S02 Attachment B Drawings Part 1.pdf

PDF 10 MB Posted

Attached to
Z2DA--691A4-20-201 Electronic Health Records Modernization (EHRM) Infrastructure Upgrades
Solicitation number
36C26221B0008_1
Issued by

About this file

This notice announces a forthcoming solicitation for construction services. The Department of Veterans Affairs seeks to upgrade infrastructure at the VA Sepulveda Ambulatory Care Center in preparation for an electronic health records modernization project. Work includes general construction, alterations, mechanical, electrical and utility systems work. The project value is estimated between $10-20 million. The solicitation will be set aside for Service-Disabled Veteran-Owned Small Businesses and issued on June 23rd via beta.sam.gov. A site visit will be scheduled. Interested firms must be verified in VIP. The North American Industry Classification Code is 236220 and the size standard is $39.5 million. The point of contact is James Barber at james.barber@va.gov.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AREA OF WORK

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Fi le

P at h U.S. Department of Veterans Affairs

B

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions: Date:

691A4-20-201FINAL CONSTRUCTION

DOCUMENTS

May 17, 2021 MS TS / JM

FULLY SPRINKLERED

A

ARCHITECT/ENGINEER OF RECORD

C

D

1611 PLUMMER ST, NORTH HILLS, CA, 91343

20801.13

Electronic Health Records Modernization (EHRM) Infrastructure Upgrades - Sepulveda, CA

GI001

TITLE SHEET

ELECTRONIC HEALTH RECORDS MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES - SEPULVEDA, CA

THE INTENT OF THIS PROJECT IS TO PROVIDE INFRASTRUCTURE IMPROVEMENTS TO PREPARE FOR VA

SYSTEMS ENGINEERING SOLUTION CERNER DEVELOPMENT AND ELECTRONIC HEALTH RECORD

MODERNIZATION (EHRM) IMPLEMENTATION. LOCATIONS CONSIST OF THE FOLLOWING BUILDINGS: 1, 4, 10, 20, 22, 23, 24, 25, 45, 63, 70, 99, 200, AND 201 AT THE VA SEPULVEDA AMBULATORY CARE CENTER (SACC) CAMPUS.

THE PROJECT INVOLVES THE RENOVATION OF PORTIONS OF THE EXISTING BUILDINGS' INFRASTRUCTURE AND SYSTEMS AND REQUIRES THOROUGH SURVEY AND PREPARATION OF COMPREHENSIVE AND DETAILED SHOP DRAWINGS BY THE CONTRACTOR. THE PROJECT INCLUDES UPGRADING EXISTING VERTICAL AND HORIZONTAL FIBER BACKBONE SYSTEMS TO TELECOM ROOMS (TRS) WITHIN THESE BUILDINGS AND UPGRADING FIBER DISTRIBUTION IN MANHOLE COMMUNICATION DUCT BANKS THROUGHOUT THE VA SACC CAMPUS. THE PROJECT PROVIDES UPGRADES FOR TRS INCLUDING ARCHITECTURAL, MECHANICAL HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC) SYSTEMS, LIGHT-EMITTING DIODE (LED) LIGHTING, ELECTRICAL POWER, DATA RACKS, POWER DISTRIBUTION UNITS (PDU), UNINTERRUPTIBLE POWER SUPPLIES (UPS), AND

TELECOMMUNICATION CABLE MANAGEMENT SYSTEMS.

NORTH

VA SEPULVEDA HEALTHCARE SYSTEM

EHRM INFRASTRUCTURE UPGRADE

KEY PLANVICINITY MAP

NORTH

SCOPE OF WORK GENERAL NOTES

APPLICABLE CODES

1. FIREPROOFING TO BE REMOVED AND REPLACED IN KIND AS REQUIRED FOR ATTACHMENTS TO

EXISTING STRUCTURE. NEW FIREPROOFING REQUIRES SPECIAL INSPECTION PER IBC 1705.14

2. FIELD VERIFY ALL EXISTING CONDITIONS INCLUDING STRUCTURAL, MECHANICAL, PLUMBING, ELECTRICAL, TELECOM, EQUIPMENT, AND OTHER EXISTING SYSTEMS. MAKE NECESSARY PROVISIONS TO MAINTAIN THE INTEGRITY OF EXISTING SYSTEMS PRIOR TO THE COMMENCEMENT OF DEMOLITION.

3. COORDINATE PHASING OF ALL DEMOLITION AND NEW WORK WITH OTHER TRADES. REVIEW

RENOVATION DRAWINGS TO VERIFY AND DETERMINE THE EXTENT OF, AND SCHEDULING FOR, ALL

DEMOLITION PRIOR TO PERFORMING ANY WORK.

4. FIELD VERIFY ALL SIZES, LOCATIONS, AND ROUTING OF EXISTING ITEMS TO REMAIN AND OF NEW WORK INDICATED ON THE PLANS. NOTIFY THE VA OF ANY DEVIATIONS WHICH MAY AFFECT RENOVATION

WORK OR SYSTEM OPERATION PRIOR TO PROCEEDING WITH THE WORK.

5. PROVIDE AN ALLOWANCE FOR TEMPORARY RELOCATION OF EXISTING ANCHORED/UNANCHORED AND

POWERED/UNPOWERED EQUIPMENT AND FURNITURE TO INSTALL EUDS PROVIDED UNDER THIS

PROJECT. ALLOWANCE SHALL INCLUDE 400 INSTANCES.

PROJECT NOTES

BUILDING 1

BUILDING

BUILDING

BUILDING 24

BUILDING 22

BUILDING 63

BUILDING 45

BUILDING 25

BUILDING 23

BUILDING 10

BUILDING 20

BUILDING 99

BUILDING 70

BUILDING 4

VA STANDARDS FOR CONSTRUCTION: COMPLY WITH THE VA OFFICE OF CONSTRUCTION & FACILITY

MANAGEMENT TECHNICAL INFORMATION LIBRARY (TIL) INCLUDING BUT NOT LIMITED TO:

VA INFRASTRUCTURE STANDARD FOR TELECOMMUNICATIONS SPACES VERSION 3.0, 2020.

VA HANDBOOK H-18-8, SEISMIC DESIGN REQUIREMENTS

VA SPACE AND FACILITY PLANNING (PG-18-9) (HANDBOOK 7610)

VA DESIGN MANUALS (PG-18-10)

VA DESIGN GUIDES (PG-18-12)

VA ACCESSIBILITY (PG-18-13)

VA ROOM FINISHES, DOOR, & HARDWARE SCHEDULE (PG-18-14)

VA OFFICE OF FACILITIES MANAGEMENT CITATIONS OF THE AIA DESIGN STANDARDS

VAMC SPECIFICATIONS.

INTERNATIONAL CODES:

INTERNATIONAL BUILDING CODES - 2018

INTERNATIONAL MECHANICAL CODE - 2018

INTERNATIONAL ELECTRICAL CODE - 2018

INTERNATIONAL PLUMBING CODE - 2018

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 13 - 2019

NFPA 70 - 2020

NFPA 75 - 2018

NFPA 90A - 2021

NFPA 99 - 2018

NFPA 101 - 2018

SMACNA, SEISMIC RESTRAINT MANUAL GUIDELINES FOR MECHANICAL SYSTEMS

NATIONAL UNIFORM SEISMIC INSTALLATION GUIDELINES (AEIC EDITION)

CALIFORNIA CODE OF REGULATIONS, TITLE 24, PART 9, THE CALIFORNIA FIRE CODE

ARCHITECTURAL BARRIERS ACT ACCESSIBILITY STANDARDS (ABAAS), 2011

OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA)

NATIONAL ELECTRICAL MANUFACTURER'S ASSOCIATION (NEMA)

INSTITUTE OF ELECTRICAL AND ELECTRONIC ENGINEERS (IEEE)

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

UNDERWRITERS LABORATORIES, INC. (UL)

ASHRAE, STANDARD 62.1 - VENTILATION FOR ACCEPTABLE INDOOR AIR QUALITY.

ACI 318-14 BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE

AISC 360-10 SPECIFICATION FOR STRUCTURAL STEEL BUILDINGS

ASCE 7-16 MINIMUM DESIGN LOADS FOR BUILDINGS AND OTHER STRUCTURES

INSULATED POWER CABLE ENGINEERS' ASSOCIATION (IPCEA).

EIA/ECA 310-E DATA EQUIPMENT RACKS,

EIA/TIA STANDARDS

IES LIGHTING STANDARDS

1. CONSTRUCTION SHALL BE PERFORMED IN ACCORDANCE WITH THE CODES. BE

FAMILIAR WITH ALL CODES AND ORDINANCES, CITY OR STATE, AS REQUIRED FOR THE

CONSTRUCTION OF THIS PROJECT. WHERE ANY CONFLICTS OCCUR BETWEEN

FEDERAL, STATE AND LOCAL LAWS, CODES, ORDINANCES, AND REGULATIONS, THE

MOST STRINGENT SHALL GOVERN.

2. THE INTENT OF THE DRAWINGS AND SPECIFICATIONS IS TO CONSTRUCT ANY

ADDITIONS, ALTERATIONS OR REPAIRS TO THE BUILDING IN ACCORDANCE WITH THE

CURRENT EDITION OF INTERNATIONAL CODES AND VA DESIGN GUIDES. SHOULD ANY

CONDITIONS DEVELOP NOT COVERED BY THE CONTRACT DOCUMENTS WHERE IN THE

FINISHED WORK WILL NOT COMPLY WITH APPLICABLE CODES AND VA STANDARDS, A

REQUEST FOR INFORMATION (RFI) DETAILING AND SPECIFYING THE REQUIRED WORK

SHALL BE SUBMITTED AND APPROVED BEFORE PROCEEDING WITH THE WORK.

3. FIELD VERIFY ALL EXISTING CONDITIONS INCLUDING BUT NOT LIMITED TO

STRUCTURAL, MECHANICAL, ELECTRICAL, PLUMBING, TELECOM, EQUIPMENT, AND ALL

OTHER EXISTING SYSTEMS. MAKE NECESSARY PROVISIONS TO MAINTAIN THE

INTEGRITY OF SYSTEMS PRIOR TO THE COMMENCEMENT OF DEMOLITION.

4. ALL POSSIBLE CARE SHALL BE EXERCISED TO INSURE THAT ANY UTILITY WILL NOT BE

THE CAUSE OF ENDANGERMENT TO THE LIFE OR HEALTH OF ANY PERSON.

5. ANY CONSTRUCTION INSTALLED IN CONFLICT WITH THE CONTRACT DOCUMENTS

SHALL BE CORRECTED AT NO EXPENSE TO THE VA.

