P03 36C24426AP0236 liquidated damages formulation Lebanon signed.pdf

PDF 255 KB Posted

Attached to
Z1DA--RFI Responses | 595-24-105 Replace Door Frames Bldg 104 DB (VA-26-00010058)
Solicitation number
36C24426R0016
Issued by

About this file

This Liquidation Damages Formulation Memo outlines the financial penalties for delays in a contract (Solicitation Number: 36C24425R0151) to replace door frames in Building 104. The document calculates liquidated damages at $609.33 per calendar day of inexcusable delay, broken down into two primary components: $340.03 for VISN 4 Contracting, Engineering, and Legal reviews, and $269.30 for Facility Engineering (COR/COTR) reviews. The damages are based on estimated hourly rates for various government personnel, including Contracting Officer Supervisors, Contract Specialists, Legal Officers, Construction Managers, and Project Engineers, with wage rates derived from the General Schedule Locality Pay Table for Lebanon County effective January 1, 2025.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Liquidation Damages Formulation Memo

Solicitation Number: 36C24425R0151 Replace Door Frames Building 104 D-B

All Civilian wage rates are based upon the General Schedule Locality Pay Table (Lebanon County) effective January 1, 2025 for Contracting and Project Engineer and FMS Manager.

1. Estimated liquidated damages for VISN 4 Contracting, Engineering, and Legal reviews per day of inexcusable delay:

CLASSIFICATION GRADE RATE HOURS TOTAL HOURLY RATE

Contracting Officer Supervisor

GS-14 / 5 $69.22 1 Hours $69.22

Contracting Officer

Contract Specialist

GS-13 / 5

GS-011 / 1

$58.58

$36.26

1 Hour

4 Hours

$58.58

$145.04

Legal Officer GS-14 / 4 $67.19 1 Hour $67.19

TOTAL PER

DAY

$340.03

2. Estimated liquidated damages for Facility Engineering (COR/COTR) per day of inexcusable delay:

CLASSIFICATION GRADE RATE HOURS TOTAL HOURLY RATE

Construction Manager GS-13 / 5 $58.58 2 Hours $117.16 Project Engineer GS-12 / 6 $50.71 3 Hours $152.14

TOTAL PER DAY $269.30

Grand Total Per Day $ 609.33

3. The Contractor shall pay liquidated damages to the Government in the amount of $609.33 for each calendar day of delay until the work is completed or accepted. The aforementioned costs were derived based upon historical trends associated with the time required of the parties to perform the additional contract administration which has not been completed by the Contractor within the specified time. The purpose of Liquidated Damages is compensatory only. The government retains the right to seek actual damages so far as they are distinguishable and separate from the Contractor failing to complete the work within the time specified in the contract.

4. The formulation of Liquidated Damages as detailed above are in accordance with Federal Acquisition Regulation 36.206 and will be assessed for each calendar day required to complete the construction work on this project past the scheduled completion date.

Elijah McIntosh Contracting Officer

2025-09-30T06:39:07-0400