This is a request for proposal for bid-build construction services. The Department of Veterans Affairs is seeking a contractor to complete a buildout of an emergency management site at its Lakemont campus in Orlando, Florida within 270 calendar days of award. The project involves renovation of an existing mailroom space and upgrades to HVAC, fire protection, power, and IT systems. The contractor must hold applicable state licensing and will be responsible for all labor, materials, and equipment to complete the project in accordance with provided drawings and specifications. The solicitation is set aside exclusively for service-disabled veteran-owned small businesses. Offerors must submit pricing, schedules, and documentation of safety training by the specified deadline.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER
7. ISSUED BY CODE 8. ADDRESS OFFER TO
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES NO
a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b. An offer guarantee is, is not required.
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C24823R0040 X
11-14-2022
675-23-1-9911-0003 675-21-803
36C248
Department of Veterans Affairs Network Contracting Office 8 (NCO 8) Orlando VA Healthcare System 13800 Veterans Way Orlando FL 32827
Department of Veterans Affairs Network Contracting Office 8 (NCO 8) Orlando VA Healthcare System 13800 Veterans Way Orlando FL 32827
Shaundrica Close 407-284-8624
Project Title: Bid-Build (BB) Buildout Emergency Management Site at Lakemont Project Number: 675-21-803 Magnitude of Construction: IAW FAR 36.204 (e), the magnitude range for this project is between $500,000 and $1,000,000.
NAICS: 236220 - Commercial and Institutional Building Construction Product Service Code: Y1DZ, Construction of Other Hospital Buildings This solicitation will be evaluated on a Trade-Off basis. As stated elsewhere in this solicitation, this procurement is a one (1) Phase BB. One (1) solicitation will be issued.
This requirement is set-aside for VIP Certified, Service-Disabled Veteran Owned Small Businesses (SDVOSB). Vendor verification for SDVOSBs can be found at https://vetbiz.va.gov/.
THIS ACQUISITION IS SET-ASIDE FOR 100% SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (SDVOSB) ONLY, UNDER THE AUTHORITY Of 38 U.S.C. PART 74. ANY PERSON OR BUSINESS ENTITY SUSPECTED OF MISREPRESENTATION FOR THE PURPOSE OF SECURING A GOVERNENT CONTRACT MAY BE CRIMINALLY INVESTIGATED AND PROSECTUED FOR FRAUD AGAINST THE UNITED STATES GOVERNMENT.
The Orlando Veterans Affairs Healthcare System (OVAHCS)is a smoke free facility. Contractors, in order to enter the campus, you must have a picture ID. All Contractors are required to wear a face covering (covering nose and mouth per CDC id li ) guidelines) while on campus. All Contractors will be screened at the entrance of the building. A series of questions will be asked, and temperature taken. While working in the Medical Center (both inside and outside), the Contractor shall be responsible for wearing a face covering at all times. Personal Protective Equipment (PPE) is not provided.
Refer to solicitation instructions for cutoff date for submission of Requests for Information (RFIs).
Please refer to solicitation 36C24823R0040 package for further requirements.
It shall be known that funds are not currently available. No contract award will be made until appropriate funds are made available.
15 270
X 52.211-10
X
VIA EMAIL 11:00 AM EST
12/05/2022
X
14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO 10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )
26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY
PHONE: FAX:
28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code)
(Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
(Type or print)
(4 copies unless otherwise specified)
(Type or print) (Type or print)
(Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror)
(To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
36C248
Department of Veterans Affairs Network Contracting Office 8 (NCO 8) Orlando VA Healthcare System 13800 Veterans Way Orlando FL 32827
Department of Veterans Affairs Financial Services Center
P.O. Box 149971 Austin TX 78714-9971
Shaundrica Close,VA-VHA-RPOE-2022-221454 Contracting Officer
36C24823R0040
Table of Contents
PART I - THE SCHEDULE
SECTION A - SOLICITATION/CONTRACT FORM
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION,
ALTERATIONS, OR REPAIR)
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION,
ALTERATION, OR REPAIR)– BACK
A.3 PRICE/COST SCHEDULE
A.4 DELIVERY SCHEUDLE
A.5 STATEMENT OF WORK
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO
BIDDERS/OFFERORS
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY
SITE OF THE WORK (MAY 2014)
2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO
ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB
1999)
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION
MATERIALS (MAY 2014)
2.5 52.228-1 BID GUARANTEE (SEP 1996)
2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE)
(FEB 2021)
2.7 52.233-2 SERVICE OF PROTEST (SEP 2006)
2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE
(FEB 1998)
2.10 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE
RESOLUTION (OCT 2018)
2.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY 2022)
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN
TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR
EQUIPMENT (NOV 2021)
3.3 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—
CERTIFICATION (NOV 2021)
GENERAL CONDITIONS
4.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF
WORK (APR 1984)
4.2 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM
REREPRESENTATION (SEP 2021)
4.3 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (NOV 2021)
4.4 SUPPLEMENTAL INSURANCE REQUIREMENTS
4.5 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
4.6 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)
4.7 852.219-10DEV VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-
OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (NOV 2020) (DEVIATION) . 39
4.8 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING
AND COMPLIANCE (JUL 2018)
4.9 VAAR 852.219-77 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—
CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (SEP
2021) (DEVIATION)
4.10 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)
4.11 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED
AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC
2009)
4.12 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION
CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)
4.13 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS
(NOV 2018)
4.14 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION
(APR 2019)……………………………………………………………………………………..44
4.15 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)
4.16 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR
2019)
4.17 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT
ADMINISTRATION (OCT 2020)
4.18 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)
4.19 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—
SUPPLEMENT (SEP 2019)
4.20 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN
2008)
4.21 IT CONTRACT SECURITY
PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
LIST OF ATTACHMENTS
5.1 ATTACHMENT A – SITE SPECIFICATIONS
5.2 ATTACHMENT B - DRAWINGS
5.3 ATTACHMENT C – DAVIS BACON WAGE DETERMINATION
5.4 ATTACHMENT D – CONTRACT PROGRESS SCHEDULES
5.5 ATTACHMENT E – EMR FORM
5.6 ATTACHMENT F – EXPERIENCE INFORMATION SHEET
5.7 ATTACHMENT G – PAST PERFORMANCE FORMS
5.8 ATTACHMENT H – PRICE MATRIX
INSTRUCTIONS TO OFFERORS AND EVALUATION INFORMATION
A.3 PRICE/COST SCHEDULE
ITEM INFORMATION
ITEM
NUMBER
DESCRIPTION OF
SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 BID/BUILD (BB)
SERVICES: BB SERVICES
FOR PROJECT 675-21-803.
Buildout Emergency Management Site at Lakemont. The selected Contractor shall be required to perform all necessary BB work per drawings and specifications. PRINCIPAL
NAICS CODE: 236220 –
Commercial and Institutional Building Construction.
PRODUCT/SERVICE
CODE: Y1DZ - Construction of Other Hospital Buildings.
PERIOD OF
PERFORMANCE - 270
calendar days after Notice to Proceed (NTP) issuance.
1.00 JB __________ __________
GRAND
TOTAL
A.4 DELIVERY SCHEDULE
ITEM
NUMBER QUANTITY DELIVERY DATE
0001 SHIP TO: Orlando Veterans Affairs Healthcare
System (OVAHCS) Lakemont Campus 2500 S. Lakemont Ave.
Orlando, FL 32814
USA
1.00 270 Calendar Days
A.5 STATEMENT OF WORK
STATEMENT OF WORK
BUILDOUT EMERGENCY MANAGEMENT SITE AT LAKEMONT
PROJECT NUMBER 675-21-803
I. DEFINITIONS AND ACRONYMS:
A. Construction: As defined by the Department of Veterans Affairs (DVA) is the procurement by the
Government, under one (1) contract, with one (1) firm for construction services on a specific project.
B. Contracting Officer (CO): The services to be performed under this contract are subject to the general supervision, direction, control and approval of the CO.
C. Project Manager (PM)/Contracting Officer’s Representative (COR): The COs representative responsible for administering contracts under the immediate direction of the CO.
D. Contractor: This term, as used herein, refers to the contractor under this contract.
E. Pre-Construction Risk Assessment (PRCA): Used to identify potential risks associated with renovation, construction, some maintenance, repair activities, and to develop risk mitigation strategies to minimize these risks. Prior to beginning work this assessment shall be completed.
F. Interim Life Safety Measures (ILSM): Measures that are instituted to compensate for significant hazards posed by existing life safety (fire) code deficiencies or construction/renovation activities.
G. Request for Proposal (RFP): A solicitation made, often through a bidding process, by an agency or company interested in procurement of a commodity or service, to potential suppliers to submit proposals.
II. SCOPE OF WORK:
A. Project Overview:
This project requires construction/renovation of the old mailroom area located on the first floor of the Orlando Veterans Affairs Healthcare System (OVAHCS) Lakemont Campus, 2500 S. Lakemont Ave.
Orlando FL 32814. The Emergency Management service will be relocated to the space. The project shall include renovation, improvement or replacement of the Heating Ventilation and Air conditioning (HVAC) system, fire protection system modifications, power and Office of Information and Technology (OI&T) infrastructure improvements, new flooring, new drop down ceiling (ceiling tiles, grid and light fixtures), new drywall partitions, refinishing of all wall surface areas in the space, new doors/frames, wall insulation/sound proofing, new lay-in ceilings, lighting, closed circuit television (CCTV), plumbing upgrades, painting, and signage. All construction/renovation work shall be completed in accordance with the project's design drawings and specifications prepared by the A&E Contractor Firm.
B. General Requirements:
The Contractor shall provide all labor, materials, tools and equipment necessary to construct the project described herein and other specific tasks as further defined by this RFP. All proposals are to provide construction services for this project. The Contractor shall be a State of Florida Certified/licensed General Contractor.
C. Special Requirements:
a) Badges: Facility Management Services (FMS) will issue identification badges to Contractors, employees and Subcontractors which must be worn at all times while on VA property.
b) Contractor shall provide a list of all personnel who will participate on the project. Personnel can be subjected to a background investigation prior to commencement of work. Contractor will be issued appropriate quantity of badges per provided list.
c) The Contractor shall have on staff either a former Accrediting Official or a former Certified TEMPEST Technical Authority for review of the design documents, to ensure construction and security work is in compliance with the requirements and specifications in Intelligence Community Directive (ICD) 705, Intelligence Community Standard (ICS)-705-1, Federal Specification (FFL)-2740 – Spec for locks, Intelligence Community (IC)-Tech-Specs for construction and management of Sensitive Compartmented Information Facility (SCIFs) v 1.5, Underwriters Laboratory (UL) 2050 Extent 3 Standards – for Intrusion Detection System (IDS), and IC SCIF Construction Best Practices.
d) The Contractor shall keep the area cleaned daily and haul away all construction debris. All materials shall be tracked and logged to be reported back to the Green Environmental System (GEMS) coordinator for recycling and tracking purposes. When removing construction debris from facility it must be in a covered cart when entering and exiting the building.
III. SCHEDULING, PHASING, AND WORKING HOURS:
A. All work hours SHALL be coordinated with the project’s COR to minimize interference with normal clinic functions. All work shall be performed during normal business hours (7:30 am to 4:00 pm) Monday through Friday. However, areas may require work to be completed OUTSIDE normal business hours (4:00 pm to 10:00 pm). Any work required on the weekends must be coordinated and approved by the project’s COR. Construction shall be performed (scheduled and phased) to ensure that areas which can be completed ahead of schedule, or priority for early acceptance and operation, can be rendered back to the facility.
B. Length of Project
1. Below is the allotted schedule for construction. Any deviations or alternations must be approved by the COR.
a) New Construction – 270 calendar days
(1) 240 calendar days for construction
(2) 30 calendar days for Punch list/Closeout
2. Project’s construction phase MUST be completed in no more than 270 calendar days from Government issuance of Notice to Proceed (NTP).
3. The contractor shall submit a Critical Path Method (CPM) schedule for the Construction with estimated dates and itemized cost of work to the Contracting Officer for review and approval prior to issuance of the NTP.
C. Utility shutdowns/Outages: All shutdowns involving temporary impairment of utilities shall be requested by the Contractor at least 14 calendar days in advance.
IV. PROJECT CLASSIFICATION:
A. The Contractor shall secure area prior to commencement of work and follow the Orlando VA Medical
Center guidelines and policies for PCRA and ILSM.
B. Risk Assessment: This project has been classified per the Construction Infection Control Risk
Assessment as a Type D, Low Risk Group, Class III (ISLM Level II) project.
V. SAFETY REQUIREMENTS:
A. All Contractor's personnel are required to have completed an Occupational Safety and Health
Administration (OSHA) approved ten (10) hour construction worker course prior to working on-site. The on-site general superintendent/supervisor is required to have completed an OSHA approved thirty (30) hour construction course prior to working on-site. The CO must receive a copy of current certificates identifying successful completion of training for every worker, prior to executing work for the Veterans Administration. In addition, Contractor shall provide submittals for contract construction or renovation work which include the names, qualifications, and training dates for Contractor’s Competent Persons (CP), who has been designated to administer the site-specific safety program, as well as the CP for other activities as required by OSHA regulation 29 Code of Federal Regulations (CFR) 1926.32 (such as scaffolds, cranes, excavations, etc.). Contractor’s CP are required to implement and maintain effective safety programs that identify and control hazards that may cause injury or illness to VA patients, staff, visitors, and Contractor employees. The VA CP does not take place of the Contractor’s CP, nor acts on their behalf. The VA CP determines if the Contractor is meeting VA standards and contractual requirements for safety and OSHA compliance. When these standards and contract requirements are not being met, the VA COR and/or CP will take immediate action to prevent injury, non-compliance, and/or property damage. The Contractor shall submit an Activity Hazard Analysis (AHA), and an Accident Prevention Plan (APA) as per Federal Acquisition Regulation (FAR) 52.236-13 prior to commencement of site activities. The Government shall have twenty-one (21) calendar days to review the AHA and
APP.
B. The Contractor shall submit documentation validating completion of the OSHA construction safety course for all personnel.
VI. GOVERNMENT FURNISHED INFORMATION:
All available record drawings will be provided upon request to the Contractor. They should not however, be considered “as-built”. These drawing files are provided without warranty or obligation as to the accuracy or information contained in the files. All information in the files shall be independently verified by the user.
Any user shall agree to indemnify and hold the VA harmless from any and all claims, damages, losses, and expenses, including, but not limited to, attorney fees arising out of the use of the Computer Aided Design and Drafting (CADD) drawing files.
VII. RESOURCES:
All designs shall comply with applicable sections of VA standards and publications, and all references therein. Ensure that construction documents comply with the latest edition of these VA construction and design standards. VA standards can be found on the World Wide Web at http://www.cfm.va.gov/TIL/. VA publications and standards shall include but shall not be limited to:
1. Office of Construction & Facilities Management Site Map: http://www.cfm.va.gov/sitemap.asp
2. The Technical Information Library (TIL): http://www.cfm.va.gov/TIL/
a) Master Construction Specifications Index (PG-18-1)
b) Design and Construction Procedures (PG-18-3)
c) VA Standard Details and CAD Standards (PG-18-4)
d) Equipment Guide List (PG-18-5)
e) Equipment Inspection Manual (Program Guide 7610.2)
f) Equipment Reference Manual (PG-18-6)
g) Space Planning Criteria (PG-18-9)
h) Design Manuals (by discipline) (PG-18-10)
i) Design Guides (graphical, by function) (PG-18-12)
j) Barrier Free Design Guide (PG-18-13)
k) Room Finishes, Door and Hardware Schedules (PG-18-14)
l) Minimum Requirements for A/E Submissions (PG-18-15)
m) Environmental Planning Guidance (PG-18-17) http://www.cfm.va.gov/TIL/ http://www.cfm.va.gov/sitemap.asp http://www.cfm.va.gov/TIL/
n) HVAC Design Manual for Hospitals Amendment B
o) Lighting Study
p) Design Alerts
q) Quality Alerts
r) VA Signage Design Guide
s) Fire Protection Design Manual – Latest Edition
t) Cost Estimating
u) Physical Security Design Manuals for VA Facilities – Mission Critical Facilities (VA Handbook
0730)
v) Information Security Handbook VA 6500
w) Sustainable Design and Energy Reduction Manual (First Draft)
3. TIL - Master Construction Specifications: http://www.cfm.va.gov/til/spec.asp.
4. Department of Veterans Affair Utilities Design Manual
B. Office of Construction & Facilities Management: http://www.cfm.va.gov/index.asp
1. VA Office of Facilities Management citations of the AIA design standards found on the world wide web at http://cfm.va.gov.TIL/
2. VA Office of Health and Safety (OHS): http://www1.va.gov/vasafety/
3. Construction Infection Control Risk Assessment Memorandum
C. Other design and construction standards and publications that shall be applied to this work includes, but are not limited to:
1. American Society of Heating, Refrigerating and Air-Conditioning Engineers Manual (ASHRAE)
2. National Fire Protection Association (NFPA) Codes & Standards - www.nfpa.org
3. OSHA Rules and Regulations
4. International Building Code (IBC) latest edition
5. Life Safety Code (NFPA 101) latest edition
D. The Joint Commission (TJC) Accreditation manual (latest edition). Applicable sections of the VA Master Construction Specifications shall be prepared by the Architect/Engineer, including all the necessary adaptations.
E. Particular attention is called to CD4, Symbol Identification of Contract Drawings.
F. Equipment symbols shall be in accordance with PG-18-6, Equipment Reference Manual (previously List of Equipment Symbols, H-08-6).
G. Standard Drawing Details, in accordance with PG-18-4, shall be utilized to the greatest extent practicable.
H. Cost estimates shall be developed in strict conformance with VA’s Manual for Preparation of Cost
Estimates & Related Documents for VA Facilities (March 8, 2011).
http://www.cfm.va.gov/til/dManual/dmCost.pdf
I. Guidelines for Design and Construction of Health Care Facilities, Latest Edition, published by The Facilities Guidelines Institute (FGI). http://www.fgiguidelines.org/
J. Physical Security Standard, compliance with Medical Center Policy 138-3 and VHA Handbook 0730/2 dated May 27, 2010 “Space Key Control”.
VIII. SUBMITTALS
A. Proof of OSHA construction safety course B. General Contractor License and Insurance C. Submittals as per Construction Documents and Specifications D. Warranties E. Bid Bond http://www.cfm.va.gov/til/spec.asp http://www.cfm.va.gov/index.asp http://cfm.va.gov.til/ http://www1.va.gov/vasafety/ http://www.nfpa.org/ http://www.cfm.va.gov/til/dManual/dmCost.pdf http://www.fgiguidelines.org/
IX. QUALITY ASSURANCE/QUALITY CONTROL:
A. The Construction Contractor shall develop and execute a Quality Assurance/Quality Control (QA/QC) plan that demonstrates the project plans and specifications have gone through a rigorous, thorough review and coordination effort.
B. Within two (2) weeks of receipt of the NTP, the Construction Contractor shall submit a detailed QA/QC plan describing each QA/QC task that will be taken during the construction phase, and the name of the Contractor’s team member responsible for QA/QC.
C. Upon its completion, each task shall be initialed and dated by the responsible Contractor’s team member.
X. RECORDS MANAGEMENT OBLIGATIONS
A. Applicability This clause applies to all Contractors whose employees create, work with, or otherwise handle Federal records, as defined in Section B, regardless of the medium in which the record exists.
B. Definitions “Federal record” as defined in 44 United States Code (U.S.C.) § 3301, includes all recorded information, regardless of form or characteristics, made or received by a Federal agency under Federal law or in connection with the transaction of public business and preserved or appropriate for preservation by that agency or its legitimate successor as evidence of the organization, functions, policies, decisions, procedures, operations, or other activities of the United States Government or because of the informational value of data in them.
The term Federal record:
1. Includes VHA records.
2. Does not include personal materials.
3. Applies to records created, received, or maintained by Contractors pursuant to their VHA contract.
4. May include deliverables and documentation associated with deliverables.
C. Requirements
1. Contractor shall comply with all applicable records management laws and regulations, as well as
National Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C. chs. 21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII Subchapter B, and those policies associated with the safeguarding of records covered by the Privacy Act of 1974 (5 U.S.C. 552a). These policies include the preservation of all records, regardless of form or characteristics, mode of transmission, or state of completion.
2. In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of 44 U.S.C.
chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA) (5 U.S.C. 552), as amended, and the Privacy Act of 1974 (5 U.S.C. 552a), as amended and must be managed and scheduled for disposition only as permitted by statute or regulation.
3. In accordance with 36 CFR 1222.32, the Contractor shall maintain all records created for Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with Federal law. Electronic records and associated metadata must be accompanied by sufficient technical documentation to permit understanding and use of the records and data.
4. VHA and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Records may not be removed from the legal custody of VHA or destroyed except in accordance with the provisions of the agency records schedules and with the written concurrence of the Head of the Contracting Activity.
5. Willful and unlawful destruction, damage, or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. In the event of any unlawful or accidental removal, defacing, alteration, or destruction of records, the Contractor must report to VHA. The agency must report promptly to NARA in accordance with 36 CFR 1230.
6. The Contractor shall immediately notify the appropriate Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records, or equipment. Disclosure of non-public information is limited to authorized personnel with a need-to-know as described in the [contract vehicle].
7. The Contractor shall ensure that the appropriate personnel, administrative, technical, and physical safeguards are established to ensure the security and confidentiality of this information, data, documentary material, records, and/or equipment is properly protected.
8. The Contractor shall not remove material from Government facilities or systems, or facilities or systems operated or maintained on the Government’s behalf, without the express written permission of the Head of the Contracting Activity. When information, data, documentary material, records, and/or equipment is no longer required, it shall be returned to VHA control or the Contractor must hold it until otherwise directed. Items returned to the Government shall be hand-carried, mailed, emailed, or securely electronically transmitted to the Contracting Officer or address prescribed in the [contract vehicle]. Destruction of records is EXPRESSLY PROHIBITED unless in accordance with Paragraph (4).
9. The Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material, and/or records generated under, or relating to, contracts. The Contractor (and any sub-contractor) is required to abide by Government and VHA guidance for protecting sensitive, proprietary information, classified, and controlled unclassified information.
10. The Contractor shall only use Government IT equipment for purposes specifically tied to or authorized by the contract and in accordance with VHA policy.
11. The Contractor shall not create or maintain any records containing any non-public VHA information that is not specifically tied to or authorized by the contract.
12. The Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected from public disclosure by an exemption to the Freedom of Information Act.
13. The VHA owns the rights to all data and records produced as part of this contract. All deliverables under the contract are the property of the U.S. Government for which VHA shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest. Any Contractor rights in the data or deliverables must be identified as required by FAR 52.227-11 through FAR 52.227-20.
14. Training. All Contractor employees assigned to this contract who create, work with or otherwise handle records are required to take VHA-provided records management training. The Contractor is responsible for confirming training has been completed according to agency policies, including initial training and any annual or refresher training.
D. Flow down of requirements to subcontractors The Contractor shall incorporate the substance of this clause, its terms, and requirements including this paragraph, in all subcontracts under this [contract vehicle], and require written subcontractor acknowledgment of same. Violation by a subcontractor of any provision set forth in this clause will be attributed to the Contractor.
VHA Supplemental Contract Requirements for Combating COVID-19
a. Contractor employees who work in or travel to VHA locations must comply with the following:
b. Documentation requirements:
i. If fully vaccinated, contractors shall show proof of vaccination.
1. NOTE: Acceptable proof of vaccination includes a signed record of immunization from a health care provider or pharmacy, a copy of the COVID-19 Vaccination Record Card (CDC Form MLS-319813_r, published on September 3, 2020), or a copy of medical records documenting the vaccination.
2. If unvaccinated, contractors shall show negative COVID-19 test results dated within three calendar days prior to desired entry date. Test must be approved by the Food and Drug Administration (FDA) for emergency use or full approval.
This includes tests available by a doctor’s order or an FDA approved over-the-counter test that includes an affiliated telehealth service.
3. Documentation cited in this section shall be digitally or physically maintained on each contractor employee while in a VA facility and is subject to inspection prior to entry to VA facilities and after entry for spot inspections by Contracting Officer Representatives (CORs) or other hospital personnel.
4. Documentation will not be collected by the VA; contractors shall, at all times, adhere to and ensure compliance with federal laws designed to protect contractor employee health information and personally identifiable information.
c. Contractor employees are subject to daily screening for COVID-19 and may be denied entry to VA facilities if they fail to pass screening protocols. As part of the screening process contractors may be asked screening questions found on the COVID-19 Screening Tool. Check regularly for updates.
d. Contractor employees who work away from VA locations, but who will have direct contact with VA patients shall self-screen utilizing the COVID-19 Screening Tool, in advance, each day that they will have direct patient contact and in accordance with their person or persons who coordinate COVID-19 workplace safety efforts at covered contractor workplaces. Contractors shall, at all times, adhere to and ensure compliance with federal laws designed to protect contractor employee health information and personally identifiable information.
e. Contractor must immediately notify their COR or Contracting Officer if contract performance is jeopardized due to contractor employees being denied entry into VA Facilities
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price, Requirements contract resulting from this solicitation.
(End of Provision)
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF
THE WORK (MAY 2014)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE
EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance
Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
15.5 % 6.9 %
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed.
Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals.
The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is
Orlando VA Healthcare System, Orlando, FL.
(End of Provision)
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION
MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.5 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3.0M, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Provision)
2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB
2021)
(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee—
(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203–1; and
(2) Standard Form 28, Affidavit of Individual Surety.
(b) The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228–1, Bid Guarantee, or as otherwise established by the Contracting Officer.
(c) The Contracting Officer may release the security interest on the individual surety’s assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.
(End of Provision)
2.7 52.233-2 SERVICE OF PROTEST (SEP 2006)
Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:
Shaundrica Close, Contracting Officer
Electronic Mail (Email) is the only acceptable authorized method to submit a protest. Email address:
shaundrica.close@va.gov.
The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of Provision)
2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for – Thursday, November 17, 2022, at 11:00 AM.
(c) Participants will meet at - 2500 S. Lakemont Ave, Orlando, FL 32814, at the main entrance.
(End of Provision)
2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB
1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/
(End of Provision)
FAR
Number
Title Date
52.204-7 SYSTEM FOR AWARD MANAGEMENT OCT 2018
52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE
REPORTING
AUG 2020
52.204-22 ALTERNATIVE LINE ITEM PROPOSAL JAN 2017
mailto:shaundrica.close@va.gov
52.215-1 INSTRUCTIONS TO OFFERORS—COMPETITIVE
ACQUISITION
NOV 2021
52.229-11 TAX ON CERTAIN FOREIGN PROCUREMENTS—
NOTICE AND REPRESENTATION
JUN 2020
52.236-28 PREPARATION OF PROPOSALS—CONSTRUCTION OCT 1997
2.10 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION
(OCT 2018)
(a) Any protest filed by an interested party shall—
(1) Include the name, address, fax number, email and telephone number of the protester;
(2) Identify the solicitation and/or contract number;
(3) Include an original signed by the protester or the protester’s representative and at least one copy;
(4) Set forth a detailed statement of the legal and factual grounds of the protest, including a description of resulting prejudice to the protester, and provide copies of relevant documents;
(5) Specifically request a ruling of the individual upon whom the protest is served;
(6) State the form of relief requested; and
(7) Provide all information establishing the timeliness of the protest.
(b) Failure to comply with the above may result in dismissal of the protest without further consideration.
(c) Bidders/offerors and Contracting Officers are encouraged to use alternative dispute resolution (ADR) procedures to resolve protests at any stage in the protest process. If ADR is used, the Department of Veterans Affairs will not furnish any documentation in an ADR proceeding beyond what is allowed by the Federal Acquisition Regulation.
(End of Provision)
2.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)
(a) As an alternative to filing a protest with the Contracting Officer, an interested party may file a protest by mail or electronically with: Executive Director, Office of Acquisition and Logistics, Risk Management and Compliance Service (003A2C), Department of Veterans Affairs, 810 Vermont Avenue NW, Washington, DC 20420 or Email: EDProtests@va.gov.
(b) The protest will not be considered if the interested party has a protest on the same or similar issue(s) pending with the Contracting Officer.
(End of Provision)
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY 2022)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.
(2) The small business size standard is $39.5 Million.
(3) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees if the acquisition—
(i) Is set aside for small business and has a value above the simplified acquisition threshold;
(ii) Uses the HUBZone price evaluation preference regardless of dollar value, unless the offeror waives the price evaluation preference; or
(iii) Is an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph
(d) of this provision applies.
(2) If the provision at 52.204–7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
[ ] (i) Paragraph (d) applies.
[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .