This file contains Prebid Requests for Information (RFIs) and corresponding Government Responses for a federal construction contract at Fort Sill National Cemetery in Oklahoma (Solicitation Number 36C78626B0030). The project involves gravesite expansion and cemetery facility condition assessment improvements, with an estimated start date of January 2027 and a period of performance of 545 calendar days (approximately 18 months).

The project is a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside solicitation managed by the National Cemetery Administration (NCA). Key deliverables include construction of 3,554 precast concrete burial crypts (with quantities confirmed as 3,503 standard 3'x8' spaces and 51 oversized 4'x10' spaces), two new columbarium sections (E and H), facility improvements to committal shelters and the administration/maintenance buildings, asphalt pavement assessment with crack repair recommendations (CLIN 0002—assessment only, with physical repairs handled separately), roadway and site work, telecommunications infrastructure upgrades, and landscape restoration. Bid Option 1 (Columbarium C) has been removed from the solicitation. The contract includes multiple CLINs: CLIN 0001 (General Construction excluding assessment and bid options), CLIN 0002 (Asphalt Assessment), and CLIN 0003 (Crypts—material and delivery only, with installation included in CLIN 0001). Wage determinations include OK20260023 (Heavy, Comanche County) and an additional building wage determination (OK20260043). Government-furnished property is limited to niche covers. The solicitation was extended to October 19, 2026, at 1200 EST for bid opening, and all prebid RFI responses were confirmed to be provided prior to that date.

View the file

Other files

File Type Posted
S06_36C78626B0030 0005.pdf PDF
S06_36C78626B0030 0004.pdf PDF
S06_36C78626B0030 0003.pdf PDF
S02_Attachment-14_IFB Contractor Cost Estimate Worksheet.xlsx XLSX spreadsheet
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_6 of 11.pdf PDF
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_1 of 11.pdf PDF
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_11 of 11.pdf PDF
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_2 of 11.pdf PDF
S02_Attachment-14_IFB Contractor Cost Estimate Worksheet.xlsx XLSX spreadsheet
S06_Fort Sill NC_920CM3006_Combined Specifications_Rev 01.pdf PDF
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_8 of 11.pdf PDF
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_10 of 11.pdf PDF
S06_36C78626B0030 0002.pdf PDF
P07_WD_OK20260043.pdf PDF
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_9 of 11.pdf PDF
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_4 of 11.pdf PDF
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_5 of 11.pdf PDF
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_7 of 11.pdf PDF
S06_Fort Sill NC_920CM3006_Plan Set_Reduced_Amend 01_3 of 11.pdf PDF
S06_36C78626B0030 0001.pdf PDF
S04_Ft Sill_Site Visit Attendance.pdf PDF
S02_Att 4_Fort Sill NC 920CM3006 Plan Set Reduced 2 of 11.pdf PDF
S02_Att 1_920CM3006 Fort Sill NC IFB SOW_Final.pdf PDF
P07_WD_OK20260023.pdf PDF
S02_Att 6_Fort Sill NC 920CM3006 Plan Set Reduced 4 of 11.pdf PDF
S02_Att 2_Fort Sill NC 920CM3006 Combined Specifications.pdf PDF
S02_Att 5_Fort Sill NC 920CM3006 Plan Set Reduced 3 of 11.pdf PDF
S02_Att 3_Fort Sill NC 920CM3006 Plan Set Reduced 1 of 11.pdf PDF
S02_36C78626B0030_Final.pdf PDF
S02_Att 11_Fort Sill NC 920CM3006 Plan Set Reduced 9 of 11.pdf PDF
S02_Att 10_Fort Sill NC 920CM3006 Plan Set Reduced 8 of 11.pdf PDF
S02_Att 9_Fort Sill NC 920CM3006 Plan Set Reduced 7 of 11.pdf PDF
S02_Att 12_Fort Sill NC 920CM3006 Plan Set Reduced 10 of 11.pdf PDF
S02_Att 13_Fort Sill NC 920CM3006 Plan Set Reduced 11 of 11.pdf PDF
S02_Att 7_Fort Sill NC 920CM3006 Plan Set Reduced 5 of 11.pdf PDF
S02_Att 8_Fort Sill NC 920CM3006 Plan Set Reduced 6 of 11.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Prebid RFIs and Responses

SOLICITATION NUMBER: 36C78626B0030

PROJECT TITLE: - Fort Sill NC Gravesite Expansion and Cemetery FCA Improvements

Question 1) EP101 / Detail C6 — Concrete ductbank is called out in the Keyed Notes #1 & #2 and shown on detail C6. It calls for this type of installation between the "Administration" and "Maintenance" buildings, however no trench is shown to be excavated between these two buildings. Is part of Irrigation Controller H's trench to be a duct bank?

Response: That is correct. The irrigation line is in a duct bank, there is no installation between the administration building and the maintenance building.

Question 2) EP103 — Keyed Notes 1-7. Was voltage drop factored into the circuit design?

Response: Yes voltage drop was factored into this design, the voltage drop for this circuit was 2.8 under the the allowable 3% according to the NEC

Question 3) Specifications, Division 28; 28 13 00, 28 13 53, 28 23 00 — Access Controls and Video Surveillance are listed in the specs, but none appear on the drawings. Are any cameras or access controls included in this project?

Response: Refer to Sheets T-102 and T-601 for access reader and other Telecommunications Room security requirements. The TR door frame has access control on sheet E-501. [See response to Question 77]

Question 4) Specifications, Division 28. 28 31 00; Drawings E-101, E-102, E-103 — Simplex is called in the Equipment Schedules. Are any other brands of equipment acceptable? Is voice/mass notification required?

Response: Simplex is provided as a basis for design, an approved equal would work as well.

Voice/mass notification is not required.

Question 5) LP-402 — Drawing LP-402 does not include sod within the planter areas at the Columbarium Plaza. Please confirm sod is to be installed within the planter areas around the new tree locations.

Response: This will be revised. Please see amendment 001.

Question 6) LP-401 — Drawing LP-401 appears to cut off portions of the new pre-placed crypt section and the restoration limits on the temporary gravel road. Please provide drawing with full limits.

