S02 36C24426R0017 Liquidated Damages signed.pdf
PDF 234 KB Posted
- Solicitation number
- 36C24426R0017
About this file
This Liquidation Damages Formulation Memo outlines the calculation of daily damages for delays in a federal contract (Solicitation Number: 36C24426R0017) related to correcting CFA Electrical Deficiencies. The document specifies liquidated damages of $582.98 per calendar day of inexcusable delay, broken down into two primary cost components: $323.28 for VISN 4 Contracting, Engineering, and Legal reviews, and $259.70 for Facility Engineering reviews. The damages are calculated using civilian wage rates from the General Schedule Locality Pay Table for the Rest of U.S., effective January 1, 2025, and are based on historical trends of additional contract administration time. The memo emphasizes that these damages are compensatory, and the government retains the right to seek additional actual damages separate from the contract completion delay.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Elijah McIntosh Contracting Officer
Liquidation Damages Formulation Memo Solicitation Number: 36C24426R0017 Correct FCA Electrical Deficiencies
All Civilian wage rates are based upon the General Schedule Locality Pay Table (For the Locality Pay Area of Rest of U.S.) effective January 1, 2025 for Contracting and Project Engineer and FMS Manager.
1. Estimated liquidated damages for VISN 4 Contracting, Engineering, and Legal reviews per day of inexcusable delay:
CLASSIFICATION GRADE RATE HOURS TOTAL HOURLY RATE
Contracting Officer Supervisor
GS-14 / 5 $67.85 1 Hours $67.85
Contracting Officer
Contract Specialist
GS-13 / 5
GS-011 / 1
$57.42
$35.54
1 Hour
4 Hours
$57.42
$142.16
Legal Officer GS-14 / 4 $ 65.85 1 Hour $ 65.85
TOTAL PER
DAY
$ 323.28
2. Estimated liquidated damages for Facility Engineering (COR/COTR) per day of inexcusable delay:
CLASSIFICATION GRADE RATE HOURS TOTAL HOURLY RATE
Construction Manager GS-13 / 5 $57.42 2 Hours $114.84 Project Engineer GS-12 / 6 $48.28 3 Hours $144.86
TOTAL PER DAY $259.70
Grand Total Per Day $ 582.98
3. The Contractor shall pay liquidated damages to the Government in the amount of $582.98 for each calendar day of delay until the work is completed or accepted. The aforementioned costs were derived based upon historical trends associated with the time required of the parties to perform the additional contract administration which has not been completed by the Contractor within the specified time. The purpose of Liquidated Damages is compensatory only. The government retains the right to seek actual damages so far as they are distinguishable and separate from the Contractor failing to complete the work within the time specified in the contract.
4. The formulation of Liquidated Damages as detailed above are in accordance with Federal Acquisition Regulation 36.206 and will be assessed for each calendar day required to complete the construction work on this project past the scheduled completion date.
| 2025-12-08T13:03:32-0500 | |
| ELIJAH MCINTOSH |
File details come from the government source that posted it. Updated .