6. VERIFICATIONS SHALL BE MADE FROM AVAILABLE SOURCES, SUCH AS BUT NOT

LIMITED TO, UTILITY COMPANIES, PLANS OF EXISTING BUILDINGS, CONTRACT

DOCUMENTS, THE VA, SITE INVESTIGATION REPORTS, ETC. IN NO WAY SHALL ANY

DOCUMENTATION PROVIDED RELIEVE THE REQUIREMENTS OF PERFORMING FIELD

INVESTIGATIONS.

7. IF AN ALTERNATE OR SUBSTITUTED MATERIAL IS ACCEPTED AS AN EQUAL, ASSUME

THE RESPONSIBILITY FOR CONSTRUCTION MODIFICATION AND/OR ADDITIONAL COSTS

ARE REQUIRED BY REASON OF THIS ACCEPTANCE.

8. ALL REQUIRED EXITS FROM OCCUPIED PORTIONS OF THE BUILDING MUST BE

MAINTAINED AT ALL TIMES. ESTABLISH PROCEDURES TO MINIMIZE CIRCULATION OF

CONSTRUCTION PERSONNEL AND MATERIALS THROUGH OCCUPIED PORTIONS OF THE

BUILDING. KEEP ALL AREAS ADJACENT TO THE WORK AREA CLEAN.

9. PRIOR TO DELIVERY OF MATERIALS TO THE CONSTRUCTION ZONE AND REMOVAL OF

WASTE FROM THE SITE, CHECK WITH THE VA FOR AN ACCEPTABLE ACCESS ROUTE

AND TIME. UNDER NO CIRCUMSTANCES SHALL ANY AREA OUTSIDE THE

CONSTRUCTION ZONE BE USED WITHOUT PRIOR APPROVAL FROM THE VA. ALL

STAGING AREAS SHALL BE PROTECTED WITH PRE-FABRICATED METAL PANEL WALL/

DOOR FIRE-RESISTANT SYSTEM. ALL TRASH SHALL BE REMOVED FROM THE BUILDING

DAILY AND PROPERLY DISPOSED. CONSTRUCTION MATERIALS SHALL NOT BE STORED

IN THE CORRIDORS AT ANY TIME.

10. FIELD VERIFY ALL EXISTING DIMENSIONS, SERVICES, AND POINTS OF CONNECTION

PRIOR TO START OF WORK.

11. PROVIDE WRITTEN REQUESTS TO VA FOR SHUT-DOWNS AT LEAST THREE WEEKS

PRIOR TO EVENT UNLESS OTHERWISE SPECIFIED. WORK REQUIRING SHUT-DOWNS

MAY BE REQUIRED TO BE PERFORMED OUTSIDE NORMAL WORK HOURS. IN ADDITION,

SHUTDOWN NOTICES SHALL BE NOTED ON THE 3 WEEK LOOK AHEAD SCHEDULE.

12. THE DESIGN ADEQUACY, SAFETY, AND ERECTION OF BRACING, SHORING,

SCAFFOLDING, AND TEMPORARY SUPPORTS AND RESTRAINTS IS THE SOLE

RESPONSIBILITY OF THE CONTRACTOR.

13. NOTIFY THE VA OF TIMES WHEN THE CONSTRUCTION NOISE WILL BE EXCESSIVE.

RESCHEDULE SUCH WORK IF SO REQUIRED BY THE FACILITY.

14. NOTIFY THE VA OF ANY DISCREPANCIES DISCOVERED IN THE FIELD FOR CORRECTIVE

ACTION.

15. ALL ITEMS TO BE REMOVED AND RELOCATED OR REPLACED SHALL BE HANDLED WITH

PROPER CARE AND STORED IN A SAFE PLACE TO PREVENT DAMAGE; WHEN DAMAGED,

REPLACED WITH NO EXPENSE TO THE VA.

16. ALL EQUIPMENT AND PIPING SHALL BE SUPPORTED OR BRACED IN ACCORDANCE WITH

THE PROVISIONS OF THE STRUCTURAL ENGINEERING DRAWINGS AND APPLICABLE

CODES.

17. ABBREVIATIONS THROUGHOUT THE DOCUMENTS ARE THOSE IN COMMON USE.

18. ALL DRAWINGS, THOUGH NOTED TO SCALE, ARE FOR ILLUSTRATION ONLY. DO NOT

SCALE THE DRAWINGS.

19. SIGNAGE CONSTRUCTION, FONT AND SIZE SHALL BE CONSISTENT WITH THE VA'S

EXISTING SIGNAGE REQUIREMENTS.

20. EXERCISE WITH CARE DURING CONSTRUCTION TO MINIMIZE DISRUPTION OF THE

MEDICAL CENTER ROUTINE. COORDINATE SEQUENCE OF WORK AND PHASING WITH VA

PROJECT MANAGER TO MINIMIZE DISRUPTION OF THE MEDICAL CENTER. SOME OF THE

WORK ITEMS REQUIRES THE WORK TO BE PERFORMED ONLY AT NIGHT, WEEKENDS,

OR HOLIDAYS AT NO ADDITIONAL COST TO THE GOVERNMENT.

21. PRIOR TO DRILLING OR CORING EXISTING CONCRETE, LOCATE EXISTING

REINFORCEMENT TO MAINTAIN ADEQUATE CLEARANCE FROM AND AVOID DAMAGE TO

EXISTING REINFORCEMENT. USE NON-DESTRUCTIVE TESTING (NDT) TO LOCATE

REINFORCEMENT. WHEREVER FEASIBLE, USE GROUND PENETRATING RADAR (GPR) OR

MEANS OTHER THAN X-RAY. WHERE X-RAY IS REQUIRED, PROVIDE WRITTEN REQUEST

AT LEAST THREE (3) WEEKS PRIOR TO EVENT; WORK MAY BE REQUIRED TO BE

PERFORMED OUTSIDE NORMAL WORK HOURS AND SHALL BE DOCUMENTED ON THE

THREE (3) WEEK LOOK AHEAD SCHEDULE.

22. PROTECT-IN-PLACE FIRE SUPPRESSION SYSTEMS DURING CONSTRUCTION.

CONTRACTOR SHALL BE RESPONSIBLE TO PROTECT ALL EXISTING FIRE ALARM

DEVICES WITHIN CONSTRUCTION AREA. IF DEVICE IS DAMAGED DUE TO DUST OR

PHYSICAL DAMAGE, CONTRACTOR SHALL BE RESPONSIBLE TO REPLACE WITH NO

COST TO THE VA.

VA SEPULVEDA AMBULATORY CARE CENTER (SACC) NORTH HILLS, CA

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Fi le

P at h U.S. Department of Veterans Affairs

B

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions: Date:

691A4-20-201FINAL CONSTRUCTION

DOCUMENTS

May 17, 2021 MS TS / JM

FULLY SPRINKLERED

A

ARCHITECT/ENGINEER OF RECORD

C

D

1611 PLUMMER ST, NORTH HILLS, CA, 91343

20801.13

Electronic Health Records Modernization (EHRM) Infrastructure Upgrades - Sepulveda, CA

GI002

SHEET INDEX

SHEET INDEX (CONTINUED)

SHEET NUMBER SHEET TITLE

99.M-1R1 MECHANICAL ROOF PLAN - BUILDING 99

200.M-111 MECHANICAL FIRST FLOOR PLAN

200.M-121 MECHANICAL SECOND FLOOR PLAN

200.M-131 MECHANICAL THIRD FLOOR PLAN

200.M-1R1 MECHANICAL ROOF PLAN

M-401 MECHANICAL ENLARGED PLANS

M-402 MECHANICAL ENLARGED PLANS

M-403 MECHANICAL ENLARGED PLANS

M-404 MECHANICAL ENLARGED PLANS

M-405 MECHANICAL ENLARGED PLANS

M-406 MECHANICAL ENLARGED PLANS

M-407 MECHANICAL ENLARGED PLANS

M-408 MECHANICAL ENLARGED PLANS

M-409 MECHANICAL ENLARGED PLANS

M-410 MECHANICAL ENLARGED PLANS

M-411 MECHANICAL ENLARGED PLANS

M-501 MECHANICAL DETAILS

M-502 MECHANICAL DETAILS

MI-701 MECHANICAL CONTROLS

M-801 MECHANICAL PHOTOS

M-802 MECHANICAL PHOTOS

ELECTRICAL

E-001 ELECTRICAL SYMBOL LIST, GENERAL NOTES ABBREVIATIONS,

SCOPE DESCRIPTION

E-002 ELECTRICAL DRAWING LIST

ES001 ELECTRICAL SITE PLAN

1.E-112 ELECTRICAL FIRST FLOOR PLAN

1.E-131 ELECTRICAL ROOF PLAN

10.E-102 ELECTRICAL BASEMENT FLOOR PLAN

10.E-103 ELECTRICAL BASEMENT FLOOR PLAN

10.E-111 ELECTRICAL FIRST FLOOR PLAN

10.E-121 ELECTRICAL SECOND FLOOR PLAN

10.E-122 ELECTRICAL SECOND FLOOR PLAN

10.E-131 ELECTRICAL ROOF PLAN

20.E-111 ELECTRICAL FIRST FLOOR PLAN

20.E-121 ELECTRICAL SECOND FLOOR PLAN

20.E-131 ELECTRICAL ROOF PLAN

22.E-111 ELECTRICAL FIRST FLOOR PLAN

22.E-121 ELECTRICAL SECOND FLOOR PLAN

22.E-131 ELECTRICAL ROOF PLAN

23.E-111 ELECTRICAL FIRST FLOOR PLAN

23.E-131 ELECTRICAL ROOF PLAN

24.E-111 ELECTRICAL FIRST FLOOR PLAN

25.E-111 ELECTRICAL FIRST FLOOR PLAN

25.E-121 ELECTRICAL ROOF PLAN

45.E-101 ELECTRICAL BASEMENT FLOOR PLAN

63.E-111 ELECTRICAL FIRST FLOOR PLAN

70.E-111 ELECTRICAL FIRST FLOOR PLAN

99.E-101 ELECTRICAL GROUND FLOOR PLAN

99.E-102 ELECTRICAL GROUND FLOOR PLAN

99.E-111 ELECTRICAL FIRST FLOOR PLAN

99.E-131 ELECTRICAL ROOF PLAN

200.E-111 ELECTRICAL FIRST FLOOR PLAN

200.E-112 ELECTRICAL FIRST FLOOR PLAN

200.E-113 ELECTRICAL FIRST FLOOR PLAN

200.E-114 ELECTRICAL FIRST FLOOR PLAN

200.E-121 ELECTRICAL SECOND FLOOR PLAN

200.E-122 ELECTRICAL SECOND FLOOR PLAN

200.E-123 ELECTRICAL SECOND FLOOR PLAN

200.E-124 ELECTRICAL SECOND FLOOR PLAN

200.E-131 ELECTRICAL THIRD FLOOR PLAN

200.E-132 ELECTRICAL THIRD FLOOR PLAN

200.E-133 ELECTRICAL THIRD FLOOR PLAN

200.E-134 ELECTRICAL THIRD FLOOR PLAN

200.E-141 ELECTRICAL ROOF PLAN

1.E-401 ELECTRICAL ENLARGED PLAN PLAN TR ROOM

10.E-401 ELECTRICAL ENLARGED PLAN PLAN TR ROOM

20.E-401 ELECTRICAL ENLARGED PLAN PLAN TR ROOM

22.E-401 ELECTRICAL ENLARGED PLAN PLAN TR ROOM

23.E-401 ELECTRICAL ENLARGED PLAN PLAN TR ROOM

24.E-401 ELECTRICAL ENLARGED PLAN PLAN TR ROOM

25.E-401 ELECTRICAL ENLARGED PLAN MDF ROOM

45.E-401 ELECTRICAL ENLARGED PLAN PLAN TR ROOM

63.E-401 ELECTRICAL ENLARGED PLAN PLAN TR ROOM

70.E-401 ELECTRICAL ENLARGED PLAN PLAN TR ROOM

99.E-401 ELECTRICAL ENLARGED PLAN PLAN TR ROOM

200.E-401 ELECTRICAL ENLARGED PLAN

200.E-402 ELECTRICAL ENLARGED PLAN

SHEET INDEX

SHEET NUMBER SHEET TITLE

GENERAL

GI001 TITLE SHEET

GI002 SHEET INDEX

GI003 ABBREVIATIONS & PHASING NOTES

ARCHITECTURAL

1.A-101 ARCHITECTURAL BASEMENT FLOOR PLAN

1.A-111 ARCHITECTURAL FIRST FLOOR PLAN

1.A-121 ARCHITECTURAL SECOND FLOOR PLAN

10.A-101 ARCHITECTURAL BASEMENT PLAN

10.A-111 ARCHITECTURAL FIRST FLOOR PLAN

10.A-121 ARCHITECTURAL SECOND FLOOR PLAN

20.A-111 ARCHITECTURAL FIRST FLOOR PLAN

20.A-121 ARCHITECTURAL SECOND FLOOR PLAN

22.A-111 ARCHITECTURAL FIRST FLOOR PLAN

22.A-121 ARCHITECTURAL SECOND FLOOR PLAN

23.A-111 ARCHITECTURAL FIRST FLOOR PLAN

24.A-101 ARCHITECTURAL BASEMENT PLAN

24.A-111 ARCHITECTURAL FIRST FLOOR PLAN

25.A-111 ARCHITECTURAL FIRST FLOOR PLAN

45.A-111 ARCHITECTURAL FIRST FLOOR PLAN

45.A-121 ARCHITECTURAL SECOND FLOOR PLAN

63.A-111 ARCHITECTURAL FIRST FLOOR PLAN

70.A-111 ARCHITECTURAL FIRST FLOOR PLAN

99.A-1G1 ARCHITECTURAL GROUND FLOOR PLAN

99.A-111 ARCHITECTURAL FIRST FLOOR PLAN

200.A-111 ARCHITECTURAL FIRST FLOOR PLAN

200.A-121 ARCHITECTURAL SECOND FLOOR PLAN

200.A-131 ARCHITECTURAL THIRD FLOOR PLAN

A-401 ARCHITECTURAL ENLARGED PLANS

A-402 ARCHITECTURAL ENLARGED PLANS

A-403 ARCHITECTURAL ENLARGED PLANS

A-404 ARCHITECTURAL ENLARGED PLANS

A-405 ARCHITECTURAL ENLARGED PLANS

A-406 ARCHITECTURAL ENLARGED PLANS

A-407 ARCHITECTURAL ENLARGED PLANS

A-408 ARCHITECTURAL ENLARGED PLANS

A-409 ARCHITECTURAL ENLARGED PLANS

A-410 ARCHITECTURAL ENLARGED PLANS

A-411 ARCHITECTURAL ENLARGED PLANS

A-601 ARCHITECTURAL DETAILS

A-602 ARCHITECTURAL DETAILS

A-603 ARCHITECTURAL DETAILS

A-604 ARCHITECTURAL SCHEDULES

A-605 FIRE STOPPING DETAILS

A-606 FIRE STOPPING DETAILS

A-801 ARCHITECTURAL PHOTOS

A-802 ARCHITECTURAL PHOTOS

A-803 ARCHITECTURAL PHOTOS

STRUCTURAL

S-001 NOTES, DETAILS & PARTIAL PLANS

S-002 DETAILS

MECHANICAL

M-001 MECHANICAL LEGEND & ABBREVIATIONS

M-002 MECHANICAL GENERAL NOTES & SCHEDULES

1.M-111 MECHANICAL FIRST FLOOR PLAN

1.M-1R1 MECHANICAL ROOF PLAN

10.M-101 MECHANICAL BASEMENT PLAN

10.M-121 MECHANICAL SECOND FLOOR PLAN

10.M-1R1 MECHANICAL ROOF PLAN

20.M-111 MECHANICAL FIRST FLOOR PLAN

20.M-121 MECHANICAL SECOND FLOOR PLAN

20.M-1R1 MECHANICAL ROOF PLAN

22.M-111 MECHANICAL FIRST FLOOR PLAN

22.M-121 MECHANICAL SECOND FLOOR PLAN

22.M-1R1 MECHANICAL ROOF PLAN

23.M-111 MECHANICAL FIRST FLOOR PLAN

23.M-121 MECHANICAL SECOND FLOOR - BUILDING 23

23.M-1R1 MECHANICAL ROOF PLAN - BUILDING 23

25.M-111 MECHANICAL FIRST FLOOR PLAN

25.M-1R1 MECHANICAL ROOF PLAN

45.M-111 MECHANICAL FIRST FLOOR PLAN

63.M-111 MECHANICAL FIRST FLOOR PLAN

70.M-111 MECHANICAL FIRST FLOOR PLAN

99.M-101 MECHANICAL GROUND FLOOR PLAN

99.M-111 MECHANICAL FIRST FLOOR PLAN

SHEET INDEX (CONTINUED)

SHEET NUMBER SHEET TITLE

200.E-403 ELECTRICAL ENLARGED PLAN

E-501 ELECTRICAL DETAILS - GROUNDING

E-502 ELECTRICAL DETAILS - GROUNDING

E-503 ELECTRICAL DETAILS - GROUNDING

E-504 ELECTRICAL DETAILS - GROUNDING

E-505 ELECTRICAL DETAILS

E-601 SINGLE LINE DIAGRAM BLDG. 10,20,99

E-602 SINGLE LINE DIAGRAM BLDG. 1

E-603 SINGLE LINE DIAGRAM

E-701 TGB GROUNDING RISER BLDG. 10,22,20

E-702 TGB GROUNDING RISER BLDG. 23.24.25.45

E-703 TGB GROUNDING RISER BLDG. 63,70,99,200

E-801 PANEL SCHEDULE

E-802 PANEL SCHEDULE

E-803 PANEL SCHEDULE

E-804 PANEL SCHEDULE

E-805 PANEL SCHEDULE

TELECOMMUNICATIONS

T-001 TELECOMMUNICATIONS SYMBOL LIST, GENERAL NOTES

ABBREVIATIONS, SCOPE DESCRIPTION

T-002 TELECOMMUNICATIONS DRAWING LIST

TS-001 TELECOMMUNICATIONS SITE PLAN -FIBER & CELL TUBE DISTRIBUTION

1.T-111 TELECOMMUNICATIONS FIRST FLOOR PLAN

1.T-112 TELECOMMUNICATIONS FIRST FLOOR PLAN

1.T-121 TELECOMMUNICATIONS SECOND FLOOR PLAN

4.T-101 TELECOMMUNICATIONS BASEMENT FLOOR PLAN

10.T-102 TELECOMMUNICATIONS BASEMENT FLOOR PLAN

10.T-111 TELECOMMUNICATIONS FIRST FLOOR PLAN

10.T-112 TELECOMMUNICATIONS FIRST FLOOR PLAN

10.T-121 TELECOMMUNICATIONS SECOND FLOOR PLAN

10.T-122 TELECOMMUNICATIONS SECOND FLOOR PLAN

20.T-111 TELECOMMUNICATIONS FIRST FLOOR PLAN

20.T-121 TELECOMMUNICATIONS SECOND FLOOR PLAN

22.T-111 TELECOMMUNICATIONS FIRST FLOOR PLAN

22.T-121 TELECOMMUNICATIONS SECOND FLOOR PLAN

23.T-111 TELECOMMUNICATIONS FIRST FLOOR PLAN

24.T-111 TELECOMMUNICATIONS FIRST FLOOR PLAN

25.T-111 TELECOMMUNICATIONS FIRST FLOOR PLAN

45.T-101 TELECOMMUNICATIONS BASEMENT FLOOR PLAN

45.T-111 TELECOMMUNICATIONS FIRST FLOOR PLAN

63.T-111 TELECOMMUNICATIONS FIRST FLOOR PLAN

70.T-111 TELECOMMUNICATIONS FIRST FLOOR PLAN

99.T-101 TELECOMMUNICATIONS GROUND FLOOR PLAN

99.T-102 TELECOMMUNICATIONS GROUND FLOOR PLAN

99.T-103 TELECOMMUNICATIONS GROUND FLOOR PLAN

99.T-104 TELECOMMUNICATIONS GROUND FLOOR PLAN

99.T-111 TELECOMMUNICATIONS FIRST FLOOR PLAN

200.T-111 TELECOMMUNICATIONS FIRST FLOOR PLAN

200.T-112 TELECOMMUNICATIONS FIRST FLOOR PLAN

200.T-113 TELECOMMUNICATIONS FIRST FLOOR PLAN

200.T-114 TELECOMMUNICATIONS FIRST FLOOR PLAN

200.T-121 TELECOMMUNICATIONS SECOND FLOOR PLAN

200.T-122 TELECOMMUNICATIONS SECOND FLOOR PLAN

200.T-123 TELECOMMUNICATIONS SECOND FLOOR PLAN

200.T-124 TELECOMMUNICATIONS SECOND FLOOR PLAN

200.T-131 TELECOMMUNICATIONS THIRD FLOOR PLAN

200.T-132 TELECOMMUNICATIONS THIRD FLOOR PLAN

200.T-133 TELECOMMUNICATIONS THIRD FLOOR

200.T-134 TELECOMMUNICATIONS THIRD FLOOR PLAN

1.T-401 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM A154 & B120A

1.T-401A TELECOMMUNICATIONS RACK ELEVATIONS TR B120A

1.T-402A TELECOMMUNICATIONS RACK ELEVATIONS B120A

4.T-401 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM

10.T-401 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM B-B110

10.T-401A TELECOMMUNICATIONS RACK ELEVATIONS B-B110

10.T-402 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 1-B100C

10.T-402A TELECOMMUNICATIONS RACK ELEVATIONS 1-B100C

10.T-403 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM A29B

10.T-403A TELECOMMUNICATIONS RACK ELEVATIONS A29B

10.T-404 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM

10.T-404A TELECOMMUNICATIONS RACK ELEVATIONS C-004

20.T-401 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 1A-115

20.T-401A TELECOMMUNICATIONS RACK ELEVATIONS 1A-115

20.T-402 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 2-A118C

20.T-402A TELECOMMUNICATIONS RACK ELEVATIONS 2-A118C

22.T-401 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 103

22.T-401A TELECOMMUNICATIONS RACK ELEVATIONS 103

22.T-402 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 202

SHEET INDEX (CONTINUED)

SHEET NUMBER SHEET TITLE

22.T-402A TELECOMMUNICATIONS RACK ELEVATIONS 202

22.T-402A TELECOMMUNICATIONS RACK ELEVATIONS 202

23.T-401 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 106

23.T-401A TELECOMMUNICATIONS RACK ELEVATIONS 106

24.T-401 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 102A

24.T-401A TELECOMMUNICATIONS RACK ELEVATIONS 102A

25.T-401 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM A109

25.T-401A TELECOMMUNICATIONS RACK ELEVATIONS A109

25.T-402 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM B125

25.T-402A TELECOMMUNICATIONS RACK ELEVATIONS B125

45.T-401 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 105

45.T-401A TELECOMMUNICATIONS RACK ELEVATIONS 105

63.T-401 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 102

63.T-401A TELECOMMUNICATIONS RACK ELEVATIONS 102

70.T-401 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM

70.T-401A TELECOMMUNICATIONS RACK ELEVATIONS

99.T-401 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM G104

99.T-401A TELECOMMUNICATIONS ENLARGED PLAN G104

99.T-402 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM G105

99.T-402A TELECOMMUNICATIONS ENLARGED PLAN G105

99.T-403 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 112

99.T-403A TELECOMMUNICATIONS ENLARGED PLAN 112

99.T-404 TELECOMMUNICATIONS ENLARGED PLAN TR 57A & 115 ELEVATION

200.T-401 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM

200.T-401A TELECOMMUNICATIONS RACK ELEVATIONS

200.T-402 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM

200.T-402A TELECOMMUNICATIONS RACK ELEVATIONS

200.T-403 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 1001B

200.T-403A TELECOMMUNICATIONS RACK ELEVATIONS 1001B

200.T-404 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 1356

200.T-404A TELECOMMUNICATIONS RACK ELEVATIONS 1356

200.T-405 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 1525

200.T-405A TELECOMMUNICATIONS RACK ELEVATIONS 1525

200.T-406 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 2466

200.T-406A TELECOMMUNICATIONS RACK ELEVATIONS 2466

200.T-407 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 2664

200.T-407A TELECOMMUNICATIONS RACK ELEVATIONS 2664

200.T-408 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 2165

200.T-408A TELECOMMUNICATIONS RACK ELEVATIONS 2165

200.T-409 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 2365

200.T-409A TELECOMMUNICATIONS RACK ELEVATIONS 2365

200.T-410 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 3406

200.T-410A TELECOMMUNICATIONS RACK ELEVATIONS 3406

200.T-411 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 3573

200.T-411A TELECOMMUNICATIONS RACK ELEVATIONS 3573

200.T-412 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 3143

200.T-412A TELECOMMUNICATIONS RACK ELEVATIONS 3143

200.T-413 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 3326

200.T-413A TELECOMMUNICATIONS RACK ELEVATIONS 3326

201.T-401 TELECOMMUNICATIONS ENLARGED PLAN TR ROOM 115 (MODIFIED)

201.T-401A TELECOMMUNICATIONS RACK ELEVATIONS

201.T-401B TELECOMMUNICATIONS RACK ELEVATIONS

T-501 TELECOMMUNICATIONS DETAILS

T-502 TELECOMMUNICATIONS DETAILS

T-503 TELECOMMUNICATIONS DETAILS

T-504 TELECOMMUNICATIONS DETAILS

T-505 TELECOMMUNICATIONS DETAILS

T-506 TELECOMMUNICATIONS MANHOLE FOLDOUTS

T-507 TELECOMMUNICATIONS MANHOLE FOLDOUTS

T-508 TELECOMMUNICATIONS MANHOLE FOLDOUTS

T-509 TELECOMMUNICATIONS MANHOLE FOLDOUTS

T-510 TELECOMMUNICATIONS MANHOLE FOLDOUTS

T-601 OPTICAL SINGLE MODE FIBER HORIZONTAL & VERTICAL RISER

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Fi le

P at h U.S. Department of Veterans Affairs

B

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions: Date:

691A4-20-201FINAL CONSTRUCTION

DOCUMENTS

May 17, 2021 MS TS / JM

FULLY SPRINKLERED

A

ARCHITECT/ENGINEER OF RECORD

C

D

1611 PLUMMER ST, NORTH HILLS, CA, 91343

20801.13

Electronic Health Records Modernization (EHRM) Infrastructure Upgrades - Sepulveda, CA

GI003

ABBREVIATIONS & PHASING NOTES

SMOKE DETECTOR

LIGHTING FIXTURE

FIRE SPRINKLER

ABBREV. DESCRIPTION

GENERAL ABBREVIATIONS

ACM ALUMINUM COMPOSITE MATERIAL

AIA AMERICAN INSTITUTE OF ARCHITECTS

BAS BUILDING AUTOMATION SYSTEM

BLDG BUILDING

CAD COMPUTER AIDED DESIGN

DDC DIRECT DIGITAL CONTROL

DEMO DEMOLITION

EHRM ELECTRONIC HEALTH RECORDS MODERNIZATION

EUD(S) END USER DEVICE(S)

EXIST OR (E) EXISTING

HAZMAT HAZARDOUS MATERIAL

I.C.C. INTERNATIONAL CODE COUNCIL

MC MEDICAL CENTER

MCR MAIN COMPUTER ROOM

MDF MAIN DISTRIBUTION FRAME

NFPA NATIONAL FIRE PROTECTION ASSOCIATION

OIT OFFICE OF INFORMATION TECHNOLOGY

OSHA OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION

RENO RENOVATION

SDS SAFETY DATA SHEET

SEOR STRUCTURAL ENGINEER OF RECORD

TAB TEST AND BALANCE

TELECOM TELECOMMUNICATION

TR TELECOMMUNICATION ROOM

TRS TELECOMMUNICATION ROOMS

U.L. UNDERWRITER LABORATORIES

U.O.N. UNLESS OTHERWISE NOTED

VA VETERAN AFFAIRS

VHA VETERAN HEALTH ADMINISTRATION

SD

FOR CRITICAL ROOMS, SUCH AS OPERATING ROOMS, ICU AND SIMILAR SPACES,

NORMAL HOURS ARE 24/7.

ONLY ONE ROOM IN THE GIVEN DEPARTMENT MAY BE SHUT DOWN AT ANY TIME. EACH

ROOM MAY ONLY BE SHUT DOWN ONCE DURING THE DURATION OF THE PROJECT.

FOR ADMINISTRATIVE SPACES, NORMAL OPERATING HOURS ARE FROM 7:00 AM TO

17:30 PM.

PREPARATION WORK MAY BE PERFORMED DURING NORMAL HOURS.

SWITCH OVER MUST OCCUR DURING ONE OFF HOUR PERIOD.

FOR CLINICAL SPACES, NORMAL OPERATING HOURS ARE FROM 6:00 AM TO 18:30 PM.

PREPARATION WORK MAY BE PERFORMED DURING NORMAL HOURS.

SWITCH OVER MUST OCCUR DURING ONE OFF HOUR PERIOD.

CONSTRUCTION ACTIVITY HOURS

THE FOLLOWING IS INTENDED AS A CONCEPTUAL PHASING PLAN AND IDENTIFIES CRITICAL STEPS REQUIRED TO BE COMPLETED. THIS LIST IS NOT INTENDED TO BE AN ALL-INCLUSIVE LIST NOR DOES IT LIST THE EXACT

REQUIREMENTS FOR DOWNTIME OR OPERATIONAL SHUT DOWN COORDINATION.

PREPARE A COMPLETE DETAILED PHASING PLAN WITHIN 30 DAYS OF NOTICE TO PROCEED. THE PHASING PLAN SHALL BE PREPARED IN "MICROSOFT PROJECT" OR SIMILAR SOFTWARE. IT SHALL INCLUDE SCHEMATIC DIAGRAMS AND LAYOUT FOR PHASING AND SHALL BE PRESENTED TO THE VA FOR APPROVAL. THERE SHALL BE NO

INSTALLATION PRIOR TO APPROVAL BY THE VA.

THE PHASING PLAN SHALL IDENTIFY AT A MINIMUM:

a. SHUTDOWNS / UTILITY SERVICE INTERRUPTIONS (INFORMATION TECHNOLOGY/TELECOMMUNICATIONS, ELECTRIC, FIRE ALARM, MECHANICAL, ETC.)

b. ENERGIZED WORK

c. HOT WORK

d. ABOVE CEILING WORK

e. CONFINED SPACES

f. FIRE WATCH

g. RADIATION SAFETY

h. INFECTION PREVENTION AND CONTROLS

i. SCHEDULE

j. TEMPORARY SERVICE REQUIREMENTS

k. PRODUCT PROCUREMENT

l. INSTALLATION

m. SKETCHES TO INDICATE EACH STEP

n. EMERGENCY CONTACT NUMBERS

IN ADDITION TO AN OVERALL PROJECT PHASING PLAN, A SEPARATE METHOD OF PROCEDURE AND PHASING PLAN SHALL BE PROVIDED FOR EACH SHUTDOWN PRIOR TO THE COMMENCEMENT OF ANY WORK WITHIN THE BUILDING.

ALL PHASING PLANS WILL REQUIRE APPROVAL BY THE OWNER PRIOR TO COMMENCEMENT OF ANY CONSTRUCTION ACTIVITIES. COORDINATE THE OVERALL PROJECT PHASING REQUIREMENTS WITH THE ARCHITECT AND THE OWNER.

DEVELOP A PLAN FOR EACH TELECOMMUNICATION ROOM (TR) BASED ON THE PHASES LISTED BELOW. THE PLAN SHALL INCLUDE PHASING OF CONSTRUCTION ACTIVITIES FOR THE TR(s) AND CORRESPONDING FLOOR PLAN AREAS SERVED BY EACH TR . EACH PHASE SHOULD BE PERFORMED IN SEQUENTIAL ORDER. TELECOM ROOMS MAY BE

COMPLETED IN PARALLEL WITH VA REVIEW AND APPROVAL.

CONCEPTUAL PHASING NOTES

ALL HAZMAT PRODUCTS WILL BE STORED IN PROPER CONTAINERS

AND CABINETS WITH SAFETY DATA SHEET (SDS) WHEN ON

CONSTRUCTION SITE. ALL HAZMAT PRODUCTS WILL BE PUT AWAY

WHEN NOT BEING UTILIZED.

BASED ON REPORTS PROVIDED BY VA SEPULVEDA AND RECENT

SAMPLING AND ANALYSIS, A SUMMARY OF ASBESTOS CONTAINING

MATERIALS NOTED TO BE PRESENT IS SUMMARIZED IN THESE NOTES.

SPECIFIC LOCATIONS AND MATERIALS ARE NOTED IN THE

SPECIFICATIONS, BUT IF THE SAME MATERIAL IS FOUND TO BE

PRESENT IN OTHER AREAS OF THE SAME BUILDINGS, IT IS REQUIRED

TO BE TREATED AS ASBESTOS.

REPORTS INDICATE THE FOLLOWING BUILDINGS HAVE DRYWALL OR

PLASTER THAT CONTAIN HAZARDOUS MATERIALS:

BLDG 1: ASBESTOS IS PRESENT IN THE DRYWALL JOINT

COMPOUND. LOCATIONS: THROUGHOUT WALLS / CEILINGS.

BLDG 22: ASBESTOS IS PRESENT IN THE DRYWALL JOINT

COMPOUND. LOCATIONS: THROUGHOUT WALLS / CEILINGS.

BLDG 23: ASBESTOS IS PRESENT IN THE TEXTURED COATING

ASSOCIATED WITH PLASTER WALLS. LOCATIONS: THROUGHOUT

WALLS.

BLDG 24: ASBESTOS IS PRESENT IN THE PLASTER. LOCATIONS:

THROUGHOUT WALLS AND CEILINGS.

BLDG 99: ASBESTOS IS PRESENT IN THE DRYWALL JOINT

COMPOUND. LOCATIONS: THROUGHOUT WALLS.

THE JOINT COMPOUND IS ASSOCIATED WITH THE DRYWALL AND

CANNOT BE SEPARATED NOR CAN BE VISIBLY SEEN WHERE THE JOINT

COMPOUND IS ON DRYWALL. FOR THIS FACT, THE DRYWALL AND

ASSOCIATED JOINT COMPOUND NEED TO BE TREATED AS ASBESTOS

CONTAINING UNLESS THE CONTRACTOR CAN VISIBLY SEE WHERE THE

JOINT COMPOUND IS LOCATED AND THE PENETRATIONS WILL NOT BE

MADE IN LOCATIONS WHERE THIS IS OBSERVED.

REPORTS INDICATE THE FOLLOWING BUILDINGS HAVE FLOORING

(TILE/MASTIC/FLOOR SHEETING) THAT CONTAIN ASBESTOS:

BLDG 1 : SERVER ROOM A154

BLDG 22: THROUGHOUT

BLDG 45: TR ROOM, ROOM 201, ROOM 203

BLDG 63: THROUGHOUT

REPORTS AND RECENT SAMPLING INDICATE THE FOLLOWING

BUILDINGS HAVE FRIABLE ASBESTOS:

BLDG 1: THERMAL SYSTEM INSULATION MAY BE PRESENT

PENETRATIONS ARE PLANNED FOR ASBESTOS CONTAINING MATERIALS

NOTED ABOVE. WORKERS CAN BE UTILIZED WITH APPROPRIATE

ASBESTOS TRAINING. EXPOSURE ASSESSMENTS SHOULD BE

PERFORMED FOR THE WORKERS PERFORMING THESE PENETRATIONS

IN ORDER TO DETERMINE THE APPROPRIATE PERSONNEL PROTECTIVE

EQUIPMENT REQUIRED FOR THESE TASKS.

BASED ON REPORTS PROVIDED BY VA SEPULVEDA AND RECENT

SAMPLING AND ANALYSIS, A SUMMARY OF LEAD CONTAINING

MATERIALS NOTED TO BE PRESENT IS SUMMARIZED IN THESE NOTES.

SPECIFIC LOCATIONS AND MATERIALS ARE NOTED IN THE

SPECIFICATIONS, BUT IF THE SAME MATERIAL IS FOUND TO BE

PRESENT IN OTHER AREAS OF THE SAME BUILDINGS, IT IS REQUIRED

TO BE TREATED AS LEAD PAINT.

REPORTS INDICATE THE FOLLOWING BUILDINGS HAVE LEAD PAINT:

BLDG 1: GREEN CERAMIC WALL TILES. LOCATIONS: THROUGHOUT

OFFICES.

BLDG 7: ORANGE CONCRETE CEILING. LOCATIONS: ROOM B-30.

BLDG 20: GRAY WOOD BASEBOARD. LOCATIONS: THROUGHOUT

HALLWAYS/CORRIDORS

BLDG 22: BLUE CONCRETE WALLS. LOCATIONS: THROUGHOUT

OFFICES.

BLDG 23: BEIGE METAL BASEBOARDS. LOCATIONS: GYM.

BLDG 24: BEIGE WOOD HORIZONTAL BEAM. LOCATIONS: OFFICES.

BLDG 25: GRAY VINYL COVE BASE. LOCATIONS: ROOM A109.

(PLANNED FOR REMOVAL)

BLDG 99: BROWN 12-INCH X 12 INCH CERAMIC FLOORING.

LOCATIONS: ROOM 102A & 100 CLOSET

PENETRATIONS ARE PLANNED FOR LEAD CONTAINING MATERIALS

NOTED ABOVE. ANY REMOVAL ACTIVITIES OR PENETRATIONS ARE TO

BE PERFORMED IN COMPLIANCE WITH CALIFORNIA CODE OF

REGULATIONS, TITLE 9, SECTION 1532.1 (LEAD IN CONSTRUCTION

STANDARD).

HAZARDOUS MATERIALS

PHASE 1 INSTALLATION OF NEW FIBERS TO ALL THE BUILDINGS FROM BUILDING 201 MCR

IN COORDINATION WITH VA, IDENTIFY ALL UNUSED COPPER CABLES IN EACH MANHOLE AND DUCT

BANK.

PULL OUT ALL EXISTING UNUSED COPPER CABLES AND DISPOSE PER VA RECYCLING REQUIREMENTS.

MANDRELL EXISTING SPARE CONDUIT AND CONDUITS FROM WHICH COPPER HAS BEEN REMOVED.

MANDRELL SHALL BE DONE MANHOLE TO MANHOLE.

BLOW PULL ROPE THROUGH THE CONDUIT DUCT BANKS.

REPEAT STEPS UNTIL ALL MANHOLES ARE COMPLETE.

INSTALL SITE TUBE DISTRIBUTION UNITS.

PULL TUBE CELL IN ALL CONDUITS AND MANHOLES AS SHOWN ON PLANS.

TEST TUBE CELL TO MAKE SURE THERE ARE NO OBSTRUCTIONS. LABEL EACH TUBE CELL “FROM___

TO___”.

INSTALL AIR BLOWN FIBERS FROM MCR TO EACH BUILDING AS SPECIFIED IN THE PLANS.

INSTALL FIBER TO EACH TR WITHIN THE BUILDINGS PER FIBER RISER DIAGRAM(S).

TERMINATE FIBER ON FIBER PATCH PANEL IN EACH TR AND BUILDING 201 MCR.

LABEL FIBER/TUBE CELLS PER LABELING REQUIREMENTS.

TEST ALL FIBERS USING OPTICAL TIME DOMAIN REFLECTOMETER (OTDR) EQUIPMENT.

REPLACE ALL FIBER THAT FAILED THE TEST.

PHASE 2 BUILD OUT NEW TELECOM ROOMS (TRS)

COMPLETE IMPROVEMENTS FOR NEW TR ROOMS PER ARCHITECTURAL DRAWINGS.

COMPLETE LIGHTING AND POWER INCLUDING TELECOMMUNICATIONS GROUNDING BUS BAR (TGB)

PER ELECTRICAL DRAWINGS.

COMPLETE HVAC PER MECHANICAL DRAWINGS INCLUDING PRE/POST TAB AND CONTROLS.

CONCEPTUAL PHASING NOTES (CONTINUED)

PHASE 3 TELECOMMUNICATION AND ELECTRICAL WORK WITHIN EXISTING TELECOM ROOMS (TRS)

REMOVE CEILING AND GRID AND PROVIDE TEMPORARILY SUPPORTS FOR THE EXISTING LIGHT FIXTURES, HVAC DIFFUSERS AND SMOKE DETECTORS. CEILING DEVICES TO REMAIN OR DEMOLISH AS INDICATED.

INSTALL LIGHT FIXTURES AND RECEPTACLE(S) (WHERE APPLICABLE). RE-ATTACH SMOKE DETECTOR

INSTALL FIRE-RATED CABLING PATHWAYS THROUGH WALLS FOR HORIZONTAL CABLE ENTRY FROM EUDS.

INSTALL CABLE LADDER RACK SYSTEMS FROM ENTRY POINT TO ROOM DISTRIBUTION.

POPULATE AVAILABLE SPACE IN EXISTING RACK(S) WITH NEW CAT6A COMPLIANT 48 PORT PATCH PANEL(S) OR

LOCATE I NEW DATA RACK INSTALLED IN A TEMPORARY LOCATION.

INSTALL WALL-MOUNTED J-HOOK CABLE SUPPORTS ALONG CORRIDOR MAIN CABLE ROUTES (EXISTING/NEW

CABLE TRAY TO BE USED WHERE INDICATED ON DRAWINGS).

INSTALL PENDANT J-HOOK CABLE SUPPORTS ALONG CABLE PATHWAYS FROM CORRIDOR TO EACH ROOM (OR

CABLE TRAY WHERE INDICATED).

INSTALL EUD COMMUNICATION CABLES FROM TR TO THE CORRIDORS ALONG MAIN CABLE ROUTES. COIL UP CABLES AT EACH TAKE OFF POINT TO INDIVIDUAL ROOMS AND LEAVE ABOVE CEILING WITH ADEQUATE CABLE

LENGTHS TO EXTEND TO EUD LOCATIONS.

SCHEDULE A GROUP OF ROOMS FOR INSTALLATION OF NEW EUD FACEPLATES WITH RJ45 JACKS.

PULL OUT THE EXISTING RJ45 FACEPLATES AND LET HANG OUT TEMPORARILY.

INSTALL COMMUNICATION CABLES FROM ABOVE CEILING TO EUD FACEPLATE LOCATIONS.

TEST AND CERTIFY THE CABLES BY A GROUP OF ROOMS.

TERMINATE AND INSTALL RJ45 JACKS AT TR ROOM AND AT EUD FACEPLATES. PLUG INTO NEW 48-PORT PATCH

PANEL(S).

INSTALL LABELS AT EACH EUD FACEPLATE AND CORRESPONDING NEW 48-PORT PATCH PANEL(S). RECORD IN THE DATA SHOP DRAWINGS FOR DOCUMENTATION. LABEL EACH RACK AND EACH PATCH PANEL PER

CONTRACT REQUIREMENTS.

VA OIT TO CROSS CONNECT NEW 48-PORT PATCH PANEL TO CISCO SWITCH(ES) AND ACTIVATE THE NEW EUD

FACEPLATES.

VA OIT TO SWITCH THE EUD DEVICES FROM OLD FACE PLATES TO NEW FACEPLATES.

EUD DEVICES ARE NOW CONNECTED TO NEW CABLING.

PULLOUT AND REMOVE EXISTING FACEPLATES AND DATA CABLING FROM THE EUD LOCATIONS TO TR ROOM

EXISTING PATCH PANEL(S).

REPEAT PROCEDURE UNTIL THE DATA CABLING FOR ALL ROOMS SERVED BY THE TR HAVE BEEN COMPLETED.

INSTALL NEW DATA RACKS AND RELOCATE EQUIPMENT FROM EXISTING DATA RACKS.

REMOVE EXISTING PATCH PANEL(S) AND DATA RACK(S) AS INDICATED.

CLEAN UP, PAINT TR ROOM, AND COMPLETE ALL OTHER FINISHES PER ARCHITECTURAL.

INSTALL RACK TEMPERATURE AND HUMIDITY SENSORS.

TURN OVER TR TO THE VA.

PHASE 4 TELECOMMUNICATION AND ELECTRICAL WITHIN NEW TURN OVER TR TO VA

INSTALL FIRE-RATED CABLING PATHWAYS THROUGH WALLS FOR HORIZONTAL CABLE ENTRY FROM EUDS.

INSTALL TELEPHONE BACKBOARD.

INSTALL 4-POST RACK(S).

INSTALL LADDER RACKS.

INSTALL CABLE LADDER RACK SYSTEMS.

POPULATE NEW RACK(S) WITH NEW CAT6A COMPLIANT 48-PORT PATCH PANEL(S).

TERMINATE NEW FIBER (BOTH SINGLE MODE AND MULTIMODE).

INSTALL WALL-MOUNTED J-HOOK CABLE SUPPORTS ALONG CORRIDOR MAIN CABLE ROUTES (EXISTING/NEW

CABLE TRAY TO BE USED WHERE INDICATED ON DRAWINGS).

INSTALL PENDANT J-HOOK CABLE SUPPORTS ALONG CABLE PATHWAYS FROM CORRIDOR TO EACH ROOM (OR

CABLE TRAY WHERE INDICATED).

INSTALL EUD COMMUNICATION CABLES FROM TR TO THE CORRIDORS ALONG MAIN CABLE ROUTES. COIL UP CABLES AT EACH TAKE OFF POINT TO INDIVIDUAL ROOMS AND LEAVE ABOVE CEILING WITH ADEQUATE CABLE

LENGTHS TO EXTEND TO EUD LOCATIONS.

SCHEDULE A GROUP OF ROOMS FOR INSTALLATION OF NEW EUD FACEPLATES WITH RJ45 JACKS.

PULL OUT THE EXISTING RJ45 FACEPLATES AND LET HANG OUT TEMPORARILY.

INSTALL COMMUNICATION CABLES FROM ABOVE CEILING TO EUD FACEPLATE LOCATIONS.

TEST AND CERTIFY THE CABLES BY A GROUP OF ROOMS.

TERMINATE AND INSTALL RJ45 JACKS AT TR ROOM AND AT EUD FACEPLATES. PLUG INTO NEW 48-PORT PATCH

PANEL(S).

INSTALL LABELS AT EACH EUD FACEPLATE AND CORRESPONDING NEW 48-PORT PATCH PANEL(S). RECORD IN THE DATA SHOP DRAWINGS FOR DOCUMENTATION. LABEL EACH RACK AND EACH PATCH PANEL PER

CONTRACT REQUIREMENTS.

VA OIT TO CROSS CONNECT NEW 48-PORT PATCH PANEL TO CISCO SWITCH(ES) AND ACTIVATE THE NEW EUD

FACEPLATES.

VA OIT TO SWITCH THE EUD DEVICES FROM OLD FACE PLATES TO NEW FACEPLATES.

EUD DEVICES ARE NOW CONNECTED TO NEW CABLING.

PULLOUT AND REMOVE EXISTING FACEPLATES AND DATA CABLING FROM THE EUD LOCATIONS TO EXISTING

TR ROOM PATCH PANEL(S).

REPEAT PROCEDURE UNTIL THE DATA CABLING FOR ALL ROOMS SERVED BY THE NEW TR HAVE BEEN

COMPLETED.

INSTALL RACK TEMPERATURE AND HUMIDITY SENSORS.

CLEAN UP TR ROOM.

TURN OVER TR TO THE VA.

REMOVE EXISTING PATCH PANEL(S) AND DATA RACK(S) FROM EXISTING TR.

CONFIRM EXISTING HAZMAT CONDITIONS AND HAZMAT CLEARANCE

REQUIREMENTS WITH VA PRIOR TO COMMENCING WORK.

SHOP DRAWING NOTES

PROVIDE AN INDEPENDENT THIRD-PARTY COMMISSIONING AGENT TO

OVERSEE COMMISSIONING ACTIVITIES. PROVIDE COMPREHENSIVE

SUPPORT FOR COMMISSIONING OF THE SYSTEMS FOR THIS PROJECT.

COMMISSIONING FOR THIS PROJECT SHALL INCLUDE, BUT IS NOT

LIMITED TO, THE PROCESS OF DOCUMENTATION, TRAINING,

ADJUSTMENT, TESTING, CERTIFICATION, AND VERIFICATION OF

SYSTEMS TO ENSURE THAT THE COMPLETED SYSTEMS OPERATE AS

INTENDED IN THE CONSTRUCTION DOCUMENTS.

THE INTENT OF THE COMMISSIONING FOR THIS PROJECT IS TO PROVIDE

A FRAMEWORK TO EXPOSE CRITICAL ISSUES AND PROVIDE

RESOLUTIONS WITH INPUT FROM THE CONSTRUCTION TEAM BEFORE

INSTALLATION AND TURNOVER OF SYSTEMS AND EQUIPMENT. SUBMIT

ISSUES TO THE COMMISSIONING AGENT FOR COORDINATION WITH THE

COMMISSIONING TEAM WITH SUFFICIENT TIME FOR COORDINATION AND

RESOLUTION WITHOUT IMPACTING THE CONSTRUCTION CRITICAL PATH

SCHEDULE.

COMMISSIONING

1 . 1 1 1A -

BUILDING NUMBER

DISCIPLINE

A: ARCHITECTURAL

S: STRUCTURAL

M: MECHANICAL

E: ELECTRICAL

T: TELECOMMUNICATION

SHEET TYPE

1. GENERAL

4. ENLARGED

FLOOR NUMBER

SHEET NUMBER

EXAMPLE

DRAWING NUMBER NOMENCLATURE

1. CONTRACTOR SHALL PERFORM FIELD SURVEY FOR AREAS THAT WORK IS

PERFORMED PRIOR TO PREPARATION OF CONTRACTOR'S SHOP

DRAWINGS.

2. PROCEED WITH THE PREPARATION OF COMPREHENSIVE CONTRACTOR'S

SHOP DRAWINGS UPON RECEIPT OF NOTICE TO PROCEED (NTP) FOR THE

PROJECT. SHOP DRAWINGS SHALL BE ORIGINALLY PREPARED BY THE

CONTRACTOR, BASED UPON CONTRACTOR'S FIELD SURVEY, FOR AREAS

THAT WORK IS PERFORMED. PROVIDE SCALABLE PLANS COMPLETED

WITH AUTOCAD PROGRAM WITHIN 60 DAYS.

3. COORDINATE WITH EXISTING CONDITIONS AND OTHER TRADES

INCLUDING, BUT NOT LIMITED TO ARCHITECTURAL, STRUCTURAL,

SEISMIC, MECHANICAL, CONTROL SYSTEMS, ELECTRICAL POWER AND

LIGHTING SYSTEMS, COMMUNICATIONS AND DATA SYSTEMS, ELECTRONIC

SAFETY AND SECURITY SYSTEMS, FIRE SUPPRESSION SYSTEMS,

PLUMBING, SITE UTILITY DISTRIBUTION SYSTEMS, AND OTHER WORK

REQUIRED UNDER THIS PROJECT.

4. PROVIDE DEDICATED CONTRACTOR'S SHOP DRAWINGS FOR EACH

DISCIPLINE INCLUDING, BUT NOT LIMITED TO: ARCHITECTURAL,

STRUCTURAL, SEISMIC, MECHANICAL, CONTROL SYSTEMS, ELECTRICAL

POWER AND LIGHTING SYSTEMS, COMMUNICATIONS AND DATA SYSTEMS,

ELECTRONIC SAFETY AND SECURITY SYSTEMS, FIRE SUPPRESSION

SYSTEMS, PLUMBING, SITE UTILITY DISTRIBUTION SYSTEMS, AND OTHER

WORK REQUIRED UNDER THIS PROJECT.

5. CONTRACTOR'S SHOP DRAWINGS SHALL BE REVIEWED AND APPROVED

BY THE CONTRACTOR'S CONSTRUCTION QUALITY CONTROL (CQC)

SYSTEM MANAGER PRIOR TO SUBMITTAL TO THE VA TO ASSURE

CONTRACTIBILITY AND COMPLIANCE WITH THE DESIGN INTENT.

6. INCLUDE SIGNATURES ON COVER SHEET OF THE CONTRACTOR'S SHOP

DRAWINGS FROM ALL APPLICABLE TRADES AND CONTRACTOR'S CQC

SYSTEM MANAGER CONFIRMING ALL COORDINATION HAS OCCURRED

AND THE SUBMITTED CONTRACTOR'S SHOP DRAWINGS ARE FREE OF

CONFLICTS.

7. OBTAIN UPDATED ROOM NAME DESIGNATIONS FROM THE VA. INDICATE

ROOM NAME DESIGNATIONS ON AREAS OF WORK UNDER THIS CONTRACT

ON CONTRACTOR'S SHOP DRAWINGS.

8. CONTRACTOR IS RESPONSIBLE FOR REVIEWING AND CERTIFYING THAT

ALL SUBMITTALS ARE IN COMPLIANCE WITH CONTRACT REQUIREMENTS

BEFORE SUBMITTING FOR VA REVIEW. SUBMIT A COMPLETE AND

COMPREHENSIVE SET OF CONTRACTOR'S SHOP DRAWINGS IN ONE

PACKAGE FOR REVIEW BY THE VA PRIOR TO MATERIAL PROCUREMENT,

FABRICATION, OR INSTALLATION. CONTINUOUS UPDATING OF

CONTRACTOR'S SHOP DRAWINGS SHALL BE THE RESPONSIBILITY OF THE

CONTRACTOR AND SHALL BE UTILIZED FOR PREPARATION OF

CONTRACTOR'S RECORD DRAWINGS.

9. CONTRACTOR'S SHOP DRAWINGS SHALL REFLECT THE WORK REQUIRED

UNDER THIS PROJECT INCLUDING BUT NOT LIMITED TO THE FOLLOWING:

A. PIPING DUCTWORK, AIR INLETS, AIR OUTLETS, SENSORS, AND

CONTROLLERS.

B. ELEVATIONS OF RACKS IN TELECOMMUNICATIONS ROOMS AND MAIN

COMPUTER ROOMS, INCLUDING LABELING AND DETAILS.

C. LOCATION OF COMMUNICATION, DATA, AND POWER OUTLETS,

SWITCHES, AND JACKS, LIGHTING, PANELS, DATA, AND EQUIPMENT

RACKS. INDICATE THE LOCATION OF ORIGIN AND TERMINATION FOR

EACH POWER, DATA, AND COMMUNICATION CIRCUIT. INCLUDE

CONNECTIONS TO EQUIPMENT.

D. POINT OF CONNECTION TO UTILITIES AND TELECOMMUNICATIONS

NODES OUTSIDE THE BUILDINGS, INCLUDING BUT NOT LIMITED TO

THE LOCATIONS OF MANHOLES, TUBE DISTRIBUTION UNITS, AND

SITE UTILITY DISTRIBUTION.

E. HANGERS AND SUPPORTS, INCLUDING METHODS FOR BUILDING

ATTACHMENTS, SEISMIC RESTRAINTS, AND VIBRATION ISOLATION.

F. LOCATIONS OF STRUCTURAL PENETRATIONS INCLUDING BUT NOT

LIMITED TO PENETRATIONS OF WALLS, FLOORS, ROOFS, AND

STRUCTURAL ELEMENTS.

G. ACCESS PANELS INCLUDING CEILING AND WALL PANELS.

H. LOCATION OF EXISTING WALLS NOT IDENTIFIED ON THE PLANS AND

DESIGNATION OF FIRE RATING AND TYPES OF WALLS AFFECTED

UNDER THIS CONTRACT. PROVIDE A LOG OF ALL FIRE

PENETRATIONS THAT OCCURRED AS PART OF THE CONSTRUCTION

AS A DELIVERABLE AT THE COMPLETION OF THE PROJECT.

I. EXISTING BUILDING SYSTEMS AND UTILITIES BEING RELOCATED TO

ACCOMMODATE DESIGN.

J. DIMENSIONS OF ACTUAL PURCHASED EQUIPMENT.

K. ACCESS CLEARANCE FOR EQUIPMENT SERVICE.

L. LABEL AND TAG SCHEDULE FOR EQUIPMENT.

M. BUILDING GRIDLINES AND NORTH ARROWS.

APPLIES TO ALL DISCIPLINES UNDER THIS CONTRACT.

INFECTION CONTROL RISK ASSESSMENT (ICRA)

PERFORM THE WORK IN ACCORDANCE WITH THE VA-APPROVED PRECAUTION CLASS. ASSIGN A “CONSTRUCTION TYPE” FOR THE SCOPE OF WORK REQUIRED FOR EACH SPACE OR AREA OF WORK. UPON REQUEST, VA WILL ASSIGN “RISK GROUP” (LOW/MEDIUM/HIGH/HIGHEST) TO EACH SPACE OR AREA OF WORK. COORDINATE WITH VA AND OBTAIN APPROVAL

FROM VA PRIOR TO COMMENCEMENT OF WORK.

FIRE PROTECTION

FIRE PROTECTION SHALL BE PROVIDED BY THE CONTRACTOR. CONTRACTOR

SHOP DRAWINGS SHALL BE REVIEWED AND APPROVED BY THE CONTRACTOR'S

LICENSED FIRE PROTECTION PROFESSIONAL ENGINEER (FPE). COMPLY WITH

VA REQUIREMENTS AND THE REQUIREMENTS OF PERFORMANCE

SPECIFICATIONS OF THE PROJECT.

NEW WALL CONSTRUCTION

EXISTING WALLS

DEMO WALLS

WALL LEGEND

SYMBOL LEGEND

PIPE PIT

STAIR

MACHINE RM

B20

MACHINE RM

B50STORAGE

B51B

B16

DR. FELIX LEON

B26

CORRIDOR

MACHINE ROOM

B53

CO

RR

ID

OR

CO

RR

ID

OR

FIRE EXIT

B27

TISSUE

CULTURE

B26A

TISSUE

CULTURE LAB

B25C

EXPERIMENTAL

IMMUNOLOGY LAB

B28

TUMOR IMMUNOLOGY

CHEMISTRY LAB

B25

TUMOR IMMUNOLOGY

CHEMISTRY LAB

B29

GENERAL LAB

B30

N.C. LAB

B24

DATA PROCESSING

& OFFICE

B31

CHEM. RES. LAB.

B32

WALKING

COLD BOX

B22

HISTO

CHEMESTRY LAB.

B23

PREP.

& WASH UP RM.

B33

RESPIRATICY

PATTERN ANALYSIS

B21

B21A

B34

B34A

TEMPERATURE

CONTROL RM

B51A

STORAGE

B51C

JANITOR CL

B19

JANITOR

CL

B20A

STORAGE

B18

OFFICE

NEURO LAB

B17

DR. RAHWA LEE

B4 B3

FEMALE

LOUNGE

B52

ANIMAL

ROOM

B51

PIPE PIT TRANSFORMER ROOM

B54

OFFICE DEVELOPMENT

BIOLOGY LAB

C12

MACHINE RM

C13

D.B. LAB

C14

OFFICE

SECTY DBL

C11

D.B. LAB

C10 C15A C15B

GLASSWARE

CLEANING ROOM

C15

CELL BIOLOGY

LAB

C9

HYPERTENSION

RESEARCH LAB

C5

HYPERTENSION

RESEARCH LAB

C6

ELECTRON

MICROSCOP. RM.

C9A

ELECTRON

MICROSCOP. RM.

C8BC8A

CELL BIOLOGY

LABORATORY

C8A

HYPERTENSION

RESEARCH LAB

C7

FIRE EXIT

A38

STORAGE FOR

DR LITTNER

A39

STORAGE FOR

PETER EGGENA

A37

A40A

DRS. MC GINTY

SHOUSE & SZYMNSIAH

A40

A37A

STORAGE FOR

DR. SIEGEL

A41

STORAGE FOR

DR WIESBART

A36 A42

STORAGE FOR

DR CLAUDE WASTERLAIN

A43

A35 A36A

A49A

STORAGE FOR

DR BERNAL

A49

STORAGE FOR

DR ROSENTHAL

A48A A47 A46

STORAGE FOR

DR WEISBERT

A44

A45

B21B

B25

B2 B2B B1B2A

1 (TYP)

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Fi le

P at h U.S. Department of Veterans Affairs

B

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions: Date:

Key Plan

691A4-20-201FINAL CONSTRUCTION

DOCUMENTS

May 17, 2021 MS TS / JM

FULLY SPRINKLERED

A

GENERAL NOTES

KEY NOTES

ARCHITECT/ENGINEER OF RECORD

C

D

1611 PLUMMER ST, NORTH HILLS, CA, 91343

20801.13

Electronic Health Records Modernization (EHRM) Infrastructure Upgrades - Sepulveda, CA

1. PROVIDE UL LISTED FIRESTOPPING AT ALL PENETRATIONS

OF FIRE RATED WALLS.

2. ALL COMMUNICATION CABLING SHALL BE PROPERLY

SUPPORTED BY INDEPENDENT ROD / CABLE SYSTEMS.

CEILING SUSPENSION SYSTEMS SHALL NOT BE USED TO

SUPPORT COMMUNICATION CABLING.

3. COORDINATE RELOCATION OF EXISTING EQUIPMENT AND

FURNITURE WITH THE VA.

4. ALL PENETRATION SHALL HAVE NEW FIRE STOP SPEED

SLEEVES (HILTI CP 653 BA) THAT PENETRATE BETWEEN

ANY SMOKE OR FIRE BARRIER WALL. APPROPRIATE FIRE

STOP SYSTEMS SHALL BE INSTALLED AND RECORDED

INTO EXCEL SPREADSHEET CREATED BY CONTRACTOR.

ALL PENETRATIONS SHALL HAVE STICKERS PLACED NEXT

TO PENETRATIONS WITH COMPANY NAME, SYSTEM

NUMBER, FIRE / SMOKE BARRIER RATING AND JOB / REF

NUMBER.

5. TEMPORARILY SUPPORT ANY CEILING MOUNTED ITEMS

DURING CONSTRUCTION. REINSTALL AND SECURE BACK

TO THE ORIGINAL CONDITION UPON COMPLETION OF

WORK IN THE AREA.

6. REMOVE AND REINSTALL CEILINGS IN ALL OTHER AREAS

AS REQUIRED FOR INSTALLATION OF CABLING OR OTHER

COMPONENTS.

1.A-101

ARCHITECTURAL BASEMENT

FLOOR PLAN - BUILDING 1 BUILDING 1

ARCHITECTURAL BASEMENT FLOOR PLAN - BUILDING 1F1 SCALE: 3/32" = 1'-0" 0' 4' 16' 24'2' 8'

NORTH

BUILDING 1

1. REMOVE AND REINSTALL CEILING AS REQUIRED FOR

INSTALLATION OF CABLING OR OTHER COMPONENTS.

EX

HAZARDOUS ROOM (NFPA 101 §8.7)

INTERIOR EXIT LOCATION

EXTERIOR EXIT DISCHARGE

WALL TYPE LEGEND

3-HR. FIRE BARRIER

2-HR. FIRE/SMOKE BARRIER

1-HR. FIRE/SMOKE BARRIER

SMOKE BARRIER

SMOKE PARTITION

LIFE SAFETY LEGEND

HZ

BUILDING WALLS FIRE RATINGS

THE VA HAS LIMITED DOCUMENTATION OF FIRE RATINGS

FOR THE WALLS OF THE BUILDINGS INVOLVED IN THE

PROJECT. FIRE RATINGS OF WALLS FOR BUILDINGS

SHOWN ON THESE DRAWINGS ARE BASED UPON LIMITED

AVAILABLE INFORMATION PROVIDED BY THE VA. FIELD

VERIFY FIRE RATINGS OF WALLS IN ALL BUILDINGS

DURING THE SHOP DRAWING PROCESS.

CORRIDOR

PASSAGE

B124

STAIR

PASSAGE

B124

FISCAL

PAYROLL OFFICE

B169

EMPLOYMENT

OFFICE

FISCAL

B168

FISCAL

PAYROLL OFFICE

B167B170AB170

LOBBY

B100AB100B

IFCAP TRAINING

BID OPENING

B101B102

KEN REINBOLD

JAMES KREVITZ

B103

FISCAL OOFICE

A165

FINANCIAL

MGR. OFFICE

A165A

CHIEF

OF STAFF

SECRETARY

TO CHIEF

SECRETARY

A-162

FEMALE

TOILET

B155

MALE

TOILET

A157

JAN.

CLO. TOI.

CONTRACT

SERVICE

C106

JANITOR

C105

PROCUREMENT

SECTION

C112

DIRECTOR'S

CONF. ROOM

B125

PERSONNEL

OFFICE

B146

B150

MAIL

CENTER

B119

POST OFFICE

CHIEF PURCHASE

CONTRACT

C110

PETER EGGENA

DEPUTY ACCS.

CHIEF OF SUPPLY

SERVICE

C108

C113

MEN'S

TOILET

C114

WOMEN'S

TOILET

C116

BREAK

ROOM

C118

C117

JIM YEANCE

OFFICE

B126

PROCESSING

AND RECORDS

B-127

RETIREMENT

B131

B132

B133

ENVIRONMENTAL

MGMT.

B135

CHIEF OF

ACOS.

LABOR REL.

SPECIALIST

B145

CHIEF OF

PERSONNEL SER.

B144A

B144

PERSONNEL

B142

WOMEN'S

LOUNGE

B140

SPIRIT 1776

CONF. ROOM

WOMEN'S

TOILET

MEN'S

TOILET

CONFERENCE

ROOM

A158

ASS. DIRECTOR'S

OFFICE PASSAGE

CONFERENCE

A160

AA TO

DIRECTOR

DIRECTOR'S

OFFICE

C108

VESTIBULE

PERSONAL PROPERTY

MANAGEM'T SECTION

SUPPLY

STAFFING

B151 B152

STAFFING

B153B

PERSONNEL

SERVICE

B153

B143

PERSONNEL

B141

CLOS.

STOR.

JAN.

CLOS.

C115

CORRIDORCORRIDOR CORRIDORCO

RR

ID

OR

CO

RR

ID

OR

CO

RR

ID

OR CO

RR

ID

OR

LOADING

DOCK

LOADING

DOCK

FIRE EXIT

B147

B148

CAREER

MGMT

B149

BUDGET

ASSISTANT

C111A

FIRE EXIT

C107

TELECOM RM

B120A

TELECOM RM

A154

C4 A-401

1 (TYP)

E4 A-401

C1 A-401

E1 A-401

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Fi le

P at h U.S. Department of Veterans Affairs

B

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions: Date:

Key Plan

691A4-20-201FINAL CONSTRUCTION

DOCUMENTS

May 17, 2021 MS TS / JM

FULLY SPRINKLERED

A

GENERAL NOTES

KEY NOTES

ARCHITECT/ENGINEER OF RECORD

C

D

1611 PLUMMER ST, NORTH HILLS, CA, 91343

20801.13

Electronic Health Records Modernization (EHRM) Infrastructure Upgrades - Sepulveda, CA

1. PROVIDE UL LISTED FIRESTOPPING AT ALL PENETRATIONS

OF FIRE RATED WALLS.

2. ALL COMMUNICATION CABLING SHALL BE PROPERLY

SUPPORTED BY INDEPENDENT ROD / CABLE SYSTEMS.

CEILING SUSPENSION SYSTEMS SHALL NOT BE USED TO

SUPPORT COMMUNICATION CABLING.

3. COORDINATE RELOCATION OF EXISTING EQUIPMENT AND

FURNITURE WITH THE VA.

4. ALL PENETRATION SHALL HAVE NEW FIRE STOP SPEED

SLEEVES (HILTI CP 653 BA) THAT PENETRATE BETWEEN

ANY SMOKE OR FIRE BARRIER WALL. APPROPRIATE FIRE

STOP SYSTEMS SHALL BE INSTALLED AND RECORDED

INTO EXCEL SPREADSHEET CREATED BY CONTRACTOR.

ALL PENETRATIONS SHALL HAVE STICKERS PLACED NEXT

TO PENETRATIONS WITH COMPANY NAME, SYSTEM

NUMBER, FIRE / SMOKE BARRIER RATING AND JOB / REF

NUMBER.

5. TEMPORARILY SUPPORT ANY CEILING MOUNTED ITEMS

DURING CONSTRUCTION. REINSTALL AND SECURE BACK

TO THE ORIGINAL CONDITION UPON COMPLETION OF

WORK IN THE AREA.

6. REMOVE AND REINSTALL CEILINGS IN ALL OTHER AREAS

AS REQUIRED FOR INSTALLATION OF CABLING OR OTHER

COMPONENTS.

1.A-111

ARCHITECTURAL FIRST FLOOR

PLAN - BUILDING 1

ARCHITECTURAL FIRST FLOOR PLAN - BUILDING 1F1 SCALE: 3/32" = 1'-0" 0' 4' 16' 24'2' 8'

1. REMOVE AND REINSTALL CEILING AS REQUIRED FOR

INSTALLATION OF CABLING.

BUILDING 1

NORTH

BUILDING 1

EX

HAZARDOUS ROOM (NFPA 101 §8.7)

INTERIOR EXIT LOCATION

EXTERIOR EXIT DISCHARGE

WALL TYPE LEGEND

3-HR. FIRE BARRIER

2-HR. FIRE/SMOKE BARRIER

1-HR. FIRE/SMOKE BARRIER

SMOKE BARRIER

SMOKE PARTITION

LIFE SAFETY LEGEND

HZ

BUILDING WALLS FIRE RATINGS

THE VA HAS LIMITED DOCUMENTATION OF FIRE RATINGS

FOR THE WALLS OF THE BUILDINGS INVOLVED IN THE

PROJECT. FIRE RATINGS OF WALLS FOR BUILDINGS

SHOWN ON THESE DRAWINGS ARE BASED UPON LIMITED

AVAILABLE INFORMATION PROVIDED BY THE VA. FIELD

VERIFY FIRE RATINGS OF WALLS IN ALL BUILDINGS

DURING THE SHOP DRAWING PROCESS.B120A

A154

1 (TYP)

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Fi le

P at h U.S. Department of Veterans Affairs

B

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions: Date:

Key Plan

691A4-20-201FINAL CONSTRUCTION

DOCUMENTS

May 17, 2021 MS TS / JM

FULLY SPRINKLERED

A

GENERAL NOTES

KEY NOTES

ARCHITECT/ENGINEER OF RECORD

C

D

1611 PLUMMER ST, NORTH HILLS, CA, 91343

20801.13

Electronic Health Records Modernization (EHRM) Infrastructure Upgrades - Sepulveda, CA

1. PROVIDE UL LISTED FIRESTOPPING AT ALL PENETRATIONS

OF FIRE RATED WALLS.

2. ALL COMMUNICATION CABLING SHALL BE PROPERLY

SUPPORTED BY INDEPENDENT ROD / CABLE SYSTEMS.

CEILING SUSPENSION SYSTEMS SHALL NOT BE USED TO

SUPPORT COMMUNICATION CABLING.

3. COORDINATE RELOCATION OF EXISTING EQUIPMENT AND

FURNITURE WITH THE VA.

4. ALL PENETRATION SHALL HAVE NEW FIRE STOP SPEED

SLEEVES (HILTI CP 653 BA) THAT PENETRATE BETWEEN

ANY SMOKE OR FIRE BARRIER WALL. APPROPRIATE FIRE

STOP SYSTEMS SHALL BE INSTALLED AND RECORDED

INTO EXCEL SPREADSHEET CREATED BY CONTRACTOR.

ALL PENETRATIONS SHALL HAVE STICKERS PLACED NEXT

TO PENETRATIONS WITH COMPANY NAME, SYSTEM

NUMBER, FIRE / SMOKE BARRIER RATING AND JOB / REF

NUMBER.

5. TEMPORARILY SUPPORT ANY CEILING MOUNTED ITEMS

DURING CONSTRUCTION. REINSTALL AND SECURE BACK

TO THE ORIGINAL CONDITION UPON COMPLETION OF

WORK IN THE AREA.

6. REMOVE AND REINSTALL CEILINGS IN ALL OTHER AREAS

AS REQUIRED FOR INSTALLATION OF CABLING OR OTHER

COMPONENTS.

1.A-121

ARCHITECTURAL SECOND FLOOR

PLAN - BUILDING 1

ARCHITECTURAL SECOND FLOOR PLAN - BUILDING 1F1 SCALE: 1/4" = 1'-0" 0' 2' 4' 8'

BUILDING 1

NORTH

1. REMOVE AND REINSTALL CEILING AS REQUIRED FOR

INSTALLATION OF CABLING.

BUILDING 1

EX

HAZARDOUS ROOM (NFPA 101 §8.7)

INTERIOR EXIT LOCATION

EXTERIOR EXIT DISCHARGE

WALL TYPE LEGEND

3-HR. FIRE BARRIER

2-HR. FIRE/SMOKE BARRIER

1-HR. FIRE/SMOKE BARRIER

SMOKE BARRIER

SMOKE PARTITION

LIFE SAFETY LEGEND

HZ

BUILDING WALLS FIRE RATINGS

THE VA HAS LIMITED DOCUMENTATION OF…

This is the start of the file's text. The full file is on GovTribe.