383167 RFP 1.0 RFP Instructions to Offerors.pdf
PDF 330 KB Posted
- Solicitation number
- RFP-383167-CD
About this file
This Request for Proposal (RFP) 383167-CD solicits a firm fixed-price subcontract for the construction and renovation of the Kautz Road Substation (KRS), a critical electrical infrastructure facility at Fermilab in Batavia, Illinois. The general contractor must furnish all supervision, labor, materials, tools, and appurtenances necessary to rebuild and renovate the substation, which supplies electricity to various laboratory buildings and systems. The project is classified under NAICS code 237130 (Power and Communication Line and Related Structures Construction) with a small business size standard of $45 million. This is not a small business set-aside; however, non-small business offerors must provide a Small Business Subcontracting Plan. Proposals are due by 4:00 PM Central Time on December 18, 2026, with a Pre-Proposal Meeting and Site Visit scheduled for Wednesday, November 18, 2026, at 1:00 PM Central Time. FFDG requires a minimum of 120 calendar days for proposal acceptance. Questions must be submitted in writing by 5:00 PM Central Time on December 4, 2026, to Procurement Specialist Chris Daley at cdaley@fnal.gov or (630)-840-4256.
The critical schedule constraint requires the contractor to complete all work within Fermilab's accelerator shutdown window, anticipated to run from January 1, 2028, to January 1, 2030, with specific milestones including foundation completion by March 31, 2028, Authorization for Use and Possession by July 2, 2029, and final project completion by September 30, 2029. Evaluation uses a tradeoff source selection methodology with technical factors (70 points) outweighing cost (30 points). Technical evaluation focuses on organizational structure and key personnel (20 points), approach/safety compliance/work plan (25 points), and past performance (25 points). Offerors must demonstrate three reference projects completed within ten years, each valued at minimum $10 million, with at least one including 345kV substation yard equipment installation and all including 138kV or higher equipment plus at least three specified components such as heavy foundations, low-voltage systems, medium-voltage feeders, transformers, harmonic filters, or demolition of active utility buildings. The solicitation requires a bid guarantee of 20 percent (not exceeding $3 million) of the bid price, performance and payment bonds at 100 percent of contract price if exceeding $150,000 and $35,000 respectively, and comprehensive insurance coverage. All work is subject to Davis-Bacon Act wage requirements with weekly certified payroll submissions through LCPTracker. Offerors must meet rigorous Pass/Fail safety and quality criteria including three-year rolling safety performance at or below 85 percent of Bureau of Labor Statistics benchmarks for both Total Recordable Case Rate and Days Away, Restricted, or Transferred Rate, NCCI Experience Modification Rating evaluation, OSHA 300A form logs, corporate safety and health plans demonstrating 10 CFR Part 851 compliance, and corporate quality plans aligned with DOE Order 414.1E or equivalent standards. Financial capability requirements mandate a current ratio of 1.10 or greater, single-project bonding capacity equal to or exceeding the proposed total price, and aggregate bonding capacity of at least $30 million, with failure to meet these thresholds resulting in automatic disqualification as non-responsible.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSAL (RFP) 383167-CD
KAUTZ ROAD SUBSTATION CONSTRUCION, UIP
SUBPROJECT 2- KRS
November 2, 2026
TABLE OF CONTENTS
INVITATION TO SUBMIT PROPOSAL
NORTH AMERICAN INDUSTRY CLASSIFICATION SYSTEM (NAICS) CODE AND SMALL
BUSINESS SUBCONTRACTING PLAN
PRE-PROPOSAL MEETING/SITE VISIT
EXPLANATION OR INTERPRETATION OF RFP DOCUMENTS
AMENDMENT OF SOLICITATION
DESCRIPTION OF WORK & CONSTRUCTION SCHEDULE
PREPARATION, SUBMISSION, AND EVALUATION OF PROPOSALS
PROPOSAL DUE DATE
EXCEPTIONS AND DEVIATIONS
LATE SUBMISSION
OFFEROR'S MODIFICATION AND WITHDRAWAL OF PROPOSALS
BID GUARANTEE
DAVIS BACON ACT, CONSTRUCTION WAGES, AND CERTIFIED PAYROLL
ILLINOIS OCCUPATION AND USE TAXES
NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS
PAYMENT BOND
PERFORMANCE BOND
INSURANCE
SUBCONTRACT AWARD
SUBCONTRACTING
EXHIBITS
The following requirements must be adhered to for the Offeror’s submission of Proposals to Fermi Forward Discovery Group, LLC (FFDG) in support of this specific requirement.
1. INVITATION TO SUBMIT PROPOSAL
You are invited to submit a proposal for the items specified in this Request for Proposal (RFP), by the provisions contained herein, and the terms and conditions of the proposed firm fixed price subcontract entered into as a result of this solicitation.
All questions concerning this RFP should be submitted in writing and directed to the Procurement Specialist listed below.
Procurement Specialist: Chris Daley, CPPO, CPPB Phone: (630)-840-4256 Email: cdaley@fnal.gov
Fermi Forward Discovery Group, LLC Procurement Department Kirk Road & Wilson Street Batavia, IL 60510-0500
2. NORTH AMERICAN INDUSTRY CLASSIFICATION SYSTEM (NAICS) CODE
The North American Industry Classification System (NAICS) code for this solicitation is 237130, Power and Communication Line and Related Structures Construction. The small business size standard for this NAICS code is $45.0 Million.
This solicitation is not a small business set aside, however any Offeror considered for award who is not a small business shall provide a Small Business Subcontracting Plan using the template provided in Exhibit O as a guide.
3. PRE-PROPOSAL MEETING/SITE VISIT
A Pre-Proposal Meeting and Site Visit is scheduled for Wednesday, November 18, 2026, at 1:00 P.M. Central Time The meeting provides an opportunity to discuss and clarify the RFP. However, nothing said or represented in the meeting shall be deemed to modify RFP requirements unless followed by a written amendment. Offerors are requested to submit questions relative to the RFP in advance of the meeting so the Procurement Specialist may prepare responses. Offerors’ participation at this meeting is strongly recommended.
Except for those already having a Fermilab Access badge, anyone attending the Pre-Proposal Meeting and Site Visit must fill out an Access Request form (see link below) at least seven (7) days before the scheduled date. In addition, please review the Business Visitor Registration Instruction Instructions and Directions provided as part of the RFP.
https://fermi.servicenowservices.com/expert_shell.do?sysparm_sys_id=63f9f6a8dbd148104e65ff621f 961975.
Upon request approval, the individual will receive an informal invitation letter with a QR code, which is required to be presented at the security gate, otherwise, access to Fermilab will be denied.
When checking in at the Security Gate House, the individual will be required to present a Valid Driver’s License (Real ID),the informal invitation letter with the QR code, and the Visitor and Business Visitor Attestation Form. If the Driver’s License is not Real ID compliant, one of the appropriate REAL ID documents (https://www.tsa.gov/travel/security-screening/identification) is required.
https://fermi.servicenowservices.com/expert_shell.do?sysparm_sys_id=63f9f6a8dbd148104e65ff621f961975 https://fermi.servicenowservices.com/expert_shell.do?sysparm_sys_id=63f9f6a8dbd148104e65ff621f961975 https://www.tsa.gov/travel/security-screening/identification
Please note that when entering Fermilab:
• No weapons, firearms, or ammunition (regardless of concealed and carry permit) are allowed on-site.
• No explosives or any other apparatus or material hazardous to the public or property are allowed on-site.
• Illinois Rules of the Road are to be followed while driving on Fermilab’s premises.
4. EXPLANATION OR INTERPRETATION OF RFP DOCUMENTS
The prospective offeror should examine and review the solicitation with care. Any prospective offeror desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing by close of business (5:00 PM Central Time), December 4, 2026. Oral explanations or instructions given before the award of a subcontract will not be binding. Any information given to a prospective offeror concerning a solicitation will be furnished promptly to all other prospective offerors as an amendment to the solicitation if that information is necessary for submitting proposals or if the lack of the information would be prejudicial to other prospective offerors.
5. AMENDMENT OF SOLICITATION
FFDG may, by amendment, modify any provision or part of this RFP at any time before the award of any resultant subcontract. All terms and conditions that are not modified remain unchanged.
An Offeror shall acknowledge receipt of any amendments to this RFP. Failure to acknowledge may result in the disqualification of an Offeror’s proposal. The acknowledgment shall be provided in one of the following ways:
• Immediately upon receipt of the amendment via email to the FFDG Procurement Specialist or
• Return the Amendment with a signature on the acknowledgment signature line or
• In the Offeror’s Proposal Letter that accompanies an Offeror’s proposal.
6. DESCRIPTION OF WORK AND CONSTRUCTION SCHEDULE
This scope of work is to rebuild and renovate the Kautz Road Substation (KRS), which is UIP subproject SP-2. The KRS supplies electricity to various lab buildings and systems. These systems serve both conventional facility needs, as well as process utility requirements. It is vital to Fermilab’s mission that KRS be revitalized and expanded, ensuring the ability to serve existing and future loads.
The General contractor shall furnish all required supervision, labor, materials, tools, plant and appurtenances necessary to perform diligently and fully all work as described in the drawings and technical specifications. All work includes transportation, overhead, bonding costs, safety oversight, quality control oversight, and supervision as required to construct the project described in the drawings, technical specification and the detailed description contained herein.
The critical schedule constraint for construction of this project is Fermilab’s accelerator shutdown, with an anticipated scheduled start on January 1, 2028, and anticipated end date of January 1, 2030- these dates may change depending on the needs of the Lab. The General Contractor must start their on-site efforts, and complete the construction scope under this contract, within the shutdown window.
This project includes the following milestones:
Milestone 1 – 60 Calendar Days after issuance of Notice to Proceed (NTP). This milestone is intended for completion of necessary submittals and RFIs, approval of shop drawings for fabrication and procurement.
Milestone 2 – 4th January 2028; This milestone marks the point where access is permitted inside Kautz Road Substation yard and construction work may begin.
Milestone 3 – 31st of March 2028; This milestone marks the completion of building foundation and ready for placement of the new prefabricated control house building (provided by FermiForward).
Milestone 4 – 2nd July 2029; This milestone marks the formal issuance of an Authorization for Use and Possession (AUP) of the KRS Substation facility, including all remedial work following removal of site trailers, but not including seasonal work and all final punch list items addressed..
Milestone 5 – 30th September 2029; This milestone marks the completion of the project.
7. PREPARATION, SUBMISSION, AND EVALUATION OF PROPOSALS
FFDG expects to award a Subcontract to an Offeror who is deemed responsible, whose proposal conforms to this solicitation’s requirements, and whose proposal is judged to represent the best value to FFDG.
FFDG will use a Tradeoff source selection method. The best value is represented by the most advantageous proposal, price and other factors considered. Offerors are advised that a proposal meeting the solicitation requirements with the lowest evaluated price may not be selected if award to a higher evaluated price proposal is determined to be most advantageous to FFDG.
FFDG expects to award only one Subcontract as a result of this solicitation. However, FFDG may reject any or all proposals and not make any award based on this solicitation. FFDG may waive any informality or minor irregularity in proposal(s) received at its sole discretion.
FFDG reserves the right to award without discussions with Offerors. Accordingly, Offerors should submit their best proposals.
Each proposal shall be evaluated relative to the factors listed below in Evaluation Criteria. All evaluation factors other than cost or price, when combined, are significantly more important than cost or price.
Proposal Submission Format
The proposal shall be submitted in two (2) parts: Part I - Technical Proposal and Part II – Business Management and Price Proposal. In no instance shall Part I and Part II be bound together or presented in such manner as to make them not severable. The Technical Proposal shall not contain any reference to cost other than the information required in the past performance section.
Evaluation Process
Proposals will be scored in accordance with the evaluation criteria set forth below. FFDG shall make a selection for award based on the principles of best value with tradeoffs.
A. Part I - Technical Proposal (70 Points)
TECHNICAL EVALUATION FACTORS AND CRITERIA
Criteria 2 and 3 are of equal importance, and both are of greater importance than Criterion 1
1) Criterion 1- Organizational Structure and Key Personnel (20 Points)
1. Offeror’s Proposal shall include the following information:
a. name of the firm,
b. names of the firm’s principal(s),
c. size of the enterprise,
d. all of the firm’s current registration/license number(s) in Illinois, and
e. length of time the firm has worked in Illinois.
2. Provide Offeror’s experience in construction management service for other governmental agencies, particularly those within Illinois or other National DOE laboratories.
3. The Offeror must provide an organization/structure chart that shows its key technical and consulting personnel, including but not limited to: Program Executive, Superintendent(s), Project Manager(s), Safety Officer, and Estimator who will be assigned to this FFDG project. Key Personnel shall not be replaced without the prior written approval of FFDG. The Offeror must provide resumes for each Key Personnel and provide at least the following information:
a. Resumes detailing each individual’s education, technical training and work experience, and professional credentials (e.g. certifications and/or licenses), including those primary team members working in a subcontracting capacity. List which team member will have primary responsibility for the FFDG account;
b. Correlation of team members to the tasks each will be performing;
c. Describe previous, related experiences and projects, particularly projects valued at
$10 million or more; and
d. Office locations of proposed team members.
4. If an Offeror is planning to joint venture, incorporate the relationship on the organization chart and provide letters of interest from those firms. Include the names and credentials of their principals and key personnel and include their resumes along with evidence of any required licenses. The Offeror should describe the roles and responsibilities of their subcontractors, including the key personnel as they relate to the Scope of Services for the RFP.
5. Detail Offeror’s and any subcontractor’s current project workloads, active bonding drawdowns, and projected backlog changes for both the prime Offeror and all major subcontractors over the next eighteen (18) months to demonstrate sufficient resource availability to absorb this project without execution delays.
2) Criteria 2 – Approach/Safety Compliance/Work Plan (25 Points)
The Offeror must provide a narrative of the project approach, and an explanation of how this approach meets FFDG objectives and requirements as specified in this RFP. In the project approach, the Offeror shall:
1. SOW Alignment and JV Delineation: Describe the execution approach to fulfill the requirements in the Statement of Work. Joint ventures must explicitly define the divisions of labor, field management, and financial responsibility between parties.
2. Value Engineering: Identify, if applicable, project-specific technical solutions, alternative construction methodologies, or value engineering approaches that may generate cost and schedule savings for FFDG without reducing quality.
3. Cost Management and Control: Provide a written overview of the Offeror’s communication strategy to manage and track project expenditures and potential change orders.
4. Subcontractor Packaging: Include a subcontractor utilization plan detailing individual work packages, the specific trade disciplines performed, procurement methods, and the percentage of work to be subcontracted.
5. Conceptual Schedule: Provide a conceptual-level schedule outlining the logical sequencing of major construction milestones. At a minimum, this schedule must reflect all phases and payment milestones outlined in the Measurement and Payment Schedule.
Bidders must:
o Describe the system used to develop the master schedule as well as a three-week look ahead.
o Outline the process, or web-based tools, used for tracking, reviewing, and approving engineering submittals, requests for information, shop drawings, daily reports, photos, inspections, and non-conformance issues.
o Demonstrate specific corporate competency and past experience in cost-loading master schedules.
o Include a sample cost-loaded schedule illustrating an ability to adhere to FFDG’s earned value tracking during the construction phase.
6. Project-Specific Environment, Safety, and Health (ES&H) and Quality Control
Execution Plan: Provide a detailed narrative and risk profile outlining field-level execution strategies to ensure zero incidents and zero quality defects. Do not submit generic corporate safety handbooks or historical lagging statistics. The response must explicitly address the following three project-specific subfactors:
o High-Risk Operational Safety Controls: Describe field protocols, Job Hazard Analyses (JHAs), and engineering controls to be enforced during high-risk project phases:
Medium-Voltage (MV) and High-Voltage (HV) Electrical Safety: Detailed lockout/tagout (LOTO), grounding boundaries, and arc flash protections during the installation, splicing, and commissioning of MV feeders, transformers, and the 345kV substation yard equipment.
Protection of Existing Assets: Protect existing assets from damage during adjacent demolition, civil excavation, and pavement renovation.
o Project-Specific Quality Assurance and Field Inspections: Detail field-level quality control methods, independent inspection hold-points, and electrical/civil testing protocols deployed on-site. Clearly define the autonomous authority of the project’s Quality Manager to issue mandatory "Stop Work" orders for non-conforming work or materials.
o Project Risk Register: Identify technical risks inherent to this specific substation scope. For each risk, provide a clear mitigation strategy.
3) Criterion 3 – Past Performance (25 Points)
The Offeror must provide a minimum of three (3) reference projects, in which substantial completion has been obtained within the last ten years, demonstrating high-voltage control house construction and substation renovations comparable in complexity to the scope of work in this solicitation, in which each project must have a minimum contract value of no less than ten million dollars ($10,000,000.00). At least on project must include the installation of 345KV (or higher) substation yard equipment and each additional project shall include the installation of a minimum of 138KV (or higher) substation yard equipment and include at least three of the following components; (i) Installation of heavy foundations or pads for high-voltage utility control enclosures; (ii) Installation and integration of complex low-voltage facility power and DC distribution systems; (iii) Installation of underground medium-voltage power feeder duct banks and cabling; (iv) Installation and field commissioning of medium-voltage utility transformers; (v) Installation, structural staging, and tuning of specialized utility harmonic filter banks; (vi) Demolition of an active or legacy utility building containing live electrical infrastructure, for which the Offeror has provided construction services for as the Prime General Contractor. The project submission shall include, at a minimum, the following:
a. Organization/Owner name, with contact information
b. Project Title and Location
c. Project date (Start/End)
d. Proposer’s role in the project (e.g., prime/lead, sub)
e. Scope of work (Brief description 1-2 sentences)
f. Total project costs
NOTE: Representative photographs and exhibits supporting the above projects are permitted as an attachment to this section.
Offerors submitting as a joint venture can combine their past performance histories to meet the contract value thresholds. The evaluation committee will aggregate the past performance of Joint Venture submittals.
B. Part II - Business Management & Price Proposal (30 Points)
The Business Management proposal shall contain the following documents/items:
1) Price Proposal Form-
The proposed pricing shall be a firm fixed price for the work. This Price Proposal Form is required to be completed and signed.
The Cost Proposal will be comparatively ranked and scored as follows:
1. The lowest overall proposal cost, to include any chosen Bid Alternatives, will receive the maximum possible score (30 Points).
2. All other proposals will receive the score determined by the following table:
Point Range Percentage Higher than Lowest Overall Proposal
30 – 0 Points 0% up to 67% Higher 0 Points Higher than 67%
As an example of score, if Proposal A were the lowest proposal cost at $15,000, Proposal B was $17,000 ,and Proposal C was $20,000 then the cost score points for Proposal B would be calculated as follows: 30 points x {1.67 – (Proposal B Cost)/(Proposal A Cost)}/0.67 = 24.03 points; and the cost for Proposal C would be calculated as follow: 30 points x {1.67- (proposal C Cost)/(Proposal A Cost)}/0.67= 15.07.
While the mathematical total score will be a primary factor, FFDG reserves the right to award the contract to an offeror whose total score is lower than the highest scorer, provided that FFDG determines that the technical superiority of the higher-ranked technical proposal justifies the price premium and represents the best overall value to FFDG and the Government.
Offerors will be evaluated on the Pass-Fail factors identified in 2 through 5 below.
2) Bid Guarantee/Bond
The offeror shall provide a bid guarantee in the amount of not less than 20 percent (not to exceed $3 million) of the bid price. Failure to furnish a bid guarantee in the proper form and amount, by the time set for the due date of the offers, may be cause for rejection of the offer. The bid guarantee shall be in the form of a firm commitment, such as a bond, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds, or notes of the United States.
3) Financial Capability and Letter of Bond ability
The Offeror must provide audited financial statements for the past three (3) fiscal years and a formal, signed Letter of Intent from a surety company listed on the Department of the Treasury’s Listing of Approved Sureties (Circular 570). To receive a Pass, the submittals must explicitly confirm:
a) A Current Ratio (Current Assets / Current Liabilities) of 1.10 or greater in the most recent audited fiscal year.
b) A single-project bonding capacity equal to or greater than the Offeror's proposed total price.
c) An aggregate bonding capacity of not less than $30,000,000.
d) Failure to meet the 1.10 current ratio, or failure to provide a Treasury-listed bonding letter meeting both the single-project and $30M aggregate thresholds, will result in an automatic Fail and immediate disqualification as non-responsible.
Using the audited financial statements, bonding letter, and years-in-business information submitted above, the CFO office will conduct a financial viability determination as part of FFDG’s responsibility determination. This determination will consider standard financial health indicators, including but not limited to Debt-to-Equity Ratio, Operating Cash Flow trend, and a Dun & Bradstreet (D&B) Failure Score obtained independently by FFDG
4) Subcontractor Annual Representations & Certifications (SARC), Form SARC
The successful Offeror’s submittal of this completed form will be incorporated in the resultant subcontract. If an offering entity is a joint venture, association, consortia, or partnership, each member entity must submit individual Representations and Certifications Forms.
5) Proposal Certifications, Form PUR-466
All appropriate sections are required to be completed and signed by a company official.
6) Safety and Quality Documents
Prior to the qualitative evaluation of technical proposals, the Procurement Officer will evaluate the required Safety and Quality submittals on a strict Pass/Fail basis. To receive a Pass and proceed to technical evaluation, the Offeror must submit all requested documentation and meet or exceed the absolute performance thresholds defined below.
Failure to submit any document, or failure to meet any individual performance threshold, will result in an immediate Fail. A rating of Fail determines the Offeror to be non-responsible, and the entire proposal will be excluded from further evaluation and award consideration without an opportunity to cure deficiencies, unless the Laboratory elects to enter into formal Discussions with all competitive offerors.
• Fermilab Subcontractor Injury & Illness Data Questionnaire: The Offeror shall submit a completed and signed Fermilab Subcontractor Injury & Illness Data Questionnaire. The Offeror shall demonstrate a three-year rolling safety performance equal to or less than 85% of the most current U.S. Bureau of Labor Statistics (BLS) averages for NAICS 237130 (Power and Communication Line and Related Structures Construction) for both the Total Recordable Case (TRC) Rate and the Days Away, Restricted, or Transferred (DART) Case Rate. If the Offeror’s three-year rolling TRC or DART rates exceed 85% of the BLS industry benchmarks, the Offeror must submit a comprehensive written explanation detailing the exact contributing factors, immediate corrective actions implemented, and permanent corporate measures established to prevent recurrence. Submission of an explanation does not guarantee acceptance. The Laboratory reserves sole discretion to determine whether the explanation proves the Offeror can safely maintain a zero-incident footprint on the FFDG project site. Failure to submit the questionnaire, or failure to provide an acceptable mitigation narrative for elevated incident rates, will result in an automatic Fail.
• Construction Environmental, Safety & Health Certification (CESHC): Must be completed, signed, and indicate full, unconditional compliance with all listed Fermilab and Department of Energy (DOE) environmental and safety directives.
• National Council on Compensation Insurance (NCCI) Workers' Compensation Experience Rating (EMR): The Offeror shall submit official NCCI Experience Modification Rating (EMR) worksheets spanning the preceding three (3) consecutive fiscal years. Safety qualification metrics will be evaluated strictly on the following tiered operational thresholds:
• Automatic Pass: A three-year rolling average EMR of 1.0 or less, with no single year exceeding 1.25.
• Conditional Review: A three-year rolling average EMR of 1.01 or higher, or fewer than three (3) years of corporate EMR history, will be subject to Conditional Review. To pass Conditional Review, the Offeror must submit a written explanation outlining the specific workplace events driving the elevated rating, the specific safety accountability policies implemented since those events, and evidence of subsequent injury reduction. The Laboratory retains sole discretion to approve or reject the explanation based on its assessment of risk.
• OSHA 300A Form Logs: Must submit signed logs for the past three consecutive years. Logs must show a historically managed safety footprint consistent with the data provided in the Fermilab Questionnaire.
• Corporate Safety and Health Plan: Must be submitted and complete. The plan must explicitly state institutional compliance with 10 CFR Part 851 (Worker Safety and Health Program) and federal OSHA regulations. General or boilerplate plans that fail to reference 10 CFR Part 851 compliance will result in a Fail.
• Corporate Quality Plan: Must be submitted and complete. The plan must demonstrate an active corporate framework aligned with DOE Order 414.1E (Quality Assurance) or equivalent industry standards (e.g., ISO 9001).
• Sample Certificate of Insurance: Must be submitted and demonstrate the immediate capability to secure the mandatory minimum commercial liability, auto, and worker's compensation coverage limits specified in Section I of this RFP.
FFDG reserves the right to waive minor informalities, clerical errors, or minor omissions in the Business Management volume (such as missing signatures on administrative certifications or missing regulatory verification sheets) via administrative clarifications under FAR 15.306(a). However, the omission of a Bid Guarantee, a formal Letter of Bondability, or required audited financial data constitutes a material non-responsiveness defect that cannot be cured administratively and will result in immediate disqualification.
8. PROPOSAL DUE DATE
The offeror’s proposal is to be emailed to the Procurement Specialist no later than 4:00 PM Central Time on December 18, 2026. Partial or incomplete proposals will not be considered.
FFDG requires a minimum acceptance of one hundred-twenty (120) calendar days for acceptance of proposals. An offeror allowing less than Fermilab’s minimum acceptance period may be rejected.
FFDG reserves the right to cancel this Solicitation at any time without incurring any liability or damages associated with such cancellation.
9. EXCEPTIONS AND DEVIATIONS
Offerors taking exceptions, deviations, or conditional assumptions must identify and explain each exception/deviation, or conditional assumption taken with sufficient amplification and justification to permit evaluations. Such exceptions, deviations, or conditional assumptions will not themselves automatically cause a proposal to be deemed unacceptable to FFDG. However, a large number of exceptions or one or more significant exceptions not providing benefit to FFDG may result in the rejection of the offeror’s proposal as unacceptable.
10. LATE SUBMISSION
Proposals received by FFDG after the Submittal Date and Time indicated may not be considered. The Respondent assumes the risk of the method of dispatch chosen.
11. OFFEROR'S MODIFICATION AND WITHDRAWAL OF PROPOSALS
The offeror may submit modifications to its proposals at any time before the solicitation closing date and time and may submit modifications in response to an amendment
Proposals may be withdrawn at any time before the submission deadline. Withdrawals are effective upon receipt of notice by the Procurement Specialist.
12. BID GUARANTEE/BOND
If the successful Offeror, upon acceptance of its offer by FFDG within the period specified for acceptance, fails to execute all contractual documents, or give a bonds as required by Sections 16 and 17 of the solicitation within the time specified, FFDG may execute upon the bid guarantee, or terminate for default the subcontract, if the subcontract has been executed.
In the event, that the bid guarantee is exercised, or the subcontract is terminated for default, the Offeror is liable for any cost of acquiring the work that exceeds the amount of its offer and the guarantee may be used to offset the difference.
13. DAVIS-BACON ACT, CONSTRUCTION WAGES, AND CERTIFIED PAYROLL
The awarded Subcontract is subject to the wage and labor standards under the Davis-Bacon Act and the related labor standards FFDG provisions that are incorporated by reference into FFDG’s General Terms and Conditions for Construction.
The wage rates set forth are the minimum rates that may be paid to the classification of laborers and mechanics designated therein according to the Davis-Bacon Act, as amended (40 U.S.C. 276 et seq.).
FFDG does not represent that said minimum rates do now, nor that they will at any time in the future, prevail in the locality of the work for such laborers or mechanics; nor that such laborers or mechanics are or will be obtainable at said rates for work under this subcontract; nor those said rates represent the most recent wage determination by the Secretary of Labor concerning such classifications of laborers or mechanics in the locality of work.
The Subcontractor and its Subcontractors are required to submit certified payrolls and labor compliance documentation weekly as required by Federal law.
FFDG currently holds a licensing agreement with LCPTracker for weekly electronic payroll submittals by the Subcontractor and its Subcontractors. LCPTracker is a web-based system, accessed using a web browser. The Subcontractor will be given a Log-on identification (i.e., User ID) and password to access the LCPTracker system. This requirement shall flow down to every lower-tier Subcontractor. The use of this system is free.
14. ILLINOIS OCCUPATION AND USE TAXES
Any resulting contract will be exempt from Illinois Occupation and Use Taxes.
15. NOTICE OF BUY AMERICAN REQUIREMENT-CONSTRUCTION MATERIALS
Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American-Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225-9).
Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Procurement Specialist in time to allow a determination before the submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
Evaluation of offers.
FFDG will evaluate an offer requesting an exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, FFDG will award to the offeror that did not request an exception based on unreasonable cost.
Alternate offers.
When an offer includes foreign construction material not listed by FFDG in this solicitation in paragraph
(b) (2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on the use of equivalent domestic construction material.
If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which FFDG has not yet determined an exception applies.
If FFDG determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, FFDG will evaluate only those offers based on the use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on the use of the foreign construction material for which an exception was requested—
• Will be rejected as nonresponsive; or
• May be accepted if revised during negotiations.
16. PAYMENT BOND
If the subcontract exceeds $35,000.00, the successful offeror is required to furnish FFDG with a Payment Bond in the amount of 100 percent of the original subcontract price within (10) calendar days after the effective date of the subcontract using Exhibit L, Payment Bond, FL-42 (Rev. 12-12-2022) SF25A (Rev 8/2016).
17. PERFORMANCE BOND
If the subcontract exceeds $150,000.00, the successful offeror is required to furnish FFDG with a Performance Bond in the amount of 100 percent of the original subcontract price using Exhibit M, Performance Bond, FL-40 (Rev. 12/12/2022) SF25 (Rev 8/2016).
18. INSURANCE
Certificates of insurance of the types and the amounts in accordance with Clause 15 in FFDG General Terms and Conditions and Insurance Requirements for Construction Subcontracts will be required of the successful offeror before physical work at the site commences. All policies, except for Worker’s Compensation and Professional Liability, shall provide by appropriate language that Fermi Forward Discovery Group, LLC, the University of Chicago, Universities Research Association, Inc., and the United States Government are additional insureds. The certificates shall state that waiver of subrogation is granted in favor of the Certificate Holder as required by written contract, that the insurance afforded by such policies is primary insurance, and that all rights of the insurer for contribution from other insurers of Fermi Forward Discovery Group, LLC, University of Chicago, Universities Research Association, and the United States Government are waived.
19. SUBCONTRACT AWARD
Issuance of the RFP does not compel FFDG to make an award. FFDG reserves the right to accept or reject all proposals if that is determined to be in its best interest. A decision may be made without discussion; hence, an offeror’s proposal should be submitted initially on the most favorable terms. The proposed award is based on a continuing program requirement and the issuance of obligation authority from the Procurement Department of the Laboratory. Any subsequent award issued by FFDG shall be constituted in writing by authorized representatives of the Procurement Department.
No other representatives of FFDG are authorized to issue contracts or agreements or bind FFDG to any form of agreement or understanding. The authorized Procurement Department official is the only individual who can legally commit FFDG to the expenditure of funds in connection with this proposed procurement.
20. SUBCONTRACTING
Unless otherwise specified, the successful Offeror shall be responsible for the performance of any Subcontractors that perform work under this subcontract.
The use of Subcontractors in the performance of the contract is subject to FFDG consent. The awarded offeror shall ensure that any Subcontractors abide by all terms and conditions of the subcontract.
EXHIBITS
A. Scope of Work entitled “UIP Subproject 2- KRS SOW” dated May 28, 2026.
B. Construction Drawing Set, “UIP Subproject 2- Kautz Road Substation Replacement” C. Specification Set D. Fermi Forward Discovery Group, LLC General Terms and Conditions for Construction, (10/2026).
E. Insurance Requirements for Construction Subcontracts (01/2025).
F. Statement and Acknowledgment (Standard Form 1413) G. Fermilab Subcontractor Injury & Illness Data Questionnaire (7010-F1-1, Rev 07/2018).
H. Proposal Price Form I. Subcontractor Annual Representations & Certifications (SARC), v1.0 (10/2026) J. Proposal Certifications Form PUR-466, Version 1.0 (10/2026) K. Bid Bond, FL-41 (Rev. 1/7/2025) / SF24 (Rev 10/2023) L. Payment Bond, FL-42 (Rev. 1/7/2025) / SF25A (Rev 8/2016) M. Performance Bond, FL-40 (Rev. 1/7/2025) / SF25 (Rev 10/2023) N. Davis Bacon Wage Rates, General Decision, IL202600011, Heavy and Highway, Modification No.
2, Publication Date 5/21/2026 O. Small Business Subcontracting Plan Template (PRC-TMP-126) P. Compliance with Federal Anti-Discrimination Laws (PROC-EXH-469) Q. Sample Firm-Fixed-Price Subcontract.
| TABLE OF CONTENTS |
| 1. INVITATION TO SUBMIT PROPOSAL |
| 2. NORTH AMERICAN INDUSTRY CLASSIFICATION SYSTEM (NAICS) CODE |
| 3. PRE-PROPOSAL MEETING/SITE VISIT |
| 4. EXPLANATION OR INTERPRETATION OF RFP DOCUMENTS |
| 5. AMENDMENT OF SOLICITATION |
| 6. DESCRIPTION OF WORK AND CONSTRUCTION SCHEDULE |
| Milestone 2 – 4th January 2028; This milestone marks the point where access is permitted inside |
| Kautz Road Substation yard and construction work may begin. |
| Milestone 3 – 31st of March 2028; This milestone marks the completion of building foundation and |
| ready for placement of the new prefabricated control house building (provided by FermiForward). |
| Milestone 4 – 2nd July 2029; This milestone marks the formal issuance of an Authorization for Use |
| and Possession (AUP) of the KRS Substation facility, including all remedial work following removal |
| of site trailers, but not including seasonal work and all final punch list items addressed.. |
| Milestone 5 – 30th September 2029; This milestone marks the completion of the project. |
| 7. PREPARATION, SUBMISSION, AND EVALUATION OF PROPOSALS |
| 1) Criterion 1- Organizational Structure and Key Personnel (20 Points) |
| 8. PROPOSAL DUE DATE |
| 9. EXCEPTIONS AND DEVIATIONS |
| 10. LATE SUBMISSION |
| 11. OFFEROR'S MODIFICATION AND WITHDRAWAL OF PROPOSALS |
| 12. BID GUARANTEE/BOND |
| 13. DAVIS-BACON ACT, CONSTRUCTION WAGES, AND CERTIFIED PAYROLL |
| 14. ILLINOIS OCCUPATION AND USE TAXES |
| 15. NOTICE OF BUY AMERICAN REQUIREMENT-CONSTRUCTION MATERIALS |
| 16. PAYMENT BOND |
| 17. PERFORMANCE BOND |
| 18. INSURANCE |
| 19. SUBCONTRACT AWARD |
| 20. SUBCONTRACTING |
| EXHIBITS |