Part 5 01_33_29.05_20.pdf
PDF 105 KB Posted
- Attached to
- Amendment 0005 Updated Evaluation Factors for Install Macro Artifacts Gallery 13 and 14 at Bldg. 1775
- Solicitation number
- N4008020R5255
About this file
This federal solicitation seeks proposals for the fabrication and installation of structural floor supports and large scale museum artifacts at the National Museum of the Marine Corps in Virginia. The scope of work includes fabricating and installing supports for five macro artifacts in Galleries 13 and 14, as well as placing the artifacts on the supports. Interested offerors should submit proposals in response to the requirements and evaluation factors laid out in Amendment 0005. The solicitation was issued by the Naval Facilities Engineering Command on behalf of the Department of the Navy.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USACE / NAVFAC / AFCEC / NASA UFGS- 01 33 29. 05 20 ( Mar ch 2019) Pr epar i ng Act i v i t y: NAVFAC Super sedi ng UFGS- 01 33 29. 05 20 ( Febr uar y 2017)
UNI FI ED FACI LI TI ES GUI DE SPECI FI CATI ONS
Ref er ences ar e i n agr eement wi t h UMRL dat ed Jul y 2019
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 29.05 20
SUSTAINABILITY REPORTING FOR DESIGN-BUILD
03/19
PART 1 GENERAL
1.1 REFERENCES
1.2 SUMMARY
1.3 SUBMITTALS
1.4 GUIDING PRINCIPLES VALIDATION (GPV)
1.4.1 Costs
1.4.2 Calculations
1.4.3 Third Party Certification (TPC) Documentation
1.4.3.1 TPC Registration Required
1.4.3.2 TPC Management and Certification
1.5 SUSTAINABILITY ENOTEBOOK
1.5.1 High Performance Sustainable Building (HPSB) Checklist
1.5.1.1 HPSB Checklist Submittals
1.5.2 Sustainability Action Plan
1.5.3 "S" Submittals for Sustainability Documentation
1.5.4 Sustainability eNotebook Submittal Schedule
1.6 DOCUMENTATION REQUIREMENTS
1.6.1 Integrated Design Process
1.6.1.1 Design Submittal Documentation
1.6.2 Commissioning (Cx)
1.6.3 Optimize Energy Performance
1.6.3.1 Design Submittal Documentation
1.6.3.2 Construction Submittal Documentation
1.6.4 Energy Efficient Products
1.6.5 On-site Renewable Energy Generation
1.6.5.1 Design Submittal Documentation
1.6.6 Solar Domestic Hot Water (SDHW)
1.6.6.1 Design Submittal Documentation
1.6.7 Building-level Power Metering
1.6.7.1 Design Submittal Documentation
1.6.8 Indoor Water Use
1.6.8.1 Construction Submittal Documentation
1.6.9 Indoor Water Metering
1.6.9.1 Design Submittal Documentation
1.6.10 Outdoor Water Use
SECTION 01 33 29.05 20 Page 1
1.6.10.1 Design Submittal Documentation
1.6.11 Outdoor Water Meters
1.6.11.1 Design Submittal Documentation
1.6.12 Alternative Water
1.6.12.1 Design Submittal Documentation
1.6.13 Stormwater Management
1.6.14 Ventilation and Thermal Comfort
1.6.14.1 Design Submittal Documentation
1.6.15 Daylighting
1.6.15.1 Design Submittal Documentation
1.6.16 Moisture Control
1.6.16.1 Design Submittal Documentation
1.6.17 Reduce Volatile Organic Compounds (VOC) (Low-Emitting
Materials)
1.6.18 Indoor Air Quality During Construction
1.6.19 Recycled Content
1.6.19.1 Construction Submittal Documentation
1.6.20 Bio-Based Products
1.6.21 Waste Material Management (Recycling – Design)
1.6.22 Waste Material Management (Recycling – Construction)
1.6.23 Address Climate Change Risk
1.6.24 Validation and Certification Restrictions
1.6.25 Additional Sustainability Requirements
1.6.25.1 [_____]
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 SUSTAINABILITY COORDINATION
3.1.1 Coordinating Sustainability Documentation Progress
3.1.1.1 Design Review Meetings
3.1.1.2 Construction Progress Meetings
3.2 THIRD PARTY CERTIFICATION CERTIFICATE, ASSESSMENT, OR VALIDATION
3.3 TABLE 3-1 VOLATILE ORGANIC COMPOUNDS (VOC) (LOW EMITTING
MATERIALS) REQUIREMENTS
-- End of Section Table of Contents --
SECTION 01 33 29.05 20 Page 2
USACE / NAVFAC / AFCEC / NASA UFGS- 01 33 29. 05 20 ( Mar ch 2019) Pr epar i ng Act i v i t y: NAVFAC Super sedi ng UFGS- 01 33 29. 05 20 ( Febr uar y 2017)
UNI FI ED FACI LI TI ES GUI DE SPECI FI CATI ONS
Ref er ences ar e i n agr eement wi t h UMRL dat ed Jul y 2019
SECTION 01 33 29.05 20
SUSTAINABILITY REPORTING FOR DESIGN-BUILD
03/19
NOTE: Thi s gui de speci f i cat i on cover s t he r equi r ement s f or pr ovi di ng sust ai nabi l i t y document at i on f or Gui di ng Pr i nci pl es Val i dat i on ( GPV) and Thi r d Par t y Cer t i f i cat i on ( TPC) . GPV i s equi val ent t o meet i ng t he r equi r ement s of UFC
1- 200- 02 " HI GH PERFORMANCE AND SUSTAI NABLE BUI LDI NG
REQUI REMENTS. " Al l pr oj ect s must meet t he r equi r ement s of UFC 1- 200- 02.
Use a pr oper l y edi t ed ver si on of t hi s gui de speci f i cat i on f or pr oj ect s t hat cont ai n one or mor e bui l di ngs wi t h any of t he f ol l owi ng: new bui l di ng;
st and- al one addi t i on ( scoped t o f unct i on l i ke st and- al one new bui l di ngs, except i t i s at t ached t o an exi st i ng bui l di ng. ) l ar ger t han 5, 000 SF; or i n an exi st i ng bui l di ng r enovat i on wi t h t ot al cost ( i ncl udes new wor k, r enovat i on, oper at i ons and mai nt enance; sust ai nment r est or at i on, and moder ni zat i on associ at ed wi t h an exi st i ng bui l di ng r enovat i on) gr eat er t han $3M, r egar dl ess of per cent age of Est i mat ed Repl acement Cost ( ERC) or squar e f oot age.
Use t he HPSB Checkl i st f or t he Ser vi ce who wi l l mai nt ai n t he bui l di ng asset i n t hei r Real Pr oper t y Recor d. Compl et e t he HPSB Checkl i st f or each appl i cabl e bui l di ng i n t he pr oj ect , bef or e at t achi ng t o t hi s speci f i cat i on. Check wi t h t he user Command f or addi t i onal r equi r ement s.
( Wher e I nt er net addr ess appear s on mul t i pl e l i nes, copy f ul l addr ess i nt o I nt er net br owser : )
a. Navy – Compl et e t he NAVFAC Hi gh Per f or mance and Sust ai nabl e Bui l di ng ( HPSB) Checkl i st . Templ at e can be downl oaded f r om t he pr oj ect ' s ePr oj ect s r ecor d, or f r om:
http://www.wbdg.org/ffc/navy-navfac/sustainable-development-program/required-tracking
b. Ai r For ce - Use " AF Sust ai nabi l i t y Requi r ement s
SECTION 01 33 29.05 20 Page 3
Scor esheet , GP ver si on" f or appl i cabl e pr oj ect s wi t h desi gn st ar t s 01Dec16 or af t er :
http://www.wbdg.org/ffc/af-afcec/sustainable-design-development-sdd/sustainability-tracking-reporting
c. Ar my - Ener gy & Sust ai nabi l i t y Recor d Car d http://www.wbdg.org/ffc/army-coe/policies-and-guidance-army-design-and-construction/army-energy-sustain-record-card
Adher e t o UFC 1-300-02 Uni f i ed Faci l i t i es Gui de Speci f i cat i ons ( UFGS) For mat St andar d when edi t i ng t hi s gui de speci f i cat i on or pr epar i ng new pr oj ect speci f i cat i ons sect i ons. Edi t t hi s gui de speci f i cat i on f or pr oj ect speci f i c r equi r ement s by addi ng, del et i ng, or r evi s i ng t ext . For br acket ed i t ems, choose appl i cabl e i t em( s) or i nser t appr opr i at e i nf or mat i on.
Remove i nf or mat i on and r equi r ement s not r equi r ed i n r espect i ve pr oj ect , whet her or not br acket s ar e present.
Comment s, suggest i ons and r ecommended changes f or t hi s gui de speci f i cat i on ar e wel come and shoul d be submi t t ed as a Criteria Change Request (CCR) .
Thi s speci f i cat i on i s f or use on Navy desi gn- bui l d pr oj ect s, and cont ai ns bot h desi gn and const r uct i on r equi r ement s. Do not use, or r equi r e t he use of , UFGS Sect i on 01 33 29 SUSTAI NABI LI TY REPORTI NG.
PART 1 GENERAL
1.1 REFERENCES
NOTE: Thi s par agr aph i s used t o l i s t t he publ i cat i ons c i t ed i n t he t ext of t he gui de speci f i cat i on. The publ i cat i ons ar e r ef er r ed t o i n t he t ext by basi c desi gnat i on onl y and l i s t ed i n t hi s par agr aph by or gani zat i on, desi gnat i on, dat e, and t i t l e.
Use t he Ref er ence Wi zar d' s Check Ref er ence f eat ur e when you add a Ref er ence I dent i f i er ( RI D) out si de of t he Sect i on' s Ref er ence Ar t i c l e t o aut omat i cal l y pl ace t he r ef er ence i n t he Ref er ence Ar t i c l e. Al so use t he Ref er ence Wi zar d' s Check Ref er ence f eat ur e t o updat e t he i ssue dat es.
Ref er ences not used i n t he t ext wi l l aut omat i cal l y be del et ed f r om t hi s sect i on of t he pr oj ect speci f i cat i on when you choose t o r econci l e r ef er ences i n t he publ i sh- pr i nt pr ocess.
The publications listed below form a part of this specification to the
SECTION 01 33 29.05 20 Page 4 extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE 90.1 - IP (2013) Energy Standard for Buildings Except Low-Rise Residential Buildings
ASHRAE 90.1 - SI (2013) Energy Standard for Buildings Except Low-Rise Residential Buildings
ASHRAE 189.1 (2014) Standard for the Design of High-Performance Green Buildings Except Low-Rise Residential Buildings
COUNCIL ON ENVIRONMENTAL QUALITY (CEQ) (WHITE HOUSE)
HPSB Guiding Principles (2016) Guiding Principles for Sustainable Federal Buildings and Determining Compliance with the Guiding Principles for Sustainable Federal Buildings
GREEN BUILDING INITIATIVE (GBI)
GBI GP Compliance (2016) GBI Guiding Principles Compliance Program for New Construction (DOD Version)
GBI Green Globes for NC (2017) Green Globes(tm) for New Construction Technical Reference Manual
GREEN BUSINESS CERTIFICATION INC. (GBCI)
GP Assessment (DOD) Guiding Principles Assessment for Department of Defense
SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION
(SMACNA)
ANSI/SMACNA 008 (2007) IAQ Guidelines for Occupied Buildings Under Construction, 2nd Edition
U.S. DEPARTMENT OF AGRICULTURE (USDA)
FSRIA 9002 Farm Security and Rural Investment Act Section 9002 (USDA Biopreferred Program)
U.S. DEPARTMENT OF DEFENSE (DOD)
FC 1-300-09N (2014; with Change 4, 2018) Navy and Marine Corps Design
U.S. DEPARTMENT OF ENERGY (DOE)
Energy Star (1992; R 2006) Energy Star Energy Efficiency Labeling System (FEMP)
SECTION 01 33 29.05 20 Page 5
U.S. GREEN BUILDING COUNCIL (USGBC)
LEED v4 BDC LEED v4 Building Design and Construction
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
10 CFR 433.300 Subpart C - Green Building Certification for Federal Buildings
40 CFR 247 Comprehensive Procurement Guideline for Products Containing Recovered Materials
1.2 SUMMARY
This specification includes general requirements and procedures for this project to be designed, constructed, and documented per the federally mandated High Performance and Sustainable Building or "HPSB Guiding Principles" (GP), [Third Party Certification (TPC) requirements], UFC 1-200-02 High Performance and Sustainable Building Requirements, and other requirements identified in this specification.
1.3 SUBMITTALS
NOTE: Submi t t al s must be l i mi t ed t o t hose necessar y f or adequat e qual i t y cont r ol . The i mpor t ance of an i t em i n t he pr oj ect shoul d be one of t he pr i mar y f act or s i n det er mi ni ng i f a submi t t al f or t he i t em shoul d be r equi r ed.
A " G" f ol l owi ng a submi t t al i t em i ndi cat es t hat t he submi t t al r equi r es Gover nment appr oval . Some submi t t al s ar e al r eady mar ked wi t h a " G" . Onl y del et e an exi st i ng " G" i f t he submi t t al i t em i s not compl ex and can be r evi ewed t hr ough t he Cont r act or ' s QC syst em. Onl y add a " G" i f t he submi t t al i s suf f i c i ent l y i mpor t ant or compl ex i n cont ext of t he project.
The " S" f ol l owi ng a submi t t al i t em i ndi cat es t hat t he submi t t al i s r equi r ed f or t he Sust ai nabi l i t y eNot ebook t o f ul f i l l f eder al l y mandat ed sust ai nabl e r equi r ement s i n accor dance wi t h Sect i on 01 33 29
SUSTAI NABI LI TY REPORTI NG.
Revi ew submi t t al descr i pt i on ( SD) def i ni t i ons i n Section 01 33 00. 05 20 CONSTRUCTI ON SUBMI TTAL PROCEDURES and edi t t he f ol l owi ng l i s t t o r ef l ect onl y t he submi t t al s r equi r ed f or t he pr oj ect .
NOTE: Sust ai nabi l i t y r equi r ement s have been i dent i f i ed i n many of t he t echni cal per f or mance sect i ons. I ncl ude addi t i onal sust ai nabi l i t y r equi r ement s t hr oughout t he t echni cal speci f i cat i on sect i ons accor di ng t o goal s of t hi s pr oj ect .
I dent i f y pr oduct s and ot her submi t t al s r equi r ed f or Gui di ng Pr i nci pl e Val i dat i on ( GPV) and Thi r d Par t y Cer t i f i cat i on ( TPC) wher e appl i cabl e, wi t h an " S" next t o t he submi t t al i t em. Use t he f ol l owi ng
SECTION 01 33 29.05 20 Page 6 f or mat t o add submi t t al i t ems i n t he t echni cal sect i ons t o compl y wi t h t he r equi r ement s of t hi s section:
I nser t Submi t t al I t em; S
" S" submi t t al s ar e pr ocessed as descr i bed i n Sections 01 33 10. 05 20 DESI GN SUBMI TTAL PROCEDURES and 01 33 00. 05 20 CONSTRUCTI ON SUBMI TTAL PROCEDURES. Edi t t he f ol l owi ng l i s t t o r ef l ect onl y t he submi t t al s r equi r ed f or t he pr oj ect .
Make cor r espondi ng edi t s i n t he t echni cal sect i ons' Par t 2 Pr oduct s or i n Par t 3 Execut i on t o di f f er ent i at e t hose pi eces of equi pment , pr oduct s, or act i v i t i es r el at ed t o GPV and TPC.
Submittals requirements are specified in the technical sections using Submittal Description (SD) numbers and titles. Submittals requiring Government approval use a "G" or submittal designator in the UFGS sections. In addition, submit the GPV[and TPC]-required sustainability documentation in this specification as "S" submittals. Submittals not having a "G" designation are for Contractor Quality Control approval.
Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with the requirements of this Section.
Government approval is required for submittals in RFP Part 2 with a "G" designation. Additional construction submittals reserved for Government approval are listed in the Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES. Submittals with a "G" designation found in the sections used by the Contractor to create construction specification, require DOR approval.
DOR approved submittals are also listed in the "Construction Submittals" paragraph in each RFP PART 4, Performance Technical Specifications.
Provide required certification or validation submittals in accordance with Section 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES, Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES, FC 1-300-09N , Navy and Marine Corps Design Procedures, and as identified below.
NOTE: For pr oj ect s t hat r equi r e an i nt er i m Gover nment r evi ew pr i or t o SD- 11 Fi nal Sust ai nabi l i t y eNot ebook Submi t t al , and wi t h suf f i c i ent i n- house Gover nment r esour ces avai l abl e t o det er mi ne submi t t al appr oval , keep " G" submi t t al act i on code f or r equi r ed SD- 01 and SD- 05 Hi gh Per f or mance and Sust ai nabl e Bui l di ng Checkl i st and Sust ai nabi l i t y eNot ebook Submi t t al s.
SD-01 Preconstruction Submittals
Preliminary High Performance and Sustainable Building Checklist [; G
Sustainability Action Plan
SECTION 01 33 29.05 20 Page 7
[ Preliminary Sustainability eNotebook [; G]
] SD-05 Design Data
[ Final Design High Performance and Sustainable Building Checklist [;
G]
][ Final Design Sustainability eNotebook [; G]
] SD-11 Closeout Submittals
Final High Performance and Sustainable Building Checklist ; G
Final Sustainability eNotebook ; G
[ Amended Final Sustainability eNotebook ; G
] Amended Final High Performance and Sustainable Building Checklist ;
G
NOTE: Choose br acket ed opt i on f or " Thi r d Par t y Cer t i f i cat i on Cer t i f i cat e, Assessment , or Val i dat i on" f or TPC pr oj ect s.
[ Third Party Certification Certificate, Assessment, or Validation ; G
] 1.4 GUIDING PRINCIPLES VALIDATION (GPV)
NOTE: GUI DI NG PRI NCI PLES VALI DATI ON ( GPV) i s r equi r ed f or al l bui l di ngs ( ver t i cal const r uct i on) i n accor dance wi t h UFC 1- 200- 02 HI GH PERFORMANCE SUSTAI NABLE BUI LDI NG REQUI REMENTS and t he not es under t hi s speci f i cat i on' s t i t l e above.
Compl et e Pr el i mi nar y HPSB Checkl i st and i ncl ude at t he end of t hi s speci f i cat i on. For pr oj ect s wi t h mul t i pl e bui l di ngs, at t ach HPSB Checkl i st f or each bui l di ng. Obt ai n HPSB checkl i st f r om r espect i ve agency. See t he not es under t hi s speci f i cat i on' s t i t l e above.
Provide sustainability documentation to verify achievement of HPSB Guiding Principles Validation (GPV).
Provide the following for GPV:
a. Refer to HPSB Checklist at the end of this specification section.
These requirements are based on legislative mandates that must be met by all projects. (Multiple checklists indicate multiple buildings that require individual HPSB Checklist tracking.)
b. No changes to the HPSB Checklist are allowed without approval from the Contracting Officer, in accordance with Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES and Section 01 33 10.05 20 DESIGN
SECTION 01 33 29.05 20 Page 8
SUBMITTAL PROCEDURES, paragraph DESIGN CHANGE AND VARIATION.
Immediately bring to the attention of the Contracting Officer any project changes that impact meeting the approved HPSB Guiding Principles Requirements for this project.
c. All work, including "S" submittals, required to incorporate the applicable HPSB Guiding Principles Requirements indicated on the HPSB Checklist and in this contract.
d. Sustainable Action Plan.
e. Design and construction related documentation for the project Sustainability eNotebook, and keep updated with regularly-scheduled construction meetings. Include design and construction related documentation containing the following components;
(1) HPSB Checklist
(2) Sustainability Action Plan
(3) Documentation illustrating HPSB Guiding Principle Requirements compliance (including "S" submittals)
1.4.1 Costs
Bear all costs associated with designing, constructing, demonstrating and documenting that project complies with approved HPSB Guiding Principles Requirements.
1.4.2 Calculations
Provide all design data, calculations, product data, labels and product certifications required in this specification to demonstrate compliance with the HPSB Guiding Principles Requirements.
NOTE: I n addi t i on t o GPV and Sust ai nabi l i t y eNot ebook, Thi r d Par t y Cer t i f i cat i on ( TPC) i s r equi r ed f or pr oj ect s t hat meet t he t hr eshol ds c i t ed i n Tabl e 1- 1 of UFC 1- 200- 02.
1. Each new bui l di ng wi t h const r uct i on cost gr eat er t han $3M.
2. I n exi st i ng bui l di ng over 5, 000 SF, r enovat i on wi t h t ot al cost gr eat er t han $3M and 50 per cent or mor e of t he Est i mat ed Repl acement Cost ( ERC) .
TPC i s t he gener i c t er m f or a t hi r d par t y pr oduct t hat pr ovi des ei t her cer t i f i cat i on of t he t hi r d par t y vendor ' s pr opr i et ar y pr oduct r equi r ement s ( exampl es LEED, Gr een Gl obes) , or a val i dat i on pr ogr am by t he t hi r d par t y vendor t hat UFC 1- 200- 02 r equi r ement s have been met ( exampl es: Gui di ng Pr i nci pl es Assessment , Gui di ng Pr i nci pl es Compliance).
SECTION 01 33 29.05 20 Page 9
[ 1.4.3 Third Party Certification (TPC) Documentation
NOTE: Choose t he r at i ng syst em bel ow t hat best assi st s wi t h Gui di ng Pr i nci pl es Val i dat i on, and del et e t he ot her s. I f Navy i s execut i ng desi gn and const r uct i on f or Ar my or Ai r For ce, ver i f y r at i ng syst ems appr oved f or use by Ser vi ce.
For Ai r For ce ONLY: Choose one of t he f ol l owi ng met hods f or execut i ng TPC:
a. For Gui di ng Pr i nci pl es Assessment f or Depar t ment of Def ense ( by GBCI ) , choose " GP Assessment ( DoD) " , use onl y DOD ver si on, and ask f or i t when registering.
b. For Gr een Bui l di ng I ni t i at i ve ( GBI ) Depar t ment of Def ense Gui di ng Pr i nci pl es Compl i ance, or " GBI GP Compl i ance" , use onl y DOD ver si on, and ask f or i t when r egi st er i ng.
For Ar my pr oj ect s ONLY: Choose onl y t he f ol l owi ng met hod f or execut i ng TPC:
a. For USGBC LEED v4, choose " LEED v4 BDC" , and ent er " Si l ver " i n t he br acket . For use of al t er nat e cer t i f i cat i on syst ems, a wai ver must be submi t t ed per t he cur r ent Ar my Sust ai nabl e Desi gn and Devel opment Pol i cy.
For Navy ONLY: Choose one of t he f ol l owi ng met hods f or execut i ng TPC:
a. For USGBC LEED v4, choose " LEED v4 BDC" , and ent er t he t ar get l evel i n t he br acket .
b. For Gui di ng Pr i nci pl es Assessment f or Depar t ment of Def ense ( by GBCI ) , choose " GP Assessment ( DoD) " , use onl y DoD ver si on, and ask f or i t when registering.
c. For Gr een Bui l di ng I ni t i at i ve ( GBI ) Depar t ment of Def ense Gui di ng Pr i nci pl es Compl i ance, or " GBI GP Compl i ance" , use onl y DoD ver si on, and ask f or i t when r egi st er i ng.
d. For " GBI Gr een Gl obes f or NC" , ent er t he t ar get l evel i n t he br acket .
e. For an al t er nat e cer t i f i cat i on syst em, use onl y t hose t hat compl y wi t h t he mi ni mum r equi r ement s of 10 CFR 433. 300 Subpar t C — Gr een Bui l di ng Cer t i f i cat i on f or Feder al Bui l di ngs, and i nser t t he name of t he compl i ant syst em i n t he empt y br acket .
Faci l i t i es Engi neer i ng Command ( FEC) Capi t al I mpr ovement s ( CI ) Cor e must aut hor i ze t he use of al t er nat i ve syst em.
SECTION 01 33 29.05 20 Page 10
Obt ai n, f i l l out , and i ncl ude TPC checkl i st wi t h t hi s UFGS. For pr oj ect s wi t h mul t i pl e bui l di ngs, at t ach TPC Checkl i st f or each bui l di ng t hat r equi r es
TPC.
For cer t i f i cat i ons, assessment s, or val i dat i ons t hat i ncl ude a pl aque, i ncl ude t he br acket ed phr ase i n t he f i r st par agr aph.
1.4.3.1 TPC Registration Required
Register and achieve Third Party Certification (TPC), by meeting all TPC and project requirements for a level of [ LEED v4 BDC [_____]] [ GP Assessment (DOD) ] [ GBI GP Compliance ] [ GBI Green Globes for NC [_____]] [[_____][_____]], or Government-approved equivalent TPC sustainability certification, assessment, or validation. An equivalent TPC organization must demonstrate equivalency for Government consideration and meet the requirements of 10 CFR 433.300 , prior to use on the project. Third Party Certification is met when Government receives TPC organization certificate, assessment, or validation[ and plaque].
Third Party Certification certificate, assessment, or validation requirements are in addition to all requirements under header above
GUIDING PRINCIPLES VALIDATION (GPV).
Register project with TPC organization using the following format and content:
a. Project Title First Line: US Army, US Air Force, US Navy or US Marine Corps, Building Name (if known)
b. Project Title Second Line: MILCON P#, DD1391 Project Name
c. Project Address: UIC (Installation code), Category code, RPUID (Real Property Unique Identifier) Number
d. Project Owner Organization: US Army, US Air Force, US Navy or US Marine Corps
e. Primary Contact, Owner: Executing DoD Service's Project Manager or Design Manager
f. Building Owner Organization: US Navy; US Marine Corps; US Army; US Air Force
g. Building Owner Organization Project Number
h. Additional Contact, Building Owner: Base Civil Engineer (Air Force), Department of Public Works (Army), Public Works Officer (Navy), or Designee.
1.4.3.2 TPC Management and Certification
Execute the following TPC Certification, assessment, or validation requirements:
a. Refer to TPC Checklist at the end of this specification section.
(Multiple checklists indicate multiple buildings that require TPC.)
SECTION 01 33 29.05 20 Page 11
b. Immediately bring to the attention of the Contracting Officer any project changes that impact meeting the approved TPC Requirements for this project.
c. Complete all design and construction work to incorporate the applicable TPC Requirements.
d. Maintain the design and construction related information, and provide replacement pages, in the Sustainability eNotebook pertaining to additions and changes to the approved sustainability requirements.
Maintain the Sustainability eNotebook in electronic format. Refer to explanation in the paragraph SUSTAINABILITY eNOTEBOOK. Provide the following components in the Sustainability eNotebook, in addition to the GPV components listed above:
(1) TPC Checklist
(2) Completed TPC [Online ]forms for each identified prerequisite and credit.[ Upload onto the TPC Online documentation website.]
(3) Copy of all correspondence with the TPC organization. Provide proof of TPC registration.
(4) Documentation illustrating compliance with TPC requirements and additional documentation as requested by the Third Party certifier.
(5) TPC Award Certificate or validation
e. Provide the following information in the Sustainability Action Plan.
Provide this TPC information in addition to the Sustainability Action Plan items above:
(1) Planned method to achieve each TPC requirement.
(2) Provide analysis of each TPC credit and how project will comply.
(3) Provide names and contact information for: Contractor sustainability point of contact (POC) and other names of sustainability professionals on the Contractor's Staff responsible for ensuring TPC sustainability goals are accomplished and documentation is assembled.
NOTE: For cer t i f i cat i ons, assessment s, or val i dat i ons t hat i ncl ude a pl aque, i ncl uded t he br acket ed phr ase.
f. Bear all costs associated with designing, constructing, demonstrating and documenting that project complies with approved TPC requirements, including but not limited to:
(1) Registration, review, certification, assessment, or validation[ and plaque] fees.
(2) Online (or offline with secure facilities) TPC management and documentation.
(3) Obtaining TPC certification, assessment, or validation based on
SECTION 01 33 29.05 20 Page 12
Government-approved sustainability goals.
(4) Design and construction work required to incorporate TPC requirements.
(5) Submittals required to demonstrate compliance with Government approved TPC checklists.
g. Provide all design data, calculations, product data, and certifications, assessments, or validations required in this specification to demonstrate compliance with the TPC Requirements.
h. Provide all online (or offline, with secure facilities) TPC management and documentation.
i. Provide all required responses to third party organization.
NOTE: I ncl ude t he br acket ed par agr aph bel ow f or TPC t hat i ncl udes r equi r ed si t e v i s i t by a TPC r epr esent at i ve. Coor di nat e wi t h t he TPC r epr esent at i ve, Pr oj ect Manager , Desi gn Manager , and Const r uct i on Manager t o det er mi ne par t i c i pat i ng t eam member s. I ncl ude CxA on appl i cabl e pr oj ect s.
For pr oj ect s t hat r equi r e t he Const r uct i on Cont r act or t o obt ai n TPC, t he Const r uct i on Cont r act or ’ s desi gnat ed Sust ai nabi l i t y POC i s r esponsi bl e t o coor di nat e t he TPC si t e v i s i t .
[ j. Facilitate and participate in required TPC site visit. Coordinate with the Executing DoD Service's Project Manager and Design Manager, to determine participating team members. Include Commissioning Authority (CxA) on applicable projects.
NOTE: I ncl ude t he br acket ed par agr aph bel ow f or TPC t hat i ncl ude a cer t i f i cat i on, assessment , or val i dat i on. For TPC t hat i ncl ude a pl aque, i ncl ude t he br acket ed phr ases.
[ k. Provide TPC [Plaque and ]Certificate, assessment, or validation. Use the following format to create the Plaque, Certificate, assessment, or validation and Letter of Congratulations. Forward to parties designated by Contracting Officer:
[ (1) Plaque:
Name: Final Building Name. If unknown, use the Form DD1391 Project Name.
] (2) Certificate, Assessment, or Validation:
Project title, first line: P-(X); (1391 Project Name). Project title, second line: UIC (installation code)
SECTION 01 33 29.05 20 Page 13
(3) Letter of Congratulation (when provided):
Address letter to the Facility's Installation Commander Name.
Address the letter to an individual person.
] l. Once Final Certification is achieved, turn over Administrative rights to online TPC to the Base Civil Engineer (Air Force), Department of Public Works (Army), Public Works Office (Navy), or designee, contact information provided by the Contracting Officer.
] 1.5 SUSTAINABILITY ENOTEBOOK
NOTE: I ncl ude t he br acket ed TPC phr ases f or pr oj ect s r equi r ed t o obt ai n TPC.
The Sustainability eNotebook is an electronic organizational file that serves as a repository for all required sustainability submittals. To support documentation of compliance with an approved HPSB[ and TPC] checklist, provide and maintain a comprehensive and current Sustainability eNotebook. Sustainability eNotebook must contain all required data to support full compliance with the HPSB Guiding Principles Requirements, including:
a. HPSB checklist
b. Sustainable Action Plan
c. calculations
d. labels
e. "S" submittals (sustainability documentation requirements)
[ f. Certifications, assessments, or validations
][ g. TPC documentation required in paragraph THIRD PARTY CERTIFICATION (TPC) above.
] Provide Sustainability eNotebook in the form of an Adobe PDF file;
bookmark each HPSB Guiding Principles Requirement[, TPC requirement,] and sub-bookmark at each document. Match format to HPSB Guiding Principles numbering system indicated herein. Maintain up-to-date information, such as spreadsheets, templates, with each current submittals.[ For TPC projects, provide a second Table of contents using TPC numbering system, for maintaining documentation unique to TPC.]
Contracting Officer may deduct from the monthly progress payment accordingly if Sustainability eNotebook information is not current, until information is updated and on track per project goals.
1.5.1 High Performance Sustainable Building (HPSB) Checklist
Provide documentation that provides proof of and supports compliance with the completed HPSB Checklist.
SECTION 01 33 29.05 20 Page 14
1.5.1.1 HPSB Checklist Submittals
[Submit updated HPSB Checklist with each Sustainability eNotebook submittal. ]Attach final HPSB Checklist to each DD1354 Real Property Record Submittal.
1.5.2 Sustainability Action Plan
Include the following information in the Sustainability Action Plan:
a. Planned method to achieve each GP requirement.
b. Provide analysis of each HPSB Guiding Principles Requirement and how project will comply. Final government approved narrative(s) must be included in the HPSB Checklist submittal.
c. Name and contact information for: Contractor's Point of Contact (POC) ensuring sustainability goals are accomplished and documentation is assembled. For TPC that include on-site visit by third party representative, provide list of required attendees.
d. Include the Indoor Air Quality plan with the Sustainability Action Plan.
1.5.3 "S" Submittals for Sustainability Documentation
NOTE: I ncl ude t he br acket ed phr ases bel ow f or pr oj ect s r equi r ed t o obt ai n TPC.
Submit the GPV[ and TPC] sustainability documentation required in this specification as "S" submittals in all affected UFGS Sections.
a. Highlight GPV[ and TPC] compliance data in "S" submittal.
b. Add "S" submittals to the Sustainability eNotebook only after submittal approval, and bookmark them as required in paragraph SUSTAINABILITY ENOTEBOOK below.
c. Ensure all approved "S" submittals (the sustainability documentation requirements) are included in each Sustainability eNotebook submittal.
1.5.4 Sustainability eNotebook Submittal Schedule
Provide Sustainability eNotebook Submittals at the following milestones of the project:
NOTE: For pr oj ect s t hat r equi r e an i nt er i m Gover nment r evi ew bef or e t he Fi nal Sust ai nabi l i t y eNot ebook Submi t t al , and wi t h suf f i c i ent i n- house Gover nment r esour ces avai l abl e t o det er mi ne submi t t al appr oval , keep one or bot h of t he f ol l owi ng par agr aphs.
I ncl ude t he f i r st br acket ed phr ase f or pr oj ect s r equi r ed t o obt ai n TPC.
SECTION 01 33 29.05 20 Page 15
[ a. Preliminary Sustainability eNotebook
Submit preliminary Sustainability eNotebook with updated Preliminary High Performance and Sustainable Building Checklist [ and TPC checklist] for approval at the Post award Kickoff meeting (PAK), in accordance with Section 01 31 19.05 20 POST AWARD MEETINGS.
NOTE: I ncl ude t he f i r st br acket ed phr ase f or pr oj ect s r equi r ed t o obt ai n TPC.
I ncl ude t he number of el ect r oni c copi es i n t he br acket ed phr ase.
][ b. Final Design Sustainability eNotebook
Submit updated Sustainability eNotebook with updated Final Design High Performance and Sustainable Building Checklist [ with TPC Checklist] with the final design, in accordance with Section 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES. If issues relating to achieving the sustainability goals of the project are subsequently identified, identify reasons and mitigation from DOR, and resubmit[ [_____] electronic copies on DVDs ]to the Contracting Officer for approval.
NOTE: I ncl ude t he br acket ed phr ases f or pr oj ect s r equi r ed t o obt ai n TPC.
c. Construction Progress Meetings.
Provide up-to-date GP[ and TPC] documentation in the Sustainability eNotebook[ and TPC Online tool] for each meeting.
NOTE: I ncl ude t he f i r st br acket ed phr ase f or pr oj ect s r equi r ed t o obt ai n TPC.
I ncl ude t he number of el ect r oni c copi es i n t he second br acket ed phr ase.
d. Final Sustainability eNotebook
Submit updated Sustainability eNotebook with updated Final High Performance and Sustainable Building Checklist [ with TPC Checklist], in accordance with Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES at Beneficial Occupancy Date (BOD). Final progress payment retainage may be held by Contracting Officer until Final Sustainability construction phase documentation is complete. Obtain DOR approval and submit [_____] electronic copies on DVDs to the Contracting Officer for approval.
NOTE: I ncl ude t he f ol l owi ng par agr aph when an amended Sust ai nabi l i t y eNot ebook i s r equi r ed ( due t o post - const r uct i on act i v i t i es such as commi ssi oni ng) .
SECTION 01 33 29.05 20 Page 16
I ncl ude t he f i r st br acket ed phr ase f or pr oj ect s r equi r ed t o obt ai n TPC.
I ncl ude t he number of el ect r oni c copi es i n t he second br acket ed phr ase.
[ e. Amended Final Sustainability eNotebook
Amend and resubmit the Amended Final Sustainability eNotebook with Amended Final High Performance and Sustainable Building Checklist [ and amended TPC Checklist], to include post-occupancy corrections, updates, and requirements. Final progress payment retainage may be held by Contracting Officer until amended final sustainability documentation is complete. Submit [_____] final electronic copies of the Amended Final Sustainability eNotebook Submittal on DVDs to the Contracting Officer no longer than 30 days after the GP[, TPC] designated data collection period.
] 1.6 DOCUMENTATION REQUIREMENTS
a. Incorporate each of the following HPSB Guiding Principles requirements into project and provide documentation that proves compliance with each listed requirement. Items below are organized by HPSB Guiding Principles . For life-cycle cost analysis requirements, one document with all analyses is acceptable, with Contracting Officer approval.
b. For each of the following paragraphs that require the use of products listed on Government-required websites, provide documentation of the process used to select products, or process used to determine why listed products do not meet project performance requirements.
NOTE: The f ol l owi ng subpar agr aphs pr ovi de Gui di ng Pr i nci pl e Requi r ement s.
Keep r equi r ement s t hat can be f ul l y achi eved, or par t i al l y achi eved t o t he gr eat est degr ee possi bl e.
For par t i al l y achi evabl e r equi r ement s, t r ack t hem as " yes" onl y wi t h one of t he f ol l owi ng j ust i f i cat i ons:
1. Li f e- cycl e cost ef f ect i veness ( an LCCA i s r equi r ed as pr oof f or j ust i f y i ng mi ssed ener gy or wat er t ar get s) ;
2. Mi ssi on r est r i ct i on ( ex: 24/ 7 oper at i on) ;
3. Locat i on/ r egi onal r est r i ct i on ( ex: avai l abi l i t y of hi gh- ef f i c i ency equi pment ser vi ce) ;
4. Local e r est r i ct i on ( ex: pr oxi mi t y of exi st i ng bui l di ngs r est r i ct s dayl i ght i ng) .
Del et e r equi r ement s t hat ar e not appl i cabl e t o t he pr oj ect . Non- appl i cabi l i t y r equi r es one of t he f ol l owi ng j ust i f i cat i ons:
1. Li f e- cycl e cost ef f ect i veness ( an LCCA i s r equi r ed as pr oof f or j ust i f y i ng mi ssed ener gy or wat er t ar get s) ;
SECTION 01 33 29.05 20 Page 17
2. Mi ssi on excl usi on ( ex: no dayl i ght i ng i n a t heat er or a SCI F) ;
3. Locat i on/ r egi onal excl usi on ( ex: no l ocal r ecycl i ng f aci l i t y) ; or
4. Local e excl usi on ( ex: t her e i s no st eam t o meter).
1.6.1 Integrated Design Process
For the submittal documentation below, follow the steps of design optimization, as applicable, in ASHRAE 189.1 Section F1.1.1 (Charrette Process), with the exception that F1.1.1, b. does not apply.
1.6.1.1 Design Submittal Documentation
a. Provide listing the sustainability integrated design team, and a description of their roles in all stages of a project's planning and delivery:
(1) Include Contractor's Sustainability Coordinators; Architecture and Engineering disciplines involved on the project, and the DOR in charge of the overall project and each discipline; Construction Subcontractors and the company representatives that align with each architectural and engineering discipline, Planning, Public Works, Environmental Specialist and other appropriate installation personnel.
(2) Describe their roles and responsibilities and plan-of-action for how each team member will be involved to achieve the project sustainability requirements, and how the Contractor will coordinate with Government personnel.
(3) Maintain the list and descriptions up-to-date throughout the project.
b. Provide narratives that:
(1) Indicate performance goals for siting, energy, water, materials, and indoor environmental quality along with other comprehensive design goals and ensures incorporation of these goals throughout the design and lifecycle of the building.
(2) Demonstrate integration of the goals into design and construction.
(3) Demonstrate collaboration with other providers, such as Commissioning Authority[ and Third Party Certification].
1.6.2 Commissioning (Cx)
NOTE: I ncl ude UFGS Sect i on 01 91 00. 15 TOTAL BUI LDI NG COMMI SSI ONI NG f or pr oj ect s t hat r equi r e commissioning.
Develop and incorporate Commissioning requirements into the documents.
Submit Final Commissioning Report required by Section 01 91 00.15 TOTAL BUILDING COMMISSIONING as proof of this tracking requirement.
SECTION 01 33 29.05 20 Page 18
1.6.3 Optimize Energy Performance
NOTE: Choose t he f i r st br acket ed par agr aph f or al l new const r uct i on pr oj ect s, and f or r enovat i on pr oj ect s t hat subst ant i al l y r epl ace t he bui l di ng f r om t he f oundat i on up, t hat conf or m t o t he c i t ed st andar d f or commer ci al and mul t i - f ami l y hi gh- r i se buildings.
Choose t he second br acket ed par agr aph f or al l new const r uct i on pr oj ect s, and f or or r enovat i on pr oj ect s t hat subst ant i al l y r epl ace t he bui l di ng f r om t he f oundat i on up, t hat conf or m t o t he c i t ed st andar d f or l ow- r i se r esi dent i al bui l di ngs.
Choose any one of t he r emai ni ng opt i ons f or al l ot her r enovat i on pr oj ect s.
[ For Commercial and Multi-Family High-Rise Residential Buildings, meet the requirements of ASHRAE 90.1 - SI ASHRAE 90.1 - IP , and achieve at least 30 percent energy efficiency below baseline, when life cycle cost effective.
][ For Low-Rise Residential Buildings, meet the requirements of International Energy Conservation Code (IECC), and achieve at least 30 percent energy efficiency below baseline, when Life cycle cost effective.
][ Reduce measured building energy use by at least 30 percent compared to building energy use in 2003 or a year thereafter with metered energy use data.
][ Reduce measured building energy use by at least 20 percent compared to building energy use in 2015 or a year thereafter with metered energy use data.
][ Reduce modeled energy use (from all sources including renewable energy) by 20 percent compared to the ASHRAE 90.1 - SI ASHRAE 90.1 - IP baseline building design.
] If none of the reduction choices is life-cycle cost-effective, modify the design of the proposed building system(s) to achieve an energy consumption level at the highest level of energy efficiency that is life-cycle cost-effective.
NOTE: For det er mi ni ng ener gy consumpt i on r educt i on l evel s, compl y wi t h UFC 1- 200- 02 HI GH PERFORMANCE AND SUSTAI NABLE BUI LDI NG REQUI REMENTS, par agr aph t i t l ed " Ener gy Ef f i c i ency" and " Ener gy Compl i ance Analysis."
[ 1.6.3.1 Design Submittal Documentation
a. Narrative that provides a summary of:
(1) The decision making process leading to the selection of at least
SECTION 01 33 29.05 20 Page 19 three energy-efficient solutions (for each individual building energy system) to be analyzed; and the selected design solution(s)
(2) The specific energy standard and version utilized; and the software used in the analysis
(3) The calculated energy consumption and energy use intensity (EUI in kBTU/sf/yr) of the baseline building and the proposed design alternatives
b. A minimum of the following energy modeling files and summaries for the baseline and proposed alternatives:
(1) Input, schedules and libraries; and output
(2) Calculated energy use by energy type
(3) Calculated energy use by building system
c. The life-cycle cost-analysis input and output files for the baseline and the proposed alternatives
] 1.6.3.2 Construction Submittal Documentation
Provide revised energy modeling for actual system constructed.
1.6.4 Energy Efficient Products
Provide only energy-using products that are Energy Star rated or have Federal Energy Management Program (FEMP) recommended efficiency. Where Energy Star or FEMP recommendations have not been established, provide most efficient product that are life-cycle cost effective. Provide only energy using product that meets FEMP requirements for low standby power consumption. Energy efficient products can be found at:
http://www1.eere.energy.gov/femp/ and http://www.energystar.gov/ .
For construction submittal documentation, provide proof that product is labeled energy efficient and complies with the cited requirements.
1.6.5 On-site Renewable Energy Generation
Provide project energy needs thru on-site renewable energy generation, when life-cycle cost effective.
1.6.5.1 Design Submittal Documentation
a. Provide design drawings and calculations that demonstrate total on-site renewable energy as an annual percentage of proposed building energy consumption in kBTU/year.
b. Provide design drawings, equipment ratings, and calculations that demonstrate the generation capacity of the system in mmbtu/year for thermal and kwAC for electricity
c. Provide life cycle cost analysis (LCCA).
1.6.6 Solar Domestic Hot Water (SDHW)
Provide 30 percent or more of domestic hot water needs through solar
SECTION 01 33 29.05 20 Page 20 thermal water heating, when life-cycle cost effective.
1.6.6.1 Design Submittal Documentation
a. Provide design drawings and calculations that demonstrate total on-site renewable energy as an annual percentage of proposed building energy consumption in kBTU/year.
b. Provide design drawings, equipment ratings, and calculations that demonstrate the generation capacity of the system in mmbtu/year for thermal and kwAC for electricity
b. Provide life cycle cost analysis (LCCA).
1.6.7 Building-level Power Metering
Provide building-level meters for electricity, natural gas (and steam where applicable) use.
1.6.7.1 Design Submittal Documentation
a. Provide design drawings that highlight meter locations on the site.
b. Provide manufacturers data validating compatibility with base-wide system and component advanced meter requirements.
1.6.8 Indoor Water Use
a. Meet the requirements of ASHRAE 189.1 Section 6.3.2 (Building Water Use Reduction), which incorporates USEPA WaterSense-labeled products.
Water closet replacements in renovations may have a flush value of up to 1.6 GPF (6.1 LPF) to accommodate existing plumbing capacity.
b. Meet the requirements of ASHRAE 189.1 Section 6.4.2 (Building Water Use Reduction).
c. Meet the requirements of ASHRAE 189.1 Section 6.4.3 (Special Water Features).
1.6.8.1 Construction Submittal Documentation
Provide proof that fixtures are labeled EPA WaterSense or Energy Star , for products available with EPA WaterSense or Energy Star labeling; for all other fixtures, proof they comply with the cited efficiency requirements.
1.6.9 Indoor Water Metering
a. Provide building-level meters for potable water use.
1.6.9.1 Design Submittal Documentation
a. Provide design drawings that highlight meter locations on the site.
b. Provide manufacturers data validating compatibility with base-wide system and component advanced meter requirements.
1.6.10 Outdoor Water Use
Potable water use is prohibited for irrigating new landscaping, other than
SECTION 01 33 29.05 20 Page 21 for plant establishment. When non-potable water is life cycle cost effective and is used for new, permanent irrigation, provide the following:
1.6.10.1 Design Submittal Documentation
a. Provide design drawings and analysis that identify the non-potable water source used and demonstrate the non-potable water source is appropriate for landscape irrigation.
b. Provide life cycle cost analysis (LCCA).
1.6.11 Outdoor Water Meters
a. Provide building-level meters for potable water used for existing irrigation systems using potable water and serving more than 25,000 square feet of landscape, when life-cycle cost effective.
b. Provide manufacturers data validating compatibility with base-wide system and component advanced meter requirements.
1.6.11.1 Design Submittal Documentation
a. Provide design drawings that highlight meter locations on the site.
b. Provide life cycle cost analysis (LCCA).
1.6.12 Alternative Water
Use alternative sources of water to replace potable water usage, when life-cycle cost effective and to the extent permitted by local laws and regulations.
1.6.12.1 Design Submittal Documentation
a. Provide design drawings and calculations that demonstrate the alternative water sources used, potable water savings as compared to non-alternative water sourcing, and projected annual potable water savings.
b. Provide life cycle cost analysis (LCCA).
1.6.13 Stormwater Management
Develop and incorporate stormwater requirements into the documents.
Submit design and construction documentation required by UFC 3-210-10 and Agency processes, as proof of this tracking requirement.
1.6.14 Ventilation and Thermal Comfort
Meet the requirements of UFC 3-410-01.
1.6.14.1 Design Submittal Documentation
a. Provide design drawings and calculations that demonstrate HVAC systems and the building envelope have been designed to meet the requirements.
1.6.15 Daylighting
Achieve the minimum daylighting requirements of ASHRAE 189.1 , Section
SECTION 01 33 29.05 20 Page 22
8.4.1.2 "Minimum Sidelighting effective Aperture for Office Spaces and Classrooms" or Section 8.5.1.2 "Usable Daylight Illuminance in Office Spaces and Classrooms". Provide automated lighting controls in accordance with UFC 3-530-01.
1.6.15.1 Design Submittal Documentation
a. Provide floor plans and elevations.
b. Provide design analysis delineating requirements, to include compliant reflective surface locations and shading devices (where applicable).
1.6.16 Moisture Control
Meet the requirements of ASHRAE 189.1 Section 10.3.1.5 (Moisture Control), UFC 3-410-01, Chapter 3, Sections 3-2 and 3-3 (Ventilation Air), and UFC 3-101-01 Chapter 3 (Building Envelope Requirements).
1.6.16.1 Design Submittal Documentation
a. Provide drawings of building envelope details and HVAC humidity controls.
b. Provide plan for construction material storage and protection, humidity controls during construction, and operation and maintenance plan for ongoing building moisture control.
1.6.17 Reduce Volatile Organic Compounds (VOC) (Low-Emitting Materials)
Meet the requirements of Table 3-1 at the end of this specification.
For Construction submittal documentation, provide certifications or labels that demonstrate compliance with cited requirements, based on the attached
TABLE 3-1.
1.6.18 Indoor Air Quality During Construction
Prior to construction, create indoor air quality plan. Develop and implement an IAQ construction management plan during construction and flush building air before occupancy.
NOTE: Choose t he f i r st br acket ed sent ence f or new const r uct i on or r enovat i on pr oj ect s i n bui l di ngs t hat ar e not occupi ed dur i ng const r uct i on.
Choose t he second br acket ed sent ence f or r enovat i on pr oj ect s i n bui l di ngs t hat r emai n occupi ed dur i ng construction.
[For new construction and for renovation of unoccupied existing buildings, meet the requirements of ASHRAE 189.1 Section 10.3.1.4 (Indoor Air Quality (IAQ) Construction Management), with maximum outdoor air consistent with achieving relative humidity no greater than 60 percent.][For renovation of occupied existing buildings, meet the requirements of ANSI/SMACNA 008 IAQ Guidelines for Occupied Buildings Under Construction.]
SECTION 01 33 29.05 20 Page 23
NOTE: Choose " bui l di ng" f or al l new const r uct i on pr oj ect s, and f or r enovat i on pr oj ect s t hat subst ant i al l y r epl ace t he bui l di ng f r om t he f oundat i on up. Choose " ar ea" f or al l ot her r enovat i on pr oj ect s.
Provide documentation showing that after construction ends and prior to occupancy, HVAC filters were replaced and [building][area] air was flushed out in accordance with the cited standard.
1.6.19 Recycled Content
Comply with 40 CFR 247 . Refer to:
https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program for assistance identifying products cited in 40 CFR 247 . Selected products must comply with non-proprietary requirements of the Federal Acquisition Regulation and must meet performance requirements.
1.6.19.1 Construction Submittal Documentation
a. Provide manufacturers' documents stating the recycled content by material, or written justification for claiming one of the exceptions allowed on the cited website.
b. Substitutions: Submit for Government approval for proposed alternative products or systems that provide equivalent performance and appearance and have greater contribution to project recycled content requirements.