ATTACHMENT C Minimum Materials Engineering and Construction Requirements (Part 4).pdf

PDF 315 KB Posted

Attached to
Amendment 0005 Updated Evaluation Factors for Install Macro Artifacts Gallery 13 and 14 at Bldg. 1775
Solicitation number
N4008020R5255
Issued by

About this file

This document provides minimum materials, engineering, and construction requirements for installing macro exhibits in Galleries 13 and 14 at the National Museum of the Marine Corps. The project scope involves fabricating and installing structural floor supports for large-scale museum artifacts, installing five macro artifacts on the fabricated supports, and ensuring all work meets applicable codes and standards. Key requirements include using new materials, recycled materials where possible, applicable building codes for fire protection, electrical systems, communications, and ensuring all demolition is conducted according to approved plans and applicable regulations for hazardous material abatement.

View the file

Other files

File Type Posted
Amend 0005 Updated Evaluation Factors.pdf PDF
Attachment J - Revised Evaluation Factors-.pdf PDF
Amend 0004 Updated Evaluation Factors and Exhibits.pdf PDF
Attachment I - Revised Evaluation Factors.pdf PDF
Site visit log.pdf PDF
Revised Exhibits A - G.pdf PDF
Amend 0003 Updated WD_Updated Clauses_Closing Date.pdf PDF
Attachment H - General Decision Number VA20200162 9.18.2020.pdf PDF
Amend 0002 Answers RFIs_Updated WD_Updated Proposal Delivery.pdf PDF
Amend 0001 ATTACHMENT D Prescriptive Specifications- Drawings (Part 5) Revised.pdf PDF
N4008020R5255 0001 Site Visit Update and Spec Update.pdf PDF
Amend 0001 Part 5 01_32_16.00_20 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES.pdf PDF
Part 5 01_31_23.13_20.pdf PDF
ATTACHMENT B Statement of Work (Part 3).pdf PDF
ATTACHMENT A General Requirements (Part 2).pdf PDF
Part 5 01_35_26.05_20.pdf PDF
Part 5 01_33_29.05_20.pdf PDF
Attachment G - Bid Schedule.pdf PDF
Attachment H - General Decision Number VA20200162 08.26.2020.pdf PDF
N4008020R5255 Bldg. 1775 Install Macro Artifacts Gallery 13 and 14.pdf PDF
ATTACHMENT E Macro Artifact Mounts_IFC (Part 6).pdf PDF
ATTACHMENT D Prescriptive Specifications- Drawings (Part 5).pdf PDF
Exhibits A- E.pdf PDF
ATTACHMENT F NMMC MAP.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

National Museum of the Marine Corps Galley 13 and 14 - Macro Exhibits PMB# - 2020061 Quantico, Virginia WON - 1662198

SMALL PROJECT TEMPLATE - PART 4 MINIMUM MATERIALS, ENGINEERING AND CONSTRUCTION

REQUIREMENTS - Page 1

PART 4

Minimum Materials, Engineering and Construction Requirements

Gallery 13 and 14 Macro Exhibits

Quantico, Virginia WON - 1662198

REQUIREMENTS - Page 2

Part 4 Minimum Materials, Engineering and Construction Requirements

1.0 GENERAL REQUIREMENTS

The requirements indicated here are minimum performance requirements. More specific project functional and performance requirements, scope items and expected quality levels over and above the standards in Part 4 are identified in Part 3 of the Request for Proposal or Basic Ordering Agreement. The Contractor is encouraged to exceed the minimum requirements. The Contractor's performance evaluation will be based in part on enhancements to materials, engineering, design and construction provided for the contract that exceed minimum requirements.

Part 4 is a general section. Not all items in Part 4 will be required for this project. See Part 3 for project-specific requirements. See "Contract and Order of Precedence" paragraph in Part 2 for relationships between all parts of the RFP.

In general, unless otherwise indicated, provide all labor, equipment and materials necessary to complete the work required for the contract. All work must be in conformance with all applicable referenced criteria, construction standards, laws and regulations, including applicable building fire and life safety codes.

Recycled Materials Considerations:

An Affirmative Procurement Program has been established within the Federal government to promote the purchase of products containing recovered materials. This program promotes the purchase of products containing materials recovered from the solid waste stream. The intent is to conserve resources and reduce solid waste by developing markets for recycled products and encouraging manufacturers to produce quality recycled content products. Use products that meet or exceed the EPA guideline standards for recovered content as required by the Federal Acquisition Regulations (FAR). Availability lists of manufacturers and EPA research on product usage are on the Construction Criteria Base (CCB) at www.wbdg.org/ccb/ccb.php under Documents Library, NAVFAC Criteria. A partial list of products containing recycled materials for possible use is as follows:

• Rock Wool Insulation

• Fiberglass Insulation

• Cellulose Insulation

• Structural Fiberboard and Laminated Paperboard

• Cement and Concrete - Coal Fly Ash

• Carpet including backings and cushions

• Floor Tiles

• Reprocessed and Consolidated Latex Paint

• Crushed Concrete Aggregate for new asphalt, concrete or subgrade http://www.wbdg.org/ccb/ccb.php

Quantico, Virginia WON - 1662198

REQUIREMENTS - Page 3

• Recycled glass for terrazzo aggregate

• Acoustical Ceiling Tile

• Gypsum Wallboard

• Steel wall studs

• Cellulose spray applied fireproofing

• HDPE Toilet Partitions

1.1 MATERIALS AND METHODS OF CONSTRUCTION

Only new materials and equipment are to be installed in the work. All materials, equipment and appliances must be of the current manufacturers' products. Do not use obsolete or discontinued materials, equipment and appliances, except that construction materials containing recycled content as described in Paragraph 1 of this Part that completely comply with all materials specifications found elsewhere in this Part may be used.

1.2 APPLICABLE CODES AND STANDARDS

The design and construction must be in accordance with established construction practices, and the latest revision/edition of the following referenced codes and standards. The term "Latest Revision/Edition" is defined as the version as of the project award date. References are available at www.wbdg.org/ndbm/ . The advisory provisions of all codes and standards is mandatory, as though the word "must" had been substituted for "should" wherever it appears. Reference to the "authority having jurisdiction" is to be construed to mean "Contracting Officer". Comply with the required and advisory portions of the current edition of the standard at the time of contract award.

All work must comply with UFC 1-200-01, General Building Requirements, and IBC 2009 or later edition as modified by applicable NFPA Standard as well as codes and standards listed in RFP Part 2.

1.3 LOCATION-SPECIFIC CODES AND STANDARDS

See Part 3.

1.4 DISCREPANCIES

When discrepancies in the referenced standards and the contract requirements occur, the more stringent requirements govern. The word "should" in all NFPA publications is to be interpreted as a requirement. The Authority Having Jurisdiction in the interpretation of the codes and standards, and approving the exceptions allowed in the referenced standards, is the Contracting Officer, and the parties designated by the Contracting Officer.

2.0 PERFORMANCE TECHNICAL SPECIFICATIONS

Note: The paragraph numbers used correspond with the numbers used in UNIFORMAT II/Work Breakdown Structures (WBS) as listed in the Whole Building Design Guide, Navy Design Build Master, accessible at this website: www.wbdg.org/ndbm .

http://www.wbdg.org/ndbm/ http://www.wbdg.org/ndbm

Quantico, Virginia WON - 1662198

SMALL PROJECT TEMPLATE - PART 4 MINIMUM MATERIALS, ENGINEERING AND CONSTRUCTION

REQUIREMENTS - Page 4

SECTION A. SUBSTRUCTURE

A10 FOUNDATION

NOT USED

SECTION B. SHELL

SECTION C. INTERIORS

C10 INTERIOR CONSTRUCTION

C1010 PARTITIONS

C1020 INTERIOR DOORS

C1030 SPECIALTIES

C20 STAIR CONSTRUCTION

C30 INTERIOR FINISHES

C3010 WALL FINISHES

Unless otherwise noted in the RFP, primary wall finish is painted gypsum wall board. Repair all damage to existing walls caused by the execution of the project.

C3020 FLOOR FINISHES

Repair all damage to existing walls caused by the execution of the project.

Quantico, Virginia WON - 1662198

REQUIREMENTS - Page 5

C3030 CEILING FINISHES

C3040 PAINTING

NOT USED

SECTION D. SERVICES

D40 FIRE PROTECTION

Project Requirements: Prior to the start of design, the Designer of Record must meet with the Government's Fire Protection Engineer to determine the extent and types of fire protection required. The Project Scope is limited to the temporary removal and reinstallation of existing components as a result of installing the macro exhibits. All replacement work shall match pre-project existing conditions.

D4010 FIRE ALARM AND DETECTION

Fire alarm system includes manual stations, system smoke detectors, duct smoke detectors, heat detectors, audio/visual alarms, connection to base wide fire alarm monitoring, electrical supervision of fire pump controllers, and electrical supervision of all sprinkler system alarm and supervisory devices as required.

D4020 FIRE SUPPRESSION WATER SUPPLY AND EQUIPMENT

D4040 SPRINKLERS

D50 ELECTRICAL

AS APPLICABLE TO TEMPORARY REQUIREMENTS AND RESTORATION OF REMOVED

AND REINSTALLED COMPONENTS.

D5010 ELECTRICAL SERVICE & DISTRIBUTION

Provide interior electrical wiring, fixtures, switches, outlets, and apparatus in accordance with applicable codes and standards. The electrical system must conform to NFPA 70. Power and lighting circuits must be separate.

Quantico, Virginia WON - 1662198

SMALL PROJECT TEMPLATE - PART 4 MINIMUM MATERIALS, ENGINEERING AND CONSTRUCTION

REQUIREMENTS - Page 6

1. Wiring: All wiring must be in electrical metal conduits and must be concealed except in the industrial spaces and at locations indicated in Part 3. No conductors are permitted to be smaller than No. 12 AWG, copper wires. Wiring below slab or underground must be in Schedule 40 PVC with ground wire. Exposed conduits on the exterior of the building are prohibited. Provide a ground conductor for each circuit; conduits must not be used as the sole means of grounding. Cable assemblies Types AC, MC, or MI and flat conductors may only be used in locations allowed by UFC 3-520-01. Circuit breakers must be bolt-on type. Series rated circuit breakers and fusible panelboards must not be used.

2. Outlet Circuits Lighting and convenience outlets must be on separate circuits. Install

GFI protected receptacles at all wet or damp areas. Location of outlets must be as required by applicable codes and standards. Provide extra outlets for maintenance and service staffs in spaces such as corridors, hallways and other public spaces as identified below. All exterior outlets must be on separate circuits, be GFI protected, and equipped with a cover to prevent accidental water infiltration into the devices.

In addition to the location requirements specified by NFPA 70, locate general purpose and dedicated outlets in accordance with the following:

a. Mechanical equipment: Provide receptacle within 7.6 m (25 ft) of mechanical equipment on the interior and exterior of buildings.

b. Office, staff support spaces, and other workstation locations: One receptacle for each workstation with a minimum of one for every 3050 mm (10 ft) of wall space.

When less than 3500 mm (10 ft) of wall at the floor line, provide a minimum of two receptacles spaced appropriately to anticipate furniture relocations. Limit loads to a maximum of four workstations per 20 amp circuit. See Appendix C, Table C1 for workstation load data.

c. Conference rooms and training rooms: One for every 3.6 m (12 ft) of wall space at the floor line. Ensure one receptacle is located next to each voice/data outlet.

Provide one receptacle above the ceiling to support video projection device.

Extend circuit to wall location for connection to motorized screen. When it is expected that a conference room table will be specifically dedicated to floor space in a conference room, locate a floor-mounted receptacle under the table.

This receptacle may be part of combination power/communications outlet.

d. Provide power outlets throughout the building to serve all proposed equipment, including government furnished equipment, and allow for future reconfiguration of equipment layout. Provide power connections to all ancillary office equipment such as printers, faxes, plotters, and shredders. Provide dedicated circuits where warranted.

e. In each telecommunications room provide a dedicated 20 amp circuit with a receptacle adjacent to each rack or backboard for each of the following:

1) CCTV for training systems

2) CCSTV for security systems

3) CATV

4) Voice systems

5) Data systems.

f. Provide dedicated receptacles as required throughout the facility for television monitors. These outlets will typically be located at the ceiling level for wall mounted television monitors.

g. Provide dedicated receptacles as required throughout the facility for tape players

Quantico, Virginia WON - 1662198

SMALL PROJECT TEMPLATE - PART 4 MINIMUM MATERIALS, ENGINEERING AND CONSTRUCTION

REQUIREMENTS - Page 7 and disc players.

h. Corridors: One every 15 m (50 ft) maximum with a minimum of one per corridor.

i. Janitor's closet and toilet rooms: One GFI receptacle per closet. Provide GFI receptacles at counter height for each counter in toilets such that there is a minimum of one outlet for each two sinks.

j. Space with counter tops: One for every 1.200 m (4 ft) of countertop, with a minimum of one outlet. Provide GFI protection of outlets when located within

1.8 m (6 ft) of plumbing fixtures.

k. Building exterior: One for each wall, GFI protected and weatherproof.

l. Kitchen non-residential: One for each 3.05 m (10 ft) of wall space at the floor line.

Provide GFI protection when located within 1.8 m (6 ft) of plumbing fixture.

m. Child occupied spaces (including toilets): One for every 3.6 m (12 ft) of wall space. Use child safety type such as those that require rotating an integral surface cover plate to access current. Removable caps and plugs are not acceptable.

n. All other rooms: One for every 7.6 m (25 ft) of wall space at the floor line. When

7.6 m (25 ft) or less of wall at the floor line exists in a room, provide a minimum of two receptacles spaced appropriately to anticipate furniture relocations.

o. Special purpose receptacles: Designer of Record must coordinate with the user to provide any special purpose outlets required. Provide outlets to allow connection of equipment in special use rooms.

3. Service Entrance Equipment: When a switchboard or switchgear is required, the

Designer of Record must utilize UFGS Section 26 23 00, Low Voltage Switchgear or UFGS 26 24 13 Switchboards, for the project specification, and must submit the edited specification section as a part of the design submittal for the project.

D5020 LIGHTING & BRANCH WIRING

1. Lighting Fixtures: All lighting fixtures must be energy conservation compact fluorescent or Light Emitting Diode (LED)except where indicated by Part 3.

a. Fixtures for Administrative and Commercial Spaces: For offices, commercial and administrative spaces and facilities provide high efficiency ballast, and instant or rapid start recessed fluorescent fixtures or LED fixtures.

b. Three-Way and Four-Way Switches: Provide three-way or four-way switching of light fixtures as necessary to facilitate movement between adjacent spaces to allow efficient energy management.

2. Exterior Lighting Fixtures for Large Open Areas: Exterior lighting fixtures for large open areas such as parking lots, streets and playgrounds must be energy efficient High-Intensity Discharge (HID) or compact fluorescent fixtures and must comply with local regulations regarding low lighting levels to avoid light pollution.

a. Photocell Overriding Switch: Provide photocell-overriding switch for all outdoor light fixtures.

D5030 COMMUNICATIONS & SECURITY

1. Telecommunications Systems: Provide a horizontal distribution system including, but not necessarily limited to, all wiring, pathway systems, connector blocks, protectors for all copper service entrance pairs, terminators for all fiber optic cables, outlet boxes, telephone jacks, and data jacks cover plates in accordance with EIA/TIA standards.

Provide Category 6 UTP telephone premise wiring where telephones are required.

Quantico, Virginia WON - 1662198

SMALL PROJECT TEMPLATE - PART 4 MINIMUM MATERIALS, ENGINEERING AND CONSTRUCTION

REQUIREMENTS - Page 8

2. Public Address Systems: Provide a Public Address system with speakers in all locations identified in Part 3.

3. Intercommunications Systems: Provide an Intercommunication System to allow two-way communications between all locations identified in Part 3.

4. Television Systems: Provide television systems to the extent specified in Part 3.

Coordinate with the local Cable Company, Local users and Local Authority at the Activity for other specific requirements. The interior cable outlets and wiring must be complete and ready for use. Wiring must not be run exposed on any surface of the building.

5. Security Systems: Provide an Intrusion Detection System (IDS) to sense all perimeter doors and windows and the interior volume in at least two locations. System must have a minimum 90-minute battery back-up and annunciate both locally and at the Base Security Office via a telephone dialer. System must have entry/exit timer. Provide wall mounted keypad control at two locations.

D5090 OTHER ELECTRICAL SERVICES

1. Surge Protective Device (SPD): Provide SPD in accordance with UFC 3-501-01, Electrical Engineering.

2. Variable Frequency Drives: When variable frequency drives are required, the

Designer of Record must utilize UFGS Section 26 29 23 20 for the project specification, and must submit the edited specification section as a part of the design submittal for the project.

3. Emergency Generators: When an emergency generator is required, the Designer of

Record must utilize UFGS Section 26 32 13.00 20 for the project specification, and must submit the edited specification section as a part of the design submittal for the project.

4. Automatic Transfer and Bypass/Isolation Switches: When an Automatic Transfer

Switch is required, the Designer of Record must utilize UFGS Section 26 36 23.00 20 for the project specification, and must submit the edited specification section as a part of the design submittal for the project.

5. Uninterruptible Power Supply (UPS) System: When a UPS system is required, the

Designer of Record must utilize UFGS Section 26 33 53.00 20 and must submit the edited specification section as a part of the design submittal for the project.

6. 400 Hertz Systems: The Designer of Record must utilize UFGS Section 26 32 26 or 26

35 43 for the project specification, and must submit the edited specification section as a part of the design submittal for the project.

7. Lightning Protection: When lightning protection is required, the Designer of Record must utilize UFGS Section 26 41 00.00 20 for the project specification, and must submit the edited specification section as a part of the design submittal for the project.

Quantico, Virginia WON - 1662198

SMALL PROJECT TEMPLATE - PART 4 MINIMUM MATERIALS, ENGINEERING AND CONSTRUCTION

REQUIREMENTS - Page 9

8. Building Photovoltaic System: When a PV system is required, the Designer of Record must utilize UFGS Section 26 31 00 for the project specification, and must submit the edited specification section as part of the design submittal for the project.

SECTION E. EQUIPMENT AND FURNISHINGS

SECTION F. SPECIAL CONSTRUCTION AND DEMOLITION

F10 SPECIAL CONSTRUCTION AND DEMOLITION

F20 SELECTIVE BUILDING DEMOLITION

In general terms, demolition work must include the removal and effective management and disposition of existing construction and or structures. Take care to prevent damage to existing utilities and construction that are not scheduled for demolition. If damage occurs, make repairs to the satisfaction of the Contracting Officer and at no cost to the Government. Comply with local Activity and Installation local requirements regarding demolition and removal. Unless otherwise specified in Part 3, all demolished materials and equipment must be removed from government property in accordance with applicable laws and regulations, including local Activity or Installation regulations. Selling of demolished or salvaged materials and equipment on government properties is prohibited.

Demolition Plan: No demolition work is permitted to take place until a Demolition Plan has been submitted to, and approved by, the Contracting Officer. The Plans must take into consideration, and indicate method of removal, disposition, and abatement of environmentally hazardous materials. Demolition, disposition, and abatement of hazardous materials must comply with all applicable Local, State, and Federal regulations and laws. If destructive investigation is to occur, the Contracting Officer shall approve a Destructive Investigation Plan.

When hazardous materials such as asbestos, lead paint, PCB and other hazardous materials are involved in the performance of the work, the contractor must abate, remove and manage the hazardous materials in construction and finish materials such as insulation, flooring, wall materials, ceiling materials, roofing materials, heating, plumbing, ventilation, air conditioning equipment and installations in accordance with National as well as local Environmental Protection Laws and Regulations.

F2020 HAZARDOUS COMPONENT ABATEMENT

SECTION G. BUILDING SITEWORK

File details come from the government source that posted it. Updated .