Response: This will be revised. Please see amendment 001.

Question 7) 03 48 24— Paragraph 1.4.B & 1.6.A.9 states to provide written documentation that verifies the installer has been regularly engaged for at least three years, in installation of pre-cast concrete similar to this project. Please confirm that the installer will be required to submit verification that they have installed precast concrete columbarium units for at least three years.

Response: Yes.

Question 8) The solicitation/SF 1442 states that bidders shall complete "S02_Attachment 5_IFB Contractor Cost Estimate Worksheet" as part of the bid submission; however, Section L identifies the required document as "S02_Attachment-16_IFB Contractor Cost Estimate Worksheet". Clarify the correct attachment/worksheet that bidders are required to complete and submit with the bid.

Response: The attachment was previously missing and mislabeled. Attached now as S02_Attachment-14_IFB Contractor Cost Estimate Worksheet.

Question 9) Please confirm whether the Contractor’s Superintendent may also serve as the Site Safety and Health Officer (SSHO) and Quality Control Manager (QCM) for this project, provided the individual meets all required qualifications, certifications, experience, and availability requirements for each position. If combining these roles is permitted, please clarify whether any limitations or additional Government approval requirements apply.

Response: Superintendent may be dual-hatted as SSHO but must have all necessary qualifications, certifications, experience and availability requirements. QCM must be a stand-alone individual.

Question 10) Bid Option 1 / Columbarium C Scope: Please confirm whether Bid Option 1 – Columbarium C is to be priced and submitted with this solicitation. The SOW identifies Columbarium C as Bid Option 1, while the specifications indicate Bid Option 1 is “not included in this solicitation.”.

Response: Option 1 will not be solicited.

Question 11) Also confirm which associated sitework, drainage, irrigation, landscaping, benches, signage, and utilities are to be included/excluded from the base bid. Columbarium C associated sitework.

Drawing G-002 states that all work associated with Columbarium C is Bid Option 1, including signage, drainage, landscaping/irrigation, Drainage Run 3, the tie-in to Columbarium B, portions of irrigation sheet LI402, flower-water stations and work within the shared columbarium yard. Please clearly identify the limits separating Base Bid work from Bid Option 1 within the shared Columbarium C/E/H area, particularly irrigation, drainage, landscaping, paving and common-yard improvements.

Response: Columbarium C infrastructure is not connected to a common-yard as Columbarium E & H. See inset D8 on sheet G-002

Question 12) Quad crypts vs. individual double-depth crypts. Specification Section 03 48 21 is specifically titled “Precast Concrete Burial Crypts (Double Depth Lawn Crypt)” and the project requires 3,554 crypts. Will the Government permit precast quad crypt units consisting of two double-depth burial spaces side-by-side in lieu of individual double-depth crypt units, provided the required plot dimensions, spacing, structural performance, finished elevations and other contract requirements are maintained?

Response: Quad crypts will be approved as an acceptable alternative as long as they meet the equivalent project specifications.

Question 13) CLIN 0002 – Asphalt assessment versus repairs. Section 01 00 02 describes CLIN 0002 as an assessment of existing asphalt cracking, including a report and recommended repair methods. Please confirm CLIN 0002 is assessment/reporting only and does not include repair, sealing or replacement of the existing asphalt deficiencies identified during the assessment, except for paving work separately indicated as part of CLIN 0001

Response: CLIN 0002 is as described in specification 01 00 02. Some roadway repairs are included as CLIN 0001 as indicated in note 1 on sheet C-102.

Question 14) Government-furnished materials — Section 01 00 02 states Government-furnished property shown on the drawings will be delivered to the contractor at the cemetery, with the contractor responsible for assembly/installation and connection materials. Please provide a complete list and quantities of all

Government-furnished materials/equipment for this project and clarify contractor responsibility for unloading, handling, storage, protection, replacement of damaged Government-furnished material and installation hardware.

Response: Government furnished property is limited to Niche Covers.

Question 15) PPC quantities/configuration — The drawing summary identifies 3,554 PPCs: Section 7 – 1,312 standard plus 22 oversized; Section 8 – 1,321 standard plus 9 oversized; Section 9 – 870 standard plus 20 oversized. Please confirm these quantities — 3,503 standard 3'x8' crypt spaces and 51 oversized 4'x10' crypt spaces — are the contractual quantities to be used for bidding and CLIN 0003 pricing.

Response: Quantities confirmed as indicated and shown in plans, also to be utilized for bidding.

Question 16) Existing/shared irrigation controller — Please identify all irrigation mainline, submain, controller, wiring and flower-water-station work that is to remain in the Base Bid if Bid Option 1 is not awarded.

Response: No irrigation will be included for the areas indicated on sheet G-002. All additional irrigation repairs and service to the columbarium included in the base bid is a part of this contract.

Question 17) When is the project expected to start?

Response: The project is estimated to start in January 2027.

Question 18) When will the sign in sheet be posted?

Response: The sign-in sheet was published on 10/8/2026.

Question 19) Please clarify what advance notice or look-ahead schedule the Government will provide for upcoming burials during construction. Will the Contractor receive an updated burial schedule at the end of each workday identifying the following day’s anticipated burial activities, or will a longer look-ahead schedule be provided? Please also confirm the minimum advance notice the Contractor can expect so that manpower, equipment, access, and construction activities can be properly coordinated on a day-to-day basis without impacting cemetery operations.

Response: The typical notice will be approximately 48-96 hours, however the NCA reserves the right to reduce that advanced notice should a short notice internment be scheduled.

Question 21) If combining these roles is permitted, please clarify whether any limitations or additional Government approval requirements apply.

Response: Personnel proposed for these roles must possess necessary certs for each role. [See response to Question 9]

Question 22) Section 31 20 11 generally states that when unsuitable material is encountered and removed, contract price and time will be adjusted under the Differing Site Conditions/Changes provisions. However, the roadway/curb/sidewalk subgrade requirements state that unsuitable soils encountered during proof-rolling shall be removed/replaced or stabilized at no additional cost to the Government until a passing proof-roll is achieved. Please clarify which requirement governs unsuitable soils encountered beneath proposed curbs, roadways, and sidewalks and identify the extent of unsuitable-soil remediation bidders are to include in the Base Bid.

