Sequence Plan.pdf

PDF 661 KB Posted

Attached to
FTQW 20 0504 2 CHPP Electrical Upgrades
Solicitation number
FTQW2005042
Issued by

About this file

This document is a Sequencing Plan for repairing electrical panels and circuits at the Eielson Air Force Base Central Heating & Power Plant (CH & PP), specifically Phase C of the project. The plan provides detailed instructions for the 354th CE Squadron, with a focus on the precise order and constraints for working on various electrical panels, including Panel N, T111, LP-4, Panel D, T109, P, T110, and Main LP.

Key sequencing requirements include: the contractor must first complete work on Panel N, T111, and LP-4; the government will provide temporary power and re-establish certain circuits; specific panels have limited daily downtime (e.g., Panel E - 4 hours, Panel CH - 12 hours); work must be performed only during summer (15 May through 15 September); and the Main LP panel must be the last panel worked on, with the contractor required to install a temporary panel and power source for the cutover. Additional panel-specific notes require government notification two weeks in advance for certain panels, such as Panel G and Panel H (Boiler #5).

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sequencing Plan

*Prior to work on P, T110, Main LP, D, T109 and LP-4; the Government will provide temporary power from LP-4 circuit numbers 8&10 through panel D.* -Contractor must complete all work on panel N, T111 and LP-4 first.

-Government will re-establish old circuits #8&10 in the new panel N circuits #16&18.

Drawing No. E1.0

Panel “Main LP” MUST be last in the sequence of all the panels.

See page 5 of sequencing plan for details.

Once contractor has completed the first sequence, panel N with critical loads will no longer be an issue according to drawing

No. E1.1.

Drawing No. E1.1

See separate sequencing for the areas outlined with this shape on page 2 & 5.

Panel H- Boiler #5 will have to be offline to work in panel. Govt. must be notified two weeks prior.

Panels CH- can only have a down time of 12 hours each day.

Panel E- can only have a down time of 4 hours each day.

-Contractor shall sequence the remainder of the work on the panels and transformers to be done with a downtime of NO longer than 4 hours per day and only in the “Summer” time.

“Summer” is considered to be 15 May through 15 September.

Panel G- Govt. must be notified at least two weeks in advance of ANY work to be done in this panel.

Drawing No. E1.0 4

-Contractor CAN NOT perform work on panel “Main LP” until all panels and transformers down stream have completed the required work.

-Contractor to install a temporary panel on a uni-strut for the cutover of panel “Main LP”.

-Contractor to provide temporary power source to power temporary panel until ALL cutovers are made to new panel

“Main LP”.

Drawing No. E1.0 5