S02-657A4-21-800-ATTACHMENT 5- Building 1 Drawings Volume 1_R_06242025.pdf
PDF 9 MB Posted
- Attached to
- Z2DA--657A4-21-800, TF - FCA - Remove and Replace End-of-Life HVAC Infrastructure Building 1
- Solicitation number
- 36C25525R0106
About this file
These are architectural and structural drawings for a renovation project at the John J. Pershing Veterans Administration Medical Center in Poplar Bluff, Missouri. The project involves removing and replacing end-of-life heating, ventilation, and air conditioning (HVAC) infrastructure in Building 1, specifically focusing on the main hospital. The comprehensive set of drawings includes detailed plans for multiple floors (basement, ground floor, first, second, third, and fourth floors), structural framing plans, and hazardous materials documentation.
The project is phased and involves complex coordination with a temporary modular building complex. Key elements include replacing air handling units (AHUs), renovating laboratory and medical spaces, managing asbestos and lead-based paint abatement, and creating new mechanical platforms for equipment. The work requires careful sequencing to maintain hospital operations, with specific instructions for relocating departments, managing equipment, and ensuring continued VA medical center functionality during the renovation process. The structural drawings provide extensive technical details for supporting new mechanical units, including steel framing, guardrails, and connections to existing building structures.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACTOR SHALL REFER TO THE MODULAR
BUILDING COMPLEX PACKAGE FOR COORDINATION
AND RELOCATION DURING PHASING OF
DEPARTMENTS, EQUIPMENT, INFRASTRUCTURE,
ETC. REQUIRED FOR CONTINUED VA OPERATIONS.
MODULAR BUILDING
COMPLEX COORDINATION
JIM
H.
HAGEMAN
A-2205
A
R C H I T E
C
T
S T
A T
E
O F N E B
R A
S K
A
8/30/2024
Project Number
Building Number
Drawing Number
Project Title
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
BID DOCUMENTS
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
STAMP
321 4 5 6 7 8 9 10
ARCHITECT/ENGINEER OF RECORD
Alesia Architecture P.C.
3705 North 200th Street Elkhorn, Nebraska 68022 Phone: (402) 291-6941
Shaffer, Stevens & Schaap 1070 Howard Street Omaha, Nebraska 68102 Phone: (402) 455-7698
AMI Environmental Inc 8802 S 135th Street Omaha, NE 68138 Phone: (402) 397-5001
IMEG Corp.
15 Sunnen Drive, Suite 104 St. Louis, MO 63143 Phone: (314) 645-1132
CC
o n e e ig h th i n c h o n e f o o t th re e i n c h e s o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t o n e i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t
A u to d e s k D o c s
/2
-1
A -2
-3
V
A P o p la r
B lu ff
R e m o v e a n d
R e p la c e
L a b A
H U a n d A
H U
/6
A
-2
-3
.B
.A rc h R
-1
-R e p l L a b A
H U
A
H U
.r v t
/9
/2
:0
:2
P M
GI001
COVER SHEET REMOVE AND REPLACE END OF
LIFE HEATING, VENTILATION, AND
AIR CONDITIONING
JOHN J. PERSHING VETERANS' ADMINISTRATION MEDICAL
CENTER 1500 N. WESTWOOD BLVD. POPLAR BLUFF, MO
63901-3318
657A4-21-800
8/30/2024 GLG KRK
REMOVE AND REPLACE END OF LIFE HEATING, VENTILATION,
AND AIR CONDITIONING/ 657A4-21-305
BUILDING 1 - MAIN HOSPITAL
JOHN J. PERSHING VETERANS ADMINISTRATION MEDICAL CENTER
1500 NORTH WESTWOOD BOULEVARD
POPLAR BLUFF, MO 63901-3318
PROJECT NUMBER 657A4-21-800
LOCATION MAP - POPLAR BLUFF
NTS
LOCATION MAP - STATE OF MISSOURI
NTS
MODULAR BLDG.
COMPLEX LOCATION
AERIAL VIEW
NTS
CAMPUS PLAN - JOHN J. PERSHING VA MEDICAL CENTER
NTS
Mark Revisions: Date:
CONTRACTOR SHALL REFER TO THE MODULAR
BUILDING COMPLEX PACKAGE FOR COORDINATION
AND RELOCATION DURING PHASING OF
DEPARTMENTS, EQUIPMENT, INFRASTRUCTURE,
ETC. REQUIRED FOR CONTINUED VA OPERATIONS.
MODULAR BUILDING
COMPLEX COORDINATION
JIM
H.
HAGEMAN
A-2205
A
R C H I T E
C
T
S T
A T
E
O F N E B
R A
S K
A
8/30/2024
Project Number
Building Number
Drawing Number
Project Title
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
BID DOCUMENTS
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
STAMP
321 4 5 6 7 8 9 10
ARCHITECT/ENGINEER OF RECORD
Alesia Architecture P.C.
3705 North 200th Street Elkhorn, Nebraska 68022 Phone: (402) 291-6941
Shaffer, Stevens & Schaap 1070 Howard Street Omaha, Nebraska 68102 Phone: (402) 455-7698
AMI Environmental Inc 8802 S 135th Street Omaha, NE 68138 Phone: (402) 397-5001
IMEG Corp.
15 Sunnen Drive, Suite 104 St. Louis, MO 63143 Phone: (314) 645-1132
CC
o n e e ig h th i n c h o n e f o o t th re e i n c h e s o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t o n e i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t
A u to d e s k D o c s
/2
-1
A -2
-3
V
A P o p la r
B lu ff
R e m o v e a n d
R e p la c e
L a b A
H U a n d A
H U
/6
A
-2
-3
.B
.A rc h R
-1
-R e p l L a b A
H U
A
H U
.r v t
/9
/2
:0
:2
P M
GI002
INDEX OF DRAWINGS REMOVE AND REPLACE END OF
LIFE HEATING, VENTILATION, AND
AIR CONDITIONING
JOHN J. PERSHING VETERANS' ADMINISTRATION MEDICAL
CENTER 1500 N. WESTWOOD BLVD. POPLAR BLUFF, MO
63901-3318
657A4-21-800
8/30/2024 GG KRK
INDEX OF DRAWINGS
GENERAL INFORMATION
GI001 COVER SHEET
GI002 INDEX OF DRAWINGS
GC001 PIPE BASEMENT - PHASE 1
GC100 GROUND FLOOR - PHASES 1 & 2
GC101 FIRST FLOOR - PHASES 1, 2, 3 & 4
GC102 SECOND FLOOR - PHASE 1
GC103 THIRD FLOOR - PHASE 1
GC104 FOURTH FLOOR - PHASE 1
HAZARDOUS MATERIALS
HA-001 HAZARDOUS MATERIALS GENERAL NOTES
HA-100 HAZARDOUS MATERIALS BASEMENT PLAN
HA-101 HAZARDOUS MATERIALS GROUND FLOOR PLAN
HA-102 HAZARDOUS MATERIALS FIRST FLOOR PLAN
HA-103 HAZARDOUS MATERIALS SECOND FLOOR - PLAN
HA-104 HAZARDOUS MATERIALS FOURTH FLOOR - PLAN
STRUCTURAL
SG001 STRUCTURAL GENERAL NOTES
SF101 FRAMING PLANS - LAB AHU AND AHU9/ DENTAL PLATFORMS
SF102 SECOND FLOOR FRAMING PLAN
SF501 FRAMING DETAILS
ARCHITECTURAL
AG001 ARCHITECTURAL ABBREVIATIONS & LEGENDS
AG002 ARCHITECTURAL GENERAL NOTES
AD101 FIRST FLOOR - DEMOLITION PLAN
AD102 SECOND FLOOR - DEMOLITION PLAN
AD103 FOURTH FLOOR - DEMOLITION PLAN
AD104 ROOF DEMOLITION PLANS
ACD100 GROUND FLOOR - CEILING DEMO PLAN
ACD101 FIRST FLOOR - CEILING DEMO PLAN
ACD102 SECOND FLOOR - CEILING DEMO PLAN
ACD110 GROUND FLOOR - LARGE SCALE CEILING DEMO PLAN
ACD111 FIRST FLOOR - LARGE SCALE CEILING DEMO PLAN
A-100 GROUND FLOOR PLAN
A-101 FIRST FLOOR PLAN
A-102 SECOND FLOOR, THIRD FLOOR, & FOURTH FLOOR - PLANS
AC100 GROUND FLOOR - REFLECTED CEILING PLANS
AC101 FIRST FLOOR - REFLECTED CEILING PLANS
AC102 SECOND FLOOR WINGS A-EAST & C - REFLECTED CEILING PLANS
AC110 GROUND FLOOR - LARGE SCALE REFLECTED CEILING PLANS
AC111 FIRST FLOOR - LARGE SCALE REFLECTED CEILING PLAN
A-200 FOURTH FLOOR - EXTERIOR ELEVATION
A-301 WING C - THIRD & FOURTH FLOOR - SECTION VIEWS & DETAILS
A-400 GROUND FLOOR - FLOOR PLANS
A-401 FIRST FLOOR - FLOOR PLANS AND SECTIONS
A-402 SECOND, THIRD & FOURTH FLOOR & ROOF PLANS
A-501 EXTERIOR DETAILS
A-701 DOOR AND FRAME TYPES, DETAILS AND DOOR SCHEDULE
A-801 PARTITION TYPES
A-802 PARTITION DETAILS
A-900 ENLARGED PLANS & INTERIOR ELEVATIONS
A-901 ENLARGED PLANS & INTERIOR ELEVATIONS
A-902 CASEWORK AND TRANSITION DETAILS
INTERIOR DESIGN
IN601 ROOM FINISH SCHEDULE
EQUIPMENT
QH102 SECOND FLOOR, EQUIPMENT PLAN
QH601 EQUIPMENT SCHEDULE - BLDG. 1
FIRE PROTECTION
FX000 FIRE PROTECTION COVERSHEET
FD100 GROUND FLOOR - FIRE PROTECTION DEMOLITION
FD101 FIRST FLOOR - FIRE PROTECTION DEMOLITION
FD102 SECOND FLOOR - FIRE PROTECTION DEMOLITION
FX100 GROUND FLOOR - FIRE PROTECTION
FX101 FIRST FLOOR - FIRE PROTECTION
FX102 SECOND FLOOR - FIRE PROTECTION
FX500 FIRE PROTECTION DETAILS
PLUMBING
PL000 PLUMBING COVERSHEET
PD100 GROUND FLOOR - PLUMBING DEMOLITION
PD101 FIRST FLOOR - PLUMBING DEMOLITION
PD102 SECOND FLOOR - PLUMBING DEMOLITION
PD103 THIRD FLOOR - PLUMBING DEMOLITION
PL100 GROUND FLOOR - PLUMBING
PL101 FIRST FLOOR - PLUMBING
PL102 SECOND FLOOR - PLUMBING
PL103 THIRD FLOOR - PLUMBING
PL104 FOURTH FLOOR - PLUMBING
PIPING
MP000 PIPING COVERSHEET
MPD001 PIPE BASEMENT - MECHANICAL PIPING DEMOLITION
MPD100 GROUND FLOOR - MECHANICAL PIPING DEMOLITION
MPD101 FIRST FLOOR - MECHANICAL PIPING DEMOLITION
MPD102 SECOND FLOOR - MECHANICAL PIPING DEMOLITION
MPD103 THIRD FLOOR - MECHANICAL PIPING DEMOLITION
MPD104 FOURTH FLOOR - MECHANICAL PIPING DEMOLITION
MP001 PIPE BASEMENT - MECHANICAL PIPING
MP100 GROUND FLOOR - MECHANICAL PIPING
MP101 FIRST FLOOR - MECHANICAL PIPING
MP102 SECOND FLOOR - MECHANICAL PIPING
MP103 THIRD FLOOR - MECHANICAL PIPING
MP104 FOURTH FLOOR - MECHANICAL PIPING
MP500 MECHANICAL PIPING DETAILS
MP600 MECHANICAL PIPING DIAGRAMS
MP601 MECHANICAL PIPING SCHEDULES
VENTILATION
MH000 VENTILATION COVERSHEET
MHD100 GROUND FLOOR - VENTILATION DEMOLITION
MHD101 FIRST FLOOR - VENTILATION DEMOLITION
MHD102 SECOND FLOOR - VENTILATION DEMOLITION
MHD103 THIRD FLOOR - VENTILATION DEMOLITION
MH100 GROUND FLOOR - VENTILATION
MH101 FIRST FLOOR - VENTILATION
MH102 SECOND FLOOR - VENTILATION
MH103 THIRD FLOOR - VENTILATION
MH104 FOURTH FLOOR - VENTILATION
MH500 VENTILATION DETAILS
MH501 VENTILATION DETAILS
MH600 VENTILATION DIAGRAMS
MH601 VENTILATION DIAGRAMS
MH602 VENTILATION DIAGRAMS
MH603 VENTILATION DIAGRAMS
MH604 VENTILATION DIAGRAMS
MH605 VENTILATION SCHEDULES
MH606 VENTILATION SCHEDULES
MH607 VENTILATION SCHEDULES
ELECTRICAL
E-000 ELECTRICAL COVERSHEET
ED100 GROUND FLOOR - ELECTRICAL DEMOLITION
ED101 FIRST FLOOR - ELECTRICAL DEMOLITION
ED102 SECOND FLOOR - ELECTRICAL DEMOLITION
ED103 THIRD FLOOR - ELECTRICAL DEMOLITION
EL100 GROUND FLOOR - ELECTRICAL LIGHTING
EL101 FIRST FLOOR - ELECTRICAL LIGHTING
EL102 SECOND FLOOR - ELECTRICAL LIGHTING
EP001 PIPE BASEMENT - ELECTRICAL POWER
EP100 GROUND FLOOR - ELECTRICAL POWER
EP101 FIRST FLOOR - ELECTRICAL POWER
EP102 SECOND FLOOR - ELECTRICAL POWER
EP103 THIRD FLOOR - ELECTRICAL POWER
EP104 FOURTH FLOOR - ELECTRICAL POWER
E-600 ELECTRICAL SCHEDULES
E-601 ELECTRICAL SCHEDULES
GENERAL PHASING NOTES:
1. PHASES 1 THROUGH 4 SHOWN ON THESE MAIN
HOSPITAL BUILDING 1 DRAWINGS ARE RELATED
TO PHASES SHOWN ON THE TEMPORARY
MODULAR BUILDING.
2. PHASES 0 AND 1 OF THE TEMPORARY
MODULAR BUILDING MUST BE COMPLETED
BEFORE PHASE 1 OF THE MAIN HOSPITAL
BUILDING 1 CAN BEGIN.
NOTE 2A:
PHASE 1 – SECOND FLOOR WORK.
THE WORK INCLUDES BUT IS NOT LIMITED TO
THE REMOVAL AND REPLACEMENT OF
DUCTWORK IN THE AREAS SHADED. REMOVAL
OF EXISTING CEILING GRID, CEILING TILES, AND
OTHER CEILING MOUNTED ITEMS IS INCLUDED.
SEISMIC STEEL TUBES BELOW EXISTING
CEILINGS REMAIN IN PLACE DURING THE
PROJECT WORK BEING PERFORMED. CEILING
MOUNTED SPEAKERS, HEAD AND EXISTING
LIGHT FIXTURES SHALL BE REMOVED AS
NEEDED AND REUSED. SPRINKLER HEADS
SHALL BE MOVED AS NEEDED TO AVOID
CONFLICTS WITH NEW DUCTWORK
INSTALLATION. EXIT SIGNAGE SHALL BE
REMOVED AS NEEDED DURING CEILING WORK
AND REINSTALLED AT THE ORIGINAL LOCATION
FOR EACH. INSTALL NEW CEILINGS AND
CEILING GRIDS. REINSTALL EXISTING LIGHT
FIXTURES, SPEAKERS, EXIT SIGNS AND ANY
OTHER REMOVED CEILING MOUNTED ITEMS.
NOTE 2B:
PHASE 1 – SECOND FLOOR ASBESTOS
REMEDIATION – REMOVE EXISTING FLOORING
IN AREAS INDICATED ON FLOOR PLANS AND
ABATE FLOOR MASTIC. THE WORK INCLUDES
BUT IS NOT LIMITED TO THE REMOVAL AND
REPLACEMENT OF DUCTWORK IN THE AREAS
SHADED. REMOVAL OF EXISTING CEILING GRID,
CEILING TILES, AND OTHER CEILING MOUNTED
ITEMS IS INCLUDED. SEISMIC STEEL TUBES
BELOW EXISTING CEILINGS REMAIN IN PLACE
DURING THE PROJECT WORK BEING
PERFORMED. CEILING MOUNTED SPEAKERS,
HEAD AND EXISTING LIGHT FIXTURES SHALL BE
REMOVED AS NEEDED AND REUSED.
SPRINKLER HEADS SHALL BE MOVED AS
NEEDED BASED TO AVOID CONFLICTS WITH
NEW DUCTWORK INSTALLATION. EXIT SIGNAGE
SHALL BE REMOVED AS NEEDED DURING
CEILING WORK AND REINSTALLED AT THE
ORIGINAL LOCATION FOR EACH. INSTALL NEW
CEILINGS AND CEILING GRIDS. REINSTALL
EXISTING LIGHT FIXTURES, SPEAKERS, EXIT
SIGNS AND ANY OTHER REMOVED CEILING
MOUNTED ITEMS. INSTALL NEW FLOOR TILES
AS REQUIRED AS A RESULT OF REMEDIATION
WORK.
NOTE 2C:
PHASE 1 – THIRD FLOOR - ROOF ACCESSED
FROM THIRD FLOOR - AHU - REMOVE AND
REPLACE EXISTING AHU MOUNTED ON ROOF
JUST NORTH OF LEVEL THREE. REMOVE
EXISTING ROOF, ROOF SHEATHING, ROOF
INSULATION BELOW. REPLACE WITH NEW.
MODIFY EXISTING AHU OPENING AS REQUIRED
TO SUPPORT NEW AHU. CREATE NEW ROOF
OPENING FOR NEW CHILLER INSTALLATION –
SEE MECHANICAL. INSTALL NEW STEEL
SUPPORT STRUCTURE AND CATWALK TO HOLD
NEW AHU ON A PLATFORM ABOVE TO ALIGN
WITH THE ELEVATION OF LEVEL 4. INSTALL NEW
GUARDRAILS ALONG LEVEL 3 PARAPET AND ON
THE ELEVATED CATWALK PERIMETER ABOVE.
NOTE 2D:
PHASE 1 – FOURTH FLOOR REMOVE EXISTING
WINDOW ON NORTH WALL AND CUT A ROUGH
OPENING FOR NEW ACCESS DOOR TO OPEN
ONTO THE NEW MECHANICAL SUPPORT STEEL
PLATFORM THAT ALIGNS WITH THE FOURTH
FLOOR ELEVATION. INSTALL NEW STRUCTURAL
CAST CONCRETE SILL AT NEW DOOR
THRESHOLD. INSTALL NEW INSULATED DOOR
AND DOOR FRAME WITH HARDWARE AS
DESCRIBED.
3. CONTRACTOR TO REVIEW AND SUBMIT
CONSTRUCTION PHASING PLAN.
4. CONTRACTOR TO PROVIDE ALL SUBMITTALS
AND RECEIVE APPROVALS BEFORE
CONSTRUCTION CAN START.
5. CONTRACTOR TO SUBMIT COORDINATION
DRAWINGS BEFORE CONSTRUCTION CAN
START.
6. PHASES SHOWN IN THE LEGEND ARE PART OF
THE SCOPE OF WORK CONTAINED IN THIS SET
OF CONTRACT DOCUMENT DRAWINGS.
W X Y AA CC BB DD FF
PIPE BASEMENT
DEDUCT ALTERNATE -
SEE AG002 & TEMPORARY MODULAR BUILDING COMPLEX DRAWINGS
PROJECT PHASING - LEGEND
NO WORK IN AREA
PHASE 1
PHASE 2
PHASE 3
PHASE 4
MODULAR BUILDING COMPLEX
PHASES 1-4
CONTRACTOR SHALL REFER TO THE MODULAR
BUILDING COMPLEX PACKAGE FOR COORDINATION
AND RELOCATION DURING PHASING OF
DEPARTMENTS, EQUIPMENT, INFRASTRUCTURE,
ETC. REQUIRED FOR CONTINUED VA OPERATIONS.
MODULAR BUILDING
COMPLEX COORDINATION
SEE PROJECT MANUAL SECTION 01 00 00-GENERAL
CONDITIONS, SHEET AG002 & TEMPORARY
MODULAR BUILDING COMPLEX DRAWINGS FOR
DESCRIPTION OF DEDUCT ALTERNATE.
DEDUCT ALTERNATE
PHASE 0 & 1 DESCRIPTIONS
PHASE 0:
A. DESIGN AND SUBMIT FOR VA APPROVAL LAYOUTS AND
PHASING PLANS FOR WORK IN BUILDING 1 AND
CONSTRUCTION OF THE TEMPORARY MODULAR
BUILDING COMPLEX (MBC), ALONG WITH PRODUCT
SUBMITTALS FOR ITEMS TO BE PART OF THE PROJECT.
B. PREPARE SITE WEST OF BUILDING 1 AND CONSTRUCT
TEMPORARY MODULAR BUILDING COMPLEX (MBC) –
PHASE 1. INCLUDING COVERED WALKWAYS, FIREWALL
AND CONNECTING LINK TO HOSPITAL AND ALL
NECESSARY UTILITY CONNECTIONS TO THE SITE AND
THE HOSPITAL, BUILDING 1.
C. THE MBC SHALL COMPRISE OF A 4-PLEX OF UNITS TO
REMAIN ON-SITE FOR THE DURATION OF THIS PROJECT
WITH DEDICATED UNITS FOR RESTROOMS,
TELECOMMUNICATIONS AND UTILITY FUNCTIONS, WITH
A CONNECTING CORRIDOR AND AN ADDITIONAL 3-PLEX
OF BUILDING MODULES TO HOUSE PHASE 1 LAB
FUNCTIONS.
D. THE CONTRACTOR HAS THE OPTION OF
1. OBTAINING SPECIALTY MODULES DEDICATED
FOR USE WITH LABORATORIES, OR
2. PROVIDING A SERIES OF CONVENTIONAL
BUILDING MODULES WHICH CAN BE OUTFITTED
FOR LAB FUNCTIONS IN PHASE 1 AND
CONVERTED FOR OTHER FUNCTIONS AS
REQUIRED FOR PHASES 2 AND 3.
PHASE 1:
A. RELOCATE EXISTING LABORATORY OPERATIONS AND
EQUIPMENT FROM SECOND FLOOR LABS IN WINGS ‘A’-
EAST AND ‘C’ TO THE TEMPORARY MODULAR BUILDING
COMPLEX.
B. COMPLETE ASBESTOS REMEDIATION IN SAME SECOND
FLOOR LAB AREAS.
C. RENOVATE SECOND FLOOR LAB AREAS, REPLACE LAB-
AHU AND RELATED EQUIPMENT AND STRUCTURAL
IMPROVEMENTS AT SECOND, THIRD AND FOURTH
FLOORS, AND MAKE ALL NECESSARY UTILITY
CONNECTIONS DOWN TO PIPE BASEMENT LEVEL.
D. CONDUCT WORK IN PIPE BASMENT RELATED TO LAB
AHU WORK.
E. INSTALLATION OF RTU-MAIL AND RENOVATION OF MAIL
ROOM 1A-173. PROVIDE HVAC RENOVATION OF MAIL
ROOM 1A-173 ON FIRST FLOOR, INCLUDING NEW RTU-
MAIL ON ROOFTOP OF THE SOUTH ENTRY LOBBY AT
SECOND FLOOR, AND NEW DUCTWORK THROUGH
CORRIDOR 1A-C04 AND MEDICAL RECORDS 1A-101.
• THIS INCLUDES STRUCTURAL
REINFORCEMENT OF EXISTING LOBBY
ROOF STRUCTURE,
• REMOVAL AND REINSTALLATION OF
LOBBY, MAIL ROOM, CORRIDOR AND
MEDICAL RECORDS CEILINGS.
B. AT THE BEGINNING OF PHASE 1:
1. THE SEPARATE 3-PLEX OF MODULES FOR LAB
FUNCTIONS SHALL BE OPERATIONAL AND
READY TO ACCEPT EQUIPMENT FROM THE LABS.
2. DESIGNATED EQUIPMENT FROM THE LAB WILL
NEED TO REMAIN IN BUILDING 1 WHILE NEW
EQUIPMENT IS INSTALLED IN THE MBC LABS. A
PERIOD OF 4-5 WEEKS IS REQUIRED FOR
TESTING AND CALIBRATION OF NEW
EQUIPMENT, WITH DESIGNATED EXISTING
EQUIPMENT TO REMAIN IN OPERATION UNTIL
THE NEW EQUIPMENT IS CERTIFIED TO BE
AVAILABLE FOR USE.
3. AFTER LAB-TESTING EQUIPMENT IS SET UP AND
READY FOR OPERATION, DESIGNATED
EQUIPMENT IN BUILDING 1 CAN BE REMOVED
AND DEMOLITION MAY COMMENCE IN BUILDING
1.
4. WORK IN PIPE BASEMENT MAY TAKE PLACE
AFTER RELOCATION OF 2ND FLOOR LABS TO
THE MBC.
5. THE MAIL ROOM WILL BE RELOCATED TO THE
MBC 4-PLEX. THE MAIL ROOM WILL BE MOVED
BACK INTO BUILDING 1 UPON COMPLETION OF
WORK RELATED TO THE MAIL ROOM RTU AND
REFINISHING OF THE MAIL ROOM.
C. AT END OF PHASE 1:
1. RELOCATE ALL LAB OPERATIONS AND
EQUIPMENT FROM THE TEMPORARY MODULAR
BUILDING BACK INTO THE SECOND FLOOR LAB
SPACE.
2. REFURBISH THE MBC IN PREPARATION FOR
PHASE 2 AND PREPARE IT TO RECEIVE
FUNCTIONS BEING DISLOCATED OUT OF THE
HOSPITAL AS PART OF PHASE 2.
a. IF SPECIALTY LAB MODULES WERE USED, REMOVE FROM MBC AND REPLACE WITH
GENERAL-PURPOSE MODULES
PREPARED FOR PHASES 2 AND 3 USES.
b. IF GENERAL-PURPOSE MODULES WERE
MODIFIED TO SERVE LABS, RENOVATE
MODULES FOR PHASES 2 AND 3 USES.
JIM
H.
HAGEMAN
A-2205
A
R C H I T E
C
T
S T
A T
E
O F N E B
R A
S K
A
8/30/2024
PLAN
NORTH
TRUE
NORTH
Project Number
Building Number
Drawing Number
Project Title
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
BID DOCUMENTS
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
STAMP
321 4 5 6 7 8 9 10
E
ARCHITECT/ENGINEER OF RECORD
Alesia Architecture P.C.
3705 North 200th Street Elkhorn, Nebraska 68022 Phone: (402) 291-6941
Shaffer, Stevens & Schaap 1070 Howard Street Omaha, Nebraska 68102 Phone: (402) 455-7698
AMI Environmental Inc 8802 S 135th Street Omaha, NE 68138 Phone: (402) 397-5001
IMEG Corp.
15 Sunnen Drive, Suite 104 St. Louis, MO 63143 Phone: (314) 645-1132
CC
o n e e ig h th i n c h o n e f o o t th re e i n c h e s o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t o n e i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t
Aw
F
D
Ac Ae
B
KEY PLAN
C
A u to d e s k D o c s
/2
-1
A -2
-3
V
A P o p la r
B lu ff
R e m o v e a n d
R e p la c e
L a b A
H U a n d A
H U
/6
A
-2
-3
.B
.A rc h R
-1
-R e p l L a b A
H U
A
H U
.r v t
/9
/2
:0
:3
P M
GC001
PIPE BASEMENT - PHASE 1 REMOVE AND REPLACE END OF
LIFE HEATING, VENTILATION, AND
AIR CONDITIONING
JOHN J. PERSHING VETERANS' ADMINISTRATION MEDICAL
CENTER 1500 N. WESTWOOD BLVD. POPLAR BLUFF, MO
63901-3318
657A4-21-800
8/30/2024 GG/AHT KRK/TJF
1/16" = 1'-0"1
PIPE BASEMENT - PHASE 1
A B B.1 W X Y AA CC BB DD FF L M N O P Q R S T U V
1.1
14.1
MORGUE
GA-072
LOCKER RM., M
GA-056
LOCKER RM F
GA-077
RESTROOM/SHOWER,
F
GA-079
RESTROOM/SHOWER,
M
GA-055
CREDIT UNION
GA-080
EMS
GA-073
LAUNDRY
GE-070
OFFICE
GE-063
OFFICE
GE-062
LINEN CHUTE
GA-078
RESTROOM, F
GA-079A
ELECTRICAL
ROOM
GA-081
STORAGE
GA-076
REST ROOM
GA-075
CLOSET
GA-058
SUPPLY
GA-059
RM
GE-064
STAFF
RESTROOM
GE-065
LAUNDRY
GE-066
STORAGE
GE-068
CORRIDOR
GA-C01
CORRIDOR
GA-C02
OFFICE
GE-068A
DEDUCT ALTERNATE -
SEE AG002 &
TEMPORARY MODULAR
BUILDING COMPLEX
DRAWINGS
STORAGE
GC-011A
STAIRWELL C
GC-S01
MECH. ROOM
GC-011
EYE CLINIC
GC-10C
EYE CLINIC
GC-10B
EYE CLINIC
GC-10A
EYE GLASS
SALES
GC-010
ELEC. CLOSET
GC-09B
CORRIDOR
GC-C01
ELEV
GC-E05
EXAM ROOM
GC-014
EXAM ROOM
GC-14A
PROCEDURE
GC-015
PROCEDURE
GC-15A
EXAM
GC-016
EYE CLINIC
GC-16A
CHECK-IN
GA-017
CHECK-IN
GA-17C
RESTROOM M/F
GA-17A
STAIRWELL 4
GA-S01
ENTRANCE
GA-09A
PHARMACY
WAITING ROOM
GA-07A
RECONCILLIATION
GA-07Q
MECH. RM
GA-07
PHYSICAL
THERAPY
GA-18
EXAM 2
GA-18A
WAITING RM
GA-17B
ELEC. CLOSET
GA-07TPROSTHETICS
GA-03
CHUTE
GA-05
PIPE CHASE
GA-01C
STORAGE
GA-07M
STAIRWELL 5
GA-S02
CALL CENTER
GB-07J
PURCHASER'S
OFFICE
GB-07K
BREAKROOM
GB-07N
RESTROOM
GB-07R
HVAC RM
GB-07S
NARCOTICS RM
GB-07G
CHEMO HD RM
GB-07F
IV ROOM
GB-07E
CLOSET
GB-07P
IV HOOD ROOM
GB-07L
IV TECHNICIAN
GB-07D
DIRECTOR'S
OFFICE
GB-07C
SECRETARY
GB-07O
STOCK AREA
GB-07I
DISPENSING
GB-07H
CORRIDOR
GB-C01
DISPENSING
GB-07B
EXAM 1
GA-02
STORAGE
GA-1AOFFICE
GA-082
PIPE CHASE
GA-01B
TELECOMMUNICATIONS
GD-22
TELECOM
SWITCH
GA-052
ELEC. CLOSET
GD-01D
SUPERVISOR
OFFICE
GD-47
RESTROOM, M
GD-46
CLOSET
GD-47A
COUMADIN
STORAGE
GD-28
COUMADIN
CLOSET
GD-29
ELEC. STORAGE
GD-27
STAIRWELL 6
GD-S03
COUMADIN
CLINIC
GD-30
CONFERENCE
ROOM
GD-45A
CORRIDOR
GD-CC
STORAGE
GD-32
BIOMED SHOP
GD-34
BIOMED
GD-35
MECH. ROOM
GD-45
ELEC. CLOSET
GD-GD
ELEC. SHOP
GD-36
BACKUP
STORAGE
GD-37
MECH. ROOM
GD-38
UNION OFFICE
GD-44
AC SHOP
GD-44A
STAIRWELL 7
GD-S01
EQUIP. STORAGE
GD-42
TRASH CART
GD-39
GENERAL PHASING NOTES:
1. PHASES 1 THROUGH 4 SHOWN ON THESE MAIN
HOSPITAL BUILDING 1 DRAWINGS ARE RELATED
TO PHASES SHOWN ON THE TEMPORARY
MODULAR BUILDING.
