S02 - Attachment 1 - Columbia EHRM Statement of Work 21Feb23.pdf
PDF 82 KB Posted
- Attached to
- EHRM Infrastructure Upgrades Construction - Columbia, SC VAMC Federal contract opportunity
- Solicitation number
- 36C77623R0096
About this file
This statement of work outlines infrastructure upgrades to support the Electronic Health Records Modernization program at the Columbia VA Health Care System in Columbia, South Carolina. The scope of work includes a complete replacement of the primary voice and data network cabling system for all in-scope buildings, creation of new telecom rooms, renovation of the existing data center including new cabinets and electrical work, replacement of the UPS system, new exterior duct banks and pathways between buildings and the data center, and electrical, security, and HVAC work. Buildings included are 5, 6, 7, 8, 9/9A, 20, 21, 22, 100, 100A, 103, 103A, 105, 106, 114, 120, 122, VARO, T25, T36, 133 and the associated outside plant. The period of performance is 365 calendar days. Bidders must comply with all requirements in the construction drawings, specifications and solicitation amendments. Normal work hours are 7am-5pm Monday through Friday excluding federal holidays and work outside these hours requires coordination.
The related federal contract opportunity is solicitation number 36C77623R0096 for the EHRM Infrastructure Upgrades Construction project at the Columbia, South Carolina VAMC, issued by the Department of Veterans Affairs Technology Acquisition Center Austin.
View the file
Other files for this federal contract opportunity
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COLUMBIA VA HEALTH CARE SYSTEM
6439 Garners Ferry Road
Columbia, SC 29209
STATEMENT OF WORK
Project #544-20-107
EHRM Infrastructure Upgrades-Columbia, SC
The purpose of the project is to provide infrastructure improvements to support Cerner’s Electronic
Health Records Modernization (EHRM) Program at Columbia VA Health Care System, Columbia, South
Carolina. These improvements include the following:
• Complete replacement of the entire primary voice/data network structured cabling system (inside and outside plant) for all in-scope buildings to meet EHRM requirements, including fiber backbone cabling, and IT racks.
• Creation of new Telecom Rooms to support the new structured cabling system.
• Complete renovation of the existing (to remain fully functional) Data Center including new IT cabinets, structured cabling and pathways, UPS/electrical, clean agent system, lighting, and
CRAC units.
• Replacement of the existing (to remain fully functional) UPS and associated equipment.
• New Outside Plant duct banks, manholes, and handholes to support the new Data Center to building voice/data network structured cabling system and provide diversified paths from remote
Telecom Rooms (TRs) in scoped buildings to the data center for WAN.
• Electrical; panel upgrades, normal and emergency power, bonding, and UPS.
• Electronic Security assets for new TRs and Data Center, including connections to existing
Building Management Systems (BMS) interfaces.
• New design and upgrades for existing HVAC.
• Reconfiguration, expansion, and renovation of existing space.
• Hazardous material abatement as required.
The scoped Buildings are: 5, 6, 7, 8, 9/9A, 20, 21, 22, 100, 100A, 103, 103A, 105, 106, 114, 120, 122, VARO, T25, T36, 133, and the site outside plant distribution system campus-wide on the Columbia VA
Health Care System Campus on Garners Ferry Rd, Columbia, SC. This project examined the best and appropriate locations for the new TRs and Telecom Enclosures (TEs) for each of the scoped buildings.
The project also examined the best location for pathways of duct banks with the diversified fiber between the scoped buildings and the main data center. Existing utility locations have been identified as best as possible, excavation in support of the duct banks will require use of ground penetrating radar to pinpoint locations that require deconflicting. Routing refinement of the duct bank trenches to avoid existing utilities and coordinating with the COR prior to excavation is an important part of the site work. Other items include:
• Bidders required to include execution of survey testing and removal of LBP in all areas of work prior to commencement of demolition and/or new construction activities. Contractor must notify
Contracting Officer Representative immediately of any positive samples and removal plans.
• Bidders required to include execution of survey testing and abatement for ACM in any areas the contractor suspects may have ACM prior to commencement of demolition and/or new construction activities. Contractor must notify Contracting Officer Representative immediately of any positive samples and the detailed abatement plans. (Recent LBP and ACM testing results are included in this bid package)
• Bidders are responsible for the entirety of the project scope described in the contract documents
(drawings and specifications) and shall submit RFI’s on any conflicts between drawings and specifications immediately that may impact bids.
• Any content in the contract documents that bidders miss or do not provide pricing for, are still the responsibility of the contractor and will be installed as directed in the contract documents at no additional cost to the government.
BID DEDUCTS:
• None identified
The contractor shall comply with all requirements as listed in the project solicitation including the construction drawings, the project specifications, and all solicitation amendments as may be issued. These documents will be followed during construction and shall be considered project requirements.
Normal operating hours of the Columbia VA Health Care System are 7am-5pm, Monday-Friday, excluding Federal Holidays. Work outside of these hours shall be coordinated with the COR.
The C&A requirements do not apply, and a Security Accreditation Package is not required.
The period of performance for this project is 365 calendar days.
File details come from the government source that posted it. Updated .