This memorandum outlines infection control requirements for a construction permit at a Veterans Affairs medical center. The project involves miscellaneous generator repairs and mechanical improvements with an estimated duration of 365 days. Infection control precautions of Class III are required, including isolating HVAC systems, erecting barriers, maintaining negative air pressure, and thoroughly cleaning and removing barriers upon completion. No work will take place in negative pressure rooms housing tuberculosis patients.
The related federal contract opportunity is a Service-Disabled Veteran-Owned Small Business set-aside solicitation to perform miscellaneous generator repairs and improvements at the Gulf Coast Veterans Health Care System facility in Pensacola, Florida. Offerors must be registered and verified as an SDVOSB in the Vendor Information Pages database. The solicitation includes requirements for joint venture agreements and current SDVOSB verification to be eligible for award.
View the file
Other files for this federal contract opportunity
Show all 50
Misc. Generator Repairs and Improvements has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MEMORANDUM NO. 18A-04-11
Infection Control Construction Permit Project Title: Miscellaneous Generator Repairs & Mechanical Improvements
Permit No:
Location of Construction: JACC Project Start Date: TBD Project Coordinator/COTR: Logan Bazo Estimated Duration: 365 days Contractor Performing Work TBD Permit Expiration Date: TBD Supervisor: Glenn Bailey Telephone: 318-990-0236
YES NO CONSTRUCTION ACTIVITY YES NO INFECTION CONTROL RISK GROUP
TYPE A: Inspection, non-invasive activity GROUP 1: Low Risk TYPE B: Small scale, short duration, moderate to high levels
GROUP 2: Medium Risk x TYPE C: Activity generates moderate to high levels of dust, requires greater than 1 work shift for completion x GROUP 3: Medium/High Risk
TYPE D: Major duration and construction activities Requiring consecutive work shifts
GROUP 4: Highest Risk
CLASS I
1. Execute work by methods to minimize raising dust from construction operations.
2. Immediately replace any ceiling tile displaced for visual inspection.
3. Minor Demolition for Remodeling
CLASS II 1. Provides active means to prevent air-borne dust from dispersing into atmosphere
2. Water mist work surfaces to control dust while cutting.
3. Seal unused doors with duct tape.
4. Block off and seal air vents.
5. Wipe surfaces with disinfectant.
6. Contain construction waste before transport in tightly covered containers.
7. Wet mop and/or vacuum with HEPA filtered vacuum before leaving work area.
8. Place dust mat at entrance and exit of work area.
9. Remove or isolate HVAC system in areas where work is being performed.
CLASS III
x
1. Obtain infection control permit before construction begins.
2. Isolate HVAC system in area where work is being done to prevent contamination of the duct system.
3. Complete all critical barriers or implement control cube method before construction begins.
6. Vacuum work with HEPA filtered vacuums.
7. Wet mop with disinfectant
8. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.
9. Contain construction waste before transport in
Date 4. Maintain negative air pressure within work site utilizing HEPA equipped air filtration units.
5. Do not remove barriers from work area until complete project is thoroughly cleaned by Facilities Management Service.
tightly covered containers.
10. Cover transport receptacles or carts. Tape covering.
11. Remove or isolate HVAC system in areas where work is being performed/
Initial
CLASS IV
1. Obtain infection control permit before construction begins.
2. Isolate HVAC system in area where work is being done to prevent contamination of duct system.
3. Complete all critical barriers or implement control cube method before construction begins.
4. Maintain negative air pressure within work site utilizing
HEPA equipped air filtration units.
5. Seal holes, pipes, conduits, and punctures appropriately.
6. Construct anteroom and require all personnel to pass through this room so they can be vacuumed using a HEPA vacuum cleaner before leaving work site or they can wear cloth or paper coveralls that are removed each time they leave the work site.
7. All personnel entering work site are required to wear shoe covers
8. Do not remove barriers from work area until completed project is thoroughly cleaned by the Environmental Service Dept.
9. Vacuum work area with HEPA filtered vacuums.
10. Wet mop with disinfectant.
11. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.
12. Contain construction waste before transport in tightly covered containers.
13. Cover transport receptacles or carts. Tape covering.
14. Remove or isolate HVAC system in areas where work is being performed.
Date
Initial
Construction taking place in negative pressure rooms where TB patients are housed or work with exhaust to these rooms? ___Yes _X__No If yes the contractor must provide written certification that all employees assigned to the work site have a negative TB screening within 90 days prior to assignment to work area.
Additional Requirements:
Infection Control: COTR:
Safety: Contracting Officer:
Adapted with permission V Kennedy, B Barnard, St Luke Episcopal Hospital, Houston TX, Forms modified and provided courtesy of Judene Bartley, ECSI Inc Beverly Hills MI 2002 Reviewed 2005
Attachment B-7
CONTRACTING ONLY
X
X
CLASS TYPE : DEPENDS ON LOCATION OF WORK AND *RISK AREA
TSC 8/6/2021
TSC 8/6/2021
TSC 8/6/2021