Response: Unsuitable soils will be considered differing site conditions. See revised specification 31 20 11.

Question 23) Please confirm that the existing irrigation system has sufficient available flow and pressure to support the proposed irrigation improvements as designed. If existing system flow or pressure is determined to be insufficient after award, please clarify whether modifications to existing pumps, mains, controls, or other existing irrigation infrastructure beyond that specifically shown in the contract documents will be considered additional work.

Response: The existing irrigation system water source is nearing its capacity. Increasing the capacity was not a part of this project. Any modifications to the water source or pumping system would be considered additional work.

Question 24) Please confirm that the required Flower Water Station (FWS) leak repairs are limited to the locations specifically identified on the contract drawings, including Sheet LI402, and that no additional FWS leak repairs beyond the locations shown are required as part of the Base Bid.

Response: Confirmed.

Question 25) Section 31 20 11 requires the upper 30 inches of subgrade below floor slabs, including the columbaria and repair-area slabs, to consist of approved Low Volume Change (LVC) material. For purposes of establishing a consistent bid basis, please provide the quantity or depth of existing soil that bidders shall assume requires removal and replacement with compliant LVC material, or confirm that bidders shall assume the entire upper 30 inches within these areas is to be removed and replaced with compliant LVC material.

Response: Bidders shall reference the geotechnical boring logs to determine the extents of material removal.

Question 26) Please confirm that existing soils within the required upper 30-inch LVC zone that are tested and determined to meet the specified LVC material requirements may remain in place and will not be required to be removed and replaced.

Response: Confirmed.

Question 27) Please confirm that CLIN 0002 shall include the required pavement assessment/report and crack sealing/repair of up to 2,500 LF of transverse asphalt cracking identified on the contract drawings, and that any crack sealing/repair exceeding 2,500 LF will be established through the required pavement assessment prior to commencement of repair work and handled as additional work through a contract modification.

Response: Confirmed.

Question 28) Please identify whether suitable excavated material may be reused elsewhere on the cemetery property and whether excess suitable soil may be stockpiled/spread at a Government-designated location, or whether bidders shall assume all excess material must be hauled off-site.

Response: All suitable may be reused pending an approved test confirming its suitability and may be stockpiled in the location indicated on the construction plans. All excess materials not used as apart of this project must be disposed of off-site at no additional cost to the government.

Question 29) Section 01 00 02 requires 7-foot-high chain-link construction fencing around construction areas indicated on the drawings. Please confirm whether the Contractor may relocate/reuse temporary fencing as work progresses between phases rather than maintaining fencing around all Base Bid work areas simultaneously.

Response: Confirmed.

Question 30) Please identify the approved construction haul route(s) and any vehicle weight, size, operating-hour, or cemetery-traffic restrictions bidders should incorporate into their pricing.

Response: Haul routes are shown on the construction plans. There are no vehicle size and weight limitations, however all damage caused by the contractor is to be repaired at no additional cost to the government. Operating hours are the same as cemetery operating hours from 8:00am to 4:30pm.

Question 31) Please confirm that bidders are not required to include an allowance for over excavation below the planned foundation excavation elevations due to unsuitable bearing soils, and that any additional excavation and replacement required below the elevations indicated in the contract documents will be addressed in accordance with the Differing Site Conditions/Changes provisions of the contract.

Response: Confirmed.

Question 32) Please confirm that correction or replacement of existing irrigation system components found to be defective during testing, but not specifically identified for repair or replacement in the contract documents, is not included in the Base Bid and will be addressed as additional work.

Response: Anything outside of the SOW identified for repair or replacement would be considered a differing condition and shall be brought to the attention of the COR prior to advancing work.

Question 33) C-506 -- Drawing C-506 includes an underdrain system at the Assembly Plaza. It is assumed that this is to be a new system, however the drawing does not include a scale and all details are labeled N.T.S. To ensure accurate takeoff of materials required, please provide scale for drawing C-506.

Response: Details are not drawn to scall. Dimensions can be scaled off drawing sheets for quantities. Dimensions on details are provided for depths of fill materials.

Question 34) 03 48 21 -- Paragraph 1.5.C states to provide written documentation that verifies the installer has been regularly engaged for at least three years, in installation of pre-cast concrete similar to this project. Please confirm that the installer will be required to submit verification that they have installed precast concrete burial crypts for at least three years.

Response: Confirmed. Three years of installation experience is required.

Question 35) 1. Missing Cost Estimate Worksheet (Attachment 5 / Attachment-16) -- SF 1442 cover (Item 10) requires the bidder to complete “S02_Attachment 5_IFB Contractor Cost Estimate Worksheet” as part of the bid package. Section L, Virtual Bid Instructions ¶3.d, likewise requires “Completed S02_Attachment-16 _IFB Contractor Cost Estimate Worksheet.” Neither that worksheet nor any file titled Attachment 5 / Attachment-16 Cost Estimate Worksheet appears among the SAM attachments for this opportunity. On SAM, “S02_Att 5” is Plan Set Reduced 3 of 11, not a cost worksheet. Please provide the Cost Estimate Worksheet (Att 5 / Att-16), or confirm the correct filename/location and whether an amendment will post it.

Response:[See response to Question 8]

Question 36) Bid Option 1 / Columbarium C — Spec vs Schedule B conflict. Schedule B CLIN 0004 — OPTION 1 Construct Columbarium C is a priced line item, and FAR 52.217-4 (Section M) states options will be evaluated by adding the option price to the basic requirement. However, Spec Section 01 00 02 ¶1.2.A states: “(Bid option 1 is not included in this solicitation).” Please confirm whether CLIN 0004 /

Columbarium C is part of this IFB and must be priced, or whether that Spec sentence is a document error to be corrected by amendment.

Response: [See response to Question 10]

Question 37) Limitations on Subcontracting — VOSB vs SDVOSB under the 85% rule -- This IFB is a 100% SDVOSB set-aside. VAAR 852.219-75 (fill-in certification required with the bid) and related 852.219-73 language address the 85% limitation on subcontracting for general construction (materials excluded). The certificate text and 852.219-73(d) wording are not fully consistent on whether a VetCert-certified VOSB (veteran-owned, not service-disabled) counts as “similarly situated” for measuring the 85% limit, or whether only VetCert-certified SDVOSBs count. Please confirm whether, for compliance with VAAR 852.219-75 / 852.219-73 on this SDVOSB set-aside, amounts paid to VetCert-certified VOSB subcontractors (not SDVOSB) are treated as similarly situated (do not count toward the 85%), or whether only VetCert-certified SDVOSBs are similarly situated.

Response: Per “VAAR 819.7004 - Limitations on subcontracting compliance requirements.

(DEVIATION)

(a) A contract awarded under this subpart is subject to the SBA limitations on subcontracting requirements in 13 CFR 125.6, provided that—

(1) Only certified SDVOSBs listed in the SBA certification database are considered eligible and/or “similarly situated” under an SDVOSB sole source or set-aside.”

Further, CFR 125.1 defines Similarly situated entity as having the same small business program status as the prime contractor and lists the following example: “for a SDVOSB contract, a subcontractor that is a certified SDVOSB.”

Question 38) CLIN 0003 Crypts vs CLIN 0001 — scope boundary (supply/install and crypt-field earthwork) Schedule B prices CLIN 0003 — Crypts, 3,554 EA. SOW §3 (Statement of Bid Item) and Spec 01 00 02 1.2 expressly describe CLIN 0001 (General Construction, excluding CLIN 0002 and Bid Option 1) and CLIN 0002 (Asphalt Assessment), and do not call out CLIN 0003. Spec 03 48 21 covers double-depth lawn crypt supply, delivery, and installation. Drawings also show crypt-field excavation, geotextile, drainage fill, backfill, topsoil, and underdrain associated with the PPC fields in Sections 7, 8, and 9. Please confirm: • (a) That CLIN 0003 covers all Spec 03 48 21 double-depth lawn crypt supply, delivery, and installation for 3,554 EA, and that CLIN 0001 excludes crypt fabrication and install (so pricing is not double-counted); • (b) Which CLIN carries crypt-field mass excavation, surplus-soil handling, geotextile, drainage stone / pea gravel, fill over lids, topsoil over crypts, and perimeter underdrain — CLIN 0001 earthwork / site, CLIN 0003, or a stated split.

Response: CLIN 001 includes the installation of Crypts while CLIN 003 includes the purchase and delivery only.

Question 39) C-102 transverse crack work vs CLIN 0002 assessment-only SOW §3.2 / Spec 01 00 02 ¶1.2.B describe CLIN 0002 as an asphalt assessment of longitudinal and transverse cracks on existing asphalt roadways, drives, and parking areas cemetery-wide, with a report and recommended repair methods (assessor ≥5 years asphalt-repair experience; written NCA approval of the assessor). Plan sheet C-102 keyed notes reference approximately 2,500 LF of transverse crack work “under separate CLIN 002,” which reads as repair quantities, not assessment alone. C-102 also shows asphalt separation along sidewalks at the shelter loop roads (about 650 LF) and related pavement work. Please clarify: • (a) Whether CLIN 0002 is assessment and report only (no repair work in that CLIN); • (b) Whether the ~2,500 LF transverse crack repair referenced on C-102 is in this contract at all, and if so under which

CLIN (0001 or 0002); • (c) Required report format, due date relative to NTP, and whether a pavement-management / PCI-style rating is expected or a narrative crack survey is sufficient; • (d) Timing and process for NCA written approval of the proposed assessor (pre-award vs post-award).

Response: The extent of repair work under CLIN 0002 will be based on the assessment provided by the contractor and their recommendations (assessment and reporting only, no physical work). The 2500 LF of transverse crack repair is for a rough guidance to existing conditions. The asphalt separation from sidewalk at the loop roads is part of the base bid not CLIN 0002 (this work will be performed). The report shall be a narrative with detailed recommendations for repairs. Should action be taken on the reports recommendations a contract modification would be required.

Question 40) Overtime / after-hours notice — 72 hours vs 7 days; phasing plan with bid SOW §5 requires work Monday–Friday 8:00 AM–4:30 PM; overtime requests in writing 72 hours in advance (Cemetery Director and COR); cease for nearby interments and ceremonies. Spec 01 00 02 ¶1.4.B.2 requires 7 days’ notice to the COR for work outside regular hours. Spec 01 00 02 ¶1.5.G requires a phasing schedule and two weeks’ advance notice before starting work in each specific area. Please confirm which overtime / after-hours advance-notice period controls (72 hours vs 7 days), and whether a draft phasing plan is expected with the bid or only after award.

Response: 72 hours notice is acceptable, see revised specification.

Question 41) Crypt load test — location, NCA Crypt Specialist scheduling, and phased production /

Install Spec 03 48 21 (Double Depth Lawn Crypt) requires NPCA plant certification; ≥3 years manufacturer experience; PE-stamped design; on-site functional confined load test and shelf test before production (three sample crypts: 2 perimeter + 1 interior); and commence production only after written submittal approval and load testing / demonstration scheduled for the NCA Crypt Specialist. Please clarify: • (a) Preferred on-cemetery location for the three-crypt load / shelf test; • (b) How far in advance the NCA Crypt Specialist must be scheduled; • (c) Whether the on-site load test must occur before any of the 3,554 production units may be fabricated, and how that sequencing is expected to fit within the 545-day period of performance; • (d) Whether installation under CLIN 0003 may begin in phases (e.g., by Section 7 / 8 / 9) before all 3,554 units are manufactured; • (e) Whether any brand-name or prior-approved crypt designs are already acceptable to NCA for this project, or if all designs are performance-spec only.

Response: Crypts require load testing in a location within the limits of disturbance. Contractor may proceed at their own risk with manufacturing of crypts prior to a passing load test. Installation may begin prior to the full manufacturing of the required number of crypts. 7 days’ notice for load testing is acceptable.

Question 42) Keying / Grand Master — information needed before bid (Spec 08 71 00) -- Spec 08 71 00 requires 7-pin removable cores keyed into the existing Grand Master; the key and core system shall match existing. The specification states that keying information will be furnished at a later date by the COR.

Hardware sets HW-E6 (committal shelter storage pairs) and HW-5 (Admin TR door 101) depend on matching the existing brand, keyway, and core format (e.g., small-format IC vs large-format IC vs conventional), and on whether the keyway is restricted / patented. XXXX has not confirmed field lock brand, keyway, or core type from the site visit. We are not stating any field finding here. Please provide, to the extent available before bid opening: • (a) Existing lock manufacturer, keyway designation, and core format at the Administration / Maintenance building and committal shelters; • (b) Whether the keyway is restricted / patented and whether a VA or cemetery authorization letter is required to order permanent cores; • (c) Who holds the grand master / great grand master and bitting records, and who pins the final 7-pin cores (Contractor vs VA / cemetery locksmith); • (d) Whether construction cores plus an allowance for permanent cores is an acceptable bid approach until the COR issues final keying.

Response: Match new to existing door keyways, cores or replace all to match.

Question 43) Construction access, badging, vehicle authorization, and photography Spec 01 00 02 ¶1.4.B.3 prohibits photography of VA premises without written COR permission. Spec 01 00 02 ¶1.4.F references a 24-hour vehicle authorization request. The solicitation does not clearly describe post-award worker badging, background checks, escort rules, or any Fort Sill / Army installation access requirement for cemetery contractor forces. Please confirm: • (a) Daily access procedures for contractor workers after award (badge, background check, escort, or other); • (b) Whether any Fort Sill / Army base-access rule applies beyond cemetery check-in; • (c) How to submit the 24-hour vehicle authorization request (form, POC, lead time); • (d) Whether progress photography after award is permitted with COR written permission, and the preferred request process.

Response: Vehicle authorization is not required for this project. photography is allowed onsite. See revised specification.

Question 44) Door 001 quantity — both committal shelters Door Schedule / A-601 notes door mark 001 “to be replaced for both shelters” (louvered steel pair, 6'-0" × 7'-0", frame type 3-STL, hardware set HW- E6). Please confirm that door 001 is two (2) openings — one at each committal shelter — each a 6'-0" × 7'-0" pair with new steel frame and HW-E6 per opening.

Response: Confirmed.

Question 45) Vendor Portal submission format and package contents Section L ¶3 requires a single PDF via the VA eCMS Vendor Portal (https://www.vendorportal.ecms.va.gov), naming convention S00_Bid_Total Dollar Amount _(Company Name)_(Solicitation Number), including cover letter (sol #, POC, phone, email, DUNS), SF 1442 Blocks 14–20, Schedule B all CLINs + grand total, Cost Estimate Worksheet, signed SF 30 amendments, and scanned bid bond. Please confirm: • (a) Whether UEI is acceptable in lieu of / in addition to DUNS on the cover letter (SAM no longer issues new DUNS); • (b) Maximum PDF file size accepted by the Vendor Portal; • (c) Whether the VAAR 852.219-75 Limitations on Subcontracting fill-in certification (Section I) must be included in the same PDF (required with the bid per the clause, but not listed in the Section L ¶3.d bullet list); • (d) Whether a test / practice upload is available before the due date.

Response: (a) UEI is the requirement as DUNS is no longer used by SAM, outdated verbiage was utilized in this posting. (b) I believe the limit is 20MB, but have been unable to confirm at this time.

Please be mindful of submission deadline to take appropriate measures. (c) Please include your certification in the same document. (d) If you have access to the Vendor Portal, you are able to submit/upload before closing and revisions can be made up until opening time.

Question 46) Period of performance — 545 calendar days vs “18 Months” SF 1442 Items 11 / cover state performance complete within 545 calendar days after NTP. SOW §11.1 states “18 Months calendar days from notice to proceed.” Please confirm the controlling period of performance is 545 calendar days from NTP (and that “18 Months” is approximate only).

Response: 18 Months is approximate.

Question 47) Wage determination — Heavy only The only wage determination posted is OK20260023 (Heavy, Comanche County, OK; Mod 1 dated 05/18/2026). No Building wage determination is posted.

The project includes building / FCA elements (windows, doors, TR room, fire alarm, siding, etc.) in https://www.vendorportal.ecms.va.gov/ addition to site / crypt work. Please confirm that OK20260023 Heavy is the sole applicable wage determination for all work under this IFB (including building / FCA / columbarium elements), or advise if a Building WD will be added by amendment.

Response: [See response to Question 47] OK20260043 added.

Question 48) Bid bond — form and amount basis FAR 52.228-1 requires a bid guarantee of 20% of bid price or $1,000,000, whichever is less. Section L requires a scanned digital bid bond with raised seals darkened. Please confirm: • (a) SF 24 (or equivalent surety bid bond) is acceptable; • (b) Whether the “bid price” for the percentage calculation is the grand total including CLIN 0004 Option 1, or base CLINs 0001–0003 only; • (c) Whether original hard-copy bonds must later be submitted if awarded, or the scanned portal copy is sufficient at opening.

Response: (a) SF24 is acceptable and preferred. (b) Bid price does not include CLIN 004 as the Bid Option 1 has been removed from the solicitation. (c) Properly scanned copies will be sufficient.

Question 49) Hazardous materials — lead / asbestos surveys; Spec 02 83 33.13 Spec 09 91 00 references Section 02 83 33.13 (lead-paint removal), which does not appear in the posted specification book. Scope includes stripping / refinishing gates and fence (C-103), metal siding replacement (AD101), shelter steel work (A-101), and building interior work (TR room). Please provide any available lead-paint or asbestos survey for the buildings and coatings that would be stripped or demolished, and confirm whether lead-paint removal per 02 83 33.13 (or equivalent) is required for C-103 gates/fence, AD101 siding, and A-101 shelter steel. If Section 02 83 33.13 was omitted in error, please post it by amendment.

Response: Due to the age of the buildings, hazardous materials are not anticipated to be encountered. Should hazardous materials be encountered, abatement will be required. This condition would be deemed differing site conditions.

Question 50) Committal shelter service seals and cap stones — quantity and GFP A-101 / related FCA notes call for new service seals and replacement cap stones at the committal shelters. Spec 01 00 02 ¶1.21 addresses Government-furnished property. Please confirm: • (a) Whether “6 new service seals and 5 replacement cap stones” is per shelter or total for both shelters; • (b) Whether the seals (and any related stone) are Government-furnished or Contractor-furnished.

Response: There are 12 total service seals, 6 at each shelter and 10 cap stones, 5 at each shelter. All seals and cap stones are to be provided by the contractor. Additionally, six more seals will be installed on the observation wall, supplied and installed by the contractor. Reference F8/A-501.

Question 51) Flower water stations — “BOD report” referenced on C-102 / LI402 Plan sheet C-102 / LI402 references a “BOD report” in connection with flower water station (FWS) repair and leak locations (4 replacements, 1 repair, and leak repairs called in the documents). Please provide the BOD report referenced on C-102 / LI402, or identify where bidders can obtain it, including FWS repair and leak locations.

Response: The BOD report is not able to be provided. The flower water station locations are on the plan sheets. The FWS’s in need of repair are either leaking or not working. Other than that, we do not know the extents of the probable repairs. See amended sheets C-102 and LI402.

Question 52) NPDES / SWPPP — who files the NOI Spec 01 00 02 ¶1.10.D addresses NPDES / stormwater requirements for construction. Please confirm who files the NOI (Contractor vs VA), and whether VA’s permit application or SWPPP template / existing coverage is available to bidders before bid.

Response: The contractor is responsible for all permit applications.

Question 53) Offsite contractor parking and job-trailer location SOW §5.3 and Spec 01 00 02 ¶1.7.D address contractor parking / staging. Offsite parking is indicated as required and not reimbursed; staging areas are shown conceptually on G-101. Please confirm the designated offsite contractor parking location(s) the cemetery expects, and whether a job trailer and limited contractor vehicles may be placed in the designated construction staging area on G-101.

Response: Offsite parking is not required. contractor may park vehicles within the staging area.

Question 54) Full-size drawings / CAD Only the “Reduced” plan set appears posted on SAM for this opportunity. Please advise whether a full-size PDF and/or CAD files of the drawings will be made available to bidders (and by what means), or whether the Reduced set is the sole bid document set.

Response: The high resolution PDF’s and CAD files will be provided to the contractor after award.

Question 55) Heavy equipment limits — weight, size, and type G-101 identifies the construction access and haul route from Jake Dunn Road / US-277, and Spec 01 00 02 ¶1.4.F addresses vehicle authorization for vehicles entering the site. The work includes crypt delivery and setting, crypt-field earthwork, grading, and road construction, which may require cranes, bulldozers, backhoes, dump trucks, lowboy trailers, and other heavy equipment. Please confirm whether the solicitation or cemetery establishes any weight, axle-load, ground-pressure, dimensional, turning-radius, height, noise, or equipment-type limits for heavy equipment operating on cemetery roads, drives, or grounds, including any restrictions applicable to cranes, bulldozers, backhoes, dump trucks, and crypt-delivery vehicles.

Response: There are no weight or size restrictions.

Question 56) Cemetery roads capacity — heavy-equipment haul routes and protection G-101 shows the construction access / haul route and temporary construction roads. The G-101 haul-route notes and Spec 01 00 02 ¶1.16.A require a pre-construction condition report and place responsibility on the Contractor for road repairs caused by construction traffic. SOW §3.2 / Spec 01 00 02 ¶1.2.B also address the existing cemetery roadways, drives, and parking areas. Please confirm whether the existing cemetery roads and designated haul routes are designed to support the heavy equipment required for this work, including crypt delivery and setting, earthwork, and dump-truck operations. If not, please identify the approved alternate haul routes and required protection measures (such as temporary roads, aggregate, mats, plates, load distribution, traffic controls, or post-work restoration) and where those requirements are specified.

Response: The contractor is responsible for any damage caused to the existing roadways at no additional cost to the government. Roadway protection measures are to be taken at the discretion of the contractor.

Question 57) Disturbed turf restoration — grade-and-seed, sod, or other method -- The site and landscape documents address grading and landscape restoration in the PPC and other disturbed areas, including G- 001 General Note 6, CD101 General Note 3, and the LP401 / LP402 landscape plans. The package references sod and native seed for disturbed areas and turf repair with imported soil and sod for construction damage, but the applicable method and limits are not clear for all areas affected by equipment, haul routes, staging, and earthwork. Please confirm the required restoration method wherever existing grass or turf is ripped up or otherwise disturbed by construction—final grade and seed, sod, mulch, or another specified treatment—and identify the controlling plan note or specification, including requirements for topsoil / soil preparation, seed or sod type, establishment and maintenance, and restoration of damage caused by construction traffic.

Response: If turfgrass is disturbed, it needs to be repaired with sod – see specifications. If undeveloped/native areas are disturbed during construction, those areas should be repaired with native seeding – see specifications.

Question 58) Pricing Structure -- SOW 3.1 and Spec 01 00 02 describe CLIN 0001 as all work except CLIN 0002 and Bid Option 1, but Section B also lists CLIN 0003 (Crypts, 3,554 EA). Please confirm which work is included in CLIN 0003 (precast unit, setting, survey, backfill between crypts) and which stays in CLIN 0001 (excavation, dewatering, base stone, grading).

Response: … [See response to Question 94]

Question 59) Option 1 -- Spec 01 00 02, paragraph 1.2.A, states that Bid Option 1 is "not included in this solicitation," but Section B lists CLIN 0004 (Option 1). Please confirm Option 1 is part of this solicitation and evaluated under FAR 52.217-4, and state when it would be exercised.

Response: Bid Option 1 is not included in the solicitation. [See response to Question 10].

Question 62) Niche covers -- Spec 04 73 00 requires storing 3,680 spare covers plus 40 additional. Please confirm the quantity, delivery schedule, and the designated storage location and size, and whether that space is inside a building.

Response: The specifications require 3,680 covers plus 40 additional spares. Covers to be stored in the maintenance yard.

Question 63) Dewatering and undercut -- The geotechnical report anticipates dewatering. Please confirm whether dewatering and over-excavation of unsuitable soil are lump-sum items in the base price or paid by unit price or allowance.

Response: The need for dewatering is not anticipated. The geotechnical report is for reference only and does not dictate the required work.

Question 64) Turf acceptance -- Spec 32 90 00 requires an established stand (about 98% cover) through a growing season. Please confirm whether final acceptance may occur before the end of establishment, with maintenance and warranty continuing, when seeding is done in the last planting window inside the 545 days.

Response: Turfgrass is going to be sodded. The seeding is only applicable to the native revegetation.

Final acceptance will not be given before the end of establishment.

Question 65) Prototype testing -- Please confirm the location on site for the buried-crypt load test, the required lead time for the NCA Crypt Specialist to witness it, and whether the test pit can remain open for inspection.

Response: Load testing may be conducted within the project limits. 7 days notice is required for NCA witness. The test pit may remain open for inspection.

Question 66) Ceremony calendar -- Please provide the known ceremony and event dates expected between NTP and completion so they can be built into the schedule.

Response: All federally observed holidays. Interment schedules with be provided as they are scheduled.

Question 67) Cost worksheet -- The IFB refers to "S02_Attachment 5_IFB Contractor Cost Estimate Worksheet" and Section L to "S02_Attachment-16." Please confirm which file is the worksheet and post it if it is not in the current package.

Response: [See response to Question 8]

Question 68) Drawing list -- Spec 00 01 15 (drawing list) has no entries, and the specification cover shows "IFB NUMBER VA-XXXXXXXX." Please confirm the governing drawing set is the 113 sheets in Attachments 3 through 13.

Response: Complete list of drawings is updated in the amended Section 00 01 15 and also provided in the sheet index on Sheet G-001 of the Bid Documents drawings.

Question 69) Parking and staging -- Please confirm areas available for worker parking and for secure covered storage, and whether off-site parking near the cemetery is expected.

Response: Off-site parking is not required. contractor may park within the staging area.

Question 70) Is there shore power located at either Staging Area to hook up to Mobile Office Trailer?

Response: Power is available in the maintenance yard [see response to Questions 143 & 144 ] and is not available in the staging areas.

Question 71) Is the old Symplex System in the Admin Building to be completely Removed and Replaced?

Response: Yes the entire fire alarm system is being replaced.

Question 72) Are there any As Built Drawings of the Current Fire Alarm System?

Response: Location for all devices on the drawings were developed from as built drawings, but these didn’t seem to cover every piece of equipment, a site visit from the electrical team was sent for confirmation and any additions to what was on those original drawings.

Question 73) Is the Fire Alarm System a complete replacement?

Response: Yes, the entire fire alarm system is being replaced

Question 74) Is there a specific Fire Alarm Manufacturer required for this project?

Response: No specific manufacturer, Simplex is provided as illustrative but an approved equal is acceptable.

Question 75) Is the Burglar Alarm to be replaced?

Response: No, the burglar alarm is not to be replaced.

Question 76) Is the Camera System at the Admin and Visitors Center to be replaced?

Response: No, the camera system is not being replaced. Refer to Sheets T-102 and T-601 for access reader and other Telecommunications Room security requirements.

Question 77) Specs 28 13 00, 28 13 53, 28 23 00, 28 26 00 (+ 28 05-series); Dwg G-001 Sheet Index-- Specification Sections 28 13 00 (Physical Access Control), 28 13 53 (Security Access Detection), 28 23 00 (Video Surveillance), and 28 26 00 (Electronic Personal Protection) are included, but no corresponding security drawings appear in the drawing set. Please confirm whether these systems are required and, if so, provide the applicable drawings; otherwise confirm the sections are not applicable to this project.

Response: Refer to Sheets T-102 and T-601 for access reader and other Telecommunications Room security requirements. There is no new surveillance equipment, but any existing equipment will need to be routed to the new TR, that is why some of those specs were included. [See response to Question 3]

Question 78) EP103 — Sheet EP103 scale is set to 4' per inch, please confirm this is correct.

Response: No, the correct scale is 1 ”= 100’.

Question 79) Fence posts — Can you confirm that the fence posts scheduled for grinding and welding repairs are steel? If not, please identify the material for bidding purposes.

Response: See Detail B2/C-103 for original fence and gate drawing notes. The posts are aluminum.

Question 80) A-101 / D1/A-501 — What is the length or radial detail for the replacement caps?

Response: These dimensions will need to be field verified by the contractor.

Question 81) Site visit — Can you please provide a copy of the site visit sign-in sheet?

Response: Sign-in sheet was published 10/8/2026.

Question 82) Tax — Can you confirm the project is sales tax exempt?

Response: Please refer to included clause FAR 52.229-3.

Question 83) Funding — Is this project funded?

Response: Yes. However, NCA reserves the right to reject all proposals based upon bid results.

John Cunningham @Dania Habboub @Sean Fitzpatrick do we have a response for this question re: caps?

Sean Fitzpatrick Added the original detail

Question 84) What other current and future projects onsite will the awarded contractor need to coordinate with?

Response: No conflicting projects are anticipated at this time.

Question 85) Lead & Asbestos to be encountered? survey/abatement required?

Response: Due to the age of the buildings, hazardous materials are not anticipated to be encountered. Should hazardous materials be encountered, abatement will be required. This condition would be deemed differing site conditions.

Question 86) Are there any roadways or work areas that cannot be shut down for construction?

Response: Roadways shall remain open at all time for single lane traffic. Should a roadway shutdown be required. the contractor shall coordinate the shutdown with NCA staff in writing.

Question 87) Can you please provide contact information for the private site utilities that will be encountered during this project for coordination purposes (gas, communications, etc.)?

Response: Contact information is unknown. Contractor shall coordinate with local utility companies as required.

Question 88) Is a Quality Control Manager required for this project? Will this individual be allowed to hold any other management positions?

Response: Yes. Must not hold another management position. [See response to Question 9]

Question 89) Is a Safety Officer required for this project? Will this individual be allowed to hold any other management positions?

Response: Yes. May be dual-hatted as Site Superintendent. [See response to Question 9]

Question 90) May the Superintendent also hold the positions of Quality Control Manager and/or Safety Manager?

Response: [See response to Question 9]

Response: All known site utilities are currently shown. See general note #3 on sheet G-001.

Question 91) 01 00 02 1.7 I. Construction Fence: Before construction operations begin, the Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height… Will a 6-foot-high construction fence suffice?

Response: Yes. See revised specification 01 00 02.

Question 92) Please confirm that the Superintendent/QC Manager is required to be a degreed engineer, degreed architect, or degreed construction manager with 5 years of construction management experience.

Response: Confirmed.

Question 93) 27 08 00 1.1B – References a complete list of equipment and systems to be commissioned is provided in Specification 27 05 11 REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS. Can this specification be provided?

Response: Yes, see specification 27 05 11 included with Amendment 001.

Question 94) SOW ¶3.1; Sol. Section B.1 (CLIN 0001, CLIN 0003 – 3,554 EA); Dwg G-001/G-002 - Section B lists CLIN 0003 “Crypts” as a separate unit-priced item (3,554 EA), while SOW ¶3.1 defines CLIN 0001 as all work shown on the plans and specifications “excluding work associated with CLIN 0002 & Bid Option 1” — CLIN 0003 is not excluded, and CLIN 0003 is not described anywhere in the SOW. Please confirm (a) that the furnish-and-install cost of the 3,554 pre-placed crypts is priced solely under CLIN 0003 and excluded from the CLIN 0001 lump sum; (b) what scope remains under CLIN 0001 within the crypt areas (e.g., earthwork, drainage, surfacing, sod); and (c) how the CLIN 0003 unit price will be adjusted if the installed quantity varies from 3,554, as no Variation in Estimated Quantity clause (FAR 52.211-18) or other unit-price adjustment mechanism appears in the solicitation.

Response: (a) CLIN 001 includes the installation, CLIN 003 is for the material and delivery cost of the crypts only. (b) Refer to Statement of Work and attached revised Drawings and Specifications.

(c) No variance in quantities is anticipated as this is a specific, designed amount.

Question 95) WD OK20260023 (Heavy); Dwgs A-101–A-104, M-101, ED101-103, EL101, EP101-102, E-101–E-103; Specs Div 08, 09, 22, 23, 26, 28 - The solicitation includes only a Heavy construction wage determination (OK20260023). The scope includes renovation of the Administration, Maintenance, and Public Information buildings and the Committal Shelters, involving building trades not classified in a Heavy WD. Please confirm whether a Building construction wage determination also applies to the building renovation work and, if so, provide it; otherwise confirm that all work is to be priced under the Heavy WD.

Response: [See response to Question 47]

Question 96) Solicitation (545 cal. days from NTP); SOW ¶11.1; SF 1442 Block 11 (blank); FAR 52.211-12 (LDs $3,125.04/day) - Please confirm the contract completion time. The solicitation states 545 calendar days from NTP, while SOW ¶11.1 states “18 months.” Confirm that 545 calendar days governs (or state the correct duration) and that SF 1442, Block 11 will be conformed accordingly.

Response: [See response to Question 46]

Question 97) Solicitation Section L (Att. 5 / Att. 16 conflict); Section J List of Attachments - The IFB Contractor Cost Estimate Worksheet, required by Section L for bid submission, is referenced as both Attachment 5 and Attachment 16 (S02_Attachment-16 _IFB Contractor Cost Estimate Worksheet) and is not included in the posted attachments (Attachment 5 is a drawing plan set). Please issue the Cost Estimate Worksheet and confirm its correct attachment number.

Response: [See response to Question 8]

Question 98) SOW ¶3.2 (CLIN 0002); Specs 32 12 16, 32 17 23; Dwgs C-201/C-202 - Please confirm CLIN 0002 is limited to assessment and reporting of existing asphalt cracking (no physical repair), and that asphalt paving/markings in the base bid apply only to new work (e.g., the road extension), with any resulting crack repairs handled under a future/separate action.

Response: Correct. This CLIN is for the assessment and reporting only. No physical repairs are to be included as a part of this CLIN.

Question 99) SOW ¶3.2 (CLIN 0002); Dwg C-405 keyed note 8 and Asphalt Road Paving Repair Notes ¶2; Spec 32 12 16 - There is a conflict regarding the approximately 2,500 LF of transverse asphalt cracking. SOW ¶3.2 defines CLIN 0002 as an assessment only — perform a survey and furnish a report with recommended repair methods. Drawing C-405, keyed note 8, states the work “shall be performed under separate CLIN 002,” which reads as though the crack repairs themselves are within this contract.

Please confirm whether CLIN 0002 includes (a) the assessment and report only, or (b) the assessment plus physical crack sealing/repair of the approximately 2,500 LF. If repairs are included, please provide the basis of payment (unit price or lump sum) and confirm whether repair quantities will be adjusted from the approved assessment report. We further confirm our understanding that the fog seal of the entire existing paved roadway and the 650 LF of longitudinal asphalt separation repair at the committal shelter loop roads are base bid (CLIN 0001) work.

Response: CLIN 002 is for the assessment only. The quantity provided is for reference only. The base bid CLIN 001 includes the repair notes indicated within your question and on the construction plans which include fog seal and longitudinal crack repairs.

Question 100) Dwg G-002 (Bid Options ¶¶1.1-1.3, 4); Dwgs C-203, C-407, LI402, CJ101, CJ501;

Section B CLIN 0004 - Please confirm that all shared drainage, irrigation, and signage items designated on Drawing G-002…