Attachment G: CSR Template A004

View the file

Other files for this federal contract opportunity

Other files attached to Service Transition Support (STS) Services, newest first.
File Type Posted
SAQMMA16R0029_A008_Final.pdf PDF
Attachment_C_-_Price_Schedule_A007.xlsx XLSX spreadsheet
SAQMMA16R0029_A007.pdf PDF
Attachment_D_-_STS_Statement_of_Work_A006_(Clean).docx DOCX document
SAQMMA16R0029_QA_A006.xlsx XLSX spreadsheet
Attachment_D.1_-_STS_Statement_of_Work_A006_(Track_Changes).docx DOCX document
Attachment_I_-_CST-SDLC.pdf PDF
SAQMMA16R0029_A006.pdf PDF
SAQMMA16R0029_A005.pdf PDF
Attachment_H_-_IVV_Survey_Deliverable_Template_A004.docx DOCX document
SAQMMA16R0029_A004.pdf PDF
Attachment_C_-_Price_Schedule_A004.xlsx XLSX spreadsheet
Attachment_D.1_-_SOW_A004_(Track_Changes).docx DOCX document
Attachment_B-_GFE_Inventory_A004.xlsx XLSX spreadsheet
Attachment_D_-_STS_SOW_A004_(Clean).docx DOCX document
SAQMMA16R0029_QA_A004.xlsx XLSX spreadsheet
SAQMMA16R0029_Q&A__1.pdf PDF
Attachment_E_-_DD254.pdf PDF
SAQMMA16R0029(A003)_Final.pdf PDF
Attachment_F_-_Wage_Determination_15-4281.pdf PDF
SAQMMA16R0029_A002_Final.pdf PDF
SAQMMA16R0029_A001_Final.pdf PDF
Attachment_C_-Price_Schedule.xlsx XLSX spreadsheet
Attachment_A_-_Past_Performance_Survey.xlsx XLSX spreadsheet
SAQMMA16R0029.pdf PDF
Attachment_D_-_STS_Statement_of_Work.pdf PDF
Attachment_B_-_GFE_IV-V_Government_Inventory_List.pdf PDF
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of State Bureau of Consular Affairs

CST Contract Status

Report (CSR)

Contract/Task No: [Insert Contract/Task No.]

Contract Description/High Level Name: [Insert Contract

Description]

Contractor: [Insert Company Name]

Project Manager: [Insert First/Last Name]

CST PM: [Insert First/Last Name]

CST GTM: [Insert First/Last Name]

CST COR: [Insert First/Last Name]

Reporting Period: [Indicate month/year, quarter/year]

Submission Date: [Month Day, Year]

Version 1.2

CONTRACTOR DETAILS

Contractor Name (Prime)

[Insert Company Name]

Corporate Sponsor Email Address & Telephone Number

Project Manager

Email Address & Telephone Number

[Insert the Contract’s Corporate

Sponsor’s Name – (i.e. Immediate

Supervisor to PM)]

[Insert Company Email Address]

[Insert Telephone

Number]

[Insert the Project

Manager’s Name]

[Insert Company Email Address]

[Insert Telephone

Number]

Sub Contractors

[List all subcontracting firms performing on contract]

New CSR Policies

• All CST Contractors (regardless of contract size, type or scope) are required to submit this CSR Deck to the CST SSPM (CA-CST-PMO-Acquisition-Management@state.gov) no later than 11:59pm on the

3rd Thursday of the month. Contractors may no longer upload decks to CST SharePoint.

• Contractor must submit (1) signed CSR deck and (1) MS Excel Workbook per contract per reporting period. The workbook must contain:

– Monthly Budget Data (per item #8 in the deck),

– Contract Modification History (per item #9 in the deck)

– Risk/Issue Log (per item #10 in the deck)

– For your convenience, the workbook also contains sections for:

– FTE Chart (per item #6 in the deck)

– Milestone Reporting (per item #13 in the deck)

• Only the requested information within the template is acceptable for submission. Any supplemental documents/content will not be reviewed.

• Contractors should remove instructions and example pages, renumbering slides thereafter.

• Contractors must use the Microsoft Excel templates provided by CST to complete the Monthly Budget, Contract Modification History and Risk/Issue slides. Contractors are not authorized to make any changes to formulas. If a Contractor is having issues applying their respective data to the CST template, please contact CST SSPM for guidance prior to the due date to ensure a timely submission.

• All data must be up to date as of the previous month’s last business day.

– For example: All data in your August 20, 2014 submission should be up to date as of July 31, 2014.

2 Version 1.2 mailto:CA-CST-PMO-Acquisition-Management@state.gov mailto:CA-CST-PMO-Acquisition-Management@state.gov mailto:CA-CST-PMO-Acquisition-Management@state.gov mailto:CA-CST-PMO-Acquisition-Management@state.gov mailto:CA-CST-PMO-Acquisition-Management@state.gov mailto:CA-CST-PMO-Acquisition-Management@state.gov mailto:CA-CST-PMO-Acquisition-Management@state.gov mailto:CA-CST-PMO-Acquisition-Management@state.gov mailto:CA-CST-PMO-Acquisition-Management@state.gov

1. CSR ACKNOWLEDGEMENT OF ACCURACY – The Contractor Program/Project Manager must sign acknowledging accuracy of the document.

2. CONTRACT SCOPE– List the contract scope as defined in your statement of work.

3. REQUEST FOR GOVERNMENT ACTION - List the requests for government action. For each, provide a description and status.

4. INVOICES – List the last 4 invoices submitted, to include invoice covering costs incurred during current reporting period and any additional invoices with outstanding issues.

5. ODCs – List the 4 most expensive ODCs for the reporting period.

– Categories include: LOCAL TRAVEL, LONG DISTANCE TRAVEL, SHIPPING, SUPPLIES, PARKING, PHONE, TRAINING, MISC

6. FTEs - List the total number of prime and subcontractor FTEs, contract definition of an FTE, FTEs removed, and FTEs added to the contract during this reporting period. The total number of FTEs is based on the total number of hours that equate to a FTE per the task order. An example is 1920 hours is one FTE.

7. CONTRACT FINANCIALS – Provide information as requested using the formulas provided. If prime contractor is a small business (SB), please document value and percentage of funded to include prime plus any SB subcontractors.

8. MONTHLY BUDGET - Provide information as requested using the format and formulas provided. Altering CST’s formulas is prohibited

- Any variance (+-) 10% must be explained at the bottom of the associated budget slide.

- The “type” field delineates CLIN type (example, FFP, T&M, CPFF, etc.)

- The information provided on the monthly budget slide should be consistent with the information provided on the following slides; Invoices Submitted (section 6), FTEs (section 7), Contract Financials Overview (section 8) and Contract Modification History (section 10)

9. CONTRACT MODIFICATION HISTORY – List all contract modifications and additional information as requested for the task order. Only display the contract modification history that support the current option period. For example, if the current year is option year one the Contractor shall display the modification history that supports option year one.

10. RISKS AND ISSUE LOG INSTRUCTIONS – See slide for details

11. RISK AND ISSUE LOG EXAMPLES – See slide for details

12. RISKS AND ISSUES – List all contractual risks, issues, and additional information as requested if additional space needed, please utilize the supporting MS Excel workbook.

13. DELIVERABLE/MILESTONE REPORTING – List current and projected Deliverables, Milestones, and/or Project End Dates. For each, provide the Baseline Completion Date, the

Current Projected or Actual Completion Date and the Period of Performance End Date.

14. KEY ACCOMPLISHMENTS– List up to 5 key accomplishments.

INSTRUCTIONS

3 Version 1.2

I certify that to the best of my knowledge and belief all of the information on this CSR deck is correct.

Contractor Program/Project Manager Date (Digital signature is acceptable, typed name is not acceptable.)

1. CSR ACKNOWLEDGEMENT OF ACCURACY:

4 Version 1.2

Invoice

Date Submitted to Vendor

Claims

Invoice

Number

Period

Covered

Submitted

Amount

Date

Payment

Received

Payment

Amount Comments

(Please list latest 4 invoices & any additional outstanding invoices) i.e. 6/1/2013

– 6/29/2013

2. CONTRACT SCOPE:

Requestor Date of Request to

COR

Description Status

Contract Scope: enter the scope of the contract per the Statement of Work

3. REQUEST FOR GOVERNMENT ACTION:

4. INVOICES SUBMITTED: (for costs incurred through current reporting period)

Name Category Amount

(Please list 4 most expensive)

5. ODCs INCURRED: (during current reporting period)

Data as of [MM/DD/YY]

5 Version 1.2

6. FTEs:

Data as of [MM/DD/YY] Instructions for FTEs

• If applicable, insert a new row for each subcontracting company, data may carry over to a new page.

• FTEs should be reported as outlined in contract, i.e. 1FTE = 1880, .5FTE = 940.

CONTRACT PERSONNEL (Added during current reporting period)

Contractor Employee Name Company Title/LCAT Start Date Remarks

<add rows as need>

*If FTE works between multiple CLINS, then list their title, LCAT Code and total.

Version 1.2

CONTRACT PERSONNEL (Removed when no longer supporting TO)

Contractor Employee Name Company Title/LCAT End Date Remarks

<add rows as need>

Title LCAT Code CLIN 1 CLIN2 CLIN3 CLIN4 Total

EXAMPLE: System Administrator 5807 0.35 0.35

<add rows as need>

<add rows as need>

<add rows as need>

Open Positions

Total (Prime + Subcontractors)

Subcontractor Counts (subset of total)

Contract Definition of an FTE (i.e. 1880 hrs. / 1920 hrs. per contract)

LABOR CATEGORIES NUMBER OF FTES

7. CONTRACT FINANCIALS OVERVIEW

TOTAL CONTRACT VALUE

Contract Type: ex. Firm-Fixed Price, Time and Materials

Contract Vehicle:

Contract Number:

Contract Period of Performance: (ex. Base + Options = 6/09 – 6/14)

Total Contract Award Value: (ex. Base + Options=$87M)

Total Contract Funded Value: (in dollars)

Total Contract Invoiced Value: (in dollars)

Total Small Business (SB) Subcontracted:

Value of invoices incurred to date by (SB) including prime when applicable. (in dollars)

Percent of funded SBs vice requirement (e.g. 50% attained vice 45% requirement)

CURRENT PERIOD OF PERFORMANCE

Contract Year: (ex. Option Year 4, Extension, Bridge)

Period of Performance: (ex. 6/01/13 – 6/01/14)

Period of Performance Budget at Completion (BAC):

(in dollars)

Period of Performance Funded Amount: (in dollars)

Date of Last Invoice Submission (for costs incurred through current period):

(ex. $10,000 as of 6/30/2013)

Actual Costs for Work Performed (ACWP) through last submitted invoice:

(in dollars) Costs incurred to date

Estimate to Complete (ETC): (in dollars)

Estimate At Completion (EAC): (in dollars)

ACWP + ETC

Funding Available/Shortfall (in dollars)

BAC – EAC

Contract Financials Instructions and Tips

Percent of funded SBs vice requirement

Total funding to SBs / total contract funding – compared to contract requirement for subcontracting to SBs.

Current Period of Performance Budget At Completion (BAC)

The total budget allocated to the project (project funding ceiling)

Current Period of Performance Actual Costs of Work Performed (ACWP)

Total costs incurred during the current Period of Performance.

Amounts incurred, but not invoiced should be included

Current Period of Performance Estimate To Complete (ETC)

The expected cost needed to complete all the remaining work for the project

Current Period of Performance Estimate At Completion (EAC)

The estimated cost at the end of the project

(ACWP + ETC)

Funding Available/Shortfall

(BAC – EAC)

Residual available funding should be displayed as a positive number – shortfall (in parenthesis)

8. MONTHLY BUDGET:

Instructions on CST Monthly Budget Calculations

• All contracts (including FFP) must use the grid and format to complete your monthly budget.

• Variance % = (Planned - Actual)/Planned

• At the bottom of slide, please provide an explanation for any variance totaling (+-)10%.

• If reporting FFP you may replace “Hrs” column heading with “Units”.

TASK NAME:

Hrs Cost Hrs Cost Hrs Cost Hrs Cost

Labor Category 1 Planned 0 $0

Actual/ETC 0 $0

Labor Category 2 Planned 0 $0

Actual/ETC 0 $0

Labor Category 3 Planned 0 $0

Actual/ETC 0 $0

Labor Category 4 Planned 0 $0

Actual/ETC 0 $0

Labor Category 5 Planned 0 $0

Actual/ETC 0 $0

Labor Category 6 Planned 0 $0

Actual/ETC 0 $0

SUBTOTALS Planned 0 $0 0 $0 0 $0 0 $0

Actual/ETC 0 $0 0 $0 0 $0 0 $0

Variance % #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!

ODCs Planned 0 $0

Actual/ETC 0 $0

LONG DISTANCE TRAVEL Planned 0 $0

Actual/ETC 0 $0

TOTALS Planned 0 $0 0 $0 0 $0 0 $0

Actual/ETC 0 $0 0 $0 0 $0 0 $0

Variance % #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!

* Cumulative = hours & costs to-date, not including current month

**Future = Projected hours & costs to end of POP (or end of contract or project)

$XXPREVIOUS FUNDING LEVEL:

FUNDS ADDED THIS PERIOD: $XX

NEW TOTAL: #VALUE!

Labor Category TYPE

(FFP, T&M, etc.)

CURRENT MONTH CUMULATIVE* FUTURE** AT COMPLETE

8 Version 1.2

EXPLANATION OF VARIANCE (+-10%)

9. CONTRACT MODIFICATION HISTORY:

Option Period

Option Period

Ceiling (and increases)

Option Period of

Performance Modification #

Date MOD

Issued Period MOD Covers MOD Amount Variance Comments

Base Year Base $0.00

MOO1 $0.00

MOO2 $0.00

MOOX $0.00

Sub Total $0.00 $0.00 $0.00

Option Period X MOOX $0.00

MOOX $0.00

Sub Total $0.00 $0.00 $0.00

Option Period X MOOX $0.00

MOOX $0.00

Sub Total $0.00 $0.00 $0.00

CONTRACT TOTAL $0.00 $0.00 $0.00

Instructions for Contract Modification History Please only list MODs for the current option period below.

Please include all MODs for the task order on the accompanying excel workbook.

9 Version 1.2

10. RISKS AND ISSUE LOG INSTRUCTIONS:

The Risk / Issue Log embedded within the CSR Slide Deck is meant to highlight any risks or issues that may impact the Contractual Team providing the data. All items identified in the Log should be risk/issues that affect the overall Performance, Level of Effort, Schedule, Facilities, or the Budget, for example, of the Contract, itself.

These are risks/issues that affect or impact the contract in its entirety. The column identifying ”Project/Release Number” remains on the log, in the case where a risk may impact the contract as a whole.

Under each column, on the Risk/Issue Log, are descriptions to better assist with what kind of information is required in that space.

If you have determined that there are no contractual risks to report for this period please write “No risks / issues” on the slide.

To further elaborate, please see below:

• Project Name and Release: If applicable, provide the project and/or release name in its entirety including all associated release numbers. Please spell out acronyms wherever possible.

• Date Risk / Issue Identified: Provide the date to which the risk listed was identified. In some cases, this may have been at project conception and in other cases it may have been identified as the project was being executed.

• Risk or Issue: Provide whether what has been identified is a risk or an issue. A risk is something that could potentially impact your project. An issue is something that is impacting your project currently.

• Risk Description (Name): The risk or issue should describe the root cause and overall impact. Use the industry standard, "if, then…" statement for risks and ensure that issues are written in the present or past tense. It is important that the information conveyed in this section is thorough and provides enough detail that CST personnel can completely understand the risk and its impact.

• Risk Realization Date: The point in time when the risk no longer exists or when the risk becomes an issue.

• Date Risk/Issue Closed: If this column does not have a date filled in, it is assumed the risk/issue is still open.

• Probability: The probability to which a risk may occur is dependent on many factors. The specific determination and attributed numerical value should be determined by the risk owner / or the person who identified the risk/issue.

• Impact: The impact of a risk becoming an issue is also dependent on many factors. Consideration should be taken for all the factors that could cause the risk to become an issue and to the level of impact that particular issue would have on the project.

• Mitigation: Provide a sequence of actions that must be taken to minimize or eliminate the risk probability. This should include actionable steps, with specific personnel identified and dates called out so mitigation can be tracked, identify the status of the risk/issue and its mitigation.

• Dependencies: Relationship between two activities, an activity and a milestone, processes, mandates or any other internal/external factor(s).

If you have any questions please contact the risk team via email at CA-CST-SSPM-Risks@state.gov.

10 Version 1.2 mailto:CA-CST-SSPM-Risks@state.gov mailto:CA-CST-SSPM-Risks@state.gov mailto:CA-CST-SSPM-Risks@state.gov mailto:CA-CST-SSPM-Risks@state.gov mailto:CA-CST-SSPM-Risks@state.gov mailto:CA-CST-SSPM-Risks@state.gov mailto:CA-CST-SSPM-Risks@state.gov

11. RISKS AND ISSUES EXAMPLES:

Project

Name &

Release #

Date Risk/

Issue

Identified

Risk or

Issue

Risk Description

(Name)

Risk Realization

Date

Date

Risk/Issue

Closed

Probability Impact Mitigation Dependencies

ACME 9/22/2014 Issue Because of the contract transitioning over to the ACME project, there is a need to obtain Fob's for after hour support and access to certain systems.

9/22/2014

5 3 Fill out FOB requests.

Obtain signatures for FOB requests Work with GTM to ensure access to FOBs.

Due Date 11/7/2014

XYZ 1/5/2015 Risk If OpenNet Access at the Team's facility could not be obtained, then the ability of team members to gain access to certain systems and content will be adversly impacted.

1/31/2015

3 2 Find an alternative location with

OpenNet access.

Access remotely via RSA Tokens.

Contractor PM and

GTM are working together to implement these steps.

Due date is

1/30/2015.

Security needs to come and inspect location

Probability Likelihood

1 Very low ~10%

2 Low ~30%

3 Medium ~50%

4 High ~70%

5 Very high ~90%

11 Version 1.2

Impact Impact

1 Minimal or no consequence to technical performance, schedule, or contractual obligations

2 Minor reduction in technical performance or supportability, can be tolerated with little or no impact on program. Able to meet key dates

3 Significant degradation in technical performance or major shortfall in supportability; may jeopardize program/project/system success. Key dates or milestones are affected

4 Severe degradation in technical performance; Cannot meet contractual requirements or key technical/supportability threshold; will jeopardize program/project/system success. Cannot met key dates or milestones

12. RISK/ISSUE LOG:

Probability Likelihood

1 Very low ~10%

2 Low ~30%

3 Medium ~50%

4 High ~70%

5 Very high ~90%

Impact Impact

1 Minimal or no consequence to technical performance, schedule, or contractual obligations

2 Minor reduction in technical performance or supportability, can be tolerated with little or no impact on program. Able to meet key dates

3 Significant degradation in technical performance or major shortfall in supportability; may jeopardize program/project/system success. Key dates or milestones are affected

4 Severe degradation in technical performance; Cannot meet contractual requirements or key technical/supportability threshold; will jeopardize program/project/system success. Cannot met key dates or milestones

Project

Name &

Release #

Date Risk/

Issue

Identified

Risk or

Issue

Risk Description

(Name)

Risk

Realization

Date

Date

Risk/Issue

Closed

Probability Impact Mitigation Dependencies

If applicable, provide the name of the

Project and the Release

Date risk or issue identified

Risk or

Issue

Provide the cause of the risk, and the effect the risk will have on your contract;

usually written as an "If…, Then…" statement

The point in time when the risk no longer exists or when the risk becomes a fact/issue, and the contract may have to be modified to accommodat e the negative consequence s

(MM/DD/YYY

Y)

The point in time when the risk/issue has been mitigated or has expired.

This is a point in time to which neither a risk nor an issue has any impact on a contract.

(MM/DD/YY

YY)

The likelihood that a risk will occur.

Reference

Probability

Table below.

(Scale 1-5;

Please refer to the

Scale listed in the

Probability

Table)

The impact on the project if a risk occurs.

Reference

Impact

Table below.

(Scale 1-

4; Please refer to the Scale listed in the Impact

Table)

Provide a sequence of actions that must be taken to minimize or eliminate the risk probability and impact, and it is the job of the action item owners to complete assigned actions

(Actionable

Step, Step

Owner, Due

Date)

Provide any relationships between two activities and/or milestones and how it affects the contract.

12 Version 1.2

13. MILESTONE REPORTING:

List Deliverables/Milestones/

Project Name

CST PM/GTM

Baseline

Completion Date

Projected/Actual

Completion Date

Period of

Performance End Date

Instructions for Milestone Reporting

• Please list current and projected (1 month) CST PM/GTM approved deliverables, milestones and projects, data may carry over to a new page.

13 Version 1.2

14. KEY ACCOMPLISHMENTS

ACCOMPLISHMENTS MONTH ACHIEVED

14 Version 1.2

Instructions for Key Accomplishments

• Please only list 5 key accomplishments.

• If applicable, per your contract, please include if you have submitted your monthly project metric report as a 6th accomplishment.