PP.docx

DOCX document 42 KB Posted

Attached to
2026 TRANSIT ASSET MANAGEMENT PLAN UPDATE
Solicitation number
250015
Issued by
Orange County, California

About this file

This is a Project Description document for the Orange County Transportation Authority (OCTA) in California regarding a 2026 Transit Asset Management Plan Update. The project seeks qualified consultants to develop a comprehensive transit asset management plan with a thirteen-month contract term. The scope of work requires the consultant to conduct a detailed assessment of OCTA's transit assets, including vehicles, infrastructure, and facilities, and to create a strategic management plan that aligns with federal and state requirements. The deliverables include an updated asset inventory, condition assessment data, lifecycle cost analysis, maintenance and replacement schedules, and a prioritized capital improvement strategy. The consultant must engage with OCTA staff and stakeholders throughout the planning process and provide recommendations for optimizing asset performance and financial planning.

The project budget is fixed at $250,000 for the entire thirteen-month engagement. The consultant will be responsible for all labor, equipment, and resources necessary to complete the work. OCTA will provide access to existing asset data and staff coordination to support the consultant's efforts. The selected consultant must demonstrate experience with transit asset management planning, familiarity with federal transit asset management regulations, and proven ability to manage complex data analysis and stakeholder engagement. Payment will be structured according to OCTA's standard invoicing procedures, with reimbursable expenses to be negotiated as part of the final contract agreement.

View the file

Other files

File Type Posted
2026_TRANSIT_ASSET_MANAGEMENT_PLAN_UPDATE_(Addendum_#1_Revision).pdf PDF
Exhibit_A_SOW.pdf PDF
Exhibit_C_Agreement.pdf PDF
RFP_5-4254_Exhibit_B.pdf PDF
Exhibit_D_Safety_Specifications.pdf PDF
Exhibit_A_SOW_gmedits.docx DOCX document
Exhibit_C_Agreement_gmedits.docx DOCX document
Exhibit_A_idedits.docx DOCX document
PP_idedits.docx DOCX document
Exhibit_B_idedits.docx DOCX document
PS_idedits.doc DOC document
Exhibit_C_Proposed_Agreement_idedits.pdf PDF
Exhibit_C_idedits.docx DOCX document
Exhibit_E_idedits.doc DOC document
Form_700_Review.pdf PDF
PS.doc DOC document
Risk_Response.pdf PDF
SOW_Verification.pdf PDF
ICE.docx DOCX document
REQ35213.pdf PDF
ICE_Worksheet.xlsx XLSX spreadsheet
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INTEROFFICE MEMO

Procurement Plan, RFP 250015

Date: August 27, 2025

To: Charles Main, Principal Transportation Analyst, Transit Service Planning

From: Michael Cardozo, Contract Administrator, CAMM

Subject: PROCUREMENT PLAN - RFP 250015, “2026 Transit Asset Management Plan Update”

Please review the procurement plan for the subject RFP and advise your concurrence with the evaluation criteria and contract elements. Include suggested evaluation team members and/or comments.

Procurement Type: |X| RFP |_| IFB

Justification:

A Request for Proposals (RFP) procurement type is applicable because there are multiple factors for selection to be considered beyond cost.

Evaluation Criteria:

PROPOSAL
WEIGHT
Qualifications of the Firm
20%
Staffing/Project Organization
25%
Work Plan
30%
Cost
25%

Justification: The standard 25 percent for each criterion was not used for this procurement. Qualifications of the firm is weighted at 20 percent to ensure firms have prior experience performing similar services. Staffing and project organization and cost are weighted at 25 percent as the firm must demonstrate it has the requisite personnel for this project and that firm-fixed rates remain competitive so OCTA receives value for the services provided. Work plan is weighted at 30 percent each as the firm must demonstrate it has the understanding associated with this project in order to complete the tasks required under the scope of work.

Contract Type: |_| Time & Expense |_| CTO-Based |X| Firm Fixed Price

Justification: (Explain the rationale for using the particular contract type):

The contract type is firm-fixed price because the RFP has a specific scope of work detailing specific tasks and deliverables

Retention:
|X| Yes 10%
|_| No
|_| N/A
Prevailing Wages:
|_| Yes
$
|_| No
|X| N/A
Liquidated Damages:
|_| Yes
$
|_| No
|X| N/A

Procurement Schedule: |X| Attached

Suggested Evaluation Team Members:

Internal Evaluators:

Charles Main, Principal Transportation Analyst, Transportation Modeling Trevor Mathias, Business Unit Analyst, Government Relations Anthony Baruch, Section Manager, Financial Planning and Analysis

Contract Term: Thirteen (13)-month term

Funding Source: |_| Local |X| Measure M |_| FTA |_| FHWA

Dollar Amount: |X| Term $250,000.00

Independent Cost Estimate Received: |X| Yes |_| No

Requisition Received: |X| Yes Req. 35213

DBE Goal: |_| Yes |X| No

Project Manager Concurrence:

_______________________________________________________
Charles Main, Principal Transportation Analyst, Transit Service PlanningDate

CAMM Section/Department Manager Concurrence:

_______________________________________________________
Iris Deneau, Section Manager, ProcurementDate

Revised: 05/09/2018 Revised: 05/09/2018 image1.png