.2 STATEMENT OF WORK

A. GENERAL GUIDANCE

Project Number: 679-22-106

Project Title: Replace HVAC Various Buildings

Scope of Work:

Contractor shall provide all materials, supervision, and labor to complete project 679-22- 106 Replace HVAC Various Buildings per contract drawings and specifications. Work includes the removal, replacement, and installation of new HVAC for Building 2 and 46.

This work will include all trades necessary to provide a finished work environment including but not limited to HVAC, plumbing, electrical, general construction, fire piping, carpentry, and other tasks.

In addition to the above requirements, Contractor shall abide by all VA safety rules and regulations, and ensure work is compliant with applicable NFPA, EPA, and NEC codes.

"Commissioning agent (CA) is not the responsibility of the contractor. The CA will be appointed by the VA in accordance with Specs 01 91 00, para. 1.8 C"

Completion Time from receipt of NTP: 365 days

SAFETY:

Contractor to provide proof that all employees have tested negative for Tuberculosis prior to arriving on campus. Contractor to provide proof that the Supervisor has completed the 30-hour OSHA course and proof that all subcontractors have completed the 10-hour OSHA course prior to arriving on campus.

IDENTIFICATION, PARKING, SMOKING, AND VA REGULATIONS:

The Contractor’s FSE shall always wear visible identification while on the premises of the Tuscaloosa VA Medical Center. Contractor shall only park in the appropriate designated parking areas. Information on parking is available from the Tuscaloosa VA Medical Center Police Section. Tuscaloosa VA Medical Center will not invalidate or make reimbursements for parking violations of the contractor under any conditions. Smoking is prohibited inside and outside any buildings at Tuscaloosa VA Medical Center. Possession of weapons is prohibited. Enclosed containers, including tool kits, shall be subject to search. Violations of VA regulations may result in citation answerable in the United States (Federal) District Court, not a local district, state, or municipal court.

OBTAINING VA IDENTIFICATION BADGE:

Contractor shall contact the Contracting Officer’s Representative (COR), upon contract award, to receive instructions on how to obtain a VA Identification Badge during the performance of this contract.

SECURITY:

The Contractor shall ensure compliance by its employees with the security regulations of the Veterans Administration where work is performed under this Contract. Contracted employees shall self-register at https://www.tms.va.gov/SecureAuth35/ . Once registered, enroll in class VA10176 VA Privacy and Information Security Awareness and Rules of Behavior. Contractors https://www.tms.va.gov/SecureAuth35/ shall provide signed certifications of completion to the Contracting Officer’s Representative (COR) prior to starting work on this contract.

Photography or Video on medical center premises is strictly prohibited. Additionally, pursuant to 38 CFR 1.218(b) (23): Use of recording devices of any kind to record patients or employees is strictly prohibited. VA-designated employee shall provide escort in sensitive areas (e.g. patient areas, MACPAC, HAS, or any areas where sensitive information is kept) and in OIT areas.

SITE VISITS:

Site visits will be determined by the Contracting Officer. Please contact the COR with any questions during the site visit.

POC:, Monteal Wiggins, COR 2, Healthcare Engineer Engineering Service Phone: 205-554-2000, ext. 6490 Email: Monteal.Wiggins@va.gov

RECORDS AND INFORMATION MANAGEMENT

Project No. 679-22-106 Project Title: Replace HVAC Various Buildings

Upon completion or termination of the applicable contract(s) or agreement(s), return and/or destroy, at Covered Entity’s option, VA information gathered, created, received, or processed during the performance of the contract(s) or agreement(s). No data will be retained by Business Associate, or contractor, subcontractor, or other agent of Business Associate, unless retention is required by law and specifically permitted by Covered Entity. As deemed appropriate by and under the direction of Covered Entity, Business Associate shall provide written assurance that all VA information has been returned to Covered Entity or destroyed by Business Associate. If immediate return or destruction of all data is not possible, Business Associate shall notify Covered Entity and assure that all VA information retained will be safeguarded to prevent unauthorized Uses or Disclosures.

Prior to termination or completion of this contract, contractor/subcontractor must not destroy information received from VA, or gathered/created by the contractor in the course of performing this contract without prior written approval by the VA. Any data destruction done on behalf of VA by a contractor/subcontractor must be done in accordance with National Archives and Records Administration (NARA) requirements as outlined in VA Directive 6300, Records and Information Management and its Handbook 6300.1 Records Management Procedures, applicable VA Records Control Schedules, and VA Handbook 6500.1, Electronic Media Sanitization. Self-certification by the contractor that the data destruction requirements above have been met must be sent to the VA Contracting Officer within 30 days of termination of the

2.3 PROPOSAL PREPARATION AND EVALUATION INFORMATION

I. Proposal Submission

This is a competitive Request for Proposal (RFP) that represents the best value to the

Government conducted under Federal Acquisition Regulation (FAR) Subpart 15.1 using the tradeoff process and evaluated in accordance with FAR Subpart 15.3, Source Selection. This section describes the method for evaluating and selecting offers for this procurement.

A. Proposal Submission:

1. Submit one (1) Electronic Proposal to the email addresses indicated on page 1, block 8 of the Standard Form 1442. The Subject Line of the email should include “Company

Name, RFP number, Project Title.”

2. The size of your file shall not exceed 10 MB. If you have multiple documents, please submit them as separate emails. Emails larger than this may be rejected by the network servers and will be considered non-responsive.

3. Interested firms are responsible for ensuring electronic submission delivery by the time and the date specified. It is highly recommended that interested firms confirm that the Contracting Officer has received electronic submissions. Failure to provide a proposal in its entirety before the deadline will render the proposal non-compliant.

B. Proposal Preparation and Format Instructions:

Offerors must provide all requested information for each factor. Proposals must separately address each element of each factor as applicable to be considered responsive to this RFP. Factor headings should be highlighted in yellow or typed in bold text for identification. It is the contractor’s responsibility to ensure the submitted proposal is in the proper format and that the provided information is clearly understood and free of ambiguities.

Offerors proposals should consist of past performance and price proposals, as described below.

1. TAB A: General Information:

(1) Cover Page with Solicitation Number, Project Title

(2) Table of Contents

(3) Signed offer/Acknowledgement of Amendments (SF1442)

(4) Copy of current VetCert SDVOSB certification

(5) SAM UEI Number

(6) Offer Guarantee Bond (DO NOT SEND HARD COPY) Electronic copy acceptable and should be emailed to Point of Contact(s) listed on page 1, block 8.

(7) Safety or Environmental Violations and Experience Modification (EMR) Rate

* Submit information regarding current experience modification rate form (See

Attachment 1). An EMR of greater than 1.0 may disqualify the bidder/offeror.

(8) 852.219-75 VA Notice of Limitations on Subcontracting—Certificate of

Compliance for Services and Construction (Jan 2023) (Deviation), (See

Attachment 2).

(9) Provide evidence of VETS-4212 Reporting (if applicable) file:///C:/Users/VHAATGGoodmE/AppData/Local/Microsoft/Windows/INetCache/Content.Outlook/5W1DJMQ7/veterans.certify.sba.gov

2. TAB B: Past Performance

(1) Offeror must submit a minimum of one (1) but no more than three (3) references utilizing page one of Attachment 3 for projects similar in scope, size, and complexity within the past five (5) years from the date of the posting of this solicitation to SAM.gov. Completed PPQs must be received directly from the client/customer for which the construction project was performed. If a CPARS is available for any of the projects submitted, they should also be submitted.

(2) The Government reserves the right to contact references for verification or additional information. The Government’s inability to contact any of the offeror’s references or the references unwillingness to provide the information requested may affect the Government’s evaluation of this factor.

(3) PPQs should be emailed to the construction contract administrator of the entity

(Government or civilian) for which the construction was completed and emailed to William C. Barton, at email William.Barton2@va.gov, and CC:

Joyce.Powers1@va.gov .

3. TAB C: Price Proposal

(1) Complete the price offer schedule in section A.3.

(2) Price shall be addressed using the attached price breakdown worksheet, which is included in Attachment 4.

(3) Provide supporting documentation showing quotes/price breakdowns for both prime and subcontractors.

NOTE: Price breakdown shall be indicative of showing at least 25% percent of the cost of the contract performance incurred for personnel will be spent on the concern's employees or the employees of other eligible service-disabled veteran-owned small business concerns in accordance with VAAR 852.219-73(d)(4).

II. EVALUATION CRITERIA/OVERVIEW

The evaluation is subjective based on the information provided in response to the information requested in the evaluation factors. The two (2) factors to be evaluated include past performance and price. Offerors proposal shall address the following:

A. FACTOR 1 - PAST PERFORMANCE:

Past Performance will be evaluated to assess recency and relevancy, resulting in a performance confidence assessment rating. For evaluation purposes, past performance will be significantly more important than price.

1. Past Performance: The basis of the evaluation will be the degree to which past performance evaluations and all other past performance information reviewed by the Government reflect a trend of satisfactory performance considering 1) compliance with the contract requirements, 2) effectiveness of the Offeror's on-site management; 3) use of appropriate personnel for contract requirements); 4) mailto:William.Barton2@va.gov mailto:Joyce.Powers1@va.gov timeliness in the submission of schedules, reports, and submittals; 5) adherence to the construction schedule; 6) coordination and control of subcontractors; 7) ability to effectively deal with the customer and other Government personnel; 8) cooperativeness in solving problems and negotiating changes; 9) response to warranty notifications, and other pertinent information obtained from past performance evaluations that have affected the overall performance of previous or ongoing projects.

2. The Government reserves the right to obtain information for use in the evaluation of past performance from any and all sources, including sources outside of the

Government. Other sources may include but are not limited to past performance information retrieved through the (CPARS), for Contractors who are part of a partnership or joint venture identified in the offeror’s proposal, inquiries of owner representative(s), and any other known sources not provided by the offeror.

3. In evaluating past performance, the government reserves the right to give greater consideration to information on those contracts deemed most relevant to the effort described in this solicitation. Common aspects of relevancy include similarity of service/support, complexity, dollar value, contract type, and degree of subcontract/teaming.

4. Relevant performance is defined as work, as a prime contractor, to include

Contractor shall provide all materials, supervision, and labor to complete project

679-22-106 Replace HVAC Various Buildings per contract drawings and specifications. Work includes the removal, replacement, and installation of new

HVAC for Building 2 and 46.

5. Recent is defined as performance within the last five (5) years, to include ongoing projects.

Table 1. Past Performance Relevancy Ratings

Rating Definition

Very

Relevant

Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.

Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.

Somewhat

Relevant

Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires

Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.

6. Past performance evaluation will allow the government to assess the offeror’s ability to perform the effort described in this solicitation based on the offeror’s demonstrated present and past performance. The assessment process will result in an overall performance confidence assessment of Substantial Confidence, Satisfactory

Confidence, Limited Confidence, No Confidence or Neutral/Unknown Confidence.

Table 2. Performance Confidence Assessments

Rating Description

Substantial

Confidence

Based on the offeror’s recent/relevant performance record, the

Government has a high expectation that the offeror will successfully perform the required effort.

Satisfactory

Confidence

Based on the offeror’s recent/relevant performance record, the

Government has a reasonable expectation that the offeror will successfully perform the required effort.

Limited

Confidence

Based on the offeror’s recent/relevant performance record, the

Government has a low expectation that the offeror will successfully perform the required effort.

No Confidence Based on the offeror’s recent/relevant performance record, the

Government has no expectation that the offeror will be able to successfully perform the required effort.

Neutral/Unknown

Confidence

No recent/relevant performance record is available or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.

7. Respondents with no previous past performance shall state this when addressing the selection criteria. Where there is no record of past performance, the proposal will be evaluated neither favorably nor unfavorably. Superior performance ratings on relevant projects may be considered more favorably in the evaluation.

B. FACTOR 2 - PRICE PROPOSAL:

The government may use various price analysis techniques and procedures to determine price reasonableness. Price will be evaluated for Price Reasonableness. The Government reserves the right to evaluate proposals and award a contract without discussions (except clarifications as described in FAR 15.306(a)). Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a performance and price standpoint. The

Government will evaluate price based on the total price. Total price may include alternate bid items.

III. EVALUATION AND BASIS FOR AWARD:

A. FAR 15.101-1 shall apply to the government’s evaluation of proposals. The factors that shall be used to evaluate offers are Past Performance and Price. Past Performance is significantly more important than Price.

B. Discussions: The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)).

Offerors should not automatically assume that they will have an opportunity to participate in discussions or be asked to submit a revised offer. Communications conducted to resolve minor or clerical errors would not constitute discussions. The

Government reserves the right to conduct discussions if the Contracting Officer later determines them necessary.

C. The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the

Government, past performance, and price considered. The proposals must conform to the RFP's requirements and evaluated to represent the Best Value to the Government.

The Best Value is the most advantageous offer, consistent with the Government's stated importance of evaluation criteria. This may result in award being made to a high-rated, higher-priced offeror where the Contracting Officer determines that it is worth the price premium to do so.

D. Offerors must provide all requested information for each factor. Proposals must separately address each of the factors as applicable to be considered responsive to this

RFP. It is the contractor’s responsibility to ensure the submitted proposal is in the proper format the provided information is clearly understood and free of ambiguities

(Reference Proposal Preparation and Format Instruction).

E. In order to determine which proposal represents the best overall value, the Government will conduct a tradeoff analysis, comparing the strengths and weaknesses of the competing proposals to determine which proposal represents the best value to the

Government and thus shall receive contract award.

F. The Government reserves the right to accept other than the lowest priced offer. The right is also reserved to reject any and all offers. The basis of award will be a conforming offer, the price or cost of which may or may not be the lowest. If other than the lowest offer, it must be sufficiently more advantageous than the lowest offer to justify the payment of additional amounts.

G. Award will result in a firm-fixed-price contract. It is the Offeror’s responsibility to ensure the submitted price proposal includes all costs for total project requirements and completion in accordance with the specifications and drawings herein. The Offeror assumes all risk for omissions in prime and/or subcontractor proposals.

H. The Government evaluation team will consider all information provided in the proposal individually. Once these individual analyses are completed, the team will meet and determine a rating by consensus decision.

I. Exceptions to the contractual terms and conditions of the solicitation (e.g., standard company terms and conditions) may result in a determination to reject a proposal.

J. Failure to submit all the data in the format indicated in this section may be cause for determining a proposal incomplete and, therefore, not considered for evaluation and for subsequent award.

K. A Determination of Responsibility will be accomplished for the apparent awardee prior to processing the award. Information obtained from government and commercial systems, will be used to determine responsibility. Any information received by the

Government that would be cause for an adverse Determination of Responsibility will make the offeror ineligible for award.

SDVOSB Verification: The Government will review SBA certification database

(https://veterans.certify.sba.gov/ ) to confirm Service-Disabled Veteran-owned Small

Business (SDVOSB) status certification for the submitted proposals. Evaluations will be performed on proposals submitted by verified SDVOSBs only. Subsequent confirmation of SDVOSB certification status will be performed for the apparent award. For a Joint

