This document includes a scope of work and related federal contract opportunity notice for construction services. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 15 is seeking a contractor to construct and renovate medical/surgical beds at the Robert J. Dole VA Medical Center in Wichita, Kansas. The scope of work involves vertically expanding an existing building two stories and renovating the east wing of an inpatient unit to provide private patient rooms. The pre-solicitation notice specifies this as a competitive total set-aside for Service-Disabled Veteran-Owned Small Businesses. The estimated cost range is between $5-10 million and the period of performance is 730 calendar days. Interested offerors should monitor the Beta SAM website for the full solicitation package releasing on or around October 20, 2020, which will include drawings, site visit information, and instructions for proposals due approximately 30 days after issuance.
View the file
Other files
Show all 45
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
May 22,2020
SCOPE OF WORK
1. PROJECT DATA:
TITLE: Construct and Renovate Med/Surg Beds for Patient Privacy, B1 & B1C
BUILDING/FACILITY: VAMC Wichita, 5500 E Kellogg Wichita, KS 67218
PROJECT NUMBER: Project #589-701
COR: Maggie Day
REQUESTOR: Conrad Pierce
CONTRACTOR: Out for Bid
CONTRACT PERIOD OF PREFORMANCE: 730 Calendar days
GENERAL SCOPE: The General Contractor shall furnish all labor, materials, supervision and perform all work to vertically expand building 1C two stories and renovate the east wing of the Med/Surg Unit on the third floor of building 1. The two additional floors are being built to provide off unit program and administrative space and the east wing is to be renovated to provide private patient rooms with restroom.
The exterior of the new two-story addition shall be brick with cast stone banding and insulated low-e glazed windows. The elements shall match the existing adjacent facades. The roof material shall be white TPO.
The work within the expansion and renovation of the 3rd floor Building 1 east wing shall be with al l new materials. The existing Med/Surg Unit shall be demolished to structural members and MEP shall be removed up to the main piping, duct trunks and electrical feeds. Wall construction shall consist of typical metal stud and gypsum board. Finishes shall include acrylic latex wall paint Low VOC, acoustic panel ceilings, carpet ti le in offices, LVT in staff administrative support areas, resilient sheet vinyl in nursing support areas, and porcelain ceramic tile in toilet and shower rooms. Handrail and wall protection shall be provided throughout patient accessed areas. Corner guards shall be provided as well as new signage/way finding. Casework shall be provided at the nurse stations, patient rooms and administrative rooms as shown in the drawings and specifications.
Construction shall include but is not limited to general construction, demolition, removal and disposal: wall al terations; required fire protection & detection to include the replacement of valves; nurse call stat ions; new air handling unit, a temporary air handler while the old is being demolished and new one installed, heating and ventilation/air conditioning (HVAC), May 22,2020 plumbing (supply and waste), electrical service, interior/exterior lighting, and monitoring connection to the existing Direct Digital Control (DDC) building automation/alarm systems, wiring for security cameras and badge access systems as well as data lines and public address systems, new interior finishes to ceiling, walls and flooring, medical gas demolition, new installation and certification, casework, installation of government furnished equipment and other items as required by the drawings and specifications.
The contractor shall locate all existing utilities within site location and determine the connections/locations that meet the needs for the proposed project; this shall include size, configuration and locations of proposed utilities in relat ion to existing utilities to eliminate conflicts and relocations to the greatest extent possible.
The construction of this project will take place in a very busy occupied building. The addition is being constructed over PET/CT and ultrasound department and the renovation is in in-patient care area. The construction is to be completed to al low medical care functions to be maintained and uninterrupted throughout construction – necessitating carefully phased construction and coordination with the VA COR/users.
END OF SCOPE OF WORK