TECHNICAL SPECIFICATIONS
REHABILITATE GRANT GROVE AND CLOVER
CREEK WASTEWATER TREATMENT PLANTS
PMIS 184084 AND 158783
Prepared for
Pacific West Regional Office National Park Service
Prepared by
SPF Water Engineering, LLC 300 East Mallard, Suite 350
Boise, Idaho 83706
(208) 383-4140
April 7, 2015
SEKI - 184084 01 11 00 - 1
031414 SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work phases.
3. Work under other contracts.
4. Contractor use of premises.
5. Public use of site.
6. Occupancy requirements for buildings.
7. Work Restrictions.
8. Special Construction Requirements.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Sequoia & Kings Canyon National Parks, Grant Grove and Clover Creek Wastewater Treatment Plants, near Fresno, California. Access to some project sites may be restricted in the months of November to June due to lingering snow in the area.
B. The Work consists of the following:
1. The Work includes component replacement and or rehabilitation of specific equipment and processes and related work items at both Grant Grove and Clover Creek Wastewater Treatment Plants (WWTP’s).
2. The following are the general work items and bid options identified for the Grant Grove and Clover Creek Wastewater Treatment Plants.
Grant Grove Wastewater Treatment Plant
1. Replace the influent grinder and controls.
2. Replace two (2) air diaphragm pumps, check valves, plug valves, and provide minor piping modifications on equalization pumps. Repaint piping.
3. Add variable frequency drives (VFD) to the existing aeration basin blowers.
4. Replace/modify clarifier mechanisms in both clarifiers.
5. Replace two (2) compressors with new equipment. Add air dryers on both compressors.
6. Install pipe loops in blower piping for Blowers 4, 5 & 6 to protect from flooding.
7. Replace two (2) exhaust fans in process area and add timed switch by door.
8. Replace two (2) telescoping valves and motorized actuators on supernatant line.
9. .
10. Install combustible gas (O2 and Methane) detectors in process area with indication at en-trances and to the PLC.
11. Replace and upsize the on-site chlorination system.
SEKI - 184084 01 11 00 - 2
12. Install level transmitters to equalization basins.
13. Install Dissolved Oxygen (DO) analyzer to the aeration basins.
14. Replace Motor Control Center.
15. Replace SCADA system with non-proprietary equipment.
16. Upgrade SCADA controls to include additional process monitoring (DO and chlorine re-sidual).
17. Conduct a system ground study.
18. Add software alarm dialer and USB modem.
19. Replace sludge building doors.
20. Bid Options:
a. Replace two (2) air diaphragm pumps, check valves, plug valves, and provide minor piping modifications on RAS/WAS pumps. Repaint piping.
b. Replace two (2) air diaphragm pumps, check valves, plug valves, and provide minor piping modifications on supernatant pumps. Repaint piping.
c. Install stairway and platform to the access opening on the north side of the effluent storage building.
d. Replace eight (8) ladders in process tanks.
e. Install scissor lift in pump room for soda ash system.
21. Motor Control Center Sequence of Replacement – Description of Work:
a. The motor control equipment on this project includes the full replacement of existing motor control center with new motor control center. New installation will utilize the existing space currently occupied by the existing motor control center.
b. The Control System Integrator shall be responsible for providing the motor control center including all related equipment shown in drawings. The Electrical Contractor shall be responsible for installing the motor control center, interconnecting all related equipment and wiring per contract documents, Control System Integrator coordina-tion and design.
c. The Control System Integrator and Electrical Contractor shall provide detailed as-built redline drawings of existing motor control center as a part of their integration package.
d. Prior to demolition of the existing motor control system the Electrical Contractor and Control System Integrator shall coordinate to provide a written plan to the Contract-ing Officer for approval outlining the sequence of removal and replacement of the motor control center. The plan shall include a coordinated effort for shut down with plant operator as not to interfere with normal operations unless approved by Con-tracting Officer. As part of the written plan the Contractor shall include an emergen-cy plan of pumping, hauling, and disposing of untreated wastewater in the event the replacement of the motor control center system takes longer than anticipated. The average wastewater flow at the Grant Grove WWTP for emergency planning purpos-es is estimated to be 10,500 gallons per day.
e. Control System Integrator and the Electrical contractor shall verify and document all wiring and equipment size to allow for replacement of the existing Motor Control Center using the exact existing foot print prior to ordering Motor Control Center.
SEKI - 184084 01 11 00 - 3
f. Shop testing of new motor control center and new control panel will be required prior to shipping the Motor Control Center and new control panel. The Control System In-tegrator shall perform a shop test witnessed by the Contracting Officer and the Elec-trical engineer. The test shall include a full functional I/O test and shall be fully functional prior to delivery to job site.
g. Motor Control Center Sequence of Replacement – Description of Work:
Clover Creek Wastewater Treatment Plant
1. Replace influent grinder and controls and install inclined screen in headworks building.
2. Replace & upsize septage tank blower and install additional diffusers.
3. Replace septage tank piping and diffusers.
4. Upgrade all electrical components in headworks to NEC and NFPA compliant.
5. Relocate ultrasonic level controller on flow meter to headworks building.
6. Replace the exhaust fan and add a unit heater in the headworks building.
7. Replace equalization pumps and modify piping.
8. Replace equalization valves with manual operators including: two (2) 3-inch knife gate valves, two (2) 4-inch plug valves, and five (5) 4-inch knife gate valves.
9. Replace two (2) 8-inch equalization tank knife gates and actuators on influent pipe to ba-sin.
10. Replace one (1) 12–inch sluice gate between equalization basins (under grating).
11. Install door header at CMU opening in chlorine room.
12. Replace two (2) effluent pumps and modify piping.
13. Replace effluent valves including two (2) 6-inch knife gates, two (2) 6-inch check valves, and two (2) 6-inch plug valves.
14. Replace surge tank on effluent discharge piping.
15. Replace eight (8) 6-inch plug valves with chain wheel operator on the RAS/WAS Piping.
16. Replace and extend two (2) ladders (one per basin) and anchors in the equalization basins.
17. Replace and extend two (2) ladders (one per basin) and anchors in the aeration basin no. 1 and no. 2; modify hand-railing and add safety chain.
18. Modify grating and hand railing around chlorine contact chamber.
19. Replace one (1) light switch in chlorine contact chamber area to meet current NEC and
NFPA requirements.
20. Provide combustible gas detection system in process area with indication at entrances and to the PLC.
21. Verify all handrails and grates are properly grounded.
22. Conduct arc flash study and apply proper labeling.
23. Bid Options:
a. Replace Clarifier No. 2 (Collection mechanism, drive and internal anchors), replace scum collector on Clarifier No. 1 & 2; and rebuild or replace mud valve on Clarifier No. 3.
C. Project will be constructed under a single prime contract.
D. For any work components wherein the component specifications are not expressly included in these Contract Documents, the Contractor is to field verify the existing work component and then include
SEKI - 184084 01 11 00 - 4
each component as ‘like-in-kind’ to the exiting work component in the appropriate bid item in the Contract Price Schedule. The Contractor must submit a technical data sheet for the ‘like-in-kind’ component specifications to the Contracting Officer for review and approval as part of the submittal requirements.
1.3 WORK PHASES
A. The work shall be conducted in an effort to minimize interruptions to existing wastewater treatment plant processes. The Contractor is encouraged to plan work items during times when flows at the treatment plants are at their lowest. Typically the lowest wastewater flows are observed during the months of October through April.
B. The construction sequence shall be such that the Grant Grove Emergency Generator and HVAC portion of the project (PMIS 157070) is substantially completed and operational on or before December 1, 2015.
C. The Contractor shall have the flexibility to sequence the construction of the work items at each site to minimize interference with subsequent work tasks.
D. Replacement of MCC must occur between January 15, 2016 and March 1, 2016.
1.4 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of the site for construction operations. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine constructions operations to limit use of premises to areas of the treatment plant which are identified to be rehabilitated or replaced as indicated.
2. All site disturbances are to be approved by Contracting Officer.
3. All damage to roads, curbing, sidewalks, etc. shall be restored to pre-construction conditions by Contractor at no additional cost to the Government. The Contracting Officer will photograph and/or video tape pre-construction conditions at the site
4. Road access to buildings and other facilities must remain open at all times.
B. Storage of Materials: Confine storage of materials and other adjacent salvage storage areas as directed by the Contracting Officer or indicated on the construction documents. Contractor shall return all storage areas to the same condition which they found them at the start of construction.
C. Preservation of Natural Features:
1. All equipment shall be power washed and inspected prior to entering the Park to ensure it is free of non-native weeds and/or seeds. In addition, sources of imported rock, sand, gravel and soil shall be inspected from invasive non-native plants, weeds and/or seeds.
The Contractor shall submit a list of proposed sources, end use and temporary storage requirements for imported material, 30 calendar days prior to delivery. Imported material shall be free of non-native weeds and/or seeds. Imported material shall be shipped directly from the source to the Park without intermediary storage or staging. Shipping vessels shall be covered to prevent spillage or blowing of their contents with in transit.
SEKI - 184084 01 11 00 - 5
2. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
3. Provide temporary barriers to protect existing trees and plants and root zones.
4. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove agreed-on roots and branches that interfere with construction.
5. Do not fasten ropes, cables, or guys to existing trees.
6. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
E. Construction Camp: Establishment of a camp within the park will not be permitted.
F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1.5 PUBLIC USE OF SITE
A. The Grant Grove and Clover Creek WWTP’s will be closed to the public during construction.
Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.
1.6 OCCUPANCY REQUIRMENTS FOR BUILIDINGS
A. Existing Buildings
1. Full Government Occupancy: Government will occupy buildings that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO.
b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.
SEKI - 184084 01 11 00 - 6
1.7 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.8 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 8:00 a.m. to 4:30 p.m., Monday through Friday, except when otherwise indicated. Work outside these hours may be approved by the Contracting Officer if requested in writing by the Contractor.
No holiday work will be permitted without prior approval from Contracting Officer.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than 72 hours in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
D. Throughout the entire construction period, the Contractor shall schedule all work and provide temporary facilities, electrical power and control circuits, and bypass pumping to minimize utility shutdowns. Work shall be scheduled such that interruptions to service (wastewater treatment) are to be completed to maintain facilities operation. Interruptions must be approved by Contracting Officer. Refer to 01 11 00 Part 1.9B.
E. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.
SEKI - 184084 01 11 00 - 7
1.9 SPECIAL CONSTRUCTION REQUIREMENTS
A. Contractor shall complete a pre-construction walk-through with the Contracting Officer Representative to verify all utility alignments, building locations, construction access points, etc.
B. The Grant Grove and Clover Creek Treatment plants must be kept in service at all times during construction. If a specific process needs to be interrupted for removal and replacement of equipment the Contractor shall provide a written notice at least 48 hours in advance of this work so process modifications can be made before the work is complete. Included in this written notice is the approximate time it will take to make the required change over and what steps the Park needs to follow to make this. The Contractor shall take the appropriate actions so that the overall treatment of raw wastewater is not interrupted.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
SEKI - 184084 01 27 00 - 1
082714 DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No. 01 Mobilization/Demobilization:
1. This item consists of moving rigs, pumps, equipment, materials, power, labor, fuel, tools and incidentals necessary to do the Work, and moving out of all such equipment, materials, tools, and incidentals, and final site cleanup upon completion of the Work at both the Clover Creek and Grant Grove Wastewater Treatment Plants. This items shall include all required equipment and vehicle cleaning for certification as weed and seed free prior to entering park boundaries.
2. Measurement for payment will be by lump sum.
3. Payment will be made at the contract lump sum price. For purposes of partial payment, the mobilization portion of this bid item shall be considered as 60% of the total lump sum.
4. May not be greater than 6% of total bid cost
B. Contract Line Item No. 02 Clover Creek, Headworks Upgrade:
1. This item consists of all labor, materials, and equipment for the demolition of various process equipment and building components in the Clover Creek Wastewater Treatment Plant Headworks Building:
a. Influent grinder and manual screen
b. Septage receiving blower as package system
c. Septage tank piping and diffusors
d. Headworks building exhaust fan
e. Seal off on all building conduit
f. Upgrade of the power distribution system for the building
g. All lighting fixtures to explosion proof fixtures
h. A new combustible gas detection system within the headworks building
i. Relocation of the ultrasonic level detector from the headworks building to the control room.
SEKI - 184084 01 27 00 - 2
1. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
2. Payment will be made at the contract lump sum price.
C. Contract Line Item No. 03 Clover Creek, Equalization Pumps, Valves and Access Improvements.
1. This item consists of all labor, materials, and equipment for modifications to the two ladders on the equalization tanks, and demolition of existing and installation of the following equalization tank piping system and components at the Clover Creek Wastewater Treatment Plant:
a. Two (2) equalization pumps and motors
b. Associated equalization tank pipe and fittings
c. Two (2) 3-inch knife gate valves
d. Five (5) 4-inch knife gate valves
e. Two (2) 4-inch plug valves
f. Two (2) 8-inch knife gate valves
g. One (1) 12-inch sluice gate
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
D. Contract Line Item No. 04 Clover Creek, Effluent Pumps, piping, Valves and Surge Tank Replacement:
1. This item consists of all labor, materials, and equipment for demolition of the existing and re-installation and painting of the following effluent piping system components at the Clover Creek Wastewater Treatment Plant:
a. Two (2) effluent pumps and motors
b. Two (2) 6-inch knife gate valves
c. Two (2) 4-inch check valves
d. Two (2) 4-inch plug valves
e. One (1) surge tank
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
E. Contract Line Item No. 05 Clover Creek, Chlorine Room and Contact Chamber Modifications:
1. This item consists of all labor, materials, and equipment for demolition of existing and installation of a new door header at the chlorine room and modification of the access platform for the chlorine contact chamber at the Clover Creek Wastewater Treatment Plant. Existing handrails will be modified to provide access for cleaning and installation of safety chains will be added. New grating will be provided over the existing chlorine contact chamber basin.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
F. Contract Line Item No. 06 Clover Creek, RAS/WAS Valve Rehabilitation:
1. This item consists of all labor, materials, and equipment for demolition of existing and installation of eight (8) 6-inch plug valves with chain operators on the RAS/WAS pump system at the Clover Creek Wastewater Treatment Plant.
SEKI - 184084 01 27 00 - 3
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
G. Contract Line Item No. 07 Clover Creek, Aeration Basin Ladder Modifications:
1. This item consists of all labor, materials, and equipment for modifications to two (2) ladders on the aeration basins at the Clover Creek Wastewater Treatment Plant. Work also includes labor, materials, and equipment for modification of the ladder access including modifying the existing hand railing and installing safety chains at each basin.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
H. Contract Line Item No. 08 Clover Creek, Process Electrical Survey and Modifications:
1. This item consists of all labor, materials, and equipment for demolition existing lights switches and installation of new explosion proof lighting switches to meet current NEC and NFPA requirements, upgrade the human machine interface (MHI) in the control room to integrating process and system improvements, and for completion of an arc flash study of the entire electrical system at the Clover Creek Wastewater Treatment Plant.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
I. Contract Line Item No. 9 Clover Creek, Combustible Gas Detector System:
1. This item consists of all labor, materials, and equipment for the installation of three (3) combustible gas detector systems in three separate process areas of the Clover Creek Wastewater Treatment Plant and incorporate fault readings and output signals into the existing SCADA system.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
J. Contract Line Item No. 10 Grant Grove, Replace Influent Grinder and Controls:
1. This item consists of all labor, materials, and equipment for demolition of existing and installation of a new influent channel grinder, disconnect, and controls at the Grant Grove Wastewater Treatment Plant.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
K. Contract Line Item No. 11 Grant Grove, Equalization System Upgrades:
1. This item consists of all labor, materials, and equipment for installation of two (2) new ultrasonic level sensors on each equalization tank, and the demolition of existing and installation of the following equalization system components at the Grant Grove Wastewater Treatment Plant: (2) equalization tank, air operated diaphragm style with selected spare parts, pumps, demolition of existing and installation of new (2) 4-inch plug valves, and any required modification and painting of the associated piping.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
SEKI - 184084 01 27 00 - 4
L. Contract Line Item No. 12 Grant Grove, Aeration Blower Motors and VFD’s:
1. This item consists of all labor, materials, and equipment for demolition of the existing aeration blower motors and installation of two new 15 hp new VFD compatible motors and VFDs at the Grant Grove Wastewater Treatment Plant.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
M. Contract Line Item No. 13 Grant Grove, Replace Clarifier Mechanisms:
1. This item consists of all labor, materials, and equipment for demolition of existing and installation of chain and flight mechanisms, remove and replace the scum collectors and actuators, and remove and replace chain and flight drive unit on clarifiers #1 & 2 at the Grant Grove Wastewater Treatment Plant. Work also includes the removal of existing wood baffles at each clarifier basin.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
N. Contract Line Item No. 14 Grant Grove, Replace Air Compressors and Add Air Dryers:
1. This item consists of all labor, materials, and equipment for demolition of existing and installation of (2) new air compressors, installation of (2) new air dryers, installation of one (1) new oil/water separator, and two (2) coalescing filters and associated appurtenances at the Grant Grove Wastewater Treatment Plant.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
O. Contract Line Item No. 15 Grant Grove, Blower 4, 5 & 6 Pipe Loop Upgrade:
1. This item consists of all labor, materials, and equipment for modification to the blower 4, 5 & 6 exhaust piping so as to prevent flooding of the blowers by installing vertical pipe loops at the Grant Grove Wastewater Treatment Plant. Work includes painting the new piping to match the existing blower piping.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
P. Contract Line Item No. 16 Grant Grove, Replace Exhaust Fans in the Process Area:
1. This item consists of all labor, materials, and equipment for demolition of existing exhaust fans in the process area and installation of two (2) new wall mounted explosion proof exhaust fans at the Grant Grove Wastewater Treatment Plant. Work also includes the installation of a new protective cover over the fan mounted on the outside of the building.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
Q. Contract Line Item No. 17 Grant Grove, Digester Telescoping Valves:
1. This item consists of all labor, materials, and equipment for demolition of existing and installation of (2) new telescoping valves and scum baffle on digester #1 & 2 at the Grant Grove Wastewater Treatment Plant. Work shall include the reuse of the existing wall mounting brackets or fabrication and installation of new mounting brackets.
SEKI - 184084 01 27 00 - 5
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
R. Contract Line Item No. 18 Grant Grove, Install Combustible Gas Detectors:
1. This item consists of all labor, materials, and equipment for installation and implementation of a combustible gas detector system at the Grant Grove Wastewater Treatment Plant and provide indication to PLC.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
S. Contract Line Item No. 19 Grant Grove, Install New Chlorination System:
1. This item consists of all labor, materials, and equipment for demolition of the existing chlorination system components and installation of a new onsite hypochlorite generation system at the Grant Grove Wastewater Treatment Plant.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
T. Contract Line Item No. 20 Grant Grove, Install DO Analyzers in Aeration Basins:
1. This item consists of all labor, materials, and equipment for installation of two (2) DO monitoring probes and dual channel transmitter within the Grant Grove Wastewater Treatment Plant’s Aeration Basins for monitoring of dissolved oxygen content.
Terminate the I/O’s from the transmitter to the PLC in the MCC.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
U. Contract Line Item No. 21 – Grant Grove, Install New SCADA System
1. This item consists of all labor, materials, and equipment for full demolition and replacement of the existing proprietary SCADA system with a new non-proprietary system at the Grant Grove Wastewater Treatment Plant.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
V. Contract Line Item No. 22 Grant Grove, Replace Motor Control Center:
1. This item consists of all labor, materials, and equipment for full demolition of existing and installation of a new motor control center including all starters, VFD’s, starter buckets, and associated appurtenances at the Grant Grove Wastewater Treatment Plant.
The automatic transfer switch will be replaced as part of the MCC replacement.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
W. Contract Line Item No. 23 Grant Grove, Conduct System Ground Survey:
1. This item consists of all labor, materials, and equipment necessary to complete a survey of all electrical components for ground faults at the Grant Grove Wastewater Treatment Plant.
SEKI - 184084 01 27 00 - 6
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
X. Contract Line Item No. 24 Grant Grove, Add Software Dialer and USB Modem:
1. This item consists of all labor, materials, and equipment for installation of a new software dialer system and USB modem at the Grant Grove Wastewater Treatment Plant.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
Y. Contract Line Item No. 25 Grant Grove, Replace Sludge Bldg. Doors:
1. This item consists of all labor, materials, and equipment for demolition of existing outward swinging doors, door frames, and hardware and installation of new inward swinging doors, door frame, door hardware and doors stops at the sludge building at the Grant Grove Wastewater Treatment Plant.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
3.2 BID OPTIONS (Bid Items 26 – 31)
A. Bid Option No. 1 (Bid Item 26), Replace RAS/WAS AOD Pumps at Grant Grove:
1. This item consists of all labor, materials, and equipment for demolition of existing and installation of the following RAS/WAS pump system components at the Grant Grove Wastewater Treatment Plant: Two (2) RAS/WAS, air operated diaphragm style pumps with CO selected spare parts, demolition of existing and installation of new (2) 4-inch plug valves, and any required modification and painting of the associated piping.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
B. Bid Option No. 2 (Bid Item 27), Replace Supernatant AOD Pumps at Grant Grove:
1. This item consists of all labor, materials, and equipment for demolition of existing and installation of the following supernatant pump system components at the Grant Grove Wastewater Treatment Plant: Two (2) supernatant equalization, air operated diaphragm style pumps with CO selected spare parts, demolition of existing and installation of new
(2) 4-inch plug valves, modification to (2) sight glasses, and any required modification and painting of the associated piping.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
C. Bid Option No. 3 (Bid Item 28), Install Stairway and Platform at Effluent Storage Building at Grant Grove:
1. This item consists of all labor, materials, and equipment for excavation, installation of foundations and support columns, platform framing, installation of stair stringers, handrails, grating and treads for a new access platform located at the effluent storage building at the Grant Grove Wastewater Treatment Plant.
SEKI - 184084 01 27 00 - 7
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
D. Bid Option No. 4 (Bid Item 29), Replace Process Area Ladders at Grant Grove:
1. This item consists of all labor, materials, and equipment demolition and installation of (8) process tank access ladders at the Grant Grove Wastewater Treatment Plant.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
E. Bid Option No. 5 (Bid Item 30), Soda Ash System Scissor Lift at Grant Grove:
1. This item consists of all labor, materials, and equipment for procurement and installation of a scissor lift in the soda ash system pump room at the Grant Grove Wastewater Treatment Plant.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
F. Bid Option No. 6 (Bid Item 31) Clover Creek, Clarifier Rehabilitation:
1. This item consists of all labor, materials, and equipment at the Clover Creek Wastewater
Treatment Plant for demolition of existing and installation of new chain and flight mechanism in clarifier # 2, demolition of existing and installation of new scum collectors and handwheel operators on clarifiers # 1 & 2, demolition of existing and installation of a new mud valve on clarifier # 3, remove existing disconnect and drive unit and install new drive unit on clarifier #1 & 2.
2. Measurement for payment will be based upon completion of the entire work as a lump sum unit.
3. Payment will be made at the contract lump sum price.
- END OF SECTION 01 27 00 -
SEKI - 184084 01 31 00 - 1
031414 PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Construction Coordination.
2. Submittals
3. Requests for Information (RFIs).
4. Project meetings.
5. Environmental Coordination.
1.2 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
SEKI - 184084 01 31 00 - 2
5. Progress meetings.
6. Pre-installation conferences.
7. Project closeout activities.
8. Commissioning activities.
1.3 SUBMITTALS
A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.
8. Waste Management Plan.
9. Quality Control Plan.
B. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies.
Work shall not commence until written Notice to Proceed has been issued.
C. Submit to the CO a list of all employees who will need access to the website. The NPS/DSC SharePoint Project website will be used for transmitting all submittals digitally (with exception of samples). The NPS Share-File system works similar to e-mail but can transmit large files.
Subject line for each submittal will include project name, transmittal number, and a brief description of transmitted data such as: Submittal, RFI, etc.
1.4 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website.
1. CO will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
SEKI - 184084 01 31 00 - 3
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
8. Contractor's signature.
9. Requested date for response.
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete the RFI Form on the NPS/DSC SharePoint website as follows:
1. Enter the general information at the top of the form.
2. Under the “Action” section at the bottom of the form, select “Question” then select
“CMR” in the drop-down of the “Send to” box.
3. Enter the details of the question and attach related documents.
4. Select “Submit Form” at the bottom of the page.
D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract
Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.
1.5 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:
1. Roles & Responsibilities/ Lines of Authority.
SEKI - 184084 01 31 00 - 4
2. Park rules and regulations.
3. Jobsite Safety.
4. Resolution of comments on required Division 01 documents.
5. Coordination of Subcontractors.
6. Labor law application.
7. Modifications.
8. Payments to Contractor.
9. Payroll reports.
10. Contract time.
11. Display of Hotline posters.
12. Notice to proceed.
13. Correspondence procedures.
14. NPS/DSC SharePoint Project website.
15. Acceptance/rejection of work.
16. Progress meetings.
17. Submittal procedures.
18. NPS Final Accessibility Inspection.
19. Permit requirements.
20. As-constructed drawings/operation and maintenance (O&M) manuals.
21. Saturday, Sunday, holiday and night work.
22. Reference materials.
23. Value engineering.
B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings.
All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:
a. Approval of minutes of previous meetings.
b. Submittal status.
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications.
f. Work in progress and projected.
g. Construction Schedule update (provide updated CPM).
h. Status of Project Record Drawings and O&M manuals.
i. Other business relating to work.
1.6 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.
SEKI - 184084 01 31 00 - 5
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; familiarity with Environmental Management Systems (EMSs) such as ISO 14001; must be familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implementation of the Storm Water Pollution Prevention Plan(SWPPP).
c. Present an overview of environmental issues and summarize site specific procedures relating to management plans at the Preconstruction conference.
d. Training for Contractor personnel in accordance with their position requirements.
e. Monitoring and documentation of environmental procedures.
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements.
2. Regulatory Requirements.
3. Noise & Acoustics Management.
4. Temporary Storm Water Pollution Prevention Environmental Management.
5. Construction Waste Management.
C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on the project site. Training shall include the following:
1. Overview of environmental issues related to the building industry.
2. Overview of environmental issues related to the Project.
3. Review of site specific procedures and management plans:
a. Construction Waste Management.
b. Indoor Air Quality (IAQ) Management.
c. Noise & Acoustics Management.
d. Temporary Storm Water Pollution Prevention.
4. Pollution Prevention (P2) practices: Submit evidence of P2 training or participation in P2 programs.
5. Compliance with environmental regulations: As specified in Regulatory Requirements.
Submit Contractor 40 CFR employee training records upon request of Contracting Officer.
D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, IAQ Management Plan, and Storm Water Pollution Prevention Plan.
PRODUCTS (Not Used)
SEKI - 184084 01 31 00 - 6
PART 2 - EXECUTION (Not Used)
END OF SECTION 01 31 00
SEKI - 184084 01 32 16 - 1
031414 CONSTRUCTION SCHEDULE
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
PART 1 - GENERAL
1.1 SUMMARY
A. This Section consists of Construction Schedule requirements including but not limited to the following:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
4. Time Impact Analysis.
B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.
1.2 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.
C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
E. Float: The measure of leeway in starting and completing an activity.
1. Float: Float is not for the exclusive use or benefit of either the Government or the Contractor but is jointly owned.
2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
SEKI - 184084 01 32 16 - 2
3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.
F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.
G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.
1.3 SUBMITTALS
A. Electronic Copies: All schedules and reports submitted shall be posted on the NPS DSC SharePoint project website, provided in the native electronic file format. It is the intent of the Government to limit the number of printed reports to only those reports determined by the project team to be essential.
B. Schedule of Values: After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule.
C. Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit two paper copies of baseline schedule, large enough to show entire schedule for entire construction period.
D. CPM Reports: Concurrent with…