Sample_Change_Order.pdf

PDF 73 KB Posted

Attached to
South Cross Bayou Replacement of Generator Controls and Switchgear (GEN2) (PID 004906A) - STEP 1
Solicitation number
26-0256-ITB-C
Issued by
Pinellas County, Clewiston City, Florida

About this file

This is a Sample Change Order form from the Pinellas County Purchasing Department in Clearwater, Florida, designed for use in conjunction with the South Cross Bayou Replacement of Generator Controls and Switchgear project. The change order document provides a structured template for documenting modifications to the original contract, including provisions for additions and deletions to the scope of work with corresponding adjustments to the total agreement value. The form requires signature authorization from the contractor, the Investigator, the Director of Purchasing, the Office of County Attorney, and the Board of County Commissioners, with attestation by the Clerk, establishing a formal approval process for any contract modifications.

The change order form explicitly states that execution by the contractor constitutes a waiver of all claims or requests for additional time or compensation for any activities prior to the change order's execution date related to included items. The contractor acknowledges that payment authorized by the change order represents full and complete compensation for labor, materials, incidental expenses, overhead, profit, impact costs, and time associated with the work, with claim procedures outlined in the contract documents. The template includes line items for Fiscal Number, Change Order Number, Account Number, addition amounts, deletion amounts, and new total agreement value, providing a comprehensive mechanism for formal contract modifications within Pinellas County's procurement framework.

View the file

Other files

File Type Posted
South_Cross_Bayou_Replacement_of_Generator_Controls_and_Switchgear_(GEN2)_(PID_004906A)_-_STEP_1_(Addendum_#1_Revision).pdf PDF
South_Cross_Bayou_Replacement_of_Generator_Controls_and_Switchgear_(GEN2)_(PID_004906A)_-_STEP_1.pdf PDF
Appendix_4_-_Special_Notice.pdf PDF
SCB_AWRF_Generator_Controls_&_Switchgear_Replacement_S&S_11x17_Drawings_09-10-25.pdf PDF
26-0256-ITB-C_Pricing_Proposal_(for_reference_only).pdf PDF
26-0256_-_Insurance_Requirements_-_South_Cross_Bayou_Replacement_of_Generator_and_Switchgear.docx DOCX document
26-0256_Sample_P&P_Bonds.pdf PDF
E-Verify_Affidavit.pdf PDF
Affdavit_of_Release_and_Guarantee.pdf PDF
APPENDIX_7_-_SBE_COMPLIANCE_FORM.pdf PDF
Florida_Trench_Safety_Form.pdf PDF
26-0256-ITB-C_Sample_Construction_Agreement.pdf PDF
Switchgear_Map_location.pdf PDF
SCB_AWRF_Generator_Controls_&_Switchgear_Replacement_Revised_Specs_04-29-25_(2).pdf PDF
QUALIFICATION_SUBMITTAL_FORM_8-25.pdf PDF
Sample_Application_for_Payment.pdf PDF
OpenGov_Fillable-_Final.pdf PDF
Airport_Security_Program.pdf PDF
Notice_of_Intent_to_Sole_Source_07-25-2023.pdf PDF
Non-Competitive_Oversight_Committee_Justification_Form.docx DOCX document
SCB_AWRF_SBE_Memo_03-24-23.pdf PDF
Bid_Submittal_Form-JOC.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX 2 – SAMPLE CHANGE ORDER

APPENDIX 2 – SAMPLE CHANGE ORDER

SAMPLE CHANGE ORDER

PINELLAS COUNTY PURCHASING DEPARTMENT

CLEARWATER, FLORIDA

FISCAL NO. CHANGE ORDER NO.

ACCOUNT NO.

TO Total Agreement $

FOR Addition $

IN CONNECTION WITH New Total $

Deletion $

New Total Agreement $

Execution by the contractor of this Change Order shall be considered a waiver of all claims or request for additional time or compensation for any activities prior to time of execution related to items included in the Change Order. The contractor also acknowledges that payment authorized by this Change Order represents full and complete compensation for labor, materials, incidental expenses, overhead profit, impact cost, and time associated with this Work. Claim procedures are outlined in the Contract documents.

Investigator

Director of Purchasing APPROVED AS TO FORM: Accepted this day of

OFFICE OF COUNTY ATTORNEY 20

By PINELLAS COUNTY Attorney BOARD OF COUNTY COMMISSIONERS

By Chairman

Attest: KEN BURKE, CLERK By

Deputy Clerk

Use Authorized Signatures Only Company

By Title

Witness