20-0002 Part 4.pdf
PDF 2 MB Posted
- Attached to
- Building 201 Repair by Replacement
- Solicitation number
- N6247020R6018
View the file
Other files
Show 40 more
Latest 50 of 51 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Buildings 115 & 201 Repair by Replacement Project # 20-0002 Marine Corps Base, Camp Lejeune
PART 4 - Page | 1
Part 4 Minimum Materials, Engineering and Construction Requirements
1.0 GENERAL REQUIREMENTS
The requirements indicated here are minimum performance requirements. More specific project functional and performance requirements, scope items and expected quality levels over and above the standards in Part 4 are identified in Part 3 of the Request for Proposal or Basic Ordering Agreement. The Contractor is encouraged to exceed the minimum requirements. The Contractor's performance evaluation will be based in part on enhancements to materials, engineering, design and construction provided for the contract that exceed minimum requirements.
Part 4 is a general section. Not all items in Part 4 will be required for this project. See Part 3 for project-specific requirements. See "Order of Precedence" paragraph in Part 2 for relationships between all parts of the
RFP.
In general, unless otherwise indicated, Contractor shall provide all labor, equipment and materials necessary to complete the work required for the contract. All work shall be in conformance with all applicable referenced criteria, construction standards, laws and regulations, including applicable building and fire, life safety codes.
Recycled Materials Considerations:
An Affirmative Procurement Program has been established within the Federal government to promote the purchase of products containing recovered materials. This program promotes the purchase of products containing materials recovered from the solid waste stream. The intent is to conserve resources and reduce solid waste by developing markets for recycled products and encouraging manufacturers to produce quality recycled content products. The contractors shall use products that meet or exceed the
EPA guideline standards for recovered content as required by the Federal Acquisition Regulations
(FAR). Availability lists of manufacturers and EPA research on product usage are on the Construction
Criteria Base (CCB) at http://www.ccb.org under Documents Library, NAVFAC Criteria. A partial list of products containing recycled materials for possible use is as follows:
Rock Wool Insulation
Fiberglass Insulation
Cellulose Insulation
Structural Fiberboard and Laminated Paperboard
Cement and Concrete - Coal Fly Ash
Carpet including backings and cushions
Floor Tiles
Reprocessed and Consolidated Latex Paint
Crushed Concrete Aggregate for new asphalt, concrete or subgrade
Recycled glass for terrazzo aggregate
Acoustical Ceiling Tile
Gypsum Wallboard
Steel wall studs
Cellulose spray applied fireproofing
HDPE Toilet Partitions
1.1 MATERIALS AND METHODS OF CONSTRUCTION
Only new materials and equipment shall be installed in the work. All materials, equipment and appliances shall be of the current manufacturers' products. No obsolete or discontinued materials, equipment and appliances shall be used, except that construction materials containing recycled content as described in
Paragraph 1 of this Part that completely comply with all materials specifications found elsewhere in this Part may be used.
http://www.ccb.org/
PART 4 - Page | 2
1.2 APPLICABLE CODES AND STANDARDS
The design and construction shall be in accordance with established construction practices, and the latest revision/edition of the following referenced codes and standards. The term "Latest Revision/Edition" is defined as the version as of the project award date. References are available at www.wbdg.org/ndbm/ . The advisory provisions of all codes and standards shall be mandatory, as though the word "shall" had been substituted for "should" wherever it appears. Reference to the "authority having jurisdiction" shall be construed to mean "Contracting Officer". Comply with the required and advisory portions of the current edition of the standard at the time of contract award. All work to comply with UFC 1-200-01, General
Building Requirements, and IBC 2009 or later edition as modified by applicable NFPA Standard as well as codes and standards listed in RFP Part 2 Attachment A.
1.3 LOCATION-SPECIFIC CODES AND STANDARDS
See Part 3.
1.4 DISCREPANCIES
When discrepancies in the referenced standards and the contract requirements occur, the more stringent requirements shall govern. The word "should" in all NFPA publications shall be interpreted as a requirement.
The Authority Having Jurisdiction in the interpretation of the codes and standards, and approving the exceptions allowed in the referenced standards, shall be the Contracting Officer, and the parties designated by the Contracting Officer.
http://www.wbdg.org/ndbm/
PART 4 - Page | 3
2.0 PERFORMANCE TECHNICAL SPECIFICATIONS
Note: The paragraph numbers used correspond with the numbers used in UNIFORMAT II/Work Breakdown
Structures (WBS) as listed in the Whole Building Design Guide, Navy Design Build Master, accessible at this website: www.wbdg.org/ndbm .
SECTION A. SUBSTRUCTURE
A10 Foundations
A10 GENERAL
RFP Part 3 including the Engineering System Requirements (ESR) provide project specific requirements. The RFP
Part 4, Performance Technical Sections (PTS) provide generalized technical requirements that apply to multiple facility types and include more requirements than are applicable to any one project. Therefore, only the RFP Part 4 requirements that apply to the project and further define the RFP Part 3 project specific requirements are required.
A10 1.1 DESIGN GUIDANCE
Provide the design and installation in accordance with the following references. This Performance
Technical Specification (PTS) adds clarification to the fundamental requirements contained in the following Government Standards. The general requirements of this PTS section are located in PTS
Section Z10, General Performance Technical Specification.
A10 1.1.1 Government Standards
UNIFIED FACILITIES CRITERIA (UFC)
UFC 1-200-01
DoD Building Code (General Building
Requirements).(A reference in this PTS section to
UFC 1-200-01 requires compliance with the Tri-
Service Core UFCs that are listed there, which includes the following significant UFC(s):UFC 3-
101-01, Architecture UFC 3-220-01, Geotechnical
Engineering UFC 3-301-01, Structural Engineering)
UNIFIED FACILITIES GUIDE SPECIFICATIONS (UFGS)
UFGS Section 31 23 00.00 20
Excavation and Fill
A10 1.2 GENERAL REQUIREMENTS
A10 1.2.1 Earthwork
Prepare the following UFGS Specification as part of the project specification and include the prepared specification section in the design submittal for the project:
UFGS Section 31 23 00.00 20 Excavation and Fill
A10 1.2.2 Geotechnical Report http://www.wbdg.org/ndbm
PART 4 - Page | 4
A10 1.2.2.1 Subsurface Soils Information
Any provided subsurface soil information is included for the Contractor’s information only, and is not guaranteed to fully represent all subsurface conditions. The data included in this RFP is to assist in proposal preparation. Perform such subsurface exploration, investigation, testing, and analysis for the design and construction of the foundation system at no additional cost to the Government.
A10 1.2.2.2 Contractor-provided Geotechnical Engineer
Retain a Geotechnical Engineer experienced and licensed in the geographic region of the project to interpret any provided data as related to his design concept and develop requirements for bidding. Requirements stated in Parts 3 and 4 of the RFP take precedence over any content of any included geotechnical report. Additional requirements for the geotechnical design of this project are provided elsewhere in this
RFP.
Coordinate all work by the Contractor-provided Geotechnical Engineer with the
Contracting Officer and ensure that work does not conflict with Base operations. When providing the Foundation Work Design submittal, provide the Contractor's Geotechnical
Report (an Adobe Acrobat PDF version on CD and two printed copies) for review and record keeping purposes. The report becomes the property of the Government. Provide the Geotechnical reports generated during construction, such as pile load tests or PDA results, pile driving results and analysis, to the Contracting Officer (an Adobe Acrobat
PDF version and two printed copies) for record keeping purposes.
A10 1.2.2.3 Contractor-Provided Geotechnical Report
Submit a written Geotechnical report based upon Government-provided subsurface investigation data and all additional field and laboratory testing accomplished at the discretion of the Contractor's Geotechnical Engineer. The Geotechnical Report must include all requirements listed in UFC 3-220-01, Geotechnical Engineering, paragraph entitled "Section 1803 "Geotechnical Investigations"; in addition, include the following:
a. The project site description, vicinity map and site map indicating the location of borings and any other sampling locations. Provide 24 hour groundwater observations for at least 20% of the borings, minimum one boring. Provide notes explaining any abbreviations or symbols used and describing any special site preparation requirements.
b. Results of all applicable field and laboratory testing, whether Government or
Contractor-provided. Address existing subsurface conditions, selection and design of the foundation and floor slab, all underground construction including utility installation and all other site-specific requirements (such as soil stabilization and slope stability).
c. Engineering analysis, discussion and recommendations addressing:
1) Settlement analysis. Settlement must be limited as required in EM 1110-1-
1904, Settlement Analysis
2) Bearing Capacity Analysis.
3) Foundation selection and construction considerations (shallow, deep, special); dimensions, and installation procedures.
4) Site preparation (earthwork procedures and equipment), compaction
PART 4 - Page | 5 requirements, building slab preparation (as applicable), soil sensitivity to weather and equipment, groundwater influence on construction, mitigation of expansive soils or liquefaction potential, dewatering requirements, slope stability, and other necessary instructions.
5) Sheeting and shoring considerations, as applicable
6) Pavement design calculations with parameters defined, actual or assumed, and recommended thicknesses and materials, whether for design or for proposed modifications to the RFP provided pavement design
7) Haul routes and stockpile locations for earthwork, as applicable.
8) Calculations to support conclusions and recommendations.
9) Present recommendations on a structure-by-structure Basis.
Provide the Geotechnical Report signed by the Contractor-provided Geotechnical
Engineer.
Submit report accompanied by a cover letter identifying any report recommendations of the report proposed to be adopted into the design which are interpreted by the Contractor as a change condition to the Geotechnical or Pavement related requirements of the RFP.
A10 1.2.2.4 Geotechnical Site Data required in Design Drawings
The Contractor's final design drawings must include the Government-provided subsurface data presented in the RFP as noted below, as well as all additional borings and laboratory test data results performed by the Contractor. The data provided must include:
a. Logs of Borings and related summary of laboratory test results and groundwater observations. Provide 24-hour groundwater observations for at least 20% of the borings, minimum one boring. Provide notes explaining any abbreviations or symbols used and describing any special site preparation requirements.
b. Indicate locations of all borings on the drawings. Revise applicable design drawings to reference the Contractor’s Geotechnical Report as being a basis for design.
A10 1.2.3 Pile Driver Analyzer (PDA)
If deemed necessary by the Contractor's Geotechnical Engineer, the dynamic wave equation method of analysis, pile driver analyzer, must be used to validate pile and pile hammer compatibility, establish pile driving criteria, establish terminal penetration resistance, or verify as-driven capacity of the pile. Provide PDA or static load test(s) for piles with required allowable design capacity equal to or greater than 40 tons.
A10 1.3 PERFORMANCE VERIFICATION AND ACCEPTANCE TESTING
Provide verification of satisfactory construction and system performance of the foundations via
Performance Verification Testing, and by field inspection, as detailed in this section of the RFP and in Part
2 Section 01 45 00.05 20, Design and Construction Quality Control. Provide special tests and special inspections in accordance with Part 2 Section 01 45 00.05 20.
A10 1.3.1 Earthwork
PART 4 - Page | 6
Perform quality assurance for earthwork in accordance with International Building Code
(IBC) Chapter 17 and UFGS Section 31 23 00.00 20. A competent person, as defined by COE
EM 385-1-1, under supervision of a registered Professional Engineer is required to provide inspection of excavations and soil/groundwater conditions throughout construction. The Engineer must perform periodic site visits throughout construction to assess site conditions. The Engineer, with the concurrence of the Contractor and the Contracting Officer, must update the excavation, sheeting, shoring, and dewatering plans as construction progresses to reflect actual site conditions and submit the updated plan and a written report (with professional stamp) at least monthly informing the Contractor and the Contracting Officer of the status of the plan and an accounting of
Contractor adherence to the plan; specifically addressing any present or potential problems. The
Engineer must be available to meet with the Contracting Officer at any time throughout the contract duration. The Contractor will bear all costs of the Engineer.
A10 1.3.2 Piles
If piles are required, perform quality assurance for pile construction in accordance with UFC 1-
200-01, DoD Building Code (General Building Requirements). Pile installation procedures and installed piles must be inspected and found to be in compliance with these specifications prior to acceptance of the work.
Provide test piles as directed by the Contractor’s Geotechnical Engineer.
Perform pile load tests, if required, in accordance with UFC 1-200-01.
Submit results of the pile test program and final pile installation criteria to the Contracting Officer prior to installation of the production piles.
If deemed necessary by the Contractor’s Geotechnical Engineer, use the dynamic wave equation method of analysis, pile driver analyzer, to validate pile and pile hammer compatibility, establish pile driving criteria, establish terminal penetration resistance, or verify as-driven capacity of the pile.
Perform PDA or static pile load test (American Society for Testing and Materials - ASTM D
1143) for piles with an allowable design capacity equal to or greater than 40 tons. When required, perform PDA on all indicator or test piles. Perform CAPWAP analysis on at least one test (indicator) pile to determine capacity with a minimum three-day set-up and develop pile installation criteria.
A10 1.4 DESIGN SUBMITTALS
Provide design submittals in accordance with Z10, General Performance Technical Specifications, Part 2
Section 01 33 10.05 20, Design Submittal Procedures, Facilities Criteria (FC) 1-300-09N, Navy and
Marine CorpsDesign Procedures,UFC 3-220-01, Geotechnical Engineering, and UFC 1-200-01, DoD
Building Code (General Building Requirements).
UFGS sections listed below or in the body of the PTS text are to be used by the Designer of Record (DOR) as a part of the design submittal. The DOR must edit these referenced UFGS sections and submit them as a part of the design submittal specification. Edit the specification sections in accordance with the limitations stated in PTS Section Z10, General Performance Technical Specifications.
UFGS Section 31 23 00.00 20 Excavation and Fill
A10 1.5 CONSTRUCTION SUBMITTALS
PART 4 - Page | 7
Submit construction submittals in accordance with PTS Section Z10, General Performance Technical
Specifications. In addition to the Z10 requirements, the Designer of Record (DOR) must approve the following submittals as a minimum:
All structural elements necessary for construction
Contractor-provided geotechnical report
Controlled fill or backfill material tests
Test pile and production pile installation records
Pile load testing reports
As-Built drawings - Include a statement on the drawings indicating the method used to verify the allowable design capacity of the piles (load tests or PDA).
A1010 STANDARD FOUNDATIONS
A1010 1.1 SHEETING AND SHORING
Provide sheeting and shoring as required. Provides sheeting and shoring plans signed by the Contractor's
Geotechnical Engineer.
A1010 1.2 TERMITE CONTROL
A1010 1.2.1 Termite Control Barrier System
Formulate and apply termiticide in accordance with the manufacturer's label directions. Provide termiticide with a label bearing evidence of registration by the U.S. Environmental Protection
Agency or appropriate requirements of the host country.
Apply termiticide to the soil that will be covered by or lie immediately adjacent to the building(s) and structure(s), providing a protective barrier against subterranean termites.
Maintain the Pest Management Maintenance Record, DD Form 1532-1 and submit the Pest
Management Report, DD Form 1532 as required.
Provide applicator(s) that are licensed or certified by the Federal government or the state or the host country, as applicable.
A1010 1.2.2 Warranty
Provide a 3-year written warranty against infestations or reinfestation by subterranean termites of the buildings or building additions constructed under this contract. Perform annual inspections of the building(s) or building addition(s). If live subterranean termite infestation or subterranean termite damage is discovered during the warranty period, and building conditions have not been altered in the interim:
a. Perform treatment as necessary for elimination of subterranean termite infestation;
b. Repair damage caused by termite infestation;
c. Reinspect the building approximately 180 calendar days after the repair.
A1010 1.2.3 Visual Inspection Guide
To maintain resistance to termites, complete the system and do not disturb, penetrate or damage during the remaining contract time period. Provide Manufacturer’s Guidance for performing a
PART 4 - Page | 8 visual assessment of the installed system to ensure the system provides the designed termite physical barrier.
A101001 WALL FOUNDATIONS
Provide foundation walls as required in accordance with the requirements of this section and other portions of this
RFP.
A101002 COLUMN FOUNDATIONS AND PILE CAPS
Provide column foundations or pile caps and grade beams as required in accordance with the requirements of this section and other portions of this RFP.
A1020 SPECIAL FOUNDATIONS
A102001 PILE FOUNDATIONS
Where piles are required, design, install, and test piles (including sheet piles, as applicable) in accordance with UFC
1-200-01, except as noted otherwise. Provide piles in accordance with the requirements of the Contractor’s
Geotechnical Engineer, and the following paragraphs.
A102001 1.1 DRIVING EQUIPMENT
Provide piles (including sheet piles, as applicable) to the required tip elevation and capacity with the appropriate equipment as recommended by the Contractor's Geotechnical Engineer. Provide pile hammer(s) of sufficient weight and energy to suitably install piles without damage.
Drive production piles with the same hammer, cap block, and cushion materials, and using the same operating conditions as test piles, including pre-augering and spudding.
Pile driving equipment must match the equipment assumptions on which the pile driving formulae used to determine blow counts are based.
A102001 1.2 INSTALLATION TOLERANCES
Locate the center of pile butts not more than four horizontal inches from the location indicated at cutoff elevation. Manipulation of the piles is not permitted. In addition to the stated tolerances, provide a minimum clear distance of five inches between the heads of piles and the edges of pile caps.
Locate top of sheet piles at cutoff elevation within 1/2 inch horizontally and 2 inches vertical of the location indicated. Manipulation of the piles is not permitted.
A variation of not more than 2 percent from the vertical for plumb piles, or not more than 4 percent from the required angle for batter piles will be permitted.
A102001 1.3 MISLOCATED AND DAMAGED PILES
Remove and replace with new piles those piles that are damaged, mislocated, or installed out of alignment tolerance or provide additional piles, installed as directed by the Contractor's Geotechnical Engineer and approved by the Contracting Officer, at no additional cost to the Government.
A102001 1.4 PILE SPACING
For cast-in-place concrete or augercast piles, provide adequate distance, as determined by the Contractor's
Geotechnical/Structural Engineer, between freshly placed concrete and other pile installation operations to
PART 4 - Page | 9 avoid damage to concrete.
A102001 1.5 COATED PILES
Handle treated or coated piles so as to protect the treatment or the coating. Repair damage or defects to treatment or coating.
A102002 CAISSONS
If required, provide caissons as required in accordance with the requirements of this section and other portions of this RFP.
A102003 UNDERPINNING
If required, underpin existing construction as required in accordance with the requirements of this section and other portions of this RFP.
A102004 DEWATERING
Dewater site for foundation construction as required by soil conditions and local subsurface and surface water, including rainfall, and considering any potential adverse impact on adjacent facilities, including settlement.
Dewatering requirements and methods must be established by the Contractor’s Geotechnical Engineer, based on his subsurface exploration and investigation.
A102005 RAFT FOUNDATIONS
If required, provide a raft foundation as required to achieve the requirements of this section and other portions of this RFP and as required by the Contractor’s Geotechnical Engineer.
A102006 PRESSURE INJECTED GROUTING
If required, pressure inject grout as required in accordance with the requirements of this section and other portions of
A1030 GROUND FLOOR SLABS
A103001 STANDARD SLAB ON GROUND
If allowed by site conditions and recommended by the Contractor-provided Geotechnical Engineer, provide standard concrete slab on grade to meet the required loading requirement in accordance with the requirements of this section and other portions of this RFP.
Design and construct floor slab on grade in accordance with EM 1110-1-1904, Settlement Analysis, and so that any settlement of the floor slab will not result in harmful distortion of the floor, nor vertical misalignment of the floor with other building components (such as doorways and trenches), building utilities or with pile-supported building elements. If these above conditions cannot be met, provide a pile supported slab.
A103003 TRENCHES
Provide reinforced concrete trenches with water proof joints and seals to prevent ground water infiltration.
A103004 PITS AND BASES
Provide reinforced concrete pits and bases with water proof joints and seals to prevent ground water infiltration.
PART 4 - Page | 10
A103005 FOUNDATION DRAINAGE
A103005 1.1 PERIMETER FOUNDATION DRAINAGE
Provide a perimeter drainage system shall be provided to remove water away from the foundation of the facility and to be deposited in the storm sewerage system of the site. Provide perforated pipe for the foundation drainage system of the type specified, and of a size sufficient to remove water from the foundation successfully. Provide one, or a combination of more than one, of the following types of pipe:
a. Corrugated Polyethylene (PE) Drainage Pipe: ASTM F 405, heavy duty, for pipe 3 to 6 inches in diameter inclusive; ASTM F 667 for pipe 8 to 24 inches in diameter. Fittings must be manufacturer's standard type and must conform to the indicated specifications.
b. Acrylonitrile-Butadiene-Styrene (ABS) Pipe: ASTM D 2751, with a maximum SDR of 35.
c. Polyvinyl Chloride (PVC) Pipe: ASTM F 758, Type PS 46, ASTM D 3034, or ASTM F 949 with a minimum pipe stiffness of 46 psi.
Installation includes wrapping the pipe with filter fabric sock and careful bedding of the pipe with appropriate fill material to ensure that the pipe does not become obstructed with the bedding material.
A103090 OTHER SLAB ON GROUND
A103090 1.1 BLOCK OR BOARD PERIMETER INSULATION
Provide only thermal insulating materials recommended by manufacturer for perimeter insulation. Provide one of the board or block thermal insulations listed below conforming to the following standards:
a. Extruded Preformed Cellular Polystyrene: ASTM C 578
Provide insulation to meet requirements of UFC 3-101-01, Architecture.
SECTION B. SHELL
B10 Superstructure
B10 GENERAL
RFP Part 3 including the Engineering System Requirements (ESR) provide project specific requirements. The RFP
Part 4, Performance Technical Sections (PTS) provide generalized technical requirements that apply to multiple facility types and include more requirements than are applicable to any one project. Therefore, only the RFP Part 4 requirements that apply to the project and further define the RFP Part 3 project specific requirements are required.
B10 1.1 DESIGN GUIDANCE
following Government Standards. The general requirements of this PTS section are located in PTS
Section Z10, General Performance Technical Specification.
B10 1.1.1 Government Standards
UFC 1-200-01 DoD Building Code (General Building
PART 4 - Page | 11
Requirements)(A reference in this PTS section to
UFC 1-200-01 requires compliance with the Tri-
Service Core UFCs that are listed therein, which includes the following significant UFC(s):UFC 3-
101-01, ArchitectureUFC 3-301-01, Structural
Engineering)
UFC 4-023-03
Design of Buildings to Resist Progressive Collapse
B10 1.2 PERFORMANCE VERIFICATION AND ACCEPTANCE TESTING
Verify satisfactory construction and system performance via Performance Verification Testing, as detailed in this section of the RFP. Provide special tests and special inspections in accordance with Part 2 Section
01 45 00.05 20, Design and Construction Quality Control. The cost of all testing is included in the
Contract.
B10 1.3 DESIGN SUBMITTALS
Provide design submittals in accordance with PTS Section Z10, General Performance Technical
Specifications, Part 2 Section 01 33 10.05 20, Design Submittal Procedures, Facilities Criteria (FC) 1-300-
09N, Navy and Marine CorpsDesign Procedures, UFC 3-101-01, Architecture, and UFC 3-301-01, Structural Engineering.
B10 1.4 CONSTRUCTION SUBMITTALS
following submittals as a minimum:
All structural elements necessary for construction of the superstructure.
B1010 FLOOR CONSTRUCTION
B101001 STRUCTURAL FRAME
Structural frame elements may include columns, girders, beams, trusses, joists, moment frames, shear walls, and bracing. See Section B20, Exterior Enclosure, for additional requirements for exterior walls used as load-bearing walls or shear walls.
B101002 STRUCTURAL INTERIOR WALLS
Provide structural interior walls as required in accordance with the requirements of this section and other portions of this RFP. See Section C10, Interior Construction, for additional requirements.
B101003 FLOOR DECKS AND SLABS
If required, provide floor decks as required in accordance with the requirements of this section and other portions of
PART 4 - Page | 12
B101005 BALCONY CONSTRUCTION
Design and construct exterior balconies to drain and with the top of the balcony high-point below the interior floor elevation as required for flashing.
B101006 RAMPS
Provide ramps as required in accordance with the requirements of this section and other portions of this RFP.
B101007 FLOOR RACEWAY SYSTEMS
See Section D50, Electrical, for floor raceway systems.
B1020 ROOF CONSTRUCTION
B102001 STRUCTURAL FRAME
Structural frame elements may include columns, girders, beams, trusses, joists, moment frames, shear walls, and bracing. See Section B20, Exterior Enclosure, for additional requirements for exterior walls used as load-bearing walls or shear walls.
B102002 STRUCTURAL INTERIOR WALLS
Provide structural interior walls as required in accordance with the requirements of this section and other portions of this RFP. See Section C10, Interior Construction, for additional requirements.
B102003 ROOF DECKS AND SLABS
Provide roof deck as required in accordance with the requirements of this section and other portions of this RFP.
B102004 CANOPIES
Provide canopies as required in accordance with the requirements of this section and other portions of this RFP.
B20 EXTERIOR ENCLOSURE
B20 GENERAL
RFP Part 3 including the Engineering System Requirements (ESR) provide project specific requirements. The RFP
Part 4, Performance Technical Sections (PTS) provide generalized technical requirements that apply to multiple facility types and include more requirements than are applicable to any one project. Therefore, only the RFP Part 4 requirements that apply to the project and further define the RFP Part 3 project specific requirements are required.
B20 1.1 DESIGN GUIDANCE
following Government Standards. The general requirements of this PTS section are located in PTS
Section Z10, General Performance Technical Specification.
Industry standards, codes, and Government standards referenced in the section text that are not found in the
Unified Master Reference List (UMRL) in the Construction Criteria Base (CCB) at the Whole Building
Design Guide Website , are listed below for basic designation identification. Comply with the required and advisory portions of the current edition of the referenced standard at the time of contract award.
http://www.wbdg.org/ccb http://www.wbdg.org/ http://www.wbdg.org/
PART 4 - Page | 13
B20 1.1.1 Industry Standards and Codes
NATIONAL LUMBER GRADES AUTHORITY (NLGA)
B20 1.1.2 Government Standards
Military Handbook 1013/1A, Design Guidance for Physical Security of Facilities
UFC 1-200-01
DoD Building Code (General Building
Requirements)(A reference in this PTS section to
UFC 1-200-01 requires compliance with the Tri-
Service Core UFCs that are listed therein, which includes the following significant UFC(s): UFC 3-
101-01, Architecture)
UFC 1-200-02
High Performance and Sustainable Building
Requirements
B20 1.2 PERFORMANCE VERIFICATION AND ACCEPTANCE TESTING
Provide verification of satisfactory exterior enclosure system performance via Performance Verification
Testing, and by field inspection as detailed in this section of the RFP. Provide special tests and special inspections in accordance with Part 2 Section 01 45 00.05 20, Design and Construction Quality Control.
The cost of all testing is included in the Contract.
B20 1.2.1 Required Brick Masonry Testing and Field Samples
a. Where field testing is required, determine masonry strength in accordance with American
Concrete Institute (ACI) 530.1.
b. Field Samples: Masonry Panel Requirements - At the job site submit for approval by the
Designer of Record, a sample masonry panel minimum 8 feet (2.4 meters) long by a minimum of 4 feet (1.2 meters) high. Actual Sample size will be determined by number of components in the sample wall but provide a span of at least 4 feet (1.2 meters) of uninterrupted brickwork and 2 feet (.6 meters) above wall openings. The approved sample must exhibit the standard for workmanship and materials for the project. The sample panel must include brick coursing, bond, weep holes, flashing, thickness, anchors, joint reinforcing, wall ties, rigid-board insulation, intersection of walls, bond beams, expansion and control joints, and tooling of joints, range of color, texture of masonry, and mortar color; or cold-formed steel framing, insulation, fiberglass-faced gypsum sheathing, air barrier, moisture barrier/vapor retarders, exterior enclosure barrier connections to adjoining construction, sealing of exterior enclosure barrier penetrations, sealant, masonry ties and anchors, and tooling of joints, the range of color and texture of brick veneer, and the color of mortar. Protect the sample panel from damage at the site until masonry work is complete and approved, at which time the panel must be removed from the site. If there are windows or curtain walls in the project which interface with the masonry, a cut-away sample window or curtain wall mock-up must be installed in the masonry field panel, with all accessories, finishes, and trim (see B20 1.2.4 and 1.2.5).
Masonry work must match the approved sample.
B20 1.2.2 Air Barrier Field Sample
Designate a portion of the project that reveals the various edge, seam, transition, and penetration
PART 4 - Page | 14 conditions that the air barrier is exposed to. Determine this location with the Contracting Officer and obtain approval of the sealing methods employed on the project from the air barrier
Manufacturer. Leave sample area exposed to view as long as practical to serve as a construction standard and comparison of future air barrier construction on the project. Before construction covers the sample area, provide detailed photographs of the air barrier details for future reference.
B20 1.2.3 Air Barrier Performance
Provide air barrier inspection on all projects and air barrier performance testing when required in
RFP Part 3, Section B20.
B20 1.2.3.1 Air Barrier Inspection
Coordinate all subcontractors that provide part of the air barrier construction to provide an air tight barrier. Review the air barrier prior to being covered by subsequent construction to confirm that the air barrier complies with the following requirements;
a. Prior to applying an air barrier, confirm that the substrate complies with conditions required by the applied air barrier material manufacturer.
b. Air barrier must create a continuous barrier, without gaps, "fish mouths", holes, unsealed seams, or unsealed penetrations.
c. Air barrier components are compatible and capable of being permanently connected to form an air tight barrier.
d. Construction of the air barrier complies with air barrier design as indicated in the Basis of Design and exterior enclosure barrier drawings.
e. Air barrier is installed in accordance with manufacturer's standard details available on the Air Barrier Association of America (ABAA) website named
"Air Barrier Materials, Components, Assemblies & Systems" and found at the following web link; http://www.airbarrier.org/materials/assemblies_e.php
B20 1.2.4 Thermal Envelope Performance Testing (Infrared Thermography)
Where required in RFP Part 3 or B20 1.2.3.2 Air Barrier Performance Testing, provide infrared thermal testing and repair as follows (coordinate with air barrier testing):
a. Test the building envelope using Infrared Thermography technology. Complete thermography testing in accordance with the requirements of ASTM C1060 and ISO
6781. The Contracting Officer will witness the testing. Testing must occur just before the building air tightness test. Testing must also occur during the air tightness test so that areas of building air leaks are detected. If the building air tightness test is failed, repeat thermographic testing just before and during subsequent air tightness tests until the air tightness test is successful.
b. Thermography Test Procedures: Submit detailed test procedures indicating the test apparatus, the test methods and procedures, and the analysis methods to be employed not later than 60 days after Notice to Proceed.
c. Thermography Test Report: Provide a report. The report must include thermographs in color and a color temperature scale to define the temperature indicated by the various colors. The report must identify the high temperature reading, the outdoor air temperature, the building indoor air temperature, and the wind speed and direction. The report must note any areas of compromise in the building envelope, and must note all actions required and taken to correct those areas.
d. Final Test: Final thermography test report must demonstrate the problem areas have been corrected. Submit the complete test and analysis for review and approval.
B20 1.2.5 Air Barrier Performance Testing http://www.airbarrier.org/materials/assemblies_e.php
PART 4 - Page | 15
Provide air barrier testing and repair as follows (coordinate with infrared thermal testing):
a. Provide a testing plan as a part of the Commissioning Plan and notify the Contracting
Officer 7 working days before the testing will take place. Do not test the building until verifying that the continuous air barrier is in place and installed without failures in accordance with installation instructions so that repairs to the continuous air barrier, if needed to comply with the required air leakage rate, can be done in a timely manner.
Also coordinate building access during the test with the Contracting Officer. Perform pretest inspection with all parties involved in the test and possible repairs of the building enclosure. Record pretest conditions and utilize pictures to assist in the documentation.
b. Designer of Record (DOR) must utilize UFGS Section 07 05 23, Pressure Testing an Air
Barrier System for Air Tightness,and Contractor must perform testing as described in that specification. Where conflicts exist between the UFGS Section 07 05 23 and this performance specification, UFGS Secction 07 05 23 will govern. The air leak flow rate must not exceed 0.25 CFM at 75 Pa per square foot (0.076 cmm 75 Pa per square meter) of building enclosure area including roof or ceiling, walls and floor as provided by the
DOR.
Method 1: This test consists of measuring the flow rates required to establish 12 positive and 12 negative building pressures from at least 25 Pa to at least 50 Pa. Take at least 12 bias pressure readings across the building enclosure averaged over 5 seconds each before and after the test. None of these readings must exceed 30% of the minimum test pressure.
Method 2: this test consists of measuring the flow rates required to establish 12 positive building pressures from at least 50 Pa to at least 75 Pa. Takeat least 12 bias pressure readings across the building enclosure averaged over 5 seconds each before and after the test. None of these readings must exceed 20% of the minimum test pressure.
The test results must be either pass or fail. Provide the theoretical size of the opening that leaks the same amount as the building enclosure at 75 Pa, to facilitate the search for leaks and repair of the exterior enclosure.
c. Provide infrared thermography to determine air leakage paths if facility fails to retain the required air pressure in the test above. Utilize infrared cameras with a resolution of 0.1 degree C or better.
Perform infrared thermography in accordance with ISO 6781:1983 and American
Society for Testing and Materials (ASTM) C1060 and B20 1.2.4 Thermal Envelope
Performance Testing (Infrared Thermography). Determine air leakage pathways in accordance with ASTM E1186-03 Standard Practices for Air Leakage Site Detection in
Building Envelopes and Air Barrier Systems, and perform corrective work as necessary to achieve the whole building air leakage rate specified.
Modify construction to stop identified air leakage until target is reached. Correct air path leaks at the source of the leak, do not use sealant to close air leakage paths that are required to be opened for maintenance of the facility such as fixtures, switches covers, receptacle covers, access doors, etc.
d. Seal air leaks in the following order of priority:
1. Top of the building. These include attics, roof/wall intersections, penthouse doors and walls, HVAC equipment.
2. Bottom of the building. These include ground floor access doors and inspection hatches, exhaust and air intake vents, service penetrations of enclosure, crawl spaces.
3. Vertical shafts. These include gasket stairwell fire doors, fire hose cabinets and recessed toilet accessories connected to vertical shaft, vertical and horizontal
PART 4 - Page | 16 utility penetrations in service rooms, elevator rooms and shafts.
4. Exterior walls. These include weather strip doors and windows, exhaust fans and ducts, service penetrations, electrical receptacles, wall base.
B20 1.2.6 Required Records for Concrete Wall Panels
a. Cast-in-place - Submit to DOR mandatory batch ticket information as ASTM C 94 for each load of ready-mixed concrete.
b. Submit to DOR commercial testing results in accordance with PCI MNL-117 and as required in paragraph entitled "Sampling and Testing for Precast"
B20 1.2.7 Precast Concrete Wall Panel Surface Finish Sample
Submit to DOR a concrete wall panel sample 12 inches (300 mm) by 12 inches (300 mm) by approximately 1 1/2 inches (38 mm) in thickness, to illustrate quality, color, and texture of both exposed-to-view surface finish and finish of panel surfaces that will be concealed by other construction. Obtain initial approval of color and texture from DOR prior to submission of sample panels.
B20 1.2.7.1 Manufacturing Plant Sampling And Testing for Precast
Plant Quality Control - PCI MNL-117 for PCI enrolled plants. Where panels are manufactured by specialists in plants not currently enrolled in the PCI "Quality Control
Program," provide a product quality control system in accordance with PCI MNL-117 and perform concrete and aggregate quality control testing using an approved, independent commercial testing laboratory. Submit test results to the Contracting
Officer.
a. Aggregate Tests: ASTM C 33. Perform one test for each aggregate size, including determination of the specific gravity.
b. Strength Tests: ASTM C 172. Provide ASTM C 39 and ASTM C 31/C 31M compression tests. Perform ASTM C 143 slump tests. Mold six cylinders each day or for every 20 cubic yards (15 cubic meters) of concrete placed, whichever is greater. Perform strength tests using two cylinders at 7 days and two at 28 days. Cure four cylinders in the same manner as the panels and place at the point where the poorest curing conditions are offered. Moist cure two cylinders and test at 28 days.
c. Changes in Proportions: If, the compressive strength falls below that specified, adjust the mix proportions and water content and make necessary changes in the temperature, moisture, and curing procedures to secure the specified strength.
Notify the Contracting Officer of all changes.
d. Strength Test Results: Evaluate compression test results at 28 days in accordance with ACI 214 using a coefficient of variation of 20 percent.
Evaluate the strength of concrete by averaging the test results (two specimens) of standard cylinders tested at 28 days. Not more than 20 percent of the individual tests must have an average compressive strength less than the specified ultimate compressive strength.
B20 1.2.7.2 Acceptable Appearance
Refer to Architectural Precast Concreteby the Prestressed Concrete Institute, in the
"Acceptability of Appearance" paragraph for reasons to reject precast panels. Panels in place may be rejected for any one of the product defects or installation deficiencies
PART 4 - Page | 17 remaining after repairs and cleaning have been accomplished. "Visible" means visible to a person with normal eyesight when viewed from a distance of 20 feet (6 meters) in broad daylight.
B20 1.2.8 Window Sample Mock-Up
a. Provide mock-up of one (1) typical combination window unit to be used within the project and conduct a field mock-up test in strict compliance with American
Architectural Manufacturers Association (AAMA) 502 method A and method B. Each opening must be tested to achieve performance of American Society of Civil
Engineers (ASCE) 7-02 calculated requirements (PSF or Kg/m2) for water resistance, which must not exceed .667 % of the products capable water based on AAMA 101/I.S.2.
Allowable rates of air leakage for field testing must be 1.5 times applicable AAMA
101/I.S.2 rate for the Product Type and Performance Class.
b. Opening is to be tested under "Quality Control" testing by a designated independent testing agency.
1) Schedule mock-up installation sufficiently in advance of need to allow adequate time for cure of sealants, testing and reconstruction, if needed, without delaying the project.
2) Build mock-up in building enclosure wall in location selected by Owner and Architect.
3) Modify mock-up construction and perform additional tests as required to achieve specified minimum acceptable results. If corrections are not adequate, construct new mock-up, at written direction of Owner and Architect. Co-ordinate construction of mock-up with other involved trades.
4) Approved mock-ups may become part of completed Work if undisturbed at time of
Substantial Completion.
5) Flood test Mock-up window subsill and obtain approval of DOR prior to installing window unit.
B20 1.3 DESIGN SUBMITTALS
Provide design submittals in accordance with PTS Section Z10, General Performance Technical
Specifications, Part 2 Section 01 33 10.05 20, Design Submittal Procedures, Facilities Criteria (FC) 1-300-
09N, Navy and Marine CorpsDesign Procedures, UFC 3-101-01, Architecture,and UFC 3-301-01, Structural Engineering.
In addition, UFGS sections listed below or in the body of the PTS text are to be used by the Designer of
Record (DOR) as a part of the design submittal. If the UFGS products or systems are applicable to the project, the DOR must edit these referenced UFGS sections and submit them as a part of the design submittal specification. Edit the specification sections in accordance with the limitations stated in PTS section Z10, General Performance Technical Specifications.
UFGS Section 08 34 16.10, Steel Sliding Hangar Door
UFGS Section 08 34 16.20, Vertical Lift Fabric Door
B20 1.4 CONSTRUCTION SUBMITTALS
PART 4 - Page | 18 following submittals as a minimum;
Shop drawings for reinforcing steel in masonry walls, doors, door hardware, windows, storefront, curtainwall, glazing, paint, exterior enclosure barrier systems, and visible exterior materials.
All structural elements necessary for construction.
B20 1.4.1 Manufacturer's Verification Inspection Documentation for Galvanized Steel
Submit manufacturer's verification inspection documentation for all galvanized steel in accordance with ASTM A123, ASTM A 153, and ASTM A 653.
B20 1.4.2 Field Inspection of Field-erected Concrete Panels
a. Perform field inspection of panel welded connections. Furnish the services of AWS-certified welding inspector for erection inspections. Welding inspector must visually inspect all welds and identify all defective welds.
b. Notify the DOR in writing of defective welds, bolts, nuts and washers within 7 working days of the date of inspection. Remove all defective connections or welds and re-welded or repaired as required by the DOR.
B20 1.4.3 Sustainable Construction Submittals
Submit sustainable construction submittals in accordance with Part 2 Section 01 33 29.05 20, Sustainability Reporting for Design-Build.
B2010 EXTERIOR WALLS
Provide exterior wall construction that consists of exterior skin system of non-structural outside face elements with rain-screen back-up wall systems that include; flashing (embedded, exposed, and thru-wall), a water resistive barrier, moisture barrier/ vapor retarder (if required), air barrier, and insulation systems with interior skin system materials to provide a protective finish on the inside face of exterior walls. Provide all components necessary for a shingled water resistive barrier to direct water that would penetrate the wall to be directed to the outside of the wall.
Provide exterior enclosure components and barriers in accordance with UFC 3-101-01, Architecture.
Design all work to comply with UFC 3-101-01, Architecture, and UFC 3-301-01, Structural Engineering, and the following requirements:
a. Vapor Pressure and Hygrothermal Analysis - Perform a job specific vapor pressure and hygrothermal analysis in accordance with UFC 3-101-01, Architecture. The conclusion of the analysis must indicate if a moisture barrier/ vapor retarder is required, the appropriate locations of needed moisture barrier/ vapor retarder, and anticipated dew-point locations in the exterior enclosure during different critical times of the year.
b. Wind Loads - Provide wind load calculations for exterior cladding in accordance with UFC 1-200-01 and
UFC 3-301-01 with comparative analysis of the cladding system to be provided.
c. Water Penetration - No water penetration must occur at a pressure of 8 psf (39 Kg/m2) of fixed area when tested in accordance with ASTM E 331.
d. Insulating Value – Comply with UFC 3-101-01, Architecture, for the American Society of Heating, Refrigerating, and Air-Conditioning Engineers (ASHRAE) standards to determine the minimum insulating value of the complete wall system.
B201001 EXTERIOR CLOSURE
B201001 1.1 MASONRY VENEER EXTERIOR WALL CLOSURE COMPONENTS
PART 4 - Page | 19
B201001 1.1.1 General Requirements
a. The masonry veneer includes the non-load bearing exterior walls of the structure, and also includes colored mortar, special shapes such as sills, headers, trim units and copings of brick masonry, precast concrete, concrete masonry units, or other approved materials.
Tie the veneer to the backup wall system with a system that allows the veneer to move independently of the backup wall system, while being structurally supported. Allow for expansion and contraction of the veneer without cracking the exterior material.
b. Use running bond, tooled concave joints and full head joint weeps at 24 inches (610 mm) on center in the course immediately above the base flashing. Where rowlocks are permitted, slope rowlocks and project not less than 1/2 inch (13 mm) beyond the face of the wall to form a wash and drip. Where required, provide colored mortar conforming to
ASTM C270. Provide special shapes where required.
c. Locate expansion/control joints and seal with proper backing material and ASTM C 920 polyurethane sealant, or preformed foam or rubberized expansion joint closure. Conform to UFC 3-101-01 and BIA Technotes 18, 18A. Match joint color of the brick, unless
DOR directs otherwise.
d. Conform to ACI 530.1 for masonry veneer installation, including cold weather construction. Antifreeze admixtures are not to be used.
e. Clean the masonry in accordance with manufacturer's instructions and BIA Technote 20.
f. Utilize BIA Technical Notes to design, detail, and construct…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .