Section 23 07 10 - Insulation.doc

DOC document 53 KB Posted

Attached to
Misc. Generator Repairs and Improvements Federal contract opportunity
Solicitation number
36C25621R0179
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16

About this file

This document contains a federal solicitation for miscellaneous generator repairs and improvements at the Gulf Coast Veterans Health Care System in Pensacola, Florida. The solicitation is set aside solely for Service-Disabled Veteran-Owned Small Businesses and requires offerors to be registered and verified as an SDVOSB in the Vendor Information Pages database. The base item involves furnishing all labor, tools, materials, equipment, supervision, and other requirements necessary to perform miscellaneous generator repairs and improvements at the Gulf Coast Veterans Health Care System facility. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16 is the contracting agency.

View the file

Other files for this federal contract opportunity

Other files attached to Misc. Generator Repairs and Improvements, newest first.
File Type Posted
36C25621R0179 0003.pdf PDF
S06 36C25621R0179 0002.pdf PDF
S06 36C25621R0179 0001 (JACC650KW).pdf PDF
S06 36C25621R0179 0001 (IMG_1379).jpg JPG image
S06 36C25621R0179 0001 (JACC350KW).pdf PDF
S06 36C25621R0179 0001 (E-5.01-Layout1).pdf PDF
36C25621R0179 0001.pdf PDF
36C25621R0179.pdf PDF
VAP-MH-205.pdf PDF
Section 28 05 11 - Common Work Results for Electronic Safety-Security.docx DOCX document
Section 22 05 11 - Common Work Results For Plumbing.docx DOCX document
Section 26 24 16 - Panelboards.docx DOCX document
ICRA.pdf PDF
Room Detail Draft VAP-MH-101-2P.pdf PDF
Room 1C151 Draft-MH-101-3.pdf PDF
EXHIBIT D CONTRACTOR EVALUATION FORM CONSTRUCTION SAFETY.docx DOCX document
Room 2A121 Draft VAP-MH-102-1.pdf PDF
EXHIBIT B PAST AND PRESENT PERFORMANCE QUESTIONNAIRE.docx DOCX document
Draft VAP-MH-101-4.pdf PDF
Section 26 05 71 - Electrical System Protective Device Study.DOC DOC document
VAP-MH-603.pdf PDF
VAP-PL-501.pdf PDF
Section 26 05 26 - Grounding and Bonding for Electrical Systems.docx DOCX document
Section 26 32 13 - Engine Generators.docx DOCX document
Section 23 09 23 - Direct Digital Control System for HVAC.docx DOCX document
Section 22 11 23 - Domestic Water Pumps.docx DOCX document
Section 23 01 00 - General Provisions of HVAC Systems.doc DOC document
Section 22 05 23 - General Duty Valves For Plumbing Piping.docx DOCX document
Draft VAP-GS-121S-6.pdf PDF
Draft VAP-MH-101-2P.pdf PDF
VA CATEX Form- JACC NRM HVAC and Generators.pdf PDF
Section 23 05 41 - Noise and Vibration Control for HVAC Piping-Equipment.docx DOCX document
VAP-MH-206.pdf PDF
General Decision FL20210203 Escambia 05-07-2021.pdf PDF
Section 23 21 23 - Hydronic Pumps.docx DOCX document
Rooms C271A_C272A_2D122_2D142_2D143_2D146_2D153 Draft-MH-102-4.pdf PDF
Section 23 21 20 - Hydronic Specialties.doc DOC document
Room 2B137 Draft-MH-102-2.pdf PDF
EXHIBIT E SURETY FORM.docx DOCX document
EXHIBIT C SUBCONTRACTOR INFORMATION AND CONSENT.docx DOCX document
EXHIBIT A PERFORMANCE RELEVANCY SURVEY.docx DOCX document
DWH2.pdf PDF
Section 23 05 93 - Testing Adjusting and Balancing for HVAC.docx DOCX document
VHA Directive 1193 - COVID 2019 Vaccination Program.pdf PDF
VAP-MH-601.pdf PDF
ACC-1 Power Supply Drawing E-6_01.pdf PDF
VAP-MH-401.pdf PDF
Section 26 36 23 - Automatic Transfer Switches.docx DOCX document
Section 23 07 11 - HVAC and Boiler Plant Insulation.docx DOCX document
Section 26 05 13 - Medium Voltage Cables.docx DOCX document
Show all 50

Misc. Generator Repairs and Improvements has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 23 07 10 - INSULATION

PART 1 GENERAL

1.1 WORK INCLUDED

A. Contractor shall provide all necessary labor, materials, tools, and equipment to perform work required on the drawings and specified herein.

B. Certain equipment and/or systems to be factory insulated by manufacturer. Factory insulation materials to be as specified in applicable sections of the specifications.

C. All pipe fittings, valves, and strainers in insulated pipe systems to be insulated.

D. Thermal resistance "R" values used herein are expressed in units of "Hour, Degrees F., Sq. Ft./BTU per Inch of Thickness" on a flat surface at a mean temperature of 75 degrees F.

E. Note that where electric cable wrap is called for, insulation is to be applied over cable.

F. "Contractor's Option" referred to in Materials below indicates optional materials which may be used as equals.

1.2 DEFINITIONS

A. "Exposed" equipment, ducts, and piping are areas which will be visible without removing ceilings or opening access panels.

B. Outdoors is considered exposed to the weather.

C. Underground is buried, whereas in a trench below grade is considered concealed.

1.3 CERTIFICATION/QUALITY ASSURANCE

A. Products shall meet applicable national, state, and local building codes and be U.L. (or other recognized testing lab) listed for intended service.

B. All insulations, jackets, adhesives, coatings, sealers, and tapes shall have a flame spread rating of 25 or less and smoke development rating of 50 or less when tested in accordance with ASTM E-84, NFPA 225, U.L. 723, and further must meet the requirements of NFPA 90-A and applicable building, plumbing, and mechanical codes.

C. All insulation materials shall be delivered and stored in manufacturers’ containers and kept free from dirt, water, chemical, and mechanical damage.

D. Insulation shall be applied in a workmanlike manner by experienced, qualified tradesmen.

E. Insulation shall not be applied until all pressure testing has been completed, inspected, and released for insulation application.

F. Surfaces shall be clean and dry.

G. Insulation joints shall be butted firmly together and all jackets and tapes shall be smoothly and securely installed.

H. Insulation for duct, pipe, and equipment for above grade exposed to weather outside building shall be certified as being self-extinguishing for 1" thickness in less than 53 seconds when tested in accordance with ASTM D-1692.

1.4 APPLICABLE CODES AND STANDARDS

A. ASTM E-84.

B. U.L. 723.

C. NFPA 90-A.

D. State of Mississippi Energy Code.

1.4 SUBMITTALS

A.

Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, and SAMPLES.

B.

Shop Drawings:

1.

All information, clearly presented, shall be included to determine compliance with drawings and specifications and ASTM, federal and military specifications.

a.

Insulation materials: Specify each type used and state surface burning characteristics.

b.

Insulation facings and jackets: Each type used. Make it clear that white finish will be furnished for exposed ductwork, casings and equipment.

c.

Insulation accessory materials: Each type used.

d.

Manufacturer's installation and fitting fabrication instructions for flexible unicellular insulation.

e.

Make reference to applicable specification paragraph numbers for coordination.

C.

Samples:

1.

Each type of insulation: Minimum size 100 mm (4 inches) square for board/block/ blanket; 150 mm (6 inches) long, full diameter for round types.

2.

Each type of facing and jacket: Minimum size 100 mm (4 inches square).

3.

Each accessory material: Minimum 120 ML (4 ounce) liquid container or 120 gram (4 ounce) dry weight for adhesives / cement / mastic.

PART 2 PRODUCTS

2.1 MATERIALS FOR PIPE AND EQUIPMENT

A. Materials for Pipe and Equipment: Provide factory pre-molded or shop or site mitered segment type insulation for pipe, pipe fittings, and valves. Fitting insulation to be of same thickness and material as adjoining pipe insulation. All insulation and related materials such as tape and mastic to meet applicable building code requirements for fire and smoke development.

1. Cellular Glass (Foamglass): Pittsburgh Corning "Foamglass." Product must be guaranteed by manufacturer to have a continuous operational temperature limit of 250 degrees F. and a minimum "R" value of 3.7 per inch (K=0.27) at 75 degrees F mean temperature. Vapor-barrier mastic for application to below ambient pipe insulation shall be fungus resistant per ASTM D 5590 with 0 growth rating; Water based; Permeance per ASTM E 96, Procedure B, 0.013 perm or less at 43-mil dry film thickness suitable for indoor and jacketed outdoor use. Products: Foster 30-80 AF. Color: White. For all butt joints, a pliable insulation joint sealant shall be used. Products: Foster 95-50 or Childers CP-76. Use foamglass for the following services:

a. Chilled water piping: below 1-1/2” - 1-1/2" thick; 1-1/2" and greater - 2" thick.

b. With saddles instead of other piping insulation (fiberglass, flexible tubular) to prevent crushing of insulation at hangers.

2. Flexible Sheet: Provide 25/50 rated, closed-cell, flexible sheet rubber type insulation, having a minimum "R" value of 3.7 per inch (K=0.27) at 75 degrees F mean temperature and continuous operational temperature limit of 200 degrees F. Product to be Armstrong "Armaflex II" or approved equal. Use flexible sheet insulation for the following services:

a. Chiller cooler, suction piping, and any chilled water pipe connections, housings, and other portions of the chiller which might sweat: 1" thick.

b. Chilled water piping valves, strainers, and hydronic specialties: 1" thick.

2.2 MATERIALS FOR FITTINGS, VALVES, AND SPECIAL COVERINGS

A. Provide coverings and finishes for specific items hereinafter specified.

1. Use pre-molded insulation fabricated by the manufacturer of insulation material or shop or site mitered segment type insulation for: All pipe fittings, elbows, tees, valves, and couplings.

2. PVC fitting covers over blanket fiberglass are NOT acceptable.

3. Contractor's option to provide factory pre-molded one-piece PVC insulated fitting covers, precut fiberglass insulation inserts, and necessary installation materials for all pipe fittings. Materials to be equal to Manville Zeston white, U.V. resistant, 25/50 rated, 20 mil thickness insulated PVC fitting covers and insulation inserts.

B. For pipe fittings, valves, strainers, air separators, and other irregular surfaces, in systems operating below 60 degrees F., when exposed to view inside building or in equipment rooms, cover insulation with white colored glass mesh embedded in white, fungus resistant vapor barrier coating Foster 30-80 AF. Coating shall meet ASTM D 5590 with 0 growth rating.

C. Fabricate and install readily removable insulation caps to facilitate service and maintenance accessibility to all strainers including suction diffusers in systems operating below 60 degrees F.

D. For any service when above grade exposed-to-the-weather outside building, cover straight pipe insulation with 0.016" thick aluminum jacket equivalent to ITW or RPR and cover valves and fittings with .024" thick aluminum factory formed covers equivalent to Childers Ell-Jacs.

E. When specifically approved by VA COR, when it is impossible to completely insulate pipe, fittings, or valves with specified insulation, Armstrong Armaflex insulation tape may be used to prevent condensate drip on small piping. Use of cork insulation tape is prohibited.

PART 3 EXECUTION

3.1 GENERAL

A. No insulation shall be cut where a hanger is located. If hangers have been installed by pipefitter tradesmen which violates this strict requirement, notify VA COR immediately.

B. Piping systems shall be tested and found free of all leaks prior to installation of insulation covering.

C. All surfaces shall be clean and dry when covering is applied. Covering to be dry when installed and during application of any finish, unless such finish specifically requires a wetted surface for application.

D. All adhesives, cements, and mastics shall be compatible with materials applied and shall not attack materials in either wet or dry state.

E. Install insulation using professional insulators who have adequate experience and ability.

F. Exposed-to-view insulation shall have a well tailored appearance.

G. See Section 23 21 13 for sleeves and insulation requirements.

H. Treat insulated pipe surfaces in equipment rooms and where exposed to normal view, so surfaces may be painted with water base latex paint. Use of mastics, adhesives, or jacketing which cause "bleeding" is prohibited.

3.2 INSTALLATION OF PIPE AND EQUIPMENT COVERING

A. Where fiberglass or flexible tubular insulation is used on piping sized 2" and larger, insert a section of foamglass insulation at hanger or support points between pipe and metal shield for full length of shield to prevent crushing of insulation. Insulation thickness to be same as adjoining insulation. Where insulation passes through pipe hangers and across trapeze supports, 12" long metal saddles shall be used. On cold pipe, vapor barrier should be carried through the hanger and sealed.

B. Foamglass insulation shall be strictly applied as follows:

1. The inside full surface of the insulation and both the circumferential and longitudinal joints shall be buttered with fire-resistive pliable joint sealant. Voids and cracks shall be filled with sealant. Sealant shall be Foster 95-50, Childers CP-76 or equal. Insulation shall be secured with 1/2" wide aluminum bands on 12" centers.

2. The circumferential joints shall be staggered.

3. Block type insulation shall be adhered by stick-clips or bands, in addition to the sealant, as required to provide support for the insulation.

4. Finish in concealed locations shall be the bare insulation.

5. Finish in equipment rooms and elsewhere where exposed-to-view shall be white 8 oz. canvas and Foster 30-36 or Childers CP-50A MV1 lagging adhesive/coating, paintable jacket.

C. Prior to application of flexible sheet insulation, thoroughly clean all metal surfaces, making sure that all dirt, scale, loose paint, plaster, and oil have been removed and that surfaces are dry. If surface has been primed, test a 2 square foot section using adhesive equivalent to Armstrong No. 520, Foster 85-75, Childers CP-82 in order to determine whether solvent in adhesive will loosen or lift the primer. If primer is loosened, then remove it. When testing proves acceptable, adhere insulation with smooth side out, using thin but adequate coating of same adhesive. Follow manufacturers’ instructions. Coat all butt edges of each sheet. Stagger all joints. Insulate all standing seams or flanges with same thickness of insulation material as that used on main surface.

D. Apply PVC insulated fitting covers and precut insulation inserts as follows:

1. Installation for cold systems:

a. Position, tuck, and fold the fiberglass insulation insert as described above in steps (a) and (b) for hot systems.

b. Apply a vapor barrier mastic around the edges of the adjoining pipe insulation. Apply the mastic along the inside of the fitting cover throat overlap seam.

c. Place the fitting cover over the insulation, lapping the mastic-covered edge over the other side of the throat seam.

d. Apply color-matched, pressure-sensitive tape over the circumferential joints. The tape should extend over the adjacent pipe insulation and overlap itself by at least 2" on the downward side of the lap.

END OF SECTION 23 07 10