RFI received 11-2-2020.docx

DOCX document 15 KB Posted

Attached to
Z2DA--Construct and Renovate Med/Surg Beds for Patient Privacy, B1 and B1C P/N:589-701
Solicitation number
36C25520R0115
Issued by

About this file

This document provides details regarding a federal construction solicitation for medical facility renovations. The Department of Veterans Affairs is seeking a contractor to vertically expand an existing building by two stories and renovate the east wing of a medical/surgical unit on the third floor. Work includes demolition, new construction, and finishes. Mechanical, electrical, and plumbing scope involves removing and replacing systems. The period of performance is 730 calendar days from notice to proceed. The project cost range is $5-10 million. The NAICS code is 236220 for construction of commercial and institutional buildings with a small business size standard of $39.5 million. This is a total SDVOSB set-aside. The solicitation package will be available for download on or around October 20th with proposals due approximately 30 days after issuance. Only one organized site visit will be scheduled. Interested parties should monitor the beta SAM website and direct any questions to the point of contact listed by the due date.

View the file

Other files

File Type Posted
281300 - Physical Access Control System.pdf PDF
18.1019.05 - Addendum 5 Dwgs - Pages 8-14.pdf PDF
18.1019.05 - Addendum 5 Revised AE601.pdf PDF
589-701 PRE BID SIGN IN SHEET.pdf PDF
36C25520R0115 0005.docx DOCX document
000110 Table of Contents revised for A0005.pdf PDF
022113 - Site Surveys.pdf PDF
As builts bldg 19 to bldg 2 connecting cor dwgs.pdf PDF
18.1019.05 Addendum 5 Dwgs pages 1-7.pdf PDF
P09 589-701 Revised Drawings Pg 81-90.pdf PDF
36C25520R0115 0004.docx DOCX document
230923.pdf PDF
P09 589-701 Revised Drawings Pg 1-10.pdf PDF
P09 589-701 Revised Drawings Pg 11-20.pdf PDF
P09 589-701 Revised Drawings Pg 41-50.pdf PDF
P09 589-701 Revised Drawings Pg 71-80.pdf PDF
P09 589-701 Revised Drawings Pg 91-100.pdf PDF
226300.pdf PDF
000110 Table of Contents.pdf PDF
P09 589-701 Revised Drawings Pg 31-40.pdf PDF
P09 589-701 Revised Drawings Pg 61-70.pdf PDF
P09 589-701 Revised Drawings Pg 101-117.pdf PDF
P09 589-701 Revised Drawings Pg 51-60.pdf PDF
P09 589-701 Revised Drawings Pg 21-30.pdf PDF
18.1019.05 - 2020.11.16 - List of Changes.docx DOCX document
226200.pdf PDF
36C25520R0115 0003.docx DOCX document
36C25520R0115 0002.docx DOCX document
S02 36C25520R0115_2.docx DOCX document
36C25520R0115 0001.docx DOCX document
P09 589-701 Drawings Pg 41-50.pdf PDF
P09 589-701 Drawings Pg 11-20.pdf PDF
P09 589-701 Drawings Pg 21-30.pdf PDF
P09 589-701 Drawings Pg 31-40.pdf PDF
P09 589-701 Drawings Pg 1-10.pdf PDF
P09 589-701 Drawings Pg 91-100.pdf PDF
P09 589-701 Drawings Pg 51-60.pdf PDF
P09 589-701 Drawings Pg 101-116.pdf PDF
P09 589-701 Drawings Pg 61-70.pdf PDF
P09 Bid Docs - Specs Vol 2.pdf PDF
P09 589-701 Drawings Pg 81-90.pdf PDF
P09 SOW 589-701rev_01.pdf PDF
P09 Bid Docs - Specs Vol 1.pdf PDF
36C25520R0115_2.docx DOCX document
P09 589-701 Drawings Pg 71-80.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question 1- Within Factor 1, Relevant Past Performance of Prime Contractor, the RFP states in paragraph (A), “Substitution of subcontractor experience is not allowed. Offers which present subcontractor experience shall not be considered for award.” However, further down under Factor 1, it continues to state, “In accordance with FAR Part 15.305(a)(2), in the case of an offeror that is without a record of relevant past performance, or for whom information on past performance is not available, the offeror may not be evaluated favorably or unfavorably on past performance. Such offerors may submit relevant past performance information regarding: predecessor companies; key personnel who have relevant experience; or subcontractors that will be performing major or critical aspects of this requirement; provided that such information is relevant to the construction in this solicitation.” Therefore, in accordance with FAR Part 15,305(a)(2), will the VA please confirm that projects submitted from partnerships in compliance with FAR 9.602 shall be allowed and equally evaluated.

Answer to 1. Our Factor 1 description was intended to relay that subcontractor performance history was not intended to be considered in lieu of prime contractor performance history. We do appreciate you bringing the noted inconsistency in the wording to our attention. To clarify our Factor 1 description , note that if the prime lacks the relevant past performance history that is requested under this Factor, the prime will not be rated as “unacceptable,” but will instead receive the equivalent to a neutral rating under FAR 15.305. As was noted in the Factor 1 Special Note 1 of the solicitation, if an offeror is without a record of relevant past performance or for whom information on past performance is not available, the offeror may not be evaluated favorably or unfavorably on past performance. Accordingly, those prime contractor offerors with an unknown past performance history will be considered as “Acceptable.” Please disregard our conflicting wording that notes “offers which present subcontractor experience shall not be considered for award.” As such, there is no need to submit subcontractor or partner information if you lack relevant past performance information as a prime. The lack of past performance history as a prime will still result in an “Acceptable” rating.

Question 2- Within Factor 2, Technical Construction Experience of Prime, the RFP states in paragraph (A), “Substitution of subcontractor experience is not allowed. Offers which present subcontractor experience shall not be considered for award.” However, as allowed by FAR 9.602, will the VA please consider allowing prime contractors and key subcontractors who are forming a partnership in accordance and in compliance with FAR 9.602 to submit projects from either the prime or key subcontractor to equally qualify for Factor 2? This will expand competition and allow significantly more otherwise equally qualified SDVOSBs to participate in this acquisition.

Answer to 2. We do not agree to your second request relating to Factor 2. Unlike past performance under Factor 1, we have experienced first-hand many issues related to working with primes that lack the necessary qualifications and experience to successfully administer these construction projects under a supposed teaming arrangement. As such, we included specific wording under Factor 2 which noted: “If submitting as a Prime/Sub teaming arrangement under FAR 9.601(2), the designated prime must meet the specific requirements of Factor 2A and 2B in order for the teaming arrangement to be deemed acceptable. Subcontractor experience will not be considered.” We want the prime to have the requested experience that we feel is necessary to successfully complete a project of this magnitude. We have experienced no lack of competition from this requirement and it protects the VA by providing SDVOSBs with the requisite experience on comparable projects.

Question 3- If the VA does not agree to allow key partnerships’ past performance for Factor 1 and 2, as defined by FAR 9.602, would the VA please consider reduce the percentage complete of the project submitted, and allow on-going (50% or greater) to be submitted and equally evaluated?

Answer to 3. Just as noted with respect to our response to your Factor 2 request, we want prime contractors that have the requisite experience at the time of proposal submittal. If the projects that you rely on to support that experience have not yet been 100% completed to satisfy that requirement, the submitted project will not count.