Venture to be considered eligible as an SDVOSB if the joint venture 13 CFR 128.402 and the managing joint venture partner makes the representations under paragraph (c) of this clause. A joint venture agrees that, in the performance of the contract, the applicable percentage specified in paragraph 852.219-73(d) of the clause will be performed by the aggregate of the joint venture participants. Failure of a prospective SDVOSB to meet these certification requirements by the SBA shall result in elimination from consideration. Joint Venture -- Any offeror submitting a proposal as a joint venture must provide a certification from each SDVOSB joint partner, signed by an authorized official of each partner to the joint venture, stating that the parties to the joint venture:

1) have entered into a joint venture agreement that fully complies with paragraph (c) of

13 CFR § 128.402; and

2) will perform the contract in compliance with the joint venture agreement. Failure to submit the certification with the offeror’s proposal will render the offeror ineligible for award.

L. Limitations on Subcontracting Certificate. VAAR 852.219-75 - VA Notice of Limitations on Subcontracting—Certificate of Compliance for Services and Construction: The formal certification required by VAAR 852.219-75 must be completed, signed, and returned with the offeror’s proposal. The Government will not consider offers for award from offerors that do not provide the certification, and all such responses will be deemed ineligible for evaluation and award. Thus, offerors must properly complete and return all pages of

Attachment 2 to the Solicitation.

M. To be eligible for an award, if applicable, offerors must have submitted the required

Federal Contractor Veterans’ Employment Report (VETS-4212 Report) with respect to the preceding fiscal year if the contractor was subject to the reporting requirements in accordance with 52.222-37.

N. Safety or Environmental Violations and Experience Modification Rate (EMR):

https://veterans.certify.sba.gov/

1. Offerors shall submit information pertaining to their past Safety and Environmental record. The information must contain a certification that the bidder/offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years. If such certification cannot be made, a

Bidder/Offeror shall explain why and submit as much information as possible regarding the circumstances of its past safety and environmental record, including the number of EPA violations and/or the number of serious, repeat, and/or willful

OSHA violations, along with a detailed description of those violations.

2. Offerors shall submit information regarding their current Experience Modification

Rate (EMR). This information shall be obtained from the Bidder’s/Offeror’s insurance carrier and be furnished on the insurance carrier’s letterhead. If a

Bidder/Offeror’s EMR is above 1.0, the Offeror must submit a written explanation of the EMR from its insurance carrier furnished on the insurance carrier’s letterhead, describing the reasons for the EMR, and the anticipated date the EMR may be reduced to 1.0 or below.

3. Self-insured contractors or other contractors who cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on

Compensation.

4. Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state-run worker’s compensation insurance rating bureau.

5. If the NCCI cannot issue an EMR because the Bidder/Offeror lacks insurance history, the Offeror shall submit a letter indicating so from its insurance carrier furnished on the insurance carrier’s letterhead and include a letter from the NCCI indicating that is has assigned Bidder/Offeror a Unity Rating of 1.0.

6. The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases, will be used to make an initial Determination of Responsibility.

7. This requirement applies to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.”

2.4 GENERAL SOLICITATION INFORMATION

I. GENERAL PROPOSAL INFORMATION

A. PROPOSAL MATERIALS

Proposal materials consisting of drawings, specifications, contract forms, and any issued

Amendments will be posted at www.sam.gov. This is the only official location where these documents can be obtained, and updates are posted. No ‘hard copy’ proposal materials are available.

B. WAGE DETERMINATION:

Wages for all contractors and subcontractors must comply with Construction Wage Rate

Requirements (Reference 52.222-6 for further information). The current determination is

General Decision Number: AL20230098 09/06/2024, Attachment 5. Be advised the determination that is current at the time of the contract award is the determination that will apply to the contract. Current determinations are always available at https://sam.gov.

II. DATABASE REGISTRATION INFORMATION

A. SYSTEM FOR AWARD MANAGEMENT REGISTRATION

The System for Award Management (SAM) is the Official U.S. Government system that consolidated the capabilities of the Central Contractor Registration (CCR including

FedReg), Online Representations and Certifications Application (ORCA), and the

Excluded Parties List System (EPLS). Federal Acquisition Registrations require that federal contractors register in SAM at www.sam.gov and enter all mandatory information into the system.

B. THE EXCLUDED PARTIES LIST SYSTEM (EPLS)

To ensure that the individuals or businesses providing services under the contract have not engaged in fraud or abuse regarding Sections 1128 and 1128A of the Social Security

Act regarding federal health care programs, the contractor is required to check the

Excluded Parties List System (EPLS) located at www.sam.gov for each person or business providing services under this contract. During the performance of this contract, the Contractor is prohibited from using any individual or business listed on the List of

Excluded Individuals/Entities.

http://www.sam.gov/ https://sam.gov/ http://www.sam.gov/ http://www.sam.gov/

C. VETS-4212 REPORTING REQUIREMENT

Contractors are required to submit a required annual Form VETS-4212, Federal

Contractor Veterans' Employment Report in all cases where the contractor or subcontractor has received an award of $150,000 or more in any fiscal year. Contracting

Officers are prohibited from awarding a contract to a contractor that has not submitted a required VETS-4212 Report with respect to the preceding fiscal year if the contractor was subject to the reporting requirement of 38 U.S.C. 4212(d). Submit this report as soon as possible, if not already submitted, to avoid delays in the contract award process. For more information on this requirement and/or for completing the web-based reporting form, visit https://www.dol.gov/agencies/vets/programs/vets4212. See FAR provision

52.222-38 (JUN 2020), Compliance with Veterans' Employment Reporting Requirements

(FEB 2016) under the Representations, Certifications and Other Statements of Offerors, and FAR clause 52.222-37, Employment Reports on Veterans (JUN 2020) under the

General Conditions.

III. BONDING INFORMATION

A. BID GUARANTEE

A bid guarantee is required in an amount not less than 20 percent of the proposal price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee in the proper form and amount by the proposal submission date and time shall require rejection in all cases except those listed in Federal Acquisition Regulation (FAR) 28.101-4. Bid

Bonds must be provided using Standard Form 24 (see FAR 28.106-1), and the form must be a scanned copy of an original (no whiteouts, clear signatures, seals must be evident and visible) and contain the proper solicitation number, proposal due date, and be from a corporate surety listed in Department of Treasury Circular 570. Individual sureties have to be acceptable to the Contracting Officer (see FAR 28.203) and be accompanied by

Standard Form 28 Affidavit of Individual Surety. Other forms of bid security are acceptable, as denoted in FAR Part 28.203-2.

B. PERFORMANCE AND PAYMENT BONDS

In accordance with Contract Clause 52.228-15 and FAR 28.102, Contractors are reminded that any amount awarded between $35,000.00 to $150,000 shall require a

Payment Bond (SF 25A) and awards exceeding$150,000.00 shall require both Payment and Performance Bonds (SF 25). Payment and Performance bonds are due no later than http://www.dol.gov/agencies/vets/programs/vets4212

10 days after notification of award as instructed by the contracting officer. The bonds shall contain no whiteouts or other corrections. Payment and Performance bonds are required in the penal sum of 100% of the contract's price.

IV. SECURITY/BADGING

A. Contractor employee (s) may be required to obtain security screenings and/or ID badges for employees through VA prior to the start of any work on site depending upon length of work time on site. The contractor must coordinate badge requests with the respective

Contracting Officer Representative (COR). Any PIV Badging requires two (2) trips to a

VA facility and the time required to complete the necessary paperwork. One trip is for completing the electronic fingerprinting, and the other to pick up the PIV Badge.

B. ROSTER: Within 15 days after issuance of the notice to proceed or as agreed to with the

Contracting Officer, the Contractor should provide a roster of Contractor and

Subcontractor employees to the COR to begin their background investigation.

C. FORMS: Contractor personnel will need to complete the forms listed below depending upon the length of facility access needed:

D. Employee access for less than 6 months: Fingerprint request form (PIV Office

Fingerprint Request Form (Updated 3-1-2020)) and SAC form (SAC FORM (NEW))

Any VA PIV facility can take fingerprints; not necessarily where the work is to be performed.

E. Employee access for les greater than 6 months: Fingerprint request form, SAC form, Contractor Background Investigation Request (Contractor Background Investigation

Request Form 06-03-2021), OPM optional form 306 (of306) Personnel shall submit all required information related to their background investigations utilizing the Office of

Personnel Management’s (OPM) Electronic Questionnaire for Investigations Processing

(e-QIP) after receiving an email notification from the Security and Investigation Center

(SIC). Emails will be sent to employees requiring completion.

F. BADGING STEPS: After completing forms, the following steps need to be followed to obtain a badge.

1) Fingerprints: Need to schedule fingerprinting in coordination PIV Office. Fingerprint request form and SAC form must be brought to the PIV office along with two forms of valid ID when Contractor gets fingerprinted. Contractor informs COR of employees that have been fingerprinted and sends COR all the required forms. Only electronic fingerprints are authorized.

2) Adjudication: COR submits the paperwork to the required office for adjudication.

COR receives confirmation that the Contractor is favorably adjudicated, or contractor answers follow up questions. The Contractor, when notified of an unfavorably adjudicated background investigation on a Contractor employee as determined by the

Government, shall withdraw the employee from consideration in working under the

3) Sponsor: COR will let the Contractor know when they have been sponsored.

4) Badging: Contractor schedules an appointment using https://portal.usaccess.gsa.gov/scheduler. Note: This link is best used in Google

Chrome. Contractor personnel must bring two forms of valid ID when picking up a badge.

C. COMPLIANCE: Failure to comply with the Contractor personnel security investigative requirements may result in loss of physical and/or logical access to the VA Facility and systems by Contractor and Subcontractor employees. Employees must follow all HSPD-

12 policies and procedures and use and protect their assigned identity credentials per VA policies and procedures, display their badges at all times, and return the identity credentials upon termination of their relationship with VA.

NOTE: VA SECURITY PROCEDURES ARE SUBJECT TO CHANGE WITHOUT NOTICE.

V. INVOICES:

A. All payments by the Government to the contractor will be made in accordance with: FAR

52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER – SYSTEM FOR

AWARD MANAGEMENT (OCT 2018)

B. Invoices shall be submitted per FAR 52.232-5 Payments under Fixed-Price Construction

Contracts (May 2014) and 852.232-70 Payments Under Fixed-Price Construction

Contracts (Without NAS-CPM). (NOV 2018). For detailed instructions, refer to

Attachment 6 Invoicing.

https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fportal.usaccess.gsa.gov%2Fscheduler&data=05%7C02%7C%7Ce36d9f33ce144b6c603b08dd131b1f72%7Ce95f1b23abaf45ee821db7ab251ab3bf%7C0%7C0%7C638687729419852310%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=UymXGgaOPR20eif3lR%2FO4vYKb1afhgI%2FRc8tWiLs%2FQw%3D&reserved=0

2.5 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023)

(a) All actual and potential offerors are encouraged to provide feedback on the preaward and debriefing processes, as applicable. Feedback may be provided to agencies up to 45 days after award. The feedback is anonymous, unless the participant self-identifies in the survey. Actual and potential offerors can participate in the survey by selecting the following link: https:// www.acquisition.gov/360.

(b) The Contracting Officer will not review the information provided until after contract award and will not consider it in the award decision. The survey is voluntary and does not convey any protections, rights, or grounds for protest. It creates a way for actual and potential offerors to provide the Government constructive feedback about the preaward and debriefing processes, as applicable, used for a specific acquisition.

(End of Clause)

2.6 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.7 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—

SECONDARY SITE OF THE WORK (MAY 2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.8 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO

ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION

(FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action

Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the

Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

20.6 % 6.9 %

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance

Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action

Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order

11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for

Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—

(1)…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .