GENERAL NOTES
CONTRACT N40085 20-0002
Buildings 115 & 201 Repair by Replacement
AT
MARINE CORPS BASE CAMP LEJEUNE, CAMP GEIGER
NORTH CAROLINA
DESIGN BY:
GUSTAVO DE LUCA
PUBLIC WORKS DEPARTMENT
DESIGN BRANCH - MCBCL
GENERAL NOTES PREPARED BY
KIM SAMPLE
DATE:
GENERAL NOTES APPROVED BY:
THOMAS H. BURTON, P.E., DIRECTOR
DESIGN BRANCH, PUBLIC WORKS DIVISION
J. M. ROCHE, COMMANDER, CEC, U.S. NAVY
FOR COMMANDER, NAVAL FACILITIES
ENGINEERING
GENERAL NOTES:
1. THE SCOPE OF WORK INDICATES GENERAL CONDITIONS WITH INFORMATION COMPILED
FROM FIELD OBSERVATION. CONSTRUCTION AND MATERIALS INDICATED ARE GENERAL
IN NATURE AND ARE NOT INTENDED TO FULLY DESCRIBE THE EXISTING
CONSTRUCTION PRESENT. THE CONTRACTOR IS RESPONSIBLE TO INSPECT ALL
FACILITIES TO BE RENOVATED TO HIS OWN SATISFACTION AND INCLUDE ALL
NECESSARY COSTS TO COMPLETELY UPGRADE EACH FACILITY AS DESCRIBED.
CONTRACTOR MUST BE RESPONSIBLE FOR ACTUAL FIELD VERIFICATION PRIOR TO
BIDDING, ORDERING MATERIALS AND DURING EVERY STEP OF CONSTRUCTION FOR
EXISTING SURFACES, DIMENSIONS AND CONDITIONS. NUMBER OF ITEMS AND
LOCATIONS SHOWN ARE APPROXIMATE, CONTRACTOR MUST VERIFY ALL CONDITIONS
AND INCLUDE IN SCOPE OF WORK ACCORDINGLY.
2. PRIOR TO STARTING DEMOLITION AND/OR RENOVATION ON ANY STRUCTURES OR
UTILITIES, THE CONTRACTOR MUST FAMILIARIZE HIMSELF WITH THE EXISTING
CONDITIONS OF ANY STRUCTURES AND UTILITIES. THE CONTRACTOR MUST DEVELOP A
PLAN OF DEMOLITION AND/OR RENOVATION THAT ENSURES ALL ACTIVITIES ARE
COMPLETED IN A SAFE MANNER. PROVIDE ANY TEMPORARY SHORING, SHEETING OR
SUPPORT REQUIRED TO COMPLETE WORK IN A SAFE MANNER.
3. COMPLETELY REMOVE ALL STRUCTURE AND UTILITIES INDICATED, BOTH ABOVE
GROUND AND BELOW GROUND.
4. WHERE ROADS, SIDEWALKS, ETC ARE INDICATED TO BE CUT AND PATCHED, EACH
ONE MUST BE REMOVED AND REPLACED ALONG NEAT SAWCUT LINES, AND TO THE
NEAREST JOINT WHERE IT EXISTS.
5. THIS AREA OF WORK IS LOCATED WITHIN RESTRICTED AREAS. ACCESS TO THIS AREA
MUST BE COORDINATED WITH RANGE CONTROL THROUGH THE COR.
6. REPAIR AND REFINISH AREAS DAMAGED OR DISTURBED BY NEW WORK TO BE
PROVIDED UNDER THIS CONTRACT.
7. DIMENSIONS/AREAS SHOWN ON EXISTING ITEMS ARE PROVIDED TO AID THE
CONTRACTOR UNDERSTAND THE SCOPE OF WORK. FIELD VERIFY ALL CONDITIONS.
ALL THE DIMENSIONS/AREAS SHOWN ARE APPROXIMATE ONLY.
8. METHOD OF REMOVAL OF ANY BUILDING COMPONENT MUST BE APPROVED BY THE
COR. THE CONTRACTOR MUST BE RESPONSIBLE FOR ENSURING THAT REMOVAL OF
EXISTING COMPONENTS DO NOT AFFECT ADJACENT OCCUPIED AREAS.
9. DEMOLITION AND/OR RENOVATION OPERATIONS MUST BE COMPLETED IN COMPLIANCE
WITH ALL STATE AND FEDERAL REGULATIONS, MCBCL STANDARDS AND
REQUIREMEMENTS, AND AS SPECIFIED.
10. ALL CONSTRUCTION ACTIVITIES MUST BE IN ACCORDANCE WITH OSHA STANDARDS,
AND GOVERNMENT REQUIREMENTS
11. THE NOTATION (TYP) INDICATES THAT THE CONDITION OCCURS IN MORE THAN ONE
PLACE INCLUDING ALL SIMILAR CONDITIONS NOT INDIVIDUALLY NOTED.
12. COORDINATE STAGING AREA, SITE ACCESS, TOILET USE WITH THE COR.
13. CONTRACTOR MUST BE RESPONSIBLE FOR SITE SECURITY AND JOB SAFETY.
14. AREAS OUTSIDE THE LIMITS OF PROPOSED WORK DISTURBED BY THE CONTRACTOR'S
OPERATIONS MUST BE RESTORED BY THE CONTRACTOR TO THEIR ORIGINAL CONDITION
AT THE CONTRACTOR'S EXPENSE AS SO0N AS PRACTICABLE.
15. CONTRACTOR MUST MINIMIZE DUST, SEDIMENT AND DEBRIS FROM EXITING THE
CONSTRUCTION SITE AND MUST BE RESPONSIBLE FOR CLEANUP, REPAIRS AND
CORRECTIVE ACTION IF SUCH OCCURS. CONTRACTOR MUST DISPOSE OF DEBRIS IN
ACCORDANCE WITH APPLICABLE FEDERAL, STATE, AND LOCAL REGULATIONS,
ORDINANCE AND STATUTES.
16. BURNING WILL NOT BE ALLOWED ON THE PROJECT SITE UNLESS AUTHORIZED IN
WRITING BY THE COR.
17. ADJACENT STRUCTURES AND UTILITIES MUST REMAIN IN OPERATION DURING
DEMOLITION AND/OR RENOVATION. ACTIVITIES. EXISTING ROADS MUST REMAIN OPEN
AND ACCESSIBLE BY VEHICULAR AND PEDESTRIAN TRAFFIC. IF ROADWAY CLOSURE
IS REQUIRED, APPROVAL MUST BE SECURED FROM THE COR. THE CONTRACTOR
MUST PROVIDE BARRICADES, LIGHTS, SIGNAGE AND OTHER PROTECTIVE DEVICES IN
ACCORDANCE
18. CONTRACTOR'S PERSONNEL MUST WEAR IDENTIFICATION AT ALL TIMES.
EROSION AND SEDIMENTATION CONTROL NOTES:
1. INSTALL GRAVEL CONTROL ENTRANCE AT DESIGNATED PROJECT ENTRANCE.
2. INSTALL SILT FENCING, CHECK DAMS, DROP INLET PROTECTION AS INDICATED OR
REQUIRED IF NOT SHOWN. ADDITIONAL MISCELLANEOUS EROSION CONTROL
MEASURES MAY BE REQUIRED BY THE COR.
3. TEMPORARY STABILIZATION: IF FINE GRADE SITE IS FOUND, STABILIZE AND SEED ALL
AREAS NOT TO BE FURTHER DISTURBED BY CONSTRUCTION ACTIVITIES TO MATCH
EXISTING CONDITIONS. FINAL LANDSCAPE: INSTALL SOD TO ESTABLISH FINAL
VEGETATION.
4. REMOVE SILT FENCING, GRAVEL CONTROL ENTRANCE, CHECK DAMS AND DROP INLET
PROTECTION ONCE VEGETATION IS 95% ESTABLISHED MINIMUM.
5. ALL EROSION AND SEDIMENTATION CONTROL DEVICES MUST BE CHECKED FOR
STABILITY AND OPERATION FOLLOWING EVERY RUNOFF-PRODUCING RAINFALL EVENT
BUT IN NO CASE LESS THAN ONCE EVERY WEEK. ANY NEEDED REPAIRS MUST BE
MADE IMMEDIATELY TO MAINTAIN ALL DEVICES IN THE OPERATIONAL CONDITIONS
INTENDED.
6. ALL DISTURBED AREAS MUST BE FERTILIZED, SEEDED/SODED AS NECESSARY AND
MULCHED ACCORDING TO SPECIFICATIONS IN THE VEGETATION PLAN IN ORDER TO
ESTABLISH AND MAINTAIN A VIGOROUS, DENSE VEGETATIVE COVER.
7. ANY SEDIMENT TRACKED ONTO THE ADJACENT ROADS MUST BE REMOVED ON A
DAILY BASIS.
8. SEDIMENT MUST BE REMOVED FROM BEHIND SILT FENCING, CHECK DAMS, AND DROP
INLET PROTECTION PRIOR TO THE SEDIMENT ACCUMULATING TO A MAXIMUM DEPTH
OF SIX INCHES.
9. ALL FILL MATERIAL NEEDED TO EXECUTE THIS PROJECT MUST BE OBTAINED FROM AN
NCDENR LAND QUALITY SECTION PERMITTED BORROW PIT.
10. ALL DENUDED AREAS MUST, WITHIN 7 CALENDAR DAYS OF COMPLETION OF ANY
PHASE OF GRADING OR CEASING OF GRADING ACTIVITIES, BE PLANTED AND
PROVIDED WITH TEMPORARY OR PERMANENT GROUND COVER, DEVICES, OR
STRUCTURES SUFFICIENT TO RESTRAIN EROSION.
11. PROVIDE PERMANENT GROUND COVER TO ALL DENUDED AREAS WITHIN 7 DAYS OF
COMPLETION OF CONSTRUCTION.
UTILITIES DEMOLITION NOTES:
1. THE LOCATION AND DEPTHS OF EXISTING UTILITIES IF SHOWN ARE APPROXIMATE.
THE CONTRACTOR MUST SECURE THE SERVICES OF A PROFESSIONAL UTILITY LOCATE
CONTRACTOR TO MARK ALL EXISTING UTILITIES IN THE AREA OF WORK. UTILITY
MARKINGS MUST BE MAINTAINED FOR THE DURATION OF DEMOLITION ACTIVITIES.
2. ALL UTILITY LINES IF SHOWN TO REMAIN MUST REMAIN ACTIVE AND MUST BE
PROTECTED DURING DEMOLITION ACTIVITIES.
3. EXISTING UTILITIES MUST NOT BE INTERRUPTED WITHOUT THE APPROVAL OF THE
COR.
4. THE CONTRACTOR MUST BE RESPONSIBLE TO REPAIR OR REPLACE, TO ORIGINAL
CONDITION, ANY UTILITIES DAMAGED DURING DEMOLITION ACTIVITIES FROM THE
CONTRACTOR'S OPERATIONS.
5. ALL COSTS ASSOCIATED WITH LOCATING, DISCONNECTING ABANDONING AND CAPPING
OF UTILITY LINES MUST BE THE RESPONSIBILITY OF THE CONTRACTOR.
6. THE CONTRACTOR MUST BE RESPONSIBLE TO COORDINATE THE REMOVAL OF ALL
UTILITIES INDICATED WITH THEIR RESPECTIVE UTILITY PURVEYORS.
7. ALL PIPES AND CONDUITS IF SHOWN THAT ARE TO BE ABANDONED IN PLACE, MUST
BE CAPPED OR PLUGGED TO SECURE ALL OPEN ENDS TO FORM A WATERTIGHT SEAL.
8. ALL ELECTRICAL WORK MUST BE COMPLETED IN ACCORDANCE WITH THE NATIONAL
ELECTRIC CODE.
9. ALL EXCAVATIONS CREATED BY DEMOLITION ACTIVITIES MUST BE BACKFILLED WITH
COMMON FILL, MUST BE GRADED TO CREATE POSITIVE DRAINAGE, AND MUST BE
VEGETATED IN ACCORDANCE WITH THE PROJECT VEGETATION PLAN OR AS INDICATED
BY THE COR. GRAVEL AND PAVED SURFACES MUST BE RESTORED TO THEIR ORIGINAL
CONDITION.
10. ALL EROSION CONTROL FEATURES MUST BE INSTALLED PRIOR TO DEMOLITION
ACTIVITIES STARTING.
11. ANY FILL MATERIAL REQUIRED TO ESTABLISH THE FINISH GRADES SHOWN MUST BE
OBTAINED FROM A PROPERLY PERMITTED BORROW PIT. ANY EXCESS SOIL MATERIAL
GENERATED FROM DEMOLITION ACTIVITIES MUST BE DISPOSED OF OFF OF THE
GOVERNMENT PROPERTY.
12. CONTACT THE EMD (ENVIRONMENTAL MANAGEMENT DIVISION) AT CAMP LEJEUNE
BEFORE ANY DIGGING IS STARTED AT EACH BUILDING, TOWER, AND SITE FEATURE.
CONTRACTOR MUST PROVIDE THE SERVICES OF A PROFESSIONAL UTILITY LOCATION
SERVICE FOR LOCATING AND IDENTIFYING UNDERGROUND UTILITIES.
13. MONITORING WELLS FOUND AT BUILDINGS AND SITE FEATURES MUST REMAIN IN
PLACE, UNLESS SPECIFICALLY STATED OTHERWISE.
14. CONTRACTOR MUST REMOVE ELECTRICAL, COMMUNICATIONS, WATER, STEAM, AND
SEWER SERVICES BACK TO THE NEAREST JUNCTION UNLESS INDICATED OTHERWISE.
15. WHERE EXISTING PIPING AND OTHER UTILITY SERVICES ARE TO BE REMOVED TO A
TERMINATION POINT AND CAPPED, AS NECESSARY FOR A SAFE AND FINISHED
TERMINATION PROVIDE NEW MATERIAL OF SAME TYPE AND QUALITY AS EXISTING IN
QUESTION OR PROVIDE IN ACCORDANCE WITH UTILITY REQUIREMENTS. ABANDONED
PIPING AND LINES MUST BE REMOVED UNLESS NOTED OTHERWISE. UNDERGROUND
SERVICES ABANDONED BY THIS WORK MUST BE REMOVED, INCLUDING CONDUIT,
PIPING, OR OTHER ITEMS.
16. THE DRAWINGS SHOW OR NOTE CERTAIN ITEMS AND FEATURES TO REMAIN. IT IS
THE CONTRACTOR'S RESPONSIBILITY TO PROTECT FEATURES TO REMAIN FROM
DAMAGE. DAMAGE TO FEATURES MUST BE CORRECTED AS DIRECTED BY THE COR.
17. IF THE CONTRACTOR ENCOUNTERS AN ITEM OR FEATURE AT THE SITE THAT THE
DRAWINGS DO NOT ADDRESS, CONTACT THE COR FOR DIRECTIONS.
18. UTILITIES, PIPING, METERS, VALVES, MANHOLES, UNDERGROUND LINES, ETC. HAVE
BEEN LOCATED BY VISUAL OBSERVATION AND BASE UTILITY MAPS WHEN AVAILABLE.
IN SOME CASES THE EXACT LOCATION AND TERMINATION OF UTILITIES MAY DIFFER
FROM WHAT IS INDICATED. CONTRACTOR MUST FIELD VERIFY AND CONSULT WITH
COR AND BASE UTILITIES BEFORE REMOVING UNDERGROUND UTILITIES.
19. ALL UTILITIES AND EXISTING FEATURES ARE TO BE FIELD VERIFIED PRIOR TO
CONSTRUCTION. CONTRACTOR MUST BE RESPONSIBLE FOR ANY DAMAGE TO EXISTING
UTILITIES.
HAZARDOUS WASTE NOTES:
1. HAZARDOUS MATERIALS REPORTS WILL BE MADE AVAILABLE IF IN EXISTENCE. THE
CONTRACTOR MUST TEST ALL ITEMS FOR HAZARDOUS MATERIALS (LEAD AND
ASBESTOS). IF FOUND THE CONTRACTOR MUST ABATE ALL HAZARDOUS MATERIALS
BEFORE THEIR DISPOSAL. COMPLY WITH ALL FEDERAL, MCBCL, AND STATE LAWS
AND REGULATIONS
2. THE CONTRACTOR TO ASSUME THAT SOME OF THE MATERIALS CONTAIN ASBESTOS
UNTIL SAMPLED AND TESTED BY ACCREDITED AND LICENSED ASBESTOS
PROFESSIONALS. CONTRACTOR TO REVIEW ASBESTOS INSPECTION REPORT AND
SPECIFICATIONS BEFORE COMMENCING DEMOLITION.
3. IF HAZARDOUS MATERIALS ARE SUSPECTED TO BE PRESENT, ENSURE THAT SUBJECT
BUILDING(S) / STRUCTURE(S) ARE EVALUATED FOR ASBESTOS / LEAD CONTAINING
MATERIALS BY A CERTIFIED PROFESSIONAL PRIOR TO THE DEMOLITION.
4. IF DURING DEMOLITION, ANY SOILS ARE ENCOUNTERED THAT ARE SUSPECTED OF
BEING CONTAMINATED, WORK MUST CEASE IMMEDIATELY AND THE COR MUST BE
CONTACTED FOR RESOLUTION. CALL 911 AND CONTACT EQB AT (910) 451-9017
FOR INSTRUCTIONS.
5. ALL HAZARDOUS WASTE GENERATED BY THIS PROJECT MUST MEET RCRA STANDARDS.
6. COORDINATE WITH ANTHONY L. RECOB, SUPERVISOR RESOURCE CONSERVATION &
SECTION ENVIRONMENT PROTECTION SPECIALIST ENVIRONMENTAL MANAGEMENT
DIVISION MARINE CORPS BASE CAMP LEJEUNE. TELEPHONE: (910)-451-5306. E-
MAIL: ANTHONY.RECOB@USMC.MIL
7. REMOVAL OR ENCAPSULATION OF LEAD PAINT PRIOR TO BUILDING DEMOLITION IS NOT
REQUIRED, ALL WORK SHOULD BE CONDUCTED BY WORKERS TRAINED IN "LEAD SAFE
WORK PRACTICES" AS OUTLINED BY THE OCCUPATIONAL SAFETY AND HEALTH
ADMINISTRATION (OSHA). CONTRACTOR TO REVIEW LEAD INSPECTION REPORT AND
SPECIFICATIONS BEFORE COMMENCING DEMOLITION. IF ADDITIONAL COATINGS ARE
FOUND DURING DEMOLITION THAT ARE NOT ON THE SURVEY REPORT, CONTRACTOR
TO ASSUME THESE MATERIALS ARE LEAD CONTAINING COATINGS UNTIL SAMPLED AND
TESTED BY ACCREDITED AND LICENSED LEAD PROFESSIONALS.
8. ASBESTOS CONTAINING MATERIALS (ACM): REMOVE ACM FROM BUILDINGS AND SITES.
COMPLETED PROJECT SITES MUST BE FREE FROM ACM. ACM MAY OCCUR IN
LOCATIONS AND IN QUANTITIES DIFFERENT FROM THOSE ESTIMATED. NOTIFY COR IF
SUSPECT ACM IS ENCOUNTERED THAT HAS NOT BEEN TESTED. SUSPECT ACM MUST
BE TREATED AS REGULATED ACM UNLESS TESTED AND DETERMINED TO NOT BE ACM.
TAKE PRECAUTIONS AS SPECIFIED. COORDIANTE WITH THE COR.
9. LEAD BASE PAINT (LBP): WHERE WORK IN PROJECT DISTURBS SURFACES WITH LBP
OR WHERE ITEMS WITH LBP ARE TO BE REMOVED, TAKE PRECAUTIONS AS SPECIFIED
AND AS REQUIRED BY AGENCIES HAVING JURISDICTION AND TO MAINTAIN SAFE
CONDITIONS. DUE TO THE AGE OF THE BUILDINGS AND THE NUMBER OF TIMES
THEY HAVE BEEN PAINTED, LBP LEVELS IN DIFFERENT AREAS MAY VARY FROM THE
TESTING DATA. TAKE PRECAUTIONS WHEN WORKING WITH PAINTED SURFACES
REGARDLESS OF TESTING DATA. IT IS RECOMMENDED THAT ITEMS AND MATERIALS
WITH LBP BE REMOVED INTACT OR AS UNITS. REMOVAL BY SANDING, ABRASIVE
BLASTING, OR CHEMICALS IS NOT RECOMMENDED AND WILL CREATE CONCENTRATED
LEVELS OF LEAD THAT MUST BE DISPOSED OF AS HAZARDOUS WASTE. SEE
SPECIFICATIONS. COORDIANTE WITH COR.
10. IF HAZARDOUS MATERIALS ARE FOUND, WORKERS MUST WEAR PROTECTIVE GEAR AND
RESPIRATORS. CONTRACTOR MUST SUBMIT PROPOSED CLEANING PROCEDURES FOR
REMOVAL OF LEAD DUST BEFORE STARTING DEMOLITION ACTIVITIES. CLEANING AND
REMOVAL MUST BE IN ACCORDANCE WITH FEDERAL, STATE, AND BASE
ENVIRONMENTAL REQUIREMENTS AND FINAL PROPOSAL MUST BE APPROVE BY USMC-
CL ENVIRONMENTAL MANAGEMENT OFFICE.