Pricing Schedule 2.xlsx

XLSX spreadsheet 65 KB Posted

Attached to
AGE Parking Pad - Dyess AFB, TX
Solicitation number
FA466125R0009
Issued by

About this file

The document is a Contract Progress Schedule (AF Form 3064) for a design-build project at Dyess Air Force Base, Texas. The project involves constructing an AGE (Aerospace Ground Equipment) Parking Pad with a contract period from June 2025 to January 2026. The detailed schedule breaks down 33 specific work elements, including bonds, mobilization, design submittals, construction activities, and project closeout, with each element assigned a percentage of total project completion.

The related federal contract opportunity is a 100% HUBZone set-aside solicitation (FA466125R0009) valued between $1,000,000 and $5,000,000. The project scope includes designing and constructing a new portland cement concrete parking area with associated stormwater drainage systems at Dyess Air Force Base. The solicitation closing date is 18 August 2025 at 2:30 PM, with a critical note that funds are not currently available and the government reserves the right to cancel the solicitation without reimbursing offeror costs.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AF3064 Front

CONTRACT PROGRESS SCHEDULEForm Approved
(See Contractor's Instructions on Reverse)OMB NO. 0704-0188
Public reporting burden for this collection of information is estimated to average 15 minutes per response, including the time for reviewing instructions, searching existing data sources, gathering maintaining the data needed, and completing and reviewing
the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department Defense of Washington Headquarters Services, Directorate for information
Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project 0704-0188. Washington DC 20503. Please DO NOT RETURN your (form questionnaire) to
either of these addresses. Send your completed (form questionnaire) to: SAF AQCO. Washington DC 20330-1000.
1. CONTRACT NO.8. PROJECT TITLE10. APPROVAL RECOMMENDED BY:
FA4661-16-C-Design-Build, Add/Alter AGE Parking PadDATE SIGNEDINSTALLATIONS ENGINEERS'S SIGNATURE
2. STARTING DATE6/1/20XX
3. COMPLETION DATE1/1/202x9. SUBMITTED BY:enter here
4. PURCHASE REQUEST NO.n/aDATE SIGNEDCONTRACTOR'S NAME (Last, First, Middle Initial) ADDRESSCONTRACTOR'S SIGNATURE11. APPROVED BY:
5. PROJECT NO. FNWZ:FNWZ 25-0106(Street, City, State, Zip Code)DATE SIGNEDCONTRACTING OFFICER'S SIGNATURE
6. ACTUAL STARTING DATE
7. ACTUAL COMPLETION DATE
2025202620262026
LINE NO.WORK ELEMENTS% TotalOct 1-15Oct 16-30Nov 1-15Nov 16-31Dec 1-15Dec 16-31Jan 1-15Jan 16-30Feb 1-15Feb 16-31Mar 1-15Mar 16-30Apr 1-15Apr 16-31May 1-15May 16-31Jun 1-15Jun 16-28Jul 1-15Jul 16-31Aug 1-15Aug 16-30Sep 1-15Sept 16-30Oct 1-15Oct 16-31Nov 1-15Nov 15-30Dec 1-15line %
ABCDEFGHIJKLMNOPQRSTUVWXYZAAABACADAEAFAG
1Bonds1.00%0.83%0.83%

2 Mobilization 1.00% 1.00% 1.00%

3 Design Submittals & Documents 1.00% 1.00% 1.00% 1.00% 1.00% 1.00% 5.00%

4 Construction Submittals 1.00% 0.00%

5 Demolition 1.00% 0.00%

6 Concrete Foundations & Slabs 1.00% 0.00%

7 Wall Framing 1.00% 0.00%

8 Wall Penetrations & Repair 1.00% 0.00%

9 Doors & Frames 1.00% 0.00%

10 Windows 1.00% 0.00%

11 Interior Framing & Sheathing 1.00% 0.00%

12 Electrical Rough-In 1.00% 0.00%

13 Fire Alarm / MNS Rough-In 1.00% 0.00%

14 Plumbing Rough-In 1.00% 0.00%

15 HVAC Equipment 1.00% 0.00%

16 HVAC Rough-In 1.00% 0.00%

17 Fire Suppression Rough-In 1.00% 0.00%

18 Exterior Concrete 1.00% 0.00%

19 Wall Insulation 1.00% 0.00%

20 Wall Sheathing 1.00% 0.00%

21 Tape, Float, Texture, & Paint 1.00% 0.00%

22 Ceramic & Porcelain Tile 1.00% 0.00%

23 Cabinets & Solid Surface 1.00% 0.00%

24 Electrical Fixtures 1.00% 0.00%

25 Plumbing Fixtures 1.00% 0.00%

26 Restroom / Toilet Accessories 1.00% 0.00%

27 HVAC Start-Up 1.00% 0.00%

28 Fire Alarm / MNS Testing 1.00% 0.00%

29 Fire Suppression Finishout 1.00% 0.00%

30 Interior & Exterior Signage 1.00% 0.00%

31 HVAC Commissioning (FIXED AMOUNT) 1.50% 0.00%

32 Contractor Punchlist 1.00% 0.00%

33 O&M, As-Builts, & Closeout (FIXED AMOUNT) 1.50% 0.00%

Column Total34.00%6.83%Column Total
PROJECT TOTAL0.83%2.00%1.00%1.00%1.00%1.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%6.83%Row Total
AF Form 3064, JUN 90 PREVIOUS EDITION IS OBSOLETE

AF3064 Back

INSTRUCTIONS TO CONTRACTORS
1. Prepare three copies of AF Form 3064, in accordance with these instructions and submit to the contracting officer at the time stated in the contract or as established
by the contracting officer.

2. Blocks 1,2, and 3. Enter the contract number, starting date, and completion date as shown on the contract.

3. Block 8. Enter the title of the project as shown on the contract.

4. Block 9. Enter the name and address of your firm. The three copies submitted to the contracting officer must be dated and signed by the contractor or an authorized
representative of the firm.
5. Lines 1 through 15. Major elements of work (whether unit price or lump sum contract) such as excavation, concrete work, carpentry, engineering, installation of
communication electronic facilities, etc., will be shown in Column B in logical sequence and in sufficient detail to identify the element. If the contract
calls for more than 14 work elements, additional copies of the AF Form 3064 may be used as a continuation for the work elements.
6. The percentage of each listed work element to the complete job will be shown opposite each element in Column C. As an example, if 3 work elements are shown:
excavation, concrete work, and backfill, and it is estimated that excavation is 50% of the total job, concrete 30%, and backfill 20%, these percentages will be shown
opposite each element. The total must equal 100%.
7. Columns D through P will be used to show planned periodic progress, as required by the contracting officer, during the period of the contract. Only the top half of the
space under these columns will be used by contractors. Using the example cited above and assuming that the contract period for performance is 8 weeks, and it
is planned to accomplish 10% of the excavation work the 1st week and 45% each week until excavation is complete, 10 would be shown in the upper half of Line 1
under Column D, 45 under Column E and 45 under Column F for a total of 100%. If it is planned to accomplish the concrete work during the 4th, 5th, and 6th weeks
in equal amounts, 33,33, and 34 would be enteredd under columns G, H, and I on Line 2. Assuming the backfill will be accomplished during the 7th and 8th weeks, 50 would
be entered under Columns J and K on Line 3. If the contract extends beyond 14 weeks, additional copies of AF Form 3064 may be used as a continuation of performance record.
8. Total amount or work planned at intervals as shown in Columns D through Q will be totaled and entered in the top half of the space under the appropriate column of line 15.
Again, using the example cited above, the totals under Column D through K would read 10, 20, 20, 10, 10, 10, 10, 10, for a total of 100%. These totals will be
used to plot an overlay graph using Lines 4 through 11, beginning with Column D and extending to the right the number of columns (weeks) authorized by the contract
for performance time.
9. In the event the contract is modified by the contracting officer under terms of the contract, changing the progress of work as originally scheduled, adding or deleting
work or changing the original completion date, a revised progress schedule will be prepared and submitted to the contracting officer for approval. In preparing the revised
schedule, the amount of work completed will be considered, together with the changed new completion date set forth in the contract modification. Considering these
factors, the work under the contract will be rescheduled over the new total performance time in the same manner that the original schedule was prepared.
The new completion date will be entered in Block 3. "First Revised Schedule," "Second Revised Schedule," etc., will be entered to the left of the form title.
Time of submission of the revised schedule will be determined by the contracting officer.
10. At such intervals as may be established by the contracting officer, the contractor will submit to the contracting officer AF Form 3065 "Contract Progress Report,"
indicating the percentage of work accomplished for each work element during the established reporting period. Accurate reports are of the utmost importance to the
contractor and th the Government, since the percentage of completion, or progress, thus reported is used in administration of the contract and maybe used in connection
with approval of partial payments under the contract. Care should be taken to plan the work in such manner that it can be accomplished as stated in this schedule. If for
any reason it becomes known that any part of the progess under this contract will be delayed, this fact should be reported to the contracting officer immediately.

AF FORM 3064, JUN 90 (REVERSE)