S02 36C24426R0017 Liquidated Damages signed.pdf

PDF 234 KB Posted

Attached to
Z1DA--NRM| 503-21-102 Correct FCA Electrical Deficiencies Phase 1 (VA-26-00004932)
Solicitation number
36C24426R0017
Issued by

About this file

This Liquidation Damages Formulation Memo outlines the calculation of daily damages for delays in a federal contract (Solicitation Number: 36C24426R0017) related to correcting CFA Electrical Deficiencies. The document specifies liquidated damages of $582.98 per calendar day of inexcusable delay, broken down into two primary cost components: $323.28 for VISN 4 Contracting, Engineering, and Legal reviews, and $259.70 for Facility Engineering reviews. The damages are calculated using civilian wage rates from the General Schedule Locality Pay Table for the Rest of U.S., effective January 1, 2025, and are based on historical trends of additional contract administration time. The memo emphasizes that these damages are compensatory, and the government retains the right to seek additional actual damages separate from the contract completion delay.

View the file

Other files

File Type Posted
36C24426R0017 0002.docx DOCX document
Revised_Statement of Work 503-21-102.pdf PDF
36C24426R0017 0001.docx DOCX document
FCA Electrical Sign In Sheet_1.22.26.pdf PDF
RFI 2.6.2026.docx DOCX document
NewSwitchGearBuildingElevationsDetails_Revision1_02032026.pdf PDF
Pre-bid Site Visit Meeting Location.png PNG image
503-21-102 FCA Electrical Construction Drawings.pdf PDF
503-21-102 CD Specifications_Revised 7-29-25.pdf PDF
36C24426R0017.docx DOCX document
Statement of Work 503-21-102.pdf PDF
EXHIBIT C - Past Performance Questionnaire.pdf PDF
503-21-102 Pre-Bid RFI .docx DOCX document
P03 36C244-26-AP-0018 Honeywell Notifier signed_Redacted.pdf PDF
P03 36C244-26-AP-0018 Inpro Contego Signage signed _Redacted.pdf PDF
P03 Sole Source BNOE 503-21-102.pdf PDF
Pre-Bid Site Visit Meeting Location.pdf PDF
P03 36C244-26-AP-0018 Avigilon Camera signed Redacted.pdf PDF
01-EP-501.pdf PDF
072113 Thermal Insulation 09192025.pdf PDF
P03 36C244-26-AP-0018 02_Salto Door signed_Redacted.pdf PDF
P03 36C244-26-AP-0018 Bettwy Systems signed Redacted.pdf PDF
P03 36C244-26-AP-0018 Wattstopper DLM signed Redacted.pdf PDF
P03 36C244-26-AP-0018_Trane Tracer Ensemble signed Redacted.pdf PDF
PA 20260077 01.09.2026.pdf PDF
EXHIBIT D - Price Proposal Breakdown.pdf PDF
Exhibit B - Subcontractor Information and Consent Form.pdf PDF
Exhibit A - Experience.pdf PDF
076000 Flashing.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Elijah McIntosh Contracting Officer

Liquidation Damages Formulation Memo Solicitation Number: 36C24426R0017 Correct FCA Electrical Deficiencies

All Civilian wage rates are based upon the General Schedule Locality Pay Table (For the Locality Pay Area of Rest of U.S.) effective January 1, 2025 for Contracting and Project Engineer and FMS Manager.

1. Estimated liquidated damages for VISN 4 Contracting, Engineering, and Legal reviews per day of inexcusable delay:

CLASSIFICATION GRADE RATE HOURS TOTAL HOURLY RATE

Contracting Officer Supervisor

GS-14 / 5 $67.85 1 Hours $67.85

Contracting Officer

Contract Specialist

GS-13 / 5

GS-011 / 1

$57.42

$35.54

1 Hour

4 Hours

$57.42

$142.16

Legal Officer GS-14 / 4 $ 65.85 1 Hour $ 65.85

TOTAL PER

DAY

$ 323.28

2. Estimated liquidated damages for Facility Engineering (COR/COTR) per day of inexcusable delay:

CLASSIFICATION GRADE RATE HOURS TOTAL HOURLY RATE

Construction Manager GS-13 / 5 $57.42 2 Hours $114.84 Project Engineer GS-12 / 6 $48.28 3 Hours $144.86

TOTAL PER DAY $259.70

Grand Total Per Day $ 582.98

3. The Contractor shall pay liquidated damages to the Government in the amount of $582.98 for each calendar day of delay until the work is completed or accepted. The aforementioned costs were derived based upon historical trends associated with the time required of the parties to perform the additional contract administration which has not been completed by the Contractor within the specified time. The purpose of Liquidated Damages is compensatory only. The government retains the right to seek actual damages so far as they are distinguishable and separate from the Contractor failing to complete the work within the time specified in the contract.

4. The formulation of Liquidated Damages as detailed above are in accordance with Federal Acquisition Regulation 36.206 and will be assessed for each calendar day required to complete the construction work on this project past the scheduled completion date.

2025-12-08T13:03:32-0500
ELIJAH MCINTOSH