ICE.docx

DOCX document 98 KB Posted

Attached to
2026 TRANSIT ASSET MANAGEMENT PLAN UPDATE
Solicitation number
250015
Issued by
Orange County, California

About this file

This is an Independent Cost Estimate (ICE) form prepared by the Orange County Transportation Authority (OCTA) for the 2026 Transit Asset Management Plan Update. The project requires the development of a comprehensive transit asset management plan over a thirteen-month contract term with an expected completion date of April 21, 2025. The procurement is valued at $250,000 and involves identifying and allocating necessary personnel resources, calculating labor hours for each position, and applying professional billing rates consistent with comparable service contracts. The cost estimate was developed by analyzing the scope of work requirements, determining staffing needs, and approximating hours required for task completion.

The cost estimate totals $250,000 and is comprised of direct labor costs of $247,050, which includes 18 hours at $290 per hour for a Principal position, 248 hours at $250 per hour for a Project Manager, and 601 hours at $220 per hour for a Senior Planner/Analyst. Additional costs include travel and mileage expenses of $2,200 and reprographics costs of $750. No overhead, materials, information technology support, or subcontractor costs are included in this estimate. The cost estimate was prepared by Charles Main, Principal Transportation Analyst, and must be submitted to Contracts Administration & Materials Management (CAMM) along with the requisition and scope of work before procurement can commence.

View the file

Other files

File Type Posted
2026_TRANSIT_ASSET_MANAGEMENT_PLAN_UPDATE_(Addendum_#1_Revision).pdf PDF
Exhibit_A_SOW.pdf PDF
Exhibit_C_Agreement.pdf PDF
RFP_5-4254_Exhibit_B.pdf PDF
Exhibit_D_Safety_Specifications.pdf PDF
Exhibit_A_SOW_gmedits.docx DOCX document
Exhibit_C_Agreement_gmedits.docx DOCX document
PP.docx DOCX document
Exhibit_B_idedits.docx DOCX document
PS_idedits.doc DOC document
Exhibit_A_idedits.docx DOCX document
PP_idedits.docx DOCX document
Exhibit_C_Proposed_Agreement_idedits.pdf PDF
Exhibit_C_idedits.docx DOCX document
Exhibit_E_idedits.doc DOC document
REQ35213.pdf PDF
Form_700_Review.pdf PDF
PS.doc DOC document
Risk_Response.pdf PDF
SOW_Verification.pdf PDF
ICE_Worksheet.xlsx XLSX spreadsheet
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INSTRUCTIONS

Complete and submit all three pages to Contracts Administration & Materials Management (CAMM), along with your requisition and scope of work. CAMM will not start the procurement until all three documents have been received.

PART I – GENERAL INFORMATION

Project Description: OCTA Transit Asset Management Plan

SHADED AREA FOR PROCUREMENT USE ONLY

Assigned Buyer No.:
D/M/WBE%:
Purchase Requisition No.:
35213

|_| New Contract / Procurement

|_| Contract Amendment
|_| Current IFAS Printout
Contract / PO No.:

(Required for Amendments)

|_| Contract Task Order

|_| Option Term

Date:
4/21/2025
Requestor:
Charles Main
Principal Transportation Analyst
Phone Ext.:
5904

Name

Title

Signature:

Cost

Estimate: $
250,000.00
(include shipping, handling and taxes, if applicable)

PART II – ESTIMATE GUIDE

Please substantiate the estimate using the following information.

Estimate Type
Items to Include
Where to Find Supporting Information

Services (Other than A&E)

1. Tasks you want done

2. Types of people needed (i.e., supervisor, administrative assistant, other)

3. Positions required (i.e., Project Manager, Deputy PM, Senior Engineer / Planner, other)

4. Estimated hours by position

5. Salary / billing rates applied

6. Prevailing wage rate category applied

7. Profit / applied fee

8. Direct expenses

9. Completion schedule

1. Current or past contracts for similar services

2. Other properties / departments doing similar work

3. Historical price and cost data

Estimate Guide Continued

INDEPENDENT COST ESTIMATE (ICE)

FA-CAMM-006.docm (09/25/15)Page 1 of 1
Estimate Type
Items to Include
Where to Find Supporting Information
Architects, Engineers, Designers
1. Tasks you want done

2. Types of people needed (i.e., engineers, administrative assistant, other)

3. Positions (Project Manager, Deputy PM, Senior Engineer / Planner, other)

4. Estimated hours by position

5. Salary / billing rates applied

6. Profit / applied fee

7. Overhead rate (%)

8. Direct expenses

9. Completion schedule

1. Current or past contracts for similar services

2. Other properties / departments doing similar work

3. Historical price and cost data

Goods/Equipment
1. Product needed

2. Quantity

3. Unit price

4. Markups, overhead, profit

5. Delivery schedule desired

6. Warranty

1. Vendor survey / market survey

2. Current or past contracts for the same or similar product

3. Historical price and cost data

4. Various published indices

Construction
1. Product needed

2. Labor (at a minimum use Davis Bacon)

3. Materials

4. Bonds

5. Insurance

6. Mobilization

7. Equipment

8. Markups, fringes, overheads, profit

9. Completion schedule

1. “Means Book”

2. “Blue Book”

3. Davis Bacon wage rates / prevailing wages

4. Current or past contracts for the same project

5. Historical price and cost data

Additional Information: The cost estimate was developed by identifiying the needed personnel and skills to complete the tasks in the scope of work, approximating the number of hours needed for each task, and using professional rates from similar or comparable professional services contracts.(Please see attached Excel worksheet.)

PART III – INDEPENDENT COST ESTIMATE

Using the information provided in Part II, prepare the ICE for your procurement.

Use any or all of the categories listed below.

Prepared By:
Charles Main
Date:
4/21/2025

Signature:

DESCRIPTION OF COST ELEMENTS

1. DIRECT LABOR

(List of Labor Categories)

Estimated Hours
Rate Per

Hour ($) Estimated Cost ($) Total Est.

Cost ($)

Principal
18
$ 290.00
$ 23,780.00
Project Manager
248
$ 250.00
$ 126,250.00
Senior Planner/Analyst
601
$ 220.00
$ 97,020.00
$
$ 0.00
$
$ 0.00
$
$ 0.00
Total Direct Labor:
$ 247,050.00
2. OVERHEAD
Rate (%)

(use decimal input) Total Labor ($) Estimated Cost ($) Total Est.

Cost ($)

%
$ 247,050.00
$ 0.00
$ 0.00
3. MATERIALS/SERVICES (Excluding Information Technology [IT])
Estimated

Cost ($) Total Est.

Cost ($)

$
$ 0.00
4. INFORMATION TECHNOLOGY SUPPORT
Estimated

Cost ($) Total Est.

Cost ($)

$
$
Total IT Support:
$ 0.00

5. TRAVEL

Estimated Cost ($) Total Est.

Cost ($)

Travel and Mileage
$ 2,200.00
$ 2,200.00

6. SUBCONTRACTOR(S) / CONSULTANT(S)

Estimated Cost ($) Total Est.

Cost ($)

$
$
$
$
$
$
Total Subcontractor(s) / Consultant(s):
$ 0.00

7. OTHER DIRECT COSTS

Estimated Cost ($) Total Est.

Cost ($)

Reprographics
$ 750.00
$ 750.00
8. TOTAL ESTIMATED COST:
$ 250,000.00

image1.png image3.jpeg image2.jpeg

File details come from the government source that posted it. Updated .