SEKI_157070_-_SOW_SPECS.pdf

PDF 2 MB Posted

Attached to
Rehabilitate & Replace Water System
Solicitation number
P15PS01011
Issued by

About this file

Specifications Statement of Work PMIS 157070

View the file

Other files

File Type Posted
SF30_Amendment_002.pdf PDF
Sol_P15PS01011_Amd_000002.pdf PDF
SEKI_15070_-_E3_-_GGCCWWTP_UST-AST.pdf PDF
P15PS01011-_SITE_VISIT_-_SIGN_IN_ _Q A.PDF PDF
Sol_P15PS01011_Amd_000001.pdf PDF
SF30_Amenment_001.pdf PDF
SEKI_184084_ _158783-_DRAWINGS.pdf PDF
DIRECTION_FRESNO_-_GRANT_GROVE_WWTP.pdf PDF
SEKI_184084_ _158783_-_SOW_SPECS.pdf PDF
Submittal_Instructions.pdf PDF
1442.pdf PDF
PAST_PERFORMANCE_QUESTIONNAIRE.pdf PDF
Bid_Schedule_157070.pdf PDF
SUBCONTRACTOR_REF_FORM.pdf PDF
Bid_Bond_SF_24.pdf PDF
General_References_Form.pdf PDF
SOLICITATION_FINAL.pdf PDF
SEKI_157070_-_DRAWINGS.pdf PDF
Bid_Schedule_SEKI_184084_ _158783.pdf PDF
Sol_P15PS01011.pdf PDF
Wages_DB_Fresno.pdf PDF
Wages_DB_Tulare.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEKI - 157070 1

09/13 TABLE OF CONTENTS

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 11 20 Natural Features Protection 01 27 00 Definition of Contract Line Items 01 31 00 Project Management & Coordination 01 32 16 Construction Schedule 01 33 23 Submittal Procedures 01 35 13.22 Archeological Protection 01 35 23 Safety Requirements 01 35 25 Explosives 01 35 91 Historic Preservation Treatment Procedures 01 40 00 Quality Requirements 01 42 00 References 01 50 00 Temporary Facilities and Controls 01 57 19.12 Noise & Acoustics Management 01 57 23 Temporary Storm Water Pollution Prevention 01 67 00 Product Requirements 01 73 29 Cutting and Patching 01 73 40 Execution 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance Data 01 79 00 Demonstration and Training 01 81 13 Sustainable Design Requirements for Non-LEEDTM Projects

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition and Salvage

DIVISION 03 – CONCRETE

03 33 00 Cast-in-Place Concrete

DIVISION 09 – FINISHES

09 91 00 Painting

DIVISION 23 – HEATING, VENTILATION, AND AIR CONDITIONING

23 01 30 Duct Cleaning 23 05 00 Common Work Results for HVAC 23 05 23 General Duty Valves for HVAC 23 05 29 Hangers and Supports for HVAC Systems 23 05 48 Wind, Seismic, and Vibration Controls for HVAC Work 23 05 93 Testing, Adjusting, and Balancing for HVAC 23 07 00 Mechanical Insulation 23 08 01 Startup Testing

SEKI - 157070 2

09/13 TABLE OF CONTENTS

23 11 23 Fuel Gas Piping and Accessories 23 13 23 Above Ground Propane Storage Tank 23 21 13 Hydronic Piping 23 31 00 Ducts and Accessories 23 34 00 Fans 23 37 00 Air Outlets and Inlets 23 51 00 Breeching, Chimneys and Stacks 23 52 00 Heating Boilers 23 54 00 Furnaces 23 82 00 Convection Units 23 83 16 Gas-Fired Radiant Heaters

DIVISION 26 – ELECTRICAL

26 00 10 Common Work Results for Electrical 26 05 26 Grounding and Bonding for Electrical Systems 26 05 48 Seismic Requirements for Electrical Systems 26 28 16 Miscellaneous Electrical Devices 26 32 13 Engine Generators

DIVISION 31 – EARTHWORK

31 05 25 Utility Line Marking 31 10 00 Site Clearing 31 10 01 Restoration and Surfaces 31 22 00 Topsoiling and Finished Grading 31 23 00 Earthwork for Structures 31 23 16.13 Rock Removal 31 23 33 Utility Trenching and Backfilling 31 25 27 Watering

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 16 00 Pavement, Curbs, and Walks

SEKI - 157070 011100 - 1

09/13 SUMMARY OF WORK

SECTION 011100 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Project Narrative

2. Work covered by the Contract Documents.

3. Work phases.

4. Work under other contracts.

5. Government Furnished Materials.

6. Use of premises.

7. Government's occupancy requirements.

8. Work Restrictions.

9. Special Construction Requirements.

1.2 PROJECT NARRATIVE

A. The scope of work under this project includes replacing oil fired heating equipment with propane fired units and providing an above ground propane storage tank with vaporizer and underground distribution piping. The tank is sized for approximately six months of heating fuel requirement and one week of generator fuel requirement. It is assumed that the heating capacity of existing equipment is adequate to meet the building heating demand. Maintenance staff indicated that during peak winter, temperature in some portions of pipe gallery remains low and that affects the operation of pneumatic valves/controls. Some of the pipes are presently being heat traced to avoid operational problems. New propane fired infra-red heaters are proposed for the pipe gallery to enhance the temperature coverage. Additional scope includes replacing the fuel oil powered generator with a propane unit piped from the new above ground propane storage tank. One week of generator operation is accounted for in sizing the tank.

1.3 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: This Project is located in Kings Canyon National Park in the Grant Grove area (approximately 6,300 feet above mean seal level.) Access to some project sites may be restricted to the months of June to November due to lingering snow in the area.

B. The Work consists of the following:

1. The Work includes fuel storage and HVAC improvements to the existing Grant Grove Wastewater Treatment Plant (WWTP). The work includes, but is not limited to, the following major components:

a. Demolish existing 4,000-gallon underground diesel storage tank and associated diesel piping. Demolition shall be in accordance with all applicable State, County and local regulations. Demolition shall include soil sampling and a summary report

SEKI - 157070 011100 - 2

that meets code requirements. Contractor shall provide report to NPS for submission to regulatory agencies. Minimum report requirements will likely include:

1) Site location map and tank vicinity map

2) Sample locations map

3) Summary of sampling procedure

4) Sampling results, including, but not limited to, diesel-range total petroleum hydrocarbons (TPH-d); benzene, toluene, ethylbenzene, and xylenes (BTEX); and methyl tertiary butyl ether (MTBE).

5) Summary of alternatives (if positive samples are encountered)

6) Conclusions and recommendations

b. Demolish existing HVAC and electrical equipment.

c. Provide new 12,000-gallon above ground liquid propane storage tank and ancillary equipment, piping, valves and appurtenances.

d. Provide new propane HVAC equipment in the Treatment Building and Sludge

Drying Building.

e. Replace existing diesel emergency generator with new 150-kW propane emergency generator. Contractor shall submit and pay all permitting fees with san Joaquin Air District (permit to construct and permit to operate) to include full manufacturer representative start-up.

f. Grind and repave existing asphalt parking lot area (Bid Option A.)

g. Lighting control switch improvements at the Treatment Building (Bid Option B.)

C. Project will be constructed under a single prime contract.

1.4 WORK PHASES

A. The Work shall be conducted in an effort to minimize interruptions to existing wastewater treatment plant process. The construction sequence shall generally be as follows:

1. Installation of new bulk propane tank and appurtenances.

2. Demolition of existing diesel generator and installation of new propane generator.

3. Demolition of existing furnace and unit heaters and installation of new furnace and unit heaters.

4. Demolition and remediation of the existing diesel UST.

5. Asphalt paving (Bid Option A.)

1.5 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to areas within the Contract limits indicated on Drawings. Staging locations are also noted on the Drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated. Contractor shall restore all disturbed surfaces, features, drainage patterns, roadside ditches, trails, etc. to pre-construction conditions.

1. Limit site disturbance, including earthwork and clearing of vegetation, to 40 feet beyond building perimeter; 10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter; 15 feet beyond primary roadway curbs and main utility branch trenches; and 25 feet beyond constructed areas with permeable surfaces (such as pervious paving areas, storm water detention facilities, and fields) that require additional staging areas in order to limit compaction in the constructed area.

SEKI - 157070 011100 - 3

2. Equipment such as track hoes may be allowed on asphalt surfaces if approved by the Contracting Officer. All damage to roads, curbing, sidewalks, etc. shall be restored to pre-construction conditions by Contractor at no additional cost to the Government. The Contracting Officer will photograph and/or videotape pre-construction condition with particular attention to historic stone paving and curbs.

3. Road access to buildings and other facilities must remain open at all times; all other internal roads may only be interrupted between the hours of 6:00PM and 6:00AM with 48-hour previous notice and approval.

B. Storage of Materials: Confine storage of materials to pre-approved areas noted as staging areas and other adjacent salvage storage areas as directed by the Contracting Officer. Contractor shall return all storage areas to the same condition which they found them at the start of construction.

C. Preservation of Natural Features:

1. All equipment shall be power washed and inspected before entering the Park to ensure it is free of non-native weeds and/or seeds. In addition sources of imported rock, sand, gravel, and soil shall be inspected for invasive non-native plants, weeds and/or seeds. The Contractor shall submit a list of proposed sources, end use and temporary storage requirements for imported material, 30 calendar days prior to delivery. Imported material shall be free of non-native weeds and/or seeds. Imported material shall be shipped directly from the source to the Park without intermediary storage or staging. Shipping vessels shall be covered to prevent spillage or blowing of their contents while in transit.

2. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

3. Major roots (greater than 4-inches in diameter) that are encountered during excavation and trenching shall be left in place (no cutting permitted), and covered with wet burlap to prevent sunscald if exposed. Protect roots that have been exposed by demolition of foundations or utilities and immediately cover with backfill. If within the critical root zone, excavate with hand tools. Provide temporary barriers to protect existing trees and plants and root zones.

4. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove agreed-on roots and branches that interfere with construction.

5. Do not fasten ropes, cables, or guys to existing trees.

6. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

7. Forest duff/litter shall be carefully collected prior to cut/fill to be used as slope stabilization on slopes of 3:1 or greater; top soil shall be collected from cut/fill to be used as slope stabilization on slopes less than 3:1.

D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

E. Construction Camp: Establishment of a camp within the park will not be permitted.

SEKI - 157070 011100 - 4

F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment. Vehicle access is best from the Highway 180 Entrance (Kings Canyon National Park.)

Vehicles longer than 22 ft must enter through the Highway 180 Entrance. Hauling restrictions exist from Ash Mountain to Giant Forest – No Vehicles Over 22-ft Long Are Permitted.

1.6 PUBLIC USE OF SITE

A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.

1.7 OCCUPANCY REQUIRMENTS FOR BUILDINGS

A. Existing Buildings

1. Full Government Occupancy: Government will occupy buildings that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO.

b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.

c. Provide a minimum 72-hour notice for all work requiring access inside existing Park buildings.

1.8 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 8:00 a.m. to 4:30 p.m., Monday through Friday, except when otherwise indicated. Work outside these hours may be approved by the Contracting Officer if requested in writing by the Contractor.

No holiday work will be permitted.

B. Contractor shall minimize service interruptions to existing services. Contractor shall provide a plan showing the sequencing of cutovers for review and approval by the Contracting Officer. This plan shall be submitted prior to the pre-construction meeting.

C. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

SEKI - 157070 011100 - 5

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

D. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than 72 hours in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

E. Throughout the entire construction period, the Contractor shall schedule all Work and provide temporary facilities, electrical power and control circuits, and bypass piping to minimize utility shutdowns. Work shall be scheduled such that interruptions to service (HVAC and backup generator) are to be completed to maintain facilities at temperatures that prevent freezing.

Contractor shall be responsible for temporary backup power during high risk power outage periods of time (December through April).

F. Contractor must supply all utilities for construction except water; water shall be metered with back flow preventer supplied by the Contractor and paid for at current rate per 1,000 gallons and up to 25,000 gallons per day may be available depending on time of year.

G. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes. Smoking shall only be allowed in approved areas in accordance with SEKI Management Directive No. 29.

1.9 SPECIAL CONSTRUCTION REQUIREMENTS

A. Contractor shall complete pre-construction walk-through with the Contracting Officer Representative to verify all utility alignments, propane tank location, building locations, construction access points, etc.

B. Current generator at Grant Grove Wastewater Treatment Plant must remain in service between December 1st and May 1st or newly installed generator must be in service prior to December 1st.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011100

SEKI 157070 011200-1

08/13 NATURAL FEATURES PROTECTION

SECTION 011200 – NATURAL FEATURES PROTECTION

PART 1 GENERAL

1 .1 DESCRIPTION

A. The work of this section consists of protection of vegetation and native soils to be retained within and adjacent to the perimeter work limits of this project. This section also consists of evaluation processes and mitigation measures in the event of tree damage, casualty, or removal and unauthorized passage outside authorized work limits.

1 .2 RELATED REQUIREMENTS

1 .3 PLANT CONDITION INVENTORY

A. Prior to the placement of all fencing, barricades and tree wrap and any excavation operations, the Contractor and Contracting Officer together shall perform an on-site inventory of trees and other natural features in the entire project site. A print of the contract document site plan will be used to note placement and condition of existing trees. Previous damage to trees and vegetation shall be noted. This site plan print shall be retained by the Contracting Officer for use during the final walk-through tree assessment scheduled during the project closeout.

PART 2 PRODUCTS

2 .1 TREE TRUNK PROTECTION

A. Four-foot high wood-lathe snow fencing.

2 .2 WORK LIMITS - CONSTRUCTION ZONE WARNING TAPE

A. Banner Guard construction zone warning tape, imprinted with “CAUTION: CONSTRUCTION AREA”, manufactured by Reed Industries, Inc., Houston, Texas, or approved equal.

2 .3 CONSTRUCTION FENCING

A. Four-foot high orange plastic mesh construction fencing.

B. 6-ft steel posts.

2 .4 TREE TRUNK PROTECTION

A. 4-ft high wood-lathe snow fencing.

2 .5 TEMPORARY BARRICADE

A. Four-foot high orange plastic mesh construction fencing.

B. 6-ft steel posts.

SEKI 157070 011200-2

07/13 NATURAL FEATURES PROTECTION

3 PART 3 EXECUTION

3 .1 IMPORT OF MATERIALS

A. Sources of rock, sand, gravel, earth, soil, or other imported natural material may be inspected for invasive non-native plants prior to acceptance. The contractor shall submit to the NPS Contracting Officer a list of proposed sources for import materials 30 calendar days in advance of importing material. The list shall also include the end use and any temporary storage requirements of those materials. NPS Natural Resources staff would inspect sources of materials that pose a risk, either by their end use or storage requirements, of allowing invasive non-native plants (also known as noxious weeds) to establish in the park. Materials may be rejected if non-native invasive plants are present at the source and seeds could be present in the material. At the discretion of the NPS Contracting Officer, potentially contaminated materials may be accepted if mitigating measures are implemented. Mitigation might include stripping the top 12 inches of source material, requiring fresh material stored less than 1 month, or sterilizing the material. Contaminated materials that contain fines and have an end-use on the surface would require sterilization before importing to the park. Import material shall be shipped directly from the source to the park without intermediary storage or staging. Shipping vessels shall be covered to prevent spillage or blowing of their contents while in transit. Materials must also be transported and stored such that they would not acquire invasive non-native plant seeds from adjacent vegetation.

B. The following is a list of import material sources within local region of Sequoia and Kings Canyon National Parks that have been used by past projects and inspected by the National Park Service. Utilization of one or more of these sources does not provide approval of the source and material but rather, the list is intended to provide contractors with information on sources that in the past have passed the NPS’s Natural Resource’s inspection. This may reduce contractors’ perceived risk that they may not have local knowledge of import material sources.

1. Lemon Cove Granite

2. Vulcan – Friant

3. Cemex – Lemon Cove

4. Vulcan - Sanger

3 .2 PROTECTION INSTALLATION

A. Provide temporary work limit fencing, tree trunk wrap, and tree barricades to protect existing trees, plants and critical root zones as directed by the Contracting Officer. Protections shall be in place before any excavation work or heavy equipment is allowed on site.

3 .3 CONSTRUCTION FENCING

A. Within the perimeter work limits, protect groups of shrubs and small trees and undisturbed soils as directed by the Contracting Officer with construction fencing. Firmly anchor fences to the ground a minimum of 2 feet from the nearest plant. Completely and continuously enclose areas of trees and shrubs to be protected with fencing.

3 .4 TREE TRUNK PROTECTION

A. For isolated trees up to 4 feet dbh (diameter breast height) within the work limits, provide tree trunk protection as directed by the Contracting Officer.

B. Wrap wood lathe snow fencing continuously around the circumference of the trunk from the base to a height of not less than 6 feet. Wrap shall be a minimum of two layers. Fence wrap shall be secured around the trunk by three strands of jute or other natural fiber rope around top, middle and bottom of the tree trunk protection. No anchoring or nailing in trees will be allowed.

SEKI 157070 011200-3

07/13 NATURAL FEATURES PROTECTION

3 .5 PROTECTION MAINTENANCE

A. Only after all tree and plant protection has been installed, and the Contracting Officer has inspected and given written approval of the tree and plant protection, will the Contractor be allowed to begin excavation. All tree and plant protection shall be maintained throughout the duration of this project.

B. If any fencing, barriers, staking or marking, which designates protected areas, limits of demolition or work limits, is knocked down, moved or destroyed by the Contractor, the Contractor will immediately move the work operation to another area, wholly or in part, or suspend work operations, until the fence or other protection is repaired to the Contracting Officer's satisfaction at the Contractor's expense. Time lost due to such stoppage will not be considered basis for adjustment of completion date nor additional payment.

C. Parking vehicles and storing materials or supplies shall be confined to areas designated as staging areas on the plans or as specifically approved by Contracting Officer. Vehicle and material storage activities are strictly prohibited from protected and fenced sensitive soil and vegetation areas.

D. Fastening ropes, cables, or guys to existing trees and disposing of materials including, but not limited to paint, paint thinner, fiberglass materials, fiberglass thinners, concrete or cement residue, washings from cement or concrete mixers or any other material considered harmful by the Contracting Officer is prohibited anywhere in the project area.

E. Do not remove, injure, or destroy trees or other plants without prior approval of the Contracting Officer. Consult with the Contracting Officer and remove agreed upon roots and branches that interfere with excavation or pipe placement. All pruning of canopy or cutting of roots will be done under the supervision of the Contracting Officer, and shall be done as set forth by the National Arborist Association or the International Society of Arboriculture.

F. If within the critical root zone, excavate with hand tools.

G. At project completion, the Contractor shall remove all protections and be properly disposed of or recycled.

END OF SECTION

SEKI - 157070 012700 - 1

09/13 DEFINITION OF CONTRACT LINE ITEMS

SECTION 012700 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item No. 1 – Mobilization / Demobilization.

1. This item includes mobilizing and demobilizing all required equipment and construction materials to the site.

2. Measurement for payment shall be by lump sum.

3. Payment will be made at the contract lump sum price. Maximum price for this bid item shall be six percent (6%) of the Total Base Bid.

B. Contract Line Item No. 2 – Demolition / Removal of Diesel Underground Storage Tank.

1. This item includes furnishing all materials, equipment and labor for demolition and removal of the existing 4,000-gallon diesel underground storage tank and appurtenances as shown on the Drawings, and disposal of demolished material in accordance with all State, County and local regulations. This item shall include providing all environmental remediation and environmental reports in accordance with all State, County and local regulations. Environmental reports are to be provided to NPS staff who will work directly with the agencies. The anticipated environmental reporting requirements are summarized in Spec Section 011100 – Summary of Work. The existing wastewater system will be required to be in service until the remainder of the project improvements are complete (tested and accepted.) Demolition will include the existing tank and all associated equipment and appurtenances.

2. Measurement for payment shall be by lump sum.

3. Payment will be made at the contract lump sum price.

C. Contract Line Item No. 3 – Propane Above-Ground Storage Tank.

1. This item consists of furnishing all materials, equipment, and labor for installation of a 12,000-gallon liquid propane above-ground storage tank as shown on the Drawings. The work includes, but is not limited to, clearing, grubbing, excavation, dewatering, bedding, SEKI - 157070 012700 - 2 backfill, compaction, concrete support piers, snow posts, bollards, erosion control measures, and all other work necessary to complete the installation. Yard piping and the vaporizer are NOT included in this line item; they are included in Contract Line Item No.

4.

2. Measurement for payment shall be by lump sum.

3. Payment will be made at the contract lump sum price.

D. Contract Line Item No. 4 – Vaporizer and Propane Piping.

1. This item consists of furnishing all materials, equipment, and labor for installation of the propane vaporizer and all associated yard piping and appurtenances. The work includes, but is not limited to, trenching, backfilling, compaction, propane piping in the yard, piping connections, a vaporizer and appurtenances on the exterior of the Treatment Building, fill station, instrumentation & controls, and all other work necessary to complete the installation.

2. Measurement for payment shall be lump sum.

3. Payment will be made at the contract lump sum price.

E. Contract Line Item No. 5 – HVAC Improvements.

1. This item consists of furnishing all materials, equipment, and labor for installation of interior HVAC improvements at the Treatment Building and Sludge Building as shown on the Drawings. The work includes, but is not limited to, demolition of existing HVAC equipment and associated interior diesel piping, new HVAC equipment, and all other work necessary to complete the installation. Please note that the electrical work associated with the HVAC replacement is separately included in Contract Line Item No.

6.

1. Measurement for payment shall be lump sum.

2. Payment will be made at the contract lump sum price.

F. Contract Line Item No. 6 – Electrical Improvements.

1. This item consists of furnishing all materials, equipment, and labor for installation of the electrical improvements associated with the HVAC improvements in the Treatment Building and Sludge Building and associated with the propane tank installation. The work includes, but is not limited to, demolition of the existing HVAC-related electrical equipment, installation of all new electrical equipment associated with the HVAC improvements, installation of all new electrical equipment associated with the propane tank, and all other work necessary to complete the installation. Please note that the emergency generator replacement, including demolition, is included separately in Contract Line Item No. 7.

2. Measurement for payment shall be by lump sum.

3. Payment will be made at the contract lump sum price.

G. Contract Line Item No. 7 – Emergency Generator Replacement.

1. This item includes furnishing all materials, equipment and labor for replacement of the existing diesel emergency generator in the Treatment Building with a new propane emergency generator as shown on the Drawings. The work includes, but is not limited to, demolition and removal of the existing emergency generator, new propane emergency

SEKI - 157070 012700 - 3

generator, new control cabinet, connection to the existing panel and auto transfer switch, and all other work necessary to complete the installation.

2. Measurement for payment shall be by lump sum.

3. Payment will be made at the contract lump sum price.

BID OPTION A – ASPHALT PAVING

H. Contract Line Item No. 8 – Option A, Asphalt Paving.

1. This item includes furnishing all materials, equipment and labor for installation of an asphalt parking area at the Wastewater Treatment Facility as shown on the Drawings.

This work includes, but is not limited to, preparation of subgrade, installation of aggregate road base, asphalt pavement, shoulder improvements, compaction, removal of excess materials, and connections to existing surfaces. Measurement and payment will be the number of actual square feet of asphalt/road base installed, completed and accepted.

2. Measurement shall be the number of actual square yards of asphalt/road base installed, completed and accepted.

3. Payment will be made at the contract price per square yard.

BID OPTION B – TREATMENT BUILDING LIGHTING REPLACEMENT

I. Contract Line Item No. 9 – Option B, Treatment Building Lighting Replacement.

1. This item includes furnishing all materials, equipment and labor for installation of new energy efficient lights at the Treatment Building as shown on the Drawings. This work includes, but is not limited to, demolition and removal of the existing lighting fixtures and replacement with new energy efficient lighting fixtures and appurtenances.

2. Measurement for payment shall be lump sum.

3. Payment will be made at the contract lump sum price.

END OF SECTION 012700

SEKI - 157070 013100 - 1

08/13 PROJECT MANAGEMENT AND COORDINATION

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Construction Coordination.

2. Project meetings.

3. Environmental Coordination.

1.2 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.

B. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule.

2. Preparation of the Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Pre-installation conferences.

7. Project closeout activities.

8. Commissioning activities.

SEKI - 157070 013100 - 2

1.3 SUBMITTALS

A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.

1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:

a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to the Contracting Officer for resolution of such conflicts.

2. Sheet Size: At least 8-1/2 by 11 inches but no larger than 30 by 40 inches.

3. Number of Copies: Submit two opaque copies of each submittal. Contracting Officer will return one copy.

4. Refer to individual Sections for Coordination Drawing requirements for Work in those

Sections.

B. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.

1. Letter designating Project Superintendent.

2. Construction Schedule.

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention Plan.

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor.

8. Quality Control Plan.

9. Storm Water Pollution Prevention Plan.

C. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies.

Work shall not commence until written Notice to Proceed has been issued.

D. Submit to the CO a list of all employees who will need access to the NPS Share-File system.

This system will be used for transmitting all submittals digitally (with exception to samples).

The NPS Share-File system works similar to email but can transmit large files. Subject line for each transmittal will include project name, transmittal number and brief description of transmitted data such as: Submittal, RFI, RPP, etc.

SEKI - 157070 013100 - 3

1.4 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:

1. Roles & Responsibilities/ Lines of Authority.

2. Park rules and regulations.

3. Resolution of comments on required Division 01 documents.

4. Coordination of Subcontractors.

5. Labor law application.

6. Modifications.

7. Payments to Contractor.

8. Payroll reports.

9. Contract time.

10. Display of Hotline posters.

11. Notice to proceed.

12. Correspondence procedures.

13. Acceptance/rejection of work.

14. Progress meetings.

15. Submittal procedures.

16. NPS Final Accessibility Inspection.

17. Environmental requirements.

18. As-constructed drawings/operation and maintenance (O&M) manuals.

19. Saturday, Sunday, holiday and night work.

20. Reference materials.

21. Value engineering.

B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the Contractor.

1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings.

All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:

a. Approval of minutes of previous meetings.

b. Submittal status.

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications.

f. Work in progress and projected.

g. Construction Schedule update (provide updated CPM).

h. Status of Project Record Drawings and O&M manuals.

i. Other business relating to work.

SEKI - 157070 013100 - 4

1.5 ENVIRONMENTAL COORDINATION

A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.

1. Qualifications: Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; familiarity with Environmental Management Systems (EMSs) such as ISO 14001; must be familiar with environmental regulations applicable to construction operations.

2. Responsibilities: Responsibilities shall include:

a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.

b. Implementation of the Storm Water Pollution Prevention Plan(SWPPP).

c. Present an overview of environmental issues and summarize site specific procedures relating to management plans at the Preconstruction conference.

d. Training for Contractor personnel in accordance with their position requirements.

e. Monitoring and documentation of environmental procedures.

B. Perform project quality control in accordance with requirements specified in Related Sections, including:

1. Quality Requirements.

2. Regulatory Requirements.

3. Noise & Acoustics Management.

4. Temporary Storm Water Pollution Prevention Environmental Management.

5. Construction Waste Management.

C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on the project site. Training shall include the following:

1. Overview of environmental issues related to the building industry.

2. Overview of environmental issues related to the Project.

3. Review of site specific procedures and management plans:

a. Construction Waste Management.

b. Noise & Acoustics Management.

c. Temporary Storm Water Pollution Prevention.

4. Pollution Prevention (P2) practices: Submit evidence of P2 training or participation in P2 programs.

5. Compliance with environmental regulations: As specified in Regulatory Requirements.

Submit Contractor 40 CFR employee training records upon request of Contracting Officer.

D. Provide documentation for environmental procedures as specified herein and in accordance with approved Storm Water Pollution Prevention Plan.

PRODUCTS (Not Used)

SEKI - 157070 013100 - 5

PART 2 - EXECUTION (Not Used)

END OF SECTION 013100

SEKI - 157070 013216 - 1

08/13 CONSTRUCTION SCHEDULE

SECTION 01 32 16 – CONSTRUCTION SCHEDULE

PART 1 - GENERAL

1.1 SUMMARY

A. This Section consists of Construction Schedule requirements including but not limited to the following:

1. Schedule of Values

2. Construction Schedule Requirements.

3. Construction Schedule Updates.

4. Time Impact Analysis.

B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.

1.2 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.

C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.

E. Float: The measure of leeway in starting and completing an activity.

1. Float: Float is not for the exclusive use or benefit of either the Government or the Contractor but is jointly owned.

2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.

SEKI - 157070 013216 - 2

3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.

G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.

1.3 SUBMITTALS

A. Electronic Copies: All schedules and reports submitted shall be on the NPS Share-File system, provided in the native electronic file format. It is the intent of the Government to limit the number of printed reports to only those reports determined by the project team to be essential.

B. Schedule of Values: After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule.

C. Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit two paper copies of baseline schedule, large enough to show entire schedule for entire construction period.

D. CPM Reports: Concurrent with CPM schedule, submit three paper copies of each of the following computer-generated reports. Format for each activity in reports shall contain activity number, activity description, cost and resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.

1. Activity Report: List of all activities sorted by activity number and then early start date, or actual start date if known.

2. Logic Report: List of predecessor and successor tasks for all activities, sorted in ascending order by activity number and then early start date, or actual start date if known.

3. Total Float Report: List of all activities sorted in ascending order of total float.

E. Construction Schedule Updates: On or before the 7th day preceding the progress payment request date, submit estimates of the percent completion of each schedule activity and necessary supporting data.

F. Construction Schedule Revisions and Time Impact Analysis: For each Construction Schedule revision submit two paper copies of a Time Impact Analysis. Each Time Impact Analysis shall include a Fragmentary Network (Fragnet), incorporated into the currently accepted Construction Schedule, demonstrating how the Contractor proposes to incorporate a modification, change, delay, or Contractor request.

1.4 QUALITY ASSURANCE

A. The Contractor shall meet with the Contracting Officer on the day of the preconstruction conference to go over the following:

1. Review software limitations, content and format for reports.

SEKI - 157070 013216 - 3

2. Verify availability of qualified personnel needed to develop and update schedule.

3. Discuss constraints, including phasing, work stages, area separations, interim milestones, and partial Government occupancy.

4. Review delivery dates for Government-furnished products.

5. Review schedule for work of separate Government contracts.

6. Review time required for review of submittals and re-submittals.

7. Review requirements for tests and inspections by independent testing and inspecting agencies.

8. Review time required for completion and startup procedures.

9. Review and finalize list of construction activities to be included in schedule.

10. Review baseline schedule comments, resolve issues and progress on incorporating them

11. Review procedures for updating schedule.

12. Discuss reporting requirements and establish a protocol for naming and transmitting electronic schedules.

B. Contractor's Schedule Representative: Before or at the preconstruction conference, designate an authorized representative to be responsible for the preparation and maintenance of the Construction Schedule. A resume outlining the qualifications of the Scheduler shall be submitted to the Contracting Officer for acceptance. The Scheduler shall have prepared and maintained at least 5 previous schedules of similar size and complexity similar to this Contract, demonstrating proficiency in the use of scheduling software. The authorized representative will be responsible for preparing the Baseline Schedule, all required updates, revisions, Time Impact Analyses, and preparation of reports.

1.5 COORDINATION

A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors.

B. Coordinate Construction Baseline Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.

1. In developing the Construction Baseline Schedule, ensure that the Subcontractor’s work at all tiers, as well as the prime Contractor’s work, is included and coordinated.

2. Secure time commitments for performing critical elements of the Work from parties involved.

3. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

PART 2 - PRODUCTS

2.1 SCHEDULE OF VALUES

A. Contractor may breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work

SEKI - 157070 013216 - 4

activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include general condition costs, overhead or profit as a separate item.

B. Do not break down unit price items. Use only the contract price for unit price items.

C. The total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments.

D. An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting Officer before the first progress payment is processed.

2.2 CONSTRUCTION SCHEDULE REQUIREMENTS

A. Construction Baseline Schedule: Prepare Construction Baseline Schedule using a computerized, cost, and resource-loaded, time-scaled CPM network analysis diagram for the Work.

1. Develop and finalize Construction Baseline Schedule so it can be accepted for use no later than 30days after date established for the Notice of Award.

a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing all work within applicable completion dates, regardless of Governments acceptance of the schedule.

2. Establish procedures for monitoring and updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.

B. Construction Baseline Schedule Preparation: Prepare a list of all activities required to complete the Work. Using the preliminary CPM network diagram, prepare a skeleton network to identify probable critical paths.

1. Activities: Indicate the estimated duration, sequence requirements, and relationship of each activity in relation to other activities.

2. Critical Path Activities: Identify critical path activities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates.

3. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the CPM schedule within the limitations of the Contract Time.

4. The Construction Baseline Schedule as developed shall show the sequence and interdependence of activities required for complete performance of the work. Ensure all work sequences are logical and the Construction Baseline Schedule shows a coordinated plan of the work.

5. Resource loading of each activity shall include all personnel by labor category and equipment type and capacity proposed to complete the activity in the duration shown.

6. Consider seasonal weather conditions in planning and scheduling all work influenced by high and low ambient temperatures, wind, or precipitation to ensure completion of all work within the contract time.

SEKI - 157070 013216 - 5

7. Time Frame: Proposed duration assigned to each activity shall be the Contractor's best estimate of time required to complete the activity considering the scope and resources…