A. SEE TEMPORARY MODULAR BUILDING
DRAWINGS FOR PORTIONS OF THE
MODULAR BUILDING COMPLEX (MBC)
AND DESCRIPTIONS OF DEPARTMENTS
TO BE RELOCATED TO THE MBC DURING
RENOVATION WORK.
2. PHASE 1 OF THE TEMPORARY MODULAR
BUILDING MUST BE COMPLETED BEFORE
PHASE 1 OF THE MAIN HOSPITAL BUILDING 1
BLOOD LAB CAN BEGIN.
NOTE 2A:
PHASE 1 – PHASE 2 - GROUND FLOOR AND
FIRST FLOOR WORK.
THE WORK INCLUDES, BUT IS NOT LIMITED TO
THE REMOVAL AND REPLACEMENT OF
DUCTWORK IN THE AREAS SHADED. REMOVAL
OF EXISTING CEILING GRID, CEILING TILES, AND
OTHER CEILING MOUNTED ITEMS IS INCLUDED.
SEISMIC STEEL TUBES BELOW EXISTING
CEILINGS ARE TO REMAIN IN PLACE DURING
THE PROJECT WORK BEING PERFORMED.
CEILING MOUNTED SPEAKERS, HEAD AND
EXISTING LIGHT FIXTURES SHALL BE REMOVED,
STORED AND PROTECTED AS NEEDED, AND
REUSED. SPRINKLER HEADS SHALL BE MOVED
AS NEEDED TO AVOID CONFLICTS WITH NEW
DUCTWORK INSTALLATION. EXIT SIGNAGE
SHALL BE REMOVED AS NEEDED DURING
CEILING WORK AND REINSTALLED AT THE
ORIGINAL LOCATION FOR EACH. INSTALL NEW
CEILINGS AND CEILING GRIDS. REINSTALL
EXISTING LIGHT FIXTURES, SPEAKERS, EXIT
SIGNS AND ANY OTHER REMOVED CEILING
MOUNTED ITEMS.
3. CONTRACTOR TO REVIEW AND SUBMIT
CONSTRUCTION PHASING PLAN FOR REVIEW
AND APPROVAL BY THE VA.
4. CONTRACTOR TO PROVIDE ALL PRODUCT
SUBMITTALS FOR REVIEW AND APPROVAL BY
THE VA BEFORE CONSTRUCTION CAN START.
5. CONTRACTOR TO SUBMIT COORDINATION
DRAWINGS FOR REVIEW AND APPROVAL BY
THE VA BEFORE CONSTRUCTION CAN START.
6. PHASES SHOWN IN THE LEGEND WITH A
PROJECT NUMBER AFTER THEM ARE PART OF
THE SCOPE OF WORK CONTAINED IN THIS SET
OF CONTRACT DOCUMENT DRAWINGS.
PROJECT PHASING - LEGEND
NO WORK IN AREA
PHASE 1
PHASE 2
PHASE 3
PHASE 4
MODULAR BUILDING COMPLEX
PHASES 1-4
CONTRACTOR SHALL REFER TO THE MODULAR
BUILDING COMPLEX PACKAGE FOR COORDINATION
AND RELOCATION DURING PHASING OF
DEPARTMENTS, EQUIPMENT, INFRASTRUCTURE,
ETC. REQUIRED FOR CONTINUED VA OPERATIONS.
MODULAR BUILDING
COMPLEX COORDINATION
PHASE 0 & 1 DESCRIPTIONS
PHASE 0:
A. DESIGN AND SUBMIT FOR VA APPROVAL LAYOUTS AND
PHASING PLANS FOR WORK IN BUILDING 1 AND
CONSTRUCTION OF THE TEMPORARY MODULAR
BUILDING COMPLEX (MBC), ALONG WITH PRODUCT
SUBMITTALS FOR ITEMS TO BE PART OF THE PROJECT.
B. PREPARE SITE WEST OF BUILDING 1 AND CONSTRUCT
TEMPORARY MODULAR BUILDING COMPLEX (MBC) –
PHASE 1. INCLUDING COVERED WALKWAYS, FIREWALL
AND CONNECTING LINK TO HOSPITAL AND ALL
NECESSARY UTILITY CONNECTIONS TO THE SITE AND
THE HOSPITAL, BUILDING 1.
C. THE MBC SHALL COMPRISE OF A 4-PLEX OF UNITS TO
REMAIN ON-SITE FOR THE DURATION OF THIS PROJECT
WITH DEDICATED UNITS FOR RESTROOMS,
TELECOMMUNICATIONS AND UTILITY FUNCTIONS, WITH
A CONNECTING CORRIDOR AND AN ADDITIONAL 3-PLEX
OF BUILDING MODULES TO HOUSE PHASE 1 LAB
FUNCTIONS.
D. THE CONTRACTOR HAS THE OPTION OF
1. OBTAINING SPECIALTY MODULES DEDICATED
FOR USE WITH LABORATORIES, OR
2. PROVIDING A SERIES OF CONVENTIONAL
BUILDING MODULES WHICH CAN BE OUTFITTED
FOR LAB FUNCTIONS IN PHASE 1 AND
CONVERTED FOR OTHER FUNCTIONS AS
REQUIRED FOR PHASES 2 AND 3.
PHASE 1:
A. RELOCATE EXISTING LABORATORY OPERATIONS AND
EQUIPMENT FROM SECOND FLOOR LABS IN WINGS ‘A’-
EAST AND ‘C’ TO THE TEMPORARY MODULAR BUILDING
COMPLEX.
B. COMPLETE ASBESTOS REMEDIATION IN SAME SECOND
FLOOR LAB AREAS.
C. RENOVATE SECOND FLOOR LAB AREAS, REPLACE LAB-
AHU AND RELATED EQUIPMENT AND STRUCTURAL
IMPROVEMENTS AT SECOND, THIRD AND FOURTH
FLOORS, AND MAKE ALL NECESSARY UTILITY
CONNECTIONS DOWN TO PIPE BASEMENT LEVEL.
D. CONDUCT WORK IN PIPE BASMENT RELATED TO LAB
AHU WORK.
E. INSTALLATION OF RTU-MAIL AND RENOVATION OF MAIL
ROOM 1A-173. PROVIDE HVAC RENOVATION OF MAIL
ROOM 1A-173 ON FIRST FLOOR, INCLUDING NEW RTU-
MAIL ON ROOFTOP OF THE SOUTH ENTRY LOBBY AT
SECOND FLOOR, AND NEW DUCTWORK THROUGH
CORRIDOR 1A-C04 AND MEDICAL RECORDS 1A-101.
• THIS INCLUDES STRUCTURAL
REINFORCEMENT OF EXISTING LOBBY
ROOF STRUCTURE,
• REMOVAL AND REINSTALLATION OF
LOBBY, MAIL ROOM, CORRIDOR AND
MEDICAL RECORDS CEILINGS.
B. AT THE BEGINNING OF PHASE 1:
1. THE SEPARATE 3-PLEX OF MODULES FOR LAB
FUNCTIONS SHALL BE OPERATIONAL AND
READY TO ACCEPT EQUIPMENT FROM THE LABS.
2. DESIGNATED EQUIPMENT FROM THE LAB WILL
NEED TO REMAIN IN BUILDING 1 WHILE NEW
EQUIPMENT IS INSTALLED IN THE MBC LABS. A
PERIOD OF 4-5 WEEKS IS REQUIRED FOR
TESTING AND CALIBRATION OF NEW
EQUIPMENT, WITH DESIGNATED EXISTING
EQUIPMENT TO REMAIN IN OPERATION UNTIL
THE NEW EQUIPMENT IS CERTIFIED TO BE
AVAILABLE FOR USE.
3. AFTER LAB-TESTING EQUIPMENT IS SET UP AND
READY FOR OPERATION, DESIGNATED
EQUIPMENT IN BUILDING 1 CAN BE REMOVED
AND DEMOLITION MAY COMMENCE IN BUILDING
1.
4. WORK IN PIPE BASEMENT MAY TAKE PLACE
AFTER RELOCATION OF 2ND FLOOR LABS TO
THE MBC.
5. THE MAIL ROOM WILL BE RELOCATED TO THE
MBC 4-PLEX. THE MAIL ROOM WILL BE MOVED
BACK INTO BUILDING 1 UPON COMPLETION OF
WORK RELATED TO THE MAIL ROOM RTU AND
REFINISHING OF THE MAIL ROOM.
C. AT END OF PHASE 1:
1. RELOCATE ALL LAB OPERATIONS AND
EQUIPMENT FROM THE TEMPORARY MODULAR
BUILDING BACK INTO THE SECOND FLOOR LAB
SPACE.
2. REFURBISH THE MBC IN PREPARATION FOR
PHASE 2 AND PREPARE IT TO RECEIVE
FUNCTIONS BEING DISLOCATED OUT OF THE
HOSPITAL AS PART OF PHASE 2.
a. IF SPECIALTY LAB MODULES WERE USED, REMOVE FROM MBC AND REPLACE WITH
GENERAL-PURPOSE MODULES
PREPARED FOR PHASES 2 AND 3 USES.
b. IF GENERAL-PURPOSE MODULES WERE
MODIFIED TO SERVE LABS, RENOVATE
MODULES FOR PHASES 2 AND 3 USES.
PHASE 2 DESCRIPTION
PHASE 2:
A. PHASE 2 INCLUDES:
1. REMOVAL AND REPLACEMENT OF
AHU-AC9 AND ASSOCIATED
DUCTWORK.
2. PLATFORM FOR NEW AHU-AC9 AND
AHU-DENTAL (TO BE INSTALLED IN
PHASE 4).
3. CONNECTION TO REPLACED AHU-
AC9.
4. RENOVATE GROUND FLOOR WEST
AREAS, WHERE IDENTIFIED, ALONG
WITH REMOVAL AND REPLACEMENT
OF RELATED EQUIPMENT AND
INTERIOR CEILINGS, AND MAKING ALL
NECESSARY UTILITY CONNECTIONS.
5. A TEMPORARY AHU IS TO BE
INSTALLED ON THE GROUND WEST
OF THE HOSPITAL AND NORTH OF
THE MBC TO SERVE AREAS
CURRENTLY BEING SERVED BY
EXISTING AHU-AC9 ON GROUND
FLOORS AS PART OF PHASE 2, AND
FIRST FLOORS AS PART OF PHASES 3
AND 4.
6. REPLACE AHU-AC9 ON ROOF AT
FIRST FLOOR (NEW AHU-DENTAL ON
SAME ROOF TO INSTALL AS PART OF
PHASE 4).
7. REPLACE ROOF AS SHOWN AT FIRST
FLOOR ALONG WITH ROOFTOP AHU
REPLACEMENT.
8. RENOVATE GROUND FLOOR WEST
AREAS, WHERE IDENTIFIED, AND
RELATED EQUIPMENT AND INTERIOR
CEILINGS, AND MAKE ALL
NECESSARY UTILITY CONNECTIONS.
B. AT THE BEGINNING OF PHASE 2:
1. ENVIRONMENTAL MANAGEMENT
SERVICES (EMS), INCLUDING (BUT
NOT LIMITED TO) LAUNDRY WILL BE
RELOCATED TO THE MODULAR
BUILDING COMPLEX PRIOR TO START
OF DEMOLITION AND RENOVATION
WORK. PROVISION FOR LAUNDRY IS
TO BE MADE AS DIRECTED BY THE
COR.
2. AFTER DESIGNATED DEPARTMENTS
ARE RELOCATED TO THE MBC, WORK
MAY BEGIN INSIDE BLDG. 1.
a. AT END OF PHASE 2:
1. ALL FUNCTIONS WILL BE MOVED
BACK INTO RENOVATED SPACES.
2. THE MBC IS TO BE PREPARED FOR
PHASE 3 ACTIVITIES.
SEE PROJECT MANUAL SECTION 01 00 00-GENERAL
CONDITIONS, SHEET AG002 & TEMPORARY
MODULAR BUILDING COMPLEX DRAWINGS FOR
DESCRIPTION OF DEDUCT ALTERNATE.
DEDUCT ALTERNATE
JIM
H.
HAGEMAN
A-2205
A
R C H I T E
C
T
S T
A T
E
O F N E B
R A
S K
A
8/30/2024
PLAN
NORTH
TRUE
NORTH
Project Number
Building Number
Drawing Number
Project Title
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
BID DOCUMENTS
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
STAMP
321 4 5 6 7 8 9 10
E
ARCHITECT/ENGINEER OF RECORD
Alesia Architecture P.C.
3705 North 200th Street Elkhorn, Nebraska 68022 Phone: (402) 291-6941
Shaffer, Stevens & Schaap 1070 Howard Street Omaha, Nebraska 68102 Phone: (402) 455-7698
AMI Environmental Inc 8802 S 135th Street Omaha, NE 68138 Phone: (402) 397-5001
IMEG Corp.
15 Sunnen Drive, Suite 104 St. Louis, MO 63143 Phone: (314) 645-1132
CC
o n e e ig h th i n c h o n e f o o t th re e i n c h e s o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t o n e i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t
Aw
F
D
Ac Ae
B
KEY PLAN
C
A u to d e s k D o c s
/2
-1
A -2
-3
V
A P o p la r
B lu ff
R e m o v e a n d
R e p la c e
L a b A
H U a n d A
H U
/6
A
-2
-3
.B
.A rc h R
-1
-R e p l L a b A
H U
A
H U
.r v t
/9
/2
:0
:4
P M
GC100
GROUND FLOOR - PHASES 1 & 2 REMOVE AND REPLACE END OF
LIFE HEATING, VENTILATION, AND
AIR CONDITIONING
JOHN J. PERSHING VETERANS' ADMINISTRATION MEDICAL
CENTER 1500 N. WESTWOOD BLVD. POPLAR BLUFF, MO
63901-3318
657A4-21-800
8/30/2024 GG KRK
1/16" = 1'-0"1
GROUND FLOOR - PHASES 1 & 2
DEDUCT ALTERNATE - SEE AG002 &
TEMPORARY MODULAR BUILDING
COMPLEX DRAWINGS
A B B.1 W X Y AA CC BB DD FF L M N O P Q R S T U V
1.1
14.1
MY HEALTH VET
OFFICE
1A-107
EXAM
ROOM/DOCTOR
OFFICE
1A-108
OFFICE
1E-116
ORAL SURGERY
1E-114
DENTAL
TREATMENT
1E-113
CLERKS OFFICE
1E-111
DENTAL WAITING
ROOM
1E-110
DENTAL
LABORATORY
1E-129
TREATMENT
ROOM
1E-130A
TREATMENT
ROOM
1E-130
DENTAL IMAGING
1E-131
DENTAL IMAGING
1E-132
VETERANS
EXPERIENCE
OFFICER
1A-172
CLOSET
1E-115A
PATIENT REP QM
1A-103
DEDUCT ALTERNATE -
SEE AG002 &
TEMPORARY
MODULAR BUILDING
COMPLEX DRAWINGS
TEMPORARY MODULAR
BUILDING COMPLEX &
COVERED WALKWAYS -
SEE TEMPORARY
MODULAR BUILDING
DRAWINGS
TEMPORARY
CONNECTING LINK &
FIREWALL -
SEE TEMPORARY
MODULAR BUILDING
DRAWINGS
PROJECT PHASING - LEGEND
NO WORK IN AREA
PHASE 1
PHASE 2
PHASE 3
PHASE 4
MODULAR BUILDING COMPLEX
PHASES 1-4
STAIRWELL C
1C-S01
NURSING CLINIC
1C-048
PRIMARY CARE
1C-053
EXAM ROOM
1C-054
EXAM ROOM
1C-055
EXAM ROOM
1C-056
EXAM ROOM
1C-057
STAFF WORK
AREA
1C-059
PRIMARY CARE
WAITING ROOM
1A-064
ACS
1A-064A
CALL CENTER
1A-063
ACS
1A-062
EXAM ROOM
1A-061
RESTROOM, F
1A-060
TELEPHONE
SYSTEM
1A-060A
EXAM ROOM
1C-042
EXAM ROOM
1C-041
CLINICAL NURSE
1C-038
RESTROOM
UNUSABLE
1C-039
RESTROOM, M/F
1C-040
MEDICAL
SUPPLIES
1C-044
RESTROOM, M/F
1C-045
STAIRWELL 4
1A-S01
BHL PRIMARY
CARE
1A-034
RESTROOM, M
1A-029
MH/BHL
1A-030
EXAM ROOM
1A-031
EXAM ROOM
1A-032STAIRWELL 5
1A-S02
ASST.
FACILITATOR
1B-009
PHARMACIST
1B-009A
RESTROOM, F
1B-010
RESTROOM, M
1B-011
EXAM ROOM
1B-028
APRN, BC
1B-027A
PRIMARY CARE
1B-027
NURSES
STATION
1B-026
EXAM ROOM
1B-025
EXAM ROOM
1B-025A
ELECTRICAL
CLOSET
1B-023
EXAM ROOM
1B-022
EXAM ROOM
1B-021
NURSE STATION
1B-020
STAIRWELL B
1B-S01
EXAM ROOM
1B-012
SOCIAL WORKER
1B-013
STAIRWELL 2
1B-S02
EXAM ROOM
1B-015
EXAM ROOM
1B-016
EXAM ROOM
1B-017
EXAM ROOM
1B-018
CORRIDOR B
1B-C01
CORRIDOR C
1C-C01
PRGM. SPPT.
PACT
1A-007
FACILITATOR
1A-007A
ACS
1A-006
RESTROOM, F
1A-005
RESTROOM, M
1A-004
AGENT CASHIER
1A-065
CLOSET
1A-065A
ELEC. CLOSET
1D-068A
MEAL ASSEMBLY
1D-098
MEAL ASSEMBLY
1D-097
STAIRWELL 6
1D-S03
DISH WASHING
1D-069
DISH WASHING
1D-071
ELEC. CLOSET
1D-070
MEAL ASSEMBLY
1D-096
FOOD
PREPARATION
1D-094
FOOD
PREPARATION
1D-072
CORRIDOR D
1D-C01
INGREDIENTS
CONTROL
1D-093
FOOD COOLER
1D-074
SUPERVISOR
1D-1073
CHIEF DIETICIAN
1D-075A
CHILLED FOOD
STORAGE
1D-076
FROZEN FOOD
STORAGE
1D-077
RESTROOM, M
1D-087
RESTROOM, F
1D-090
STORAGE ROOM
1D-091
STORAGE ROOM
1D-089
STORAGE ROOM
1D-088
STAIRWELL 7
1D-S01
EQUIPMENT/COMPRESSOR
ROOM
1D-079
SUPPLY ROOM
1D-082
OXYGEN
STORAGE
1D-081
WASH ROOM
1D-080
LOADING DOCK
1D-085
DATA CABLE
RUN
1A-003A
INFORMATION
1A-003
RESTROOM, M
1F-169
CLOSET
1F-168
HOLDING AREA
1A-170
STAFF WORK
ROOM
1F-160
EXAM
1F-159
RESTROOM, F
1F-158
RESTROOM
1F-162
STORAGE
1F-161
EXAM
1F-157
CHECK-IN/WAITING
1F-156
C&P CHECK IN
1F-163
STAIRWELL
1F-S02
OEF/OIF CASE
MANAGER
1F-155
EXAM
1F-154
CARE GIVER
SUPPORT/RN
ASSESSOR
1F-165
WAITING ROOM
1F-166
EXAM
1F-153
BUSINESS
OFFICE
1F-152
MEDICATION
ROOM
1F-150
EXAM
1F-167
CORRIDOR F
1F-C01
RESTROOM, F
1F-149
SOILED
LINEN/CLOSET
1A-147
ELECTRICAL
CLOSET
1A-189
PATIENT
EDUCATION
1A-144
ADMISSIONS
1A-142
MEDICAL
RECORDS
1A-101
RELEASE OF
INFORMATION
1A-102
BUSINESS
1A-104
BUSINESS
1A-105
BREAK ROOM
1A-106
MAIL ROOM
1A-173
COMPRESSOR
1A-109
CORRIDOR
1A-C04
CORRIDOR
1A-C02
CORRIDOR
1A-C01
CORRIDOR E
1E-C01
CORRIDOR
1A-C03
CORRIDOR
1F-C02
STAIRWELL 3
1A-S03
WEST LOBBY
1A-001
EAST LOBBY
1A-002
CONTRACTOR SHALL REFER TO THE MODULAR
BUILDING COMPLEX PACKAGE FOR COORDINATION
AND RELOCATION DURING PHASING OF
DEPARTMENTS, EQUIPMENT, INFRASTRUCTURE,
ETC. REQUIRED FOR CONTINUED VA OPERATIONS.
MODULAR BUILDING
COMPLEX COORDINATION SEE PROJECT MANUAL SECTION 01 00 00-GENERAL
CONDITIONS, SHEET AG002 & TEMPORARY
MODULAR BUILDING COMPLEX DRAWINGS FOR
DESCRIPTION OF DEDUCT ALTERNATE.
DEDUCT ALTERNATE
PHASE 0 & 1 DESCRIPTIONS
PHASE 0:
A. DESIGN AND SUBMIT FOR VA APPROVAL LAYOUTS AND
PHASING PLANS FOR WORK IN BUILDING 1 AND
CONSTRUCTION OF THE TEMPORARY MODULAR
BUILDING COMPLEX (MBC), ALONG WITH PRODUCT
SUBMITTALS FOR ITEMS TO BE PART OF THE PROJECT.
B. PREPARE SITE WEST OF BUILDING 1 AND CONSTRUCT
TEMPORARY MODULAR BUILDING COMPLEX (MBC) –
PHASE 1. INCLUDING COVERED WALKWAYS, FIREWALL
AND CONNECTING LINK TO HOSPITAL AND ALL
NECESSARY UTILITY CONNECTIONS TO THE SITE AND
THE HOSPITAL, BUILDING 1.
C. THE MBC SHALL COMPRISE OF A 4-PLEX OF UNITS TO
REMAIN ON-SITE FOR THE DURATION OF THIS PROJECT
WITH DEDICATED UNITS FOR RESTROOMS,
TELECOMMUNICATIONS AND UTILITY FUNCTIONS, WITH
A CONNECTING CORRIDOR AND AN ADDITIONAL 3-PLEX
OF BUILDING MODULES TO HOUSE PHASE 1 LAB
FUNCTIONS.
D. THE CONTRACTOR HAS THE OPTION OF
1. OBTAINING SPECIALTY MODULES DEDICATED
FOR USE WITH LABORATORIES, OR
2. PROVIDING A SERIES OF CONVENTIONAL
BUILDING MODULES WHICH CAN BE OUTFITTED
FOR LAB FUNCTIONS IN PHASE 1 AND
CONVERTED FOR OTHER FUNCTIONS AS
REQUIRED FOR PHASES 2 AND 3.
PHASE 1:
A. RELOCATE EXISTING LABORATORY OPERATIONS AND
EQUIPMENT FROM SECOND FLOOR LABS IN WINGS ‘A’-
EAST AND ‘C’ TO THE TEMPORARY MODULAR BUILDING
COMPLEX.
B. COMPLETE ASBESTOS REMEDIATION IN SAME SECOND
FLOOR LAB AREAS.
C. RENOVATE SECOND FLOOR LAB AREAS, REPLACE LAB-
AHU AND RELATED EQUIPMENT AND STRUCTURAL
IMPROVEMENTS AT SECOND, THIRD AND FOURTH
FLOORS, AND MAKE ALL NECESSARY UTILITY
CONNECTIONS DOWN TO PIPE BASEMENT LEVEL.
D. CONDUCT WORK IN PIPE BASMENT RELATED TO LAB
AHU WORK.
E. INSTALLATION OF RTU-MAIL AND RENOVATION OF MAIL
ROOM 1A-173. PROVIDE HVAC RENOVATION OF MAIL
ROOM 1A-173 ON FIRST FLOOR, INCLUDING NEW RTU-
MAIL ON ROOFTOP OF THE SOUTH ENTRY LOBBY AT
SECOND FLOOR, AND NEW DUCTWORK THROUGH
CORRIDOR 1A-C04 AND MEDICAL RECORDS 1A-101.
• THIS INCLUDES STRUCTURAL
REINFORCEMENT OF EXISTING LOBBY
ROOF STRUCTURE,
• REMOVAL AND REINSTALLATION OF
LOBBY, MAIL ROOM, CORRIDOR AND
MEDICAL RECORDS CEILINGS.
B. AT THE BEGINNING OF PHASE 1:
1. THE SEPARATE 3-PLEX OF MODULES FOR LAB
FUNCTIONS SHALL BE OPERATIONAL AND
READY TO ACCEPT EQUIPMENT FROM THE LABS.
2. DESIGNATED EQUIPMENT FROM THE LAB WILL
NEED TO REMAIN IN BUILDING 1 WHILE NEW
EQUIPMENT IS INSTALLED IN THE MBC LABS. A
PERIOD OF 4-5 WEEKS IS REQUIRED FOR
TESTING AND CALIBRATION OF NEW
EQUIPMENT, WITH DESIGNATED EXISTING
EQUIPMENT TO REMAIN IN OPERATION UNTIL
THE NEW EQUIPMENT IS CERTIFIED TO BE
AVAILABLE FOR USE.
3. AFTER LAB-TESTING EQUIPMENT IS SET UP AND
READY FOR OPERATION, DESIGNATED
EQUIPMENT IN BUILDING 1 CAN BE REMOVED
AND DEMOLITION MAY COMMENCE IN BUILDING
1.
4. WORK IN PIPE BASEMENT MAY TAKE PLACE
AFTER RELOCATION OF 2ND FLOOR LABS TO
THE MBC.
5. THE MAIL ROOM WILL BE RELOCATED TO THE
MBC 4-PLEX. THE MAIL ROOM WILL BE MOVED
BACK INTO BUILDING 1 UPON COMPLETION OF
WORK RELATED TO THE MAIL ROOM RTU AND
REFINISHING OF THE MAIL ROOM.
C. AT END OF PHASE 1:
1. RELOCATE ALL LAB OPERATIONS AND
EQUIPMENT FROM THE TEMPORARY MODULAR
BUILDING BACK INTO THE SECOND FLOOR LAB
SPACE.
2. REFURBISH THE MBC IN PREPARATION FOR
PHASE 2 AND PREPARE IT TO RECEIVE
FUNCTIONS BEING DISLOCATED OUT OF THE
HOSPITAL AS PART OF PHASE 2.
a. IF SPECIALTY LAB MODULES WERE USED, REMOVE FROM MBC AND REPLACE WITH
GENERAL-PURPOSE MODULES
PREPARED FOR PHASES 2 AND 3 USES.
b. IF GENERAL-PURPOSE MODULES WERE
MODIFIED TO SERVE LABS, RENOVATE
MODULES FOR PHASES 2 AND 3 USES.
PHASE 2 DESCRIPTION
PHASE 2:
A. PHASE 2 INCLUDES:
1. REMOVAL AND REPLACEMENT OF
AHU-AC9 AND ASSOCIATED
DUCTWORK.
2. PLATFORM FOR NEW AHU-AC9 AND
AHU-DENTAL (TO BE INSTALLED IN
PHASE 4).
3. CONNECTION TO REPLACED AHU-
AC9.
4. RENOVATE GROUND FLOOR WEST
AREAS, WHERE IDENTIFIED, ALONG
WITH REMOVAL AND REPLACEMENT
OF RELATED EQUIPMENT AND
INTERIOR CEILINGS, AND MAKING ALL
NECESSARY UTILITY CONNECTIONS.
5. A TEMPORARY AHU IS TO BE
INSTALLED ON THE GROUND WEST
OF THE HOSPITAL AND NORTH OF
THE MBC TO SERVE AREAS
CURRENTLY BEING SERVED BY
EXISTING AHU-AC9 ON GROUND
FLOORS AS PART OF PHASE 2, AND
FIRST FLOORS AS PART OF PHASES 3
AND 4.
6. REPLACE AHU-AC9 ON ROOF AT
FIRST FLOOR (NEW AHU-DENTAL ON
SAME ROOF TO INSTALL AS PART OF
PHASE 4).
7. REPLACE ROOF AS SHOWN AT FIRST
FLOOR ALONG WITH ROOFTOP AHU
REPLACEMENT.
8. RENOVATE GROUND FLOOR WEST
AREAS, WHERE IDENTIFIED, AND
RELATED EQUIPMENT AND INTERIOR
CEILINGS, AND MAKE ALL
NECESSARY UTILITY CONNECTIONS.
B. AT THE BEGINNING OF PHASE 2:
1. ENVIRONMENTAL MANAGEMENT
SERVICES (EMS), INCLUDING (BUT
NOT LIMITED TO) LAUNDRY WILL BE
RELOCATED TO THE MODULAR
BUILDING COMPLEX PRIOR TO START
OF DEMOLITION AND RENOVATION
WORK. PROVISION FOR LAUNDRY IS
TO BE MADE AS DIRECTED BY THE
COR.
2. AFTER DESIGNATED DEPARTMENTS
ARE RELOCATED TO THE MBC, WORK
MAY BEGIN INSIDE BLDG. 1.
a. AT END OF PHASE 2:
1. ALL FUNCTIONS WILL BE MOVED
BACK INTO RENOVATED SPACES.
2. THE MBC IS TO BE PREPARED FOR
PHASE 3 ACTIVITIES.
PHASE 3 DESCRIPTION
PHASE 3:
A. PHASE 3 INCLUDES:
1. REMOVAL, REPLACEMENT AND
CONNECTION OF NEW DUCTWORK TO
REPLACED AHU-AC9 AT FIRST FLOOR.
2. RELATED WORK ON FIRST FLOOR,
WEST PLAN AREAS. INCLUDING
REMOVAL AND REPLACEMENT OF
INTERIOR CEILINGS.
3. RENOVATE FIRST FLOOR WEST AREAS,
WHERE IDENTIFIED, AND RELATED
EQUIPMENT, AND MAKE ALL
NECESSARY UTILITY CONNECTIONS.
B. AT THE BEGINNING OF PHASE 3:
1. DEPARTMENTS, INCLUDING VETERANS
SERVICE OFFICES (VSOS), PAIN CLINIC
AND WOMEN’S CLINIC, IN WINGS 'A'-
WEST AND 'F' WILL BE RELOCATED TO
THE MBC PRIOR TO START OF
DEMOLITION AND RENOVATION WORK.
2. AFTER DEPARTMENTS ARE
RELOCATED TO MBC, WORK MAY
BEGIN INSIDE BLDG. 1.
C. AT THE END OF PHASE 3:
1. ALL DEPARTMENTS WILL BE MOVED
BACK INTO RENOVATED SPACES.
2. THE MBC IS TO BE PREPARED FOR
PHASE 4 ACTIVITIES.
A. THE MODULAR BUILDING 3-PLEX
WILL BE DISCONNECTED FROM
THE MBC AND REMOVED FROM
THE SITE.
B. THE CONNECTING CORRIDOR-
COVERED WALKWAY BETWEEN
THE 3-PLEX AND 4-PLEX IS TO
BE REBUILT TO ACCOMMODATE
SPECIALTY DENTAL TRAILERS,
WHICH ARE TO BE PLACED AT
THE BEGINNING OF PHASE 4.
PHASE 4 DESCRIPTION
PHASE 4:
A. PHASE 4 INCLUDES:
a. REPLACEMENT AND CONNECTION TO
NEW AHU-DENTAL AND RELATED
WORK ON FIRST FLOOR, WEST PLAN
AREAS IN WING ‘E’.
b. RENOVATE FIRST FLOOR WEST
AREAS, WHERE IDENTIFIED, AND
RELATED EQUIPMENT AND INTERIOR
CEILINGS, AND MAKE ALL
NECESSARY UTILITY CONNECTIONS.
B. AT THE BEGINNING OF PHASE 4:
1. TWO SPECIALTY DENTAL TRAILERS
ARE TO BE PLACED AT THE WEST
END OF THE MBC, WITH TEMPORARY
WALKWAY STRUCTURES MODIFIED
AND ADDED TO CONNECT THE
DENTAL TRAILERS TO THE MBC.
2. THE DENTAL DEPARTMENT WILL BE
RELOCATED TO THE DENTAL
TRAILERS AND WITHIN THE MBC 4-
PLEX PRIOR TO START OF WORK
INSIDE BUILDING 1.
3. UPON COMPLETION OF HVAC WORK
IN BUILDING 1, REMOVE THE
TEMPORARY GROUND MOUNTED
AHU. RELOCATE THE DENTAL
DEPARTMENT TO BUILDING 1 UPON
COMPLETION AND ACCEPTANCE OF
RENOVATION WORK.
C. END OF PHASE 4:
1. DEMOLISH TEMPORARY MODULAR
BUILDING COMPLEX – PHASE 4 OF
THOSE DRAWINGS. INCLUDING
COVERED WALKWAYS, FIREWALL
AND CONNECTING WALKWAY TO
HOSPITAL.
2. REMOVE ALL MBC UTILITY
CONNECTIONS TO THE SITE AND THE
HOSPITAL, BUILDING 1.
3. RESTORE AND RETURN SITE TO
CURRENT STATE AS SHOWN ON CIVIL
DRAWINGS
GENERAL PHASING NOTES
1. PHASES 1 THROUGH 4 SHOWN ON THESE MAIN
HOSPITAL BUILDING 1 DRAWINGS ARE RELATED
TO PHASES SHOWN ON THE TEMPORARY
MODULAR BUILDING.
A. SEE TEMPORARY MODULAR BUILDING
DRAWINGS FOR PORTIONS OF THE
MODULAR BUILDING COMPLEX (MBC) AND
DESCRIPTIONS OF DEPARTMENTS TO BE
RELOCATED TO THE MBC DURING
RENOVATION WORK.
2. PHASES 0 AND 1 OF THE TEMPORARY MODULAR
BUILDING MUST BE COMPLETED BEFORE PHASE 1
OF THE MAIN HOSPITAL BUILDING 1 CAN BEGIN.
NOTE 2A:
PHASE 1 – SECOND FLOOR WORK.
THE WORK INCLUDES BUT IS NOT LIMITED TO THE
REMOVAL AND REPLACEMENT OF DUCTWORK IN
THE AREAS SHADED. REMOVAL OF EXISTING
CEILING GRID, CEILING TILES, AND OTHER
CEILING MOUNTED ITEMS IS INCLUDED. SEISMIC
STEEL TUBES BELOW EXISTING CEILINGS REMAIN
IN PLACE DURING THE PROJECT WORK BEING
PERFORMED. CEILING MOUNTED SPEAKERS,
HEAD AND EXISTING LIGHT FIXTURES SHALL BE
REMOVED AS NEEDED AND REUSED. SPRINKLER
HEADS SHALL BE MOVED AS NEEDED TO AVOID
CONFLICTS WITH NEW DUCTWORK INSTALLATION.
EXIT SIGNAGE SHALL BE REMOVED AS NEEDED
DURING CEILING WORK AND REINSTALLED AT THE
ORIGINAL LOCATION FOR EACH. INSTALL NEW
CEILINGS AND CEILING GRIDS. REINSTALL
EXISTING LIGHT FIXTURES, SPEAKERS, EXIT
SIGNS AND ANY OTHER REMOVED CEILING
MOUNTED ITEMS.
NOTE 2B:
PHASE 1 – SECOND FLOOR - ASBESTOS
REMEDIATION – REMOVE EXISTING FLOORING IN
AREAS INDICATED ON FLOOR PLANS AND ABATE
FLOOR MASTIC. THE WORK INCLUDES BUT IS NOT
LIMITED TO THE REMOVAL AND REPLACEMENT OF
DUCTWORK IN THE AREAS SHADED. REMOVAL OF
EXISTING CEILING GRID, CEILING TILES, AND
OTHER CEILING MOUNTED ITEMS IS INCLUDED.
SEISMIC STEEL TUBES BELOW EXISTING CEILINGS
REMAIN IN PLACE DURING THE PROJECT WORK
BEING PERFORMED. CEILING MOUNTED
SPEAKERS, HEAD AND EXISTING LIGHT FIXTURES
SHALL BE REMOVED AS NEEDED AND REUSED.
SPRINKLER HEADS SHALL BE MOVED AS NEEDED
BASED TO AVOID CONFLICTS WITH NEW
DUCTWORK INSTALLATION. EXIT SIGNAGE SHALL
BE REMOVED AS NEEDED DURING CEILING WORK
AND REINSTALLED AT THE ORIGINAL LOCATION
FOR EACH. INSTALL NEW CEILINGS AND CEILING
GRIDS. REINSTALL EXISTING LIGHT FIXTURES,
SPEAKERS, EXIT SIGNS AND ANY OTHER
REMOVED CEILING MOUNTED ITEMS. INSTALL
NEW FLOOR TILES AS REQUIRED AS A RESULT OF
REMEDIATION WORK.
NOTE 2C:
PHASE 1 – THIRD FLOOR - ROOF ACCESSED FROM
THIRD FLOOR - AHU -
REMOVE AND REPLACE EXISTING AHU MOUNTED
ON ROOF JUST NORTH OF LEVEL THREE. REMOVE
EXISTING ROOF, ROOF SHEATHING, ROOF
INSULATION BELOW. REPLACE WITH NEW. MODIFY
EXISTING AHU OPENING AS REQUIRED TO
SUPPORT NEW AHU. CREATE NEW ROOF
OPENING FOR NEW CHILLER INSTALLATION – SEE
MECHANICAL. INSTALL NEW STEEL SUPPORT
STRUCTURE AND CATWALK TO HOLD NEW AHU
ON A PLATFORM ABOVE TO ALIGN WITH THE
ELEVATION OF LEVEL 4. INSTALL NEW
GUARDRAILS ALONG LEVEL 3 PARAPET AND ON
THE ELEVATED CATWALK PERIMETER ABOVE.
NOTE 2D:
PHASE 1 – FOURTH FLOOR REMOVE EXISTING
WINDOW ON NORTH WALL AND CUT A ROUGH
OPENING FOR NEW ACCESS DOOR TO OPEN
ONTO THE NEW MECHANICAL SUPPORT STEEL
PLATFORM THAT ALIGNS WITH THE FOURTH
FLOOR ELEVATION. INSTALL NEW STRUCTURAL
CAST CONCRETE SILL AT NEW DOOR
THRESHOLD. INSTALL NEW INSULATED DOOR AND
DOOR FRAME WITH HARDWARE AS DESCRIBED.
3. CONTRACTOR TO REVIEW AND SUBMIT
CONSTRUCTION PHASING PLAN.
4. CONTRACTOR TO SUBMIT ALL SUBMITTALS
BEFORE CONSTRUCTION CAN START.
5. CONTRACTOR TO SUBMIT COORDINATION
DRAWINGS BEFORE CONSTRUCTION CAN START.
6. PHASES SHOWN IN THE LEGEND ARE PART OF
THE SCOPE OF WORK CONTAINED IN THIS SET OF
CONTRACT DOCUMENT DRAWINGS.
JIM
H.
HAGEMAN
A-2205
A
R C H I T E
C
T
S T
A T
E
O F N E B
R A
S K
A
8/30/2024
PLAN
NORTH
TRUE
NORTH
Project Number
Building Number
Drawing Number
Project Title
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
BID DOCUMENTS
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
STAMP
321 4 5 6 7 8 9 10
ARCHITECT/ENGINEER OF RECORD
Alesia Architecture P.C.
3705 North 200th Street Elkhorn, Nebraska 68022 Phone: (402) 291-6941
Shaffer, Stevens & Schaap 1070 Howard Street Omaha, Nebraska 68102 Phone: (402) 455-7698
AMI Environmental Inc 8802 S 135th Street Omaha, NE 68138 Phone: (402) 397-5001
IMEG Corp.
15 Sunnen Drive, Suite 104 St. Louis, MO 63143 Phone: (314) 645-1132
CC
o n e e ig h th i n c h o n e f o o t th re e i n c h e s o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t o n e i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t
KEY PLAN
E
F
D
B
TT
Aw Ac Ae
C
A u to d e s k D o c s
/2
-1
A -2
-3
V
A P o p la r
B lu ff
R e m o v e a n d
R e p la c e
L a b A
H U a n d A
H U
/6
A
-2
-3
.B
.A rc h R
-1
-R e p l L a b A
H U
A
H U
.r v t
/9
/2
:0
:5
P M
GC101
FIRST FLOOR - PHASES 1, 2, 3 & 4 REMOVE AND REPLACE END OF
LIFE HEATING, VENTILATION, AND
AIR CONDITIONING
JOHN J. PERSHING VETERANS' ADMINISTRATION MEDICAL
CENTER 1500 N. WESTWOOD BLVD. POPLAR BLUFF, MO
63901-3318
657A4-21-800
8/30/2024 GG KRK
1/16" = 1'-0"1
FIRST FLOOR - PHASES 1, 2, 3 & 4
DEDUCT ALTERNATE - SEE AG002 &
TEMPORARY MODULAR BUILDING
COMPLEX DRAWINGS
A B B.1 W X Y AA CC BB DD FF L M N O P Q R S T U V
1.1
14.1
PROJECT PHASING - LEGEND
NO WORK IN AREA
PHASE 1
PHASE 2
PHASE 3
PHASE 4
MODULAR BUILDING COMPLEX
PHASES 1-4
CHEMISTRY
2C-046
SPECIMEN &
REAGENT
STORAGE
2C-045
ANCILLARY
OFFICE
2C-051
BREAK ROOM
2C-044
HEMATOLOGY
2C-048
REAGENT /
SUPPLIES ROOM
2C-054
LAB
SUPERVISOR
OFFICE
2C-041
LAB
INFORMATION
OFFICE
2C-042
RESTROOM, M/F
2C-043
HOUSEKEEPING
CLOSET
2C-052
HOUSEKEEPING
CLOSET
2C-053
RESTROOM, M/F
2C-055A
LAB COAT
CLOSET
2C-054A
STAIR A1
2A-S01
STAIR C
2C-S01
CULTURE ROOM
2A-038
MICROBIOLOGY
2A-037B
BLOOD BANK /
HISTOLOGY
2A-037A
LAB SUPPLY
ROOM
2A-037
RECORDS/SUPPLY
STORAGE
2A-036
GENERAL PHASING NOTES
1. PHASES 1 THROUGH 4 SHOWN ON THESE MAIN
HOSPITAL BUILDING 1 DRAWINGS ARE RELATED
TO PHASES SHOWN ON THE TEMPORARY
MODULAR BUILDING.
A. SEE TEMPORARY MODULAR BUILDING
DRAWINGS FOR PORTIONS OF THE
MODULAR BUILDING COMPLEX (MBC) AND
DESCRIPTIONS OF DEPARTMENTS TO BE
RELOCATED TO THE MBC DURING
RENOVATION WORK.
2. PHASES 0 AND 1 OF THE TEMPORARY MODULAR
BUILDING MUST BE COMPLETED BEFORE PHASE 1
OF THE MAIN HOSPITAL BUILDING 1 CAN BEGIN.
NOTE 2A:
PHASE 1 – SECOND FLOOR WORK.
THE WORK INCLUDES BUT IS NOT LIMITED TO THE
REMOVAL AND REPLACEMENT OF DUCTWORK IN
THE AREAS SHADED. REMOVAL OF EXISTING
CEILING GRID, CEILING TILES, AND OTHER
CEILING MOUNTED ITEMS IS INCLUDED. SEISMIC
STEEL TUBES BELOW EXISTING CEILINGS REMAIN
IN PLACE DURING THE PROJECT WORK BEING
PERFORMED. CEILING MOUNTED SPEAKERS,
HEAD AND EXISTING LIGHT FIXTURES SHALL BE
REMOVED AS NEEDED AND REUSED. SPRINKLER
HEADS SHALL BE MOVED AS NEEDED TO AVOID
CONFLICTS WITH NEW DUCTWORK INSTALLATION.
EXIT SIGNAGE SHALL BE REMOVED AS NEEDED
DURING CEILING WORK AND REINSTALLED AT THE
ORIGINAL LOCATION FOR EACH. INSTALL NEW
CEILINGS AND CEILING GRIDS. REINSTALL
EXISTING LIGHT FIXTURES, SPEAKERS, EXIT
SIGNS AND ANY OTHER REMOVED CEILING
MOUNTED ITEMS.
NOTE 2B:
PHASE 1 – SECOND FLOOR - ASBESTOS
REMEDIATION – REMOVE EXISTING FLOORING IN
AREAS INDICATED ON FLOOR PLANS AND ABATE
FLOOR MASTIC. THE WORK INCLUDES BUT IS NOT
LIMITED TO THE REMOVAL AND REPLACEMENT OF
DUCTWORK IN THE AREAS SHADED. REMOVAL OF
EXISTING CEILING GRID, CEILING TILES, AND
OTHER CEILING MOUNTED ITEMS IS INCLUDED.
SEISMIC STEEL TUBES BELOW EXISTING CEILINGS
REMAIN IN PLACE DURING THE PROJECT WORK
BEING PERFORMED. CEILING MOUNTED
SPEAKERS, HEAD AND EXISTING LIGHT FIXTURES
SHALL BE REMOVED AS NEEDED AND REUSED.
SPRINKLER HEADS SHALL BE MOVED AS NEEDED
BASED TO AVOID CONFLICTS WITH NEW
DUCTWORK INSTALLATION. EXIT SIGNAGE SHALL
BE REMOVED AS NEEDED DURING CEILING WORK
AND REINSTALLED AT THE ORIGINAL LOCATION
FOR EACH. INSTALL NEW CEILINGS AND CEILING
GRIDS. REINSTALL EXISTING LIGHT FIXTURES,
SPEAKERS, EXIT SIGNS AND ANY OTHER
REMOVED CEILING MOUNTED ITEMS. INSTALL
NEW FLOOR TILES AS REQUIRED AS A RESULT OF
REMEDIATION WORK.
NOTE 2C:
PHASE 1 – THIRD FLOOR - ROOF ACCESSED FROM
THIRD FLOOR - AHU -
REMOVE AND REPLACE EXISTING AHU MOUNTED
ON ROOF JUST NORTH OF LEVEL THREE. REMOVE
EXISTING ROOF, ROOF SHEATHING, ROOF
INSULATION BELOW. REPLACE WITH NEW. MODIFY
EXISTING AHU OPENING AS REQUIRED TO
SUPPORT NEW AHU. CREATE NEW ROOF
OPENING FOR NEW CHILLER INSTALLATION – SEE
MECHANICAL. INSTALL NEW STEEL SUPPORT
STRUCTURE AND CATWALK TO HOLD NEW AHU
ON A PLATFORM ABOVE TO ALIGN WITH THE
ELEVATION OF LEVEL 4. INSTALL NEW
GUARDRAILS ALONG LEVEL 3 PARAPET AND ON
THE ELEVATED CATWALK PERIMETER ABOVE.
NOTE 2D:
PHASE 1 – FOURTH FLOOR REMOVE EXISTING
WINDOW ON NORTH WALL AND CUT A ROUGH
OPENING FOR NEW ACCESS DOOR TO OPEN
ONTO THE NEW MECHANICAL SUPPORT STEEL
PLATFORM THAT ALIGNS WITH THE FOURTH
FLOOR ELEVATION. INSTALL NEW STRUCTURAL
CAST CONCRETE SILL AT NEW DOOR
THRESHOLD. INSTALL NEW INSULATED DOOR AND
DOOR FRAME WITH HARDWARE AS DESCRIBED.
3. CONTRACTOR TO REVIEW AND SUBMIT
CONSTRUCTION PHASING PLAN.
4. CONTRACTOR TO SUBMIT ALL SUBMITTALS
BEFORE CONSTRUCTION CAN START.
5. CONTRACTOR TO SUBMIT COORDINATION
DRAWINGS BEFORE CONSTRUCTION CAN START.
6. PHASES SHOWN IN THE LEGEND ARE PART OF
THE SCOPE OF WORK CONTAINED IN THIS SET OF
CONTRACT DOCUMENT DRAWINGS.
CONTRACTOR SHALL REFER TO THE MODULAR
BUILDING COMPLEX PACKAGE FOR COORDINATION
AND RELOCATION DURING PHASING OF
DEPARTMENTS, EQUIPMENT, INFRASTRUCTURE,
ETC. REQUIRED FOR CONTINUED VA OPERATIONS.
MODULAR BUILDING
COMPLEX COORDINATION
PHASE 0 & 1 DESCRIPTIONS
PHASE 0:
A. DESIGN AND SUBMIT FOR VA APPROVAL LAYOUTS AND
PHASING PLANS FOR WORK IN BUILDING 1 AND
CONSTRUCTION OF THE TEMPORARY MODULAR
BUILDING COMPLEX (MBC), ALONG WITH PRODUCT
SUBMITTALS FOR ITEMS TO BE PART OF THE PROJECT.
B. PREPARE SITE WEST OF BUILDING 1 AND CONSTRUCT
TEMPORARY MODULAR BUILDING COMPLEX (MBC) –
PHASE 1. INCLUDING COVERED WALKWAYS, FIREWALL
AND CONNECTING LINK TO HOSPITAL AND ALL
NECESSARY UTILITY CONNECTIONS TO THE SITE AND
THE HOSPITAL, BUILDING 1.
C. THE MBC SHALL COMPRISE OF A 4-PLEX OF UNITS TO
REMAIN ON-SITE FOR THE DURATION OF THIS PROJECT
WITH DEDICATED UNITS FOR RESTROOMS,
TELECOMMUNICATIONS AND UTILITY FUNCTIONS, WITH
A CONNECTING CORRIDOR AND AN ADDITIONAL 3-PLEX
OF BUILDING MODULES TO HOUSE PHASE 1 LAB
FUNCTIONS.
D. THE CONTRACTOR HAS THE OPTION OF
1. OBTAINING SPECIALTY MODULES DEDICATED
FOR USE WITH LABORATORIES, OR
2. PROVIDING A SERIES OF CONVENTIONAL
BUILDING MODULES WHICH CAN BE OUTFITTED
FOR LAB FUNCTIONS IN PHASE 1 AND
CONVERTED FOR OTHER FUNCTIONS AS
REQUIRED FOR PHASES 2 AND 3.
PHASE 1:
A. RELOCATE EXISTING LABORATORY OPERATIONS AND
EQUIPMENT FROM SECOND FLOOR LABS IN WINGS ‘A’-
EAST AND ‘C’ TO THE TEMPORARY MODULAR BUILDING
COMPLEX.
B. COMPLETE ASBESTOS REMEDIATION IN SAME SECOND
FLOOR LAB AREAS.
C. RENOVATE SECOND FLOOR LAB AREAS, REPLACE LAB-
AHU AND RELATED EQUIPMENT AND STRUCTURAL
IMPROVEMENTS AT SECOND, THIRD AND FOURTH
FLOORS, AND MAKE ALL NECESSARY UTILITY
CONNECTIONS DOWN TO PIPE BASEMENT LEVEL.
D. CONDUCT WORK IN PIPE BASMENT RELATED TO LAB
AHU WORK.
E. INSTALLATION OF RTU-MAIL AND RENOVATION OF MAIL
ROOM 1A-173. PROVIDE HVAC RENOVATION OF MAIL
ROOM 1A-173 ON FIRST FLOOR, INCLUDING NEW RTU-
MAIL ON ROOFTOP OF THE SOUTH ENTRY LOBBY AT
SECOND FLOOR, AND NEW DUCTWORK THROUGH
CORRIDOR 1A-C04 AND MEDICAL RECORDS 1A-101.
• THIS INCLUDES STRUCTURAL
REINFORCEMENT OF EXISTING LOBBY
ROOF STRUCTURE,
• REMOVAL AND REINSTALLATION OF
LOBBY, MAIL ROOM, CORRIDOR AND
MEDICAL RECORDS CEILINGS.
B. AT THE BEGINNING OF PHASE 1:
1. THE SEPARATE 3-PLEX OF MODULES FOR LAB
FUNCTIONS SHALL BE OPERATIONAL AND
READY TO ACCEPT EQUIPMENT FROM THE LABS.
2. DESIGNATED EQUIPMENT FROM THE LAB WILL
NEED TO REMAIN IN BUILDING 1 WHILE NEW
EQUIPMENT IS INSTALLED IN THE MBC LABS. A
PERIOD OF 4-5 WEEKS IS REQUIRED FOR
TESTING AND CALIBRATION OF NEW
EQUIPMENT, WITH DESIGNATED EXISTING
EQUIPMENT TO REMAIN IN OPERATION UNTIL
THE NEW EQUIPMENT IS CERTIFIED TO BE
AVAILABLE FOR USE.
3. AFTER LAB-TESTING EQUIPMENT IS SET UP AND
READY FOR OPERATION, DESIGNATED
EQUIPMENT IN BUILDING 1 CAN BE REMOVED
AND DEMOLITION MAY COMMENCE IN BUILDING
1.
4. WORK IN PIPE BASEMENT MAY TAKE PLACE
AFTER RELOCATION OF 2ND FLOOR LABS TO
THE MBC.
5. THE MAIL ROOM WILL BE RELOCATED TO THE
MBC 4-PLEX. THE MAIL ROOM WILL BE MOVED
BACK INTO BUILDING 1 UPON COMPLETION OF
WORK RELATED TO THE MAIL ROOM RTU AND
REFINISHING OF THE MAIL ROOM.
C. AT END OF PHASE 1:
1. RELOCATE ALL LAB OPERATIONS AND
EQUIPMENT FROM THE TEMPORARY MODULAR
BUILDING BACK INTO THE SECOND FLOOR LAB
SPACE.
2. REFURBISH THE MBC IN PREPARATION FOR
PHASE 2 AND PREPARE IT TO RECEIVE
FUNCTIONS BEING DISLOCATED OUT OF THE
HOSPITAL AS PART OF PHASE 2.
a. IF SPECIALTY LAB MODULES WERE USED, REMOVE FROM MBC AND REPLACE WITH
GENERAL-PURPOSE MODULES
PREPARED FOR PHASES 2 AND 3 USES.
b. IF GENERAL-PURPOSE MODULES WERE
MODIFIED TO SERVE LABS, RENOVATE
MODULES FOR PHASES 2 AND 3 USES.
SEE PROJECT MANUAL SECTION 01 00 00-GENERAL
CONDITIONS, SHEET AG002 & TEMPORARY
MODULAR BUILDING COMPLEX DRAWINGS FOR
DESCRIPTION OF DEDUCT ALTERNATE.
DEDUCT ALTERNATE
JIM
H…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .