S02_Att 1_920CM3006 Fort Sill NC IFB SOW_Final.pdf

PDF 371 KB Posted

Attached to
Y1PZ--Fort Sill NC Gravesite Expansion and FCA Deficiencies 920CM3006
Solicitation number
36C78626B0030
Issued by

About this file

This is an Invitation for Bid (IFB) Scope of Work document for construction services at Fort Sill National Cemetery in Elgin, Oklahoma, issued by the Department of Veterans Affairs National Cemetery Administration.

The project, numbered 920CM3006, encompasses burial expansion and correction of FCA (Facilities Condition Assessment) deficiencies at the cemetery. The contract contains two contract line items (CLINs): CLIN 0001 for general construction work including all installation activities shown in the plans and specifications, with Bid Option 1 covering additional work for construction of Columbarium C; and CLIN 0002 for an asphalt assessment of all longitudinal and transverse cracks in existing roadways throughout the cemetery, with the contractor required to provide a detailed assessment report and recommended repair methods. The assessor must have five or more years of experience with asphalt repairs and be approved in writing by the National Cemetery Administration.

The contractor is responsible for providing all labor, materials, tools, equipment, and services necessary for project completion, including complete coordination between trades and quality control of all subcontractor work. All work must occur during normal cemetery operating hours (Monday–Friday, 8:00 a.m.–4:30 p.m., closed federal holidays except Memorial Day and Veterans Day), with work ceasing during internments and ceremonies. The construction performance schedule allows 18 calendar months from notice to proceed. The document requires submission of a detailed price breakdown and cost schedule matching the project performance schedule line items. Work must comply with historic preservation standards, as the cemetery is listed in the National Register of Historic Places and subject to Section 106 of the National Historic Preservation Act.

View the file

Other files

File Type Posted
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_11 of 11.pdf PDF
S02_Attachment-14_IFB Contractor Cost Estimate Worksheet.xlsx XLSX spreadsheet
S06_Fort Sill NC_920CM3006_Combined Specifications_Rev 01.pdf PDF
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_10 of 11.pdf PDF
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_4 of 11.pdf PDF
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_6 of 11.pdf PDF
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_8 of 11.pdf PDF
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_1 of 11.pdf PDF
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_5 of 11.pdf PDF
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_3 of 11.pdf PDF
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_7 of 11.pdf PDF
P07_WD_OK20260043.pdf PDF
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_9 of 11.pdf PDF
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_2 of 11.pdf PDF
S05_Prebid RFI_26B0030 Fort Sill_Gravesite Expansion and FCA.pdf PDF
S06_36C78626B0030 0002.pdf PDF
S06_36C78626B0030 0001.pdf PDF
S04_Ft Sill_Site Visit Attendance.pdf PDF
P07_WD_OK20260023.pdf PDF
S02_Att 4_Fort Sill NC 920CM3006 Plan Set Reduced 2 of 11.pdf PDF
S02_Att 5_Fort Sill NC 920CM3006 Plan Set Reduced 3 of 11.pdf PDF
S02_36C78626B0030_Final.pdf PDF
S02_Att 12_Fort Sill NC 920CM3006 Plan Set Reduced 10 of 11.pdf PDF
S02_Att 2_Fort Sill NC 920CM3006 Combined Specifications.pdf PDF
S02_Att 3_Fort Sill NC 920CM3006 Plan Set Reduced 1 of 11.pdf PDF
S02_Att 9_Fort Sill NC 920CM3006 Plan Set Reduced 7 of 11.pdf PDF
S02_Att 8_Fort Sill NC 920CM3006 Plan Set Reduced 6 of 11.pdf PDF
S02_Att 7_Fort Sill NC 920CM3006 Plan Set Reduced 5 of 11.pdf PDF
S02_Att 13_Fort Sill NC 920CM3006 Plan Set Reduced 11 of 11.pdf PDF
S02_Att 6_Fort Sill NC 920CM3006 Plan Set Reduced 4 of 11.pdf PDF
S02_Att 11_Fort Sill NC 920CM3006 Plan Set Reduced 9 of 11.pdf PDF
S02_Att 10_Fort Sill NC 920CM3006 Plan Set Reduced 8 of 11.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Invitation For Bid Scope of Work

Fort Sill National Cemetery Elgin, OK

Gravesite Expansion AND FCA Deficiencies

Project Number 920CM3006

Project Scope For Construction Date: June 2026

Department of Veterans Affairs

National Cemetery Administration

Design and Construction Service

TABLE OF CONTENTS

1. GENERAL

2. PROJECT GOAL

3. STATEMENT OF BID ITEM

4. BACKGROUND

5. OPERATIONAL CONSIDERATIONS

6. ENVIRONMENTAL COMPLIANCE

7. HISTORIC COMPLIANCE

8. PROJECT SCOPE - VA NCA

9. GOVERNMENT PROVIDED CONSTRUCTION DOCUMENT PACKAGE

10. CONSTRUCTION CRITERIA

11. CONSTRUCTION PERFORMANCE SCHEDULE

1. GENERAL

1.1. This Scope of work (SOW) identifies the goal and objectives of this construction project.

1.2. The construction contractor shall provide all labor, materials, tools and equipment, and services necessary to construct this project per the construction documents and specifications.

1.3. The construction contractor shall be responsible for the quality and completeness of the construction project. Complete and accurate coordination between the trades and quality control of all sub-contractor’s work shall be required.

2. PROJECT GOAL

2.1. Construction goal for Fort Sill National Cemetery is Burial Expansion and Correct FCA

Deficiencies per the construction documents and specifications attached herewith.

3. STATEMENT OF BID ITEM

3.1. CLIN 0001, GENERAL CONSTRUCTION: Installation of all work shown on the plans and described in the specifications excluding work associated with CLIN 0002 & Bid Option 1.

• Bid Option 1 includes all work associated with the construction of Columbarium C and as described within the plans as BID OPTION 1

3.2. CLIN 0002, ASSESSMENT: Contractor shall perform an asphalt assessment by of all longitudinal and transverse cracks within the existing asphalt roadways throughout the entirety of the cemetery including all roadways, drives and parking areas. The contractor shall provide the NCA with an assessment report describing the current roadway conditions and provide recommended repairs methods to address the deficiencies. The assessment shall be performed by a competent person with five or more years of experience with asphalt repairs.

The assessor shall be approved in writing by the NCA.

4. BACKGROUND

4.1. Fort Sill National Cemetery in Elgin, OK, was dedicated on November 2, 2001. The Fort Sill

National Cemetery was the second national cemetery to be constructed in Oklahoma and became the 120th national cemetery to be administered by the National Cemetery Administration. Fort Sill National Cemetery lies in southwestern Oklahoma, approximately 75 miles from Oklahoma City and five miles north of Lawton. Land for the national cemetery was transferred from the Department of the Army's Ft. Sill Military Reservation in 1998.

5. OPERATIONAL CONSIDERATIONS

5.1. Each national cemetery is managed by VA National Cemetery Administration (NCA) personnel in conformance with national and regional (Continental District) policies, priorities, goals, and objectives. The functions of a national cemetery include the operation and maintenance of all aspects of the cemetery. Typically, this includes burial of veterans and eligible family members, the interment of cremated remains, and the placement and maintenance of a headstone or grave marker. Cemetery operations include the conduct of Memorial Day and other special ceremonies, as well as the care of graves, structures and grounds. Fort Sill National Cemetery is operated and maintained by Cemetery staff and operating hours are Monday through Friday, 8:00 am – 4:30 pm. Closed federal holidays except Memorial Day and Veterans Day.

5.2. All work must take place during normal operating hours. Any request to work over these hours must be requested in writing and approved by Cemetery Director in conjunction with COR a minimum of 72 hrs. in advance. Also, the Cemetery hosts numerous ceremonies and events. Work that interferes with these ceremonies will cease during ceremonies. Notice will be provided by the Cemetery staff 5 days in advance of scheduled ceremonies whenever possible. Occasionally events are scheduled with less than 5 days’ notice in which case the Cemetery will provide as much notice as is possible.

5.3. Parking is limited. Construction staff vehicle parking areas are to be coordinated with the COR and cemetery director. Offsite parking will be required, VA NCA will not reimburse for such parking.

5.4. No smoking inside cemetery grounds.

5.5. Proper attire and professional conduct are required at all times.

5.6. All work must cease during the time an internment is taking place near the construction site. Special care must be taken to accommodate visitors and to ensure work does not interfere with their visit and ensure that there are no safety hazards present.

6. ENVIRONMENTAL COMPLIANCE

6.1. Based upon Department of Veterans Affairs “Environmental Effects of VA Actions,” 38

CFR Part 26, this project is “categorically excluded” from the need for environmental documentation, specifically Section 26.6 of said code paragraph (b)(2).

7. HISTORIC COMPLIANCE

7.1. This project is located at the Fort Sill National Cemetery, which is listed in the National

Register of Historic Places (NRHP). The proposed scope of work for this project is subject to compliance with Section 106 of the National Historic Preservation Act (P.L. 89-665, as amended). Accurate documentation of the work is required for this project to indicate the protection of cultural landscapes and be compatible with contributing elements within the Cemetery. Work on historic resources must meet the Secretary of the Interiors Standards for the Treatment of Historic Resources.

8. PROJECT SCOPE ‐ VA NCA requires the offeror to submit a detailed price breakdown/cost schedule in the proposal which includes cost detail for each scope of work item, cost schedule line items shall match project performance schedule line items.

9. Government Provided Construction Document Package

9.1. The following construction documents are attached for your use.

• Drawings

• Specification.

10. Construction Criteria‐ See government provided construction document package, section 9 above.

11. Construction Performance Schedule:

11.1. 18 Months calendar days from notice to proceed.

Signed by Homayoun Kazemipour, COR -----------------------------------------------------

1. GENERAL
2. PROJECT GOAL
3. STATEMENT OF BID ITEM
4. BACKGROUND
5. OPERATIONAL CONSIDERATIONS
6. ENVIRONMENTAL COMPLIANCE
7. HISTORIC COMPLIANCE
9. Government Provided Construction Document Package
11. Construction Performance Schedule: