S02. Specs Vol 1.pdf
PDF 2 MB Posted
- Attached to
- Y1DA--RENOVATE RADIATION THERAPY Federal contract opportunity
- Solicitation number
- 36C25021B0003_1
About this file
This solicitation is for the renovation of the Radiation Therapy department at the Louis Stokes Cleveland VA Medical Center. The project scope involves renovating 5,000 square feet in the basement to create additional exam rooms and dressing areas by reconfiguring the existing suite as well as updating infrastructure. Offerors should provide pricing to complete mechanical, electrical and architectural construction work. The performance period is TBD with an anticipated completion date in 2022. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 10 is listed as the contracting agency.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| S02. Solicitation 36C25021B0003_1.pdf | ||
| S02. Specs Vol 2.pdf | ||
| S02. JA Sole Source - Russwin_Redacted.pdf | ||
| S02. JA Sole Source - Notifier Fire Alarm_Redacted.pdf | ||
| S02. JA Sole Source - Hill-Rom_Redacted.pdf | ||
| S02. Brand Name or Equal Memo.pdf | ||
| S02. Site Visit Information.pdf | ||
| S02. Calculation of Self-Performed and Sub-Contracted Work.pdf | ||
| S02. JA Sole Source - Lenel_Redacted.pdf | ||
| S02. RFI Form.pdf | ||
| S02. Drawings_FINAL CD SET.pdf | ||
| S02. Safety.pdf | ||
| S02. Wage Determination.pdf | ||
| S02. Bid Opening Instructions.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL SPECIFICATIONS
Department of Veterans Affairs Louis Stokes Cleveland VA Medical Center
10701 East Boulevard Cleveland, OH 44106
RENOVATE RADIATION THERAPY
Project No. 541-20-102
PREPARED BY:
Perspectus Architecture Fredrick, Fredrick & Heller Engineers 13212 Shaker Square 672 East Royalton Road Cleveland, Ohio 44120 Broadview Heights, Ohio 44147 P (216) 752-1800 P (440) 546-9696 Project Director: Tim Huffman Project Director: Michael Long
FINAL CONSTRUCTION DOCUMENTS SUBMISSION
VOLUME 1 OF 2
ISSUE DATE: 08/14/2020
Louis Stokes Cleveland VA Medical Center 01-01-20 Renovate Radiation Therapy
Table of Contents 00 01 10-1
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
Volume 1
DIVISION 00 - SPECIAL SECTIONS
00 01 10 Table of Contents 01-20 00 01 15 List of Drawing Sheets 07-15
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 03-20 01 32 16.15 Project Schedules 03-20 01 33 23 Shop Drawings, Product Data, and Samples 06-17 01 35 26 Safety Requirements 03-20 01 42 19 Reference Standards 05-16 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 09-13 01 81 13 Sustainable Construction Requirements 10-17 01 91 00 General Commissioning Requirements 10-15
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
DIVISION 03 – CONCRETE
Not Used
DIVISION 04 – MASONRY
Not Used
DIVISION 05 – METALS
05 50 00 Metal Fabrications 08-18 05 73 00 Decorative Metal Railings ---
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17 06 20 00 Finish Carpentry & Millwork 08-16
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 13 Thermal Insulation 10-17 07 84 00 Firestopping 02-16 07 92 00 Joint Sealants 10-17
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 08-16 08 14 00 Interior Wood Doors 08-16 08 31 13 Access Doors and Frames 02-16 08 51 13 Aluminum Windows 08-16 08 71 00 Door Hardware 01-20 08 71 13 Automatic Door Operators 02-16 08 80 00 Glazing 08-16
00 01 10-2
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 08-16 09 22 16 Non-Structural Metal Framing 08-16 09 29 00 Gypsum Board 08-16 09 30 13 Ceramic/Porcelain Tiling 08-16 09 51 00 Acoustical Ceilings 08-16 09 65 13 Resilient Base and Accessories 08-16 09 65 19 Resilient Tile Flooring 08-16 09 91 00 Painting 08-16
DIVISION 10 – SPECIALTIES
10 26 00 Wall and Door Protection 08-16 10 28 00 Toilet, Bath, and Laundry Accessories 08-16 10 44 13 Fire Extinguisher Cabinets 08-18 10 51 13 Metal Lockers ---
DIVISION 11 – EQUIPMENT
Not Used
DIVISION 12 – FURNISHINGS
12 36 61.19 Quartz Agglomerate Countertops ---
DIVISION 13 - SPECIAL CONSTRUCTION
Not Used
DIVISION 14– CONVEYING EQUIPEMENT
Not Used
Volume 2
DIVISION 21- FIRE SUPPRESSION
21 08 00 Commissioning of Fire Suppression System 06-16 21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 07-16 22 05 23 General-Duty Valves for Plumbing Piping 09-15 22 07 11 Plumbing Insulation 09-19 22 08 00 Commissioning of Plumbing Systems 11-16 22 11 00 Facility Water Distribution 11-19 22 13 00 Facility Sanitary and Vent Piping 09-15 22 40 00 Plumbing Fixtures 09-15 22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 09-15 22 63 00 Gas Systems for Laboratory and Healthcare Facilities 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING
(HVAC)
23 05 11 Common Work Results for HVAC 08-17 23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15 23 07 11 HVAC and Boiler Plant Insulation 02-15 23 08 00 Commissioning of HVAC Systems 11-16
00 01 10-3
SECTION NO. DIVISION AND SECTION TITLES DATE
23 09 23 Direct-Digital Control System for HVAC 09-11 23 21 13 Hydronic Piping 08-17 23 22 13 Steam and Condensate Heating Piping 08-17 23 31 00 HVAC Ducts and Casings 03-13 23 36 00 Air Terminal Units 02-15 23 37 00 Air Outlets and Inlets 02-15 23 83 00 UVC Emitters 4-11
DIVISION 25 – INTEGRATED AUTOMATION
25 09 00 Systems Integration
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 05-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 05 73 Overcurrent Protective Device Coordination Study 01-18 26 08 00 Commissioning of Electrical Systems 11-16 26 09 23 Lighting Controls 01-18 26 27 26 Wiring Devices 01-18 26 29 11 Motor Controllers 01-18 26 29 21 Enclosed Switches and Circuit Breakers 12-12 26 51 00 Interior Lighting 01-18
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 06-15 27 05 26 Grounding and Bonding for Communications Systems 06-15 27 05 33 Raceways and Boxes for Communications Systems 10-18 27 08 00 Commissioning of Communications Systems 11-16 27 15 00 Communications Structured Cabling 05-16 27 41 31 Master Antenna Television Equipment and Systems 06-15 27 52 23 Nurse Call and Code Blue Systems 10-18
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18 28 05 13 Conductors and Cables for Electronic Safety and Security 10-18 28 05 26 Grounding and Bonding for Electronic Safety and Security 09-11 28 05 28.33 Conduits and Backboxes for Electronic Safety and Security 09-11 28 08 00 Commissioning of Electronic Safety and Security Systems 11-16 28 13 00 Physical Access Control System 10-11 28 23 00 Video Surveillance 09-11 28 31 00 Fire Detection and Alarm 10-11
DIVISION 31 – EARTHWORK
Not Used
DIVISION 32 – EXTERIOR IMPROVEMENTS
Not Used
00 01 10-4
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 33 – UTILITIES
Not Used
DIVISION 34 – TRANSPORTATION
Not Used
DIVISION 48 – Electrical Power Generation Not Used
- - - E N D - - -
Louis Stokes Cleveland VA Medical Center 07-01-15
List of Drawing Sheets 00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
DRAWING NO. TITLE
GENERAL
G-001 COVER SHEET
G-002 GENERAL INFORMATION
G-101 PARTIAL BASEMENT PHASING PLANS
G-102 PARTIAL BASEMENT LIFE SAFETY PLANS
ARCHITECTURAL
A-101 PARTIAL BASEMENT DEMOLITION PLANS
A-102 PARTIAL BASEMENT FLOOR PLANS
A-103 PARTIAL BASEMENT REFLECTED CEILING PLANS
A-401 INTERIOR ELEVATIONS
A-501 MILLWORK DETAILS
A-601 SCHEDULES AND DETAILS
INTERIOR
I-101 PARTIAL BASEMENT FLOOR FINISH PLAN
I-102 PARTIAL BASEMENT WALL FINISH PLAN
I-601 FINISH SCHEDULE, LEGEND & DETAILS
FIRE PROTECTION
FX-001 FIRE SUPRESSION LEGEND AND GENERAL NOTES
FX-101 PARTIAL BASEMENT FIRE SUPRESSION PLANS
MECHANICAL
M-001 HVAC LEGEND AND GENERAL NOTES
M-002 AIR BALANCE CRITERIA
MD-101 PARTIAL BASEMENT HVAC DUCTWORK DEMOLITION PLANS
MD-111 PARTIAL BASEMENT HVAC PIPING DEMOLITION PLANS
MH-101 PARTIAL BASEMENT DUCTWORK PLANS
MH-102 PARTIAL SECOND FLOOR ROOF MECHANICAL PLAN
MP-111 PARTIAL BASEMENT HVAC PIPING PLANS
M-501 HVAC DETAILS
M-601 HVAC SCHEDULES
M-701 HVAC CONTROLS
M-702 HVAC CONTROLS
M-801 PARTIAL BASEMENT AIR BALANCE PLAN
PLUMBING
Louis Stokes Cleveland VA Medical Center 07-01-15
List of Drawing Sheets 00 01 15 - 2
P-001 PLUMBING AND MEDICAL GAS LEGEND AND GENERAL NOTES
PD-101 PARTIAL UNDERGROUND PLUMBING DEMOLITION PLANS
PD-102 PARTIAL BASEMENT PLUMBING DEMOLITION PLANS
PD-111 PARTIAL BASEMENT MEDICAL GAS DEMOLITION PLANS
PL-101 PARTIAL UNDERGROUND PLUMBING PLANS
PL-102 PARTIAL BASEMENT PLUMBING PLANS
PG-111 PARTIAL BASEMENT MEDICAL GAS PLANS
P-501 PLUMBING AND MEDICAL GAS DETAILS
P-601 PLUMBING AND MEDICAL GAS SCHEDULES AND ISOMETRICS
ELECTRICAL
E-001 ELECTRICAL LEGEND AND GENERAL NOTES
E-002 PARTIAL BASEMENT ELECTRICAL AND TECHNOLOGY KEY PLAN
ED-101 PARTIAL BASEMENT LIGHTING DEMOLITION PLANS
ED-111 PARTIAL BASEMENT POWER DEMOLITION PLANS
ED-121 PARTIAL BASEMENT FA AND SECURITY DEMOLITION
EL-101 PARTIAL BASEMENT LIGHTING PLANS
EP-111 PARTIAL BASEMENT POWER PLANS
EP-121 PARTIAL SECOND FLOOR ROOF ELECTRICAL PLAN
EY-121 PARTIAL BASEMENT FIRE ALARM AND SECURITY PLANS
E-501 ELECTRICAL DETAILS
E-502 ACCESS CONTROL RISER AND DOOR DETAILS
E-503 FIRE ALARM RISER DIAGRAM
E-504 FIRE ALARM DETAILS
E-601 LIGHTING FIXTURE SCHEDULE
E-602 PANELBOARD SCHEDULE
TECHNOLOGY
T-001 TECHNOLOGY LEGEND AND GENERAL NOTES
TD-101 PARTIAL BASEMENT TECHNOLOGY DEMOLITION PLANS
T-101 PARTIAL BASEMENT TECHNOLOGY PLANS
T-501 TECHNOLOGY DETAILS
T-502 TECHNOLOGY DETAILS
- - - END - - -
Louis Stokes Cleveland VA Medical Center 03-01-20
Project No. 541-20-102
General Requirements i
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
1.9 RESTORATION
1.10 LAYOUT OF WORK
1.11 AS-BUILT DRAWINGS
1.12 USE OF ROADWAYS
1.13 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.14 TEMPORARY USE OF EXISTING ELEVATORS
1.15 TEMPORARY TOILETS
1.16 AVAILABILITY AND USE OF UTILITY SERVICES
1.17 NEW TELEPHONE EQUIPMENT
1.18 TESTS
1.19 INSTRUCTIONS
1.20 GOVERNMENT-FURNISHED PROPERTY
ATTACHMENTS
OSHA Requirements and Safety and Health Regulations - Attachment 1
Pre-Construction Risk Assessment (PCRA) - Attachment 2
Construction Safety Poster - Cleveland VA - Attachment 3
Interim Life Safety Risk Assessment Form - Attachment 4
Project No. 541-20-102
General Requirements ii
Contractor Safety and Security Orientation - Attachment 5
Job Safety Check Sheet - Attachment 6
General Requirements and
OSHA Requirements and Safety and Health Regulations
01 00 00 - 1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to Section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Project Description: This is a multi‐phased Project that will renovate
5,000 square feet of the Radiation Therapy Department in the Basement.
Project will create additional exam rooms and dressing areas by reconfiguring the existing suite as well as updating infrastructure.
1. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Renovate Radiation Therapy as required by Drawings and Specifications.
B. Visits to the site by Bidders may be made only by appointment with the
Contracting Officer Representative (COR).
C. Offices of Perspectus Architecture and Fredrick, Fredrick and Heller
Engineers, as Architect-Engineers, will render certain technical services during Construction. Such services shall be considered as advisory to the
Government and shall not be construed as expressing or implying a
Contractual act of the Government without affirmations by COR.
D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three (3) work days unless otherwise designated by the COR.
E. All employees of General Contractor and Subcontractors shall comply with
VA security management program and obtain permission of the VA police, be identified by Project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. General Contractor shall refer to solicitation for Bid Item Descriptions.
01 00 00 - 2
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. AFTER AWARD OF CONTRACT, zero (0) sets of Specifications and Drawings will be furnished.
B. Drawings and Contract Documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the
Project.
2. The General Contractor is responsible for assuring that all Sub-contractors working on the Project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the Project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the Project site.
2. Before starting work the General Contractor shall give one week’s notice to the COR so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this Section.
3. No photography of VA premises is allowed without written permission of the COR.
4. VA reserves the right to close down or shut down the Project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the COR.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock
01 00 00 - 3 combinations to the COR for the purpose of security inspections of every area of Project including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71 00, DOOR HARDWARE and coordinate.
D. Document Control:
1. Before starting any work, the General Contractor/Subcontractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
2. The General Contractor is responsible for safekeeping of all Drawings, Project Manual and other Project information. This information shall be shared only with those with a specific need to accomplish the
Project.
3. Certain documents, sketches, videos or photographs and Drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the Project. Return the information to the COR upon request.
4. These security documents shall not be removed or transmitted from the
Project site without the written approval of COR.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify COR and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all Project Drawings, both scanned and electronic shall be performed and tracked through the
01 00 00 - 4
EDMS system.
b. “Sensitive information” including Drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
F. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of (2 to 5) permits shall be issued for General
Contractor and its employees for parking in designated areas only.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the
COR. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the
Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the COR and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the
Contractor at its expense upon completion of the work. With the written consent of the COR, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the COR use only established roadways, or use temporary roadways constructed by the
Contractor when and as authorized by the COR. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them
01 00 00 - 5 from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by the COR.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during Construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by
COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate Construction working areas within buildings in use by Department of Veterans
Affairs in quantities sufficient for not more than two (2)work days.
Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
G. Phasing:
The Medical Center must maintain its operation 24 hours a day, 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and Schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a Schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
01 00 00 - 6
To ensure such executions, Contractor shall furnish the COR with a
Schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to
COR and Contractor, as indicated on Drawings.
H. The Building will be occupied during performance of work; but immediate areas of alterations will be vacated. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of Construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to
Department of Veterans Affairs personnel and patients through other
Construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the Construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access.
Coordinate alteration work in areas occupied by Department of Veterans
Affairs so that Medical Center operations will continue during the
Construction period.
I. When a building and/or Construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
01 00 00 - 7
Contractor's employee or watchman.
K. Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to individual Electrical Specification Sections for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a Contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in
01 00 00 - 8 writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the Construction
Project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
M. To minimize interference of construction activities with flow of Medical
Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
N. Coordinate the work for this Contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by COR. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.
01 00 00 - 9
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by Drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with
Specifications which will be furnished by Government. Provided the
Contract work is changed by reason of this subparagraph B, the Contract will be modified accordingly, under provisions of clause entitled
"DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workers in executing work of this Contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing
01 00 00 - 10 structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this Contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during Contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the COR.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the
Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this Contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the COR may have the necessary work performed and charge the cost to the Contractor.
(FAR 52.236-9)
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning
01 00 00 - 11 repair of damage to structures and site improvements.
D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge
Elimination System (NPDES) permit is required for this Project. The
Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate medical center) office.
The apparent low bidder, Contractor and affected Subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing Construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
- Designating areas for equipment maintenance and repair;
- Providing waste receptacles at convenient locations and provide regular collection of wastes;
- Locating equipment wash down areas on site, and provide appropriate control of wash-waters;
- Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and
- Providing adequately maintained sanitary facilities.
1.9 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR.
Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed.
Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing Construction, except as
01 00 00 - 12 otherwise shown or specified.
B. Upon completion of Contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to Contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-
4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
1.10 LAYOUT OF WORK
A. The Contractor shall lay out the work indicated on the drawings and shall be responsible for all measurements in connection with the layout. The
Contractor shall furnish, at Contractor's own expense, all templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the
COR. The Contractor shall also be responsible for maintaining and preserving all marks established by the COR until authorized to remove them. If such marks are destroyed by the Contractor or through
Contractor's negligence before their removal is authorized, the COR may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
B. Establish and plainly mark lines for each partition and such other lines that are reasonably necessary to properly assure that location, orientation, and elevations established are in accordance with lines and elevations shown on Contract Drawings.
01 00 00 - 13
1.11 AS-BUILT DRAWINGS
A. The Contractor shall maintain two full size sets of as-built Drawings which will be kept current during Construction of the Project, to include all Contract changes, modifications, and clarifications.
B. All variations shall be shown in the same general detail as used in the
Contract Drawings. To ensure compliance, As-Built Drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built Drawings in the electronic version (scanned PDF) to the COR within fifteen (15) calendar days after each completed phase and after the acceptance of the
Project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.12 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center property and, when authorized by the COR such temporary roads which are necessary in the performance of Contract work. Temporary roads shall be re-constructed and restoration performed by the Contractor at
Contractor's expense. When necessary to cross curbing, sidewalks, or similar Construction, they must be protected by well-constructed bridges.
B. When new permanent roads are to be a part of this Contract, Contractor may construct them immediately for use to facilitate building operations.
These roads may be used by all who have business thereon within zone of building operations.
C. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads leading thereto must be completed and available for use at time set for completion of such buildings or parts thereof.
1.13 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by COR in writing.
01 00 00 - 14
If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the Drawings and Specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.
Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014 Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned. Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of Construction and prior to testing and balancing of system.
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at
01 00 00 - 15 no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical Specifications Sections.
D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the Contractor at the Contractor’s expense.
1.14 TEMPORARY USE OF EXISTING ELEVATORS
A. Contractor will not be allowed the use of existing elevators. Outside type hoist shall be used by Contractor for transporting materials and equipment.
1.15 TEMPORARY TOILETS
A. Contractor may have for use of Contractor's workers, such toilet accommodations as may be assigned to Contractor by Medical Center.
Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workers. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.
1.16 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the Contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the COR, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
C. Contractor shall install meters at Contractor's expense and furnish the
01 00 00 - 16
Medical Center a monthly record of the Contractor's usage of electricity as hereinafter specified.
D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:
1. Obtain heat by connecting to Medical Center heating distribution system.
E. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.
F. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the Contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR discretion) of use of water from Medical
Center's system.
G. Fuel: Natural and LP gas and burner fuel oil required for boiler cleaning, normal initial boiler-burner setup and adjusting, and for performing the specified boiler tests will be furnished by the
Government. Fuel required for prolonged boiler-burner setup, adjustments, or modifications due to improper design or operation of boiler, burner, or control devices shall be furnished and paid by the Contractor at
Contractor's expense.
01 00 00 - 17
1.17 NEW TELEPHONE EQUIPMENT
The Contractor shall coordinate with the work of installation of telephone equipment by others. This work shall be completed before the building is turned over to VA.
1.18 TESTS
A. As per Specification Section 23 05 93 the Contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a Schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The Contractor shall document the results of the approved plan and submit for approval with the as built documentation.
B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.
C. Conduct final tests required in various Sections of Specifications in presence of an authorized representative of the COR. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
D. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, exhaust air, steam, chilled water, refrigerant, hot water, controls and electricity, etc. Another example of a system which involves several components of different disciplines is a boiler installation. Efficient and acceptable boiler operation depends upon the coordination and proper operation of fuel, combustion air, controls, steam, feedwater, condensate and other related components.
01 00 00 - 18
E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably period of time during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.
F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.19 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various
Sections of the Specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item.
Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned
Department of Veterans Affairs personnel in the operation and complete
01 00 00 - 19 maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical Sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed. This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The Contractor shall submit a course outline with associated material to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the Contractual requirements. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
1.20 GOVERNMENT-FURNISHED PROPERTY
A. The Government shall deliver to the Contractor, the Government-furnished property shown on the Drawings.
B. Equipment furnished by Government to be installed by Contractor will be furnished to Contractor at the Medical Center.
C. Storage space for equipment will be provided by the Government and the
Contractor shall be prepared to unload and store such equipment therein upon its receipt at the Medical Center.
D. Notify COR in writing, 60 days in advance, of date on which Contractor will be prepared to receive equipment furnished by Government.
Arrangements will then be made by the Government for delivery of equipment.
1. Immediately upon delivery of equipment, Contractor shall arrange for a joint inspection thereof with a representative of the Government. At such time the Contractor shall acknowledge receipt of equipment
01 00 00 - 20 described, make notations, and immediately furnish the Government representative with a written statement as to its condition or shortages.
2. Contractor thereafter is responsible for such equipment until such time as acceptance of Contract work is made by the Government.
E. Equipment furnished by the Government will be delivered in a partially assembled (knock down) condition in accordance with existing standard commercial practices, complete with all fittings, fastenings, and appliances necessary for connections to respective services installed under Contract. All fittings and appliances (i.e., couplings, ells, tees, nipples, piping, conduits, cables, and the like) necessary to make the connection between the Government furnished equipment item and the utility stub-up shall be furnished and installed by the Contractor at no additional cost to the Government.
F. Completely assemble and install the Government furnished equipment in place ready for proper operation in accordance with Specifications and
Drawings.
G. Furnish supervision of installation of equipment at Construction site by qualified factory trained technicians regularly employed by the equipment manufacturer.
01 00 00 - 21
Attachment 1
PART 1 - OSHA Requirements
1.1 General
A. Contractors are required to comply with the Occupational Safety and Health Act of
1970. This will include the safety and health standard found in Code of Federal Regulations
(CFR) 1910 and 1926. Copies of those standards can be obtained from the Superintendent of Documents, U.S. Government Printing Office, Washington, D.C., 20420.
B. In addition, Contractor will be required to comply with other applicable Medical Center policies and safety regulations. These policies and regulations will be presented to the
Contractor at the pre-construction meeting. Each of the Contractor’s employees will be required to read the statement of policies and regulations, and sign an acknowledgment that such policies and regulations are understood. Signed acknowledgment will be returned to the Contract Officer Technical Representative.
C. Contractors involved with the removal, alteration or disturbance of asbestos-type insulation or materials or lead paint will be required to comply strictly with the regulations found in
CFR 1910.1001 and the appropriate Environmental Protection Agency (EPA) lead regulations regarding disposal of asbestos or lead paint. Assistance in identifying asbestos or lead can be requested from the Medical Center’s Industrial Hygienist and the COR.
D. Contractors entering locations of asbestos contamination or lead paint residue (i.e., pipe, basements, walls, windows) shall be responsible for providing respiratory protection to their employees and ensuring respirators are worn in accordance with the Occupational Safety and Health Administration (OSHA) [CFR 1910.1001(g)]. Asbestos-or lead paint-contaminated areas shall be defined on Project Drawings.