Pricing Sheet.pdf

PDF 90 KB Posted

Attached to
Roof Repairs Buildings FC571, FC520, FC525, FC573, and FC574
Solicitation number
N4008526R9018
Issued by

About this file

This is a pricing sheet for a roof repairs solicitation issued by the U.S. Navy for buildings at MCB Camp Lejeune, North Carolina. Solicitation No. N40085-26-R-9018 (Project No. 26-0410) was issued on February 24, 2026, and requires contractors to submit pricing for five Exhibit Line Items (ELINs) covering roof repair work on five separate buildings: FC525, FC520, FC571, FC573, and FC574. Each ELIN price must include all applicable costs, overhead, and profit for completing the specified work in accordance with provided drawings and specifications.

Contractors must submit proposals on all five line items or risk rejection as non-responsive. Pricing is structured so the Government will evaluate offers for award by summing all ELIN prices (0001-0005), though the Government reserves the unilateral right to award only ELINs 0002, 0003, 0004, and/or 0005 at the proposed price within 90 days after contract award, with no provision for economic price adjustment. All markups including overhead, labor burden, and profit must be included within each ELIN price, and evaluation of these options will not obligate the Government to exercise them.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Roof Repairs Bldgs FC571, FC520, FC525, etc Solicitation No. N40085-26-R-9018 MCB Camp Lejeune, North Carolina Project No. 26-0410

RFP 2/24/26

PRICING SHEET

Under the line items furnished, the offers shall state prices for each Exhibit Line Item Number (ELIN) given hereinafter:

ELIN 0001

Price includes completing all work associated with building FC525 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0002-0005. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0002

Price includes completing all work associated with building FC520 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001 and 0003- 0005. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0003

Price includes completing all work associated with building FC571 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0002 and 0004-0005. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0004

Price includes completing all work associated with building FC573 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0003 and 0005. The price for this line item should include all applicable costs, overhead and profit for this work.

Roof Repairs Bldgs FC571, FC520, FC525, etc Solicitation No. N40085-26-R-9018 MCB Camp Lejeune, North Carolina Project No. 26-0410

RFP 2/24/26

ELIN 0005

Price includes completing all work associated with building FC574 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0004. The price for this line item should include all applicable costs, overhead and profit for this work.

TOTAL ELINs 0001 - 0005: $______________________________________

Notes

A. Offers must be submitted on all line items. Failure to propose on all line items may result in the offer being rejected as non-responsive.

B. The Government reserves the unilateral right to award ELIN 0002, 0003, 0004, and/or 0005 to the Contractor at the proposed price within 90 days after the contract award. No provision is made for economic price adjustment.

C. Evaluation of Options (JUL 1990). Except when it is determined in accordance with FAR 17.206(b) Evaluation not to be in the Government's best interest, the Government will evaluate offers for award purposes by adding the price for ELINs 0001 through 0005. In accordance with FAR 52.217-5 Evaluation of Options, evaluation of options will not obligate the Government to exercise the Option(s).

D. ELINs shall include all markups (overhead, labor burden, and profit).

File details come from the government source that posted it